Escolar Documentos
Profissional Documentos
Cultura Documentos
BAYESIAN-NETWORK-BASED HYDRO-POWER
FAULT DIAGNOSIS SYSTEM DEVELOPMENT
BY FAULT TREE TRANSFORMATION
Key words: fault tree, Bayesian Network, system reliability, Weibull periodic inspection and maintenance are carried out to main-
distribution. tain the facilities in normal operation. However, the goal of
fault prevention and economic maintenance costs cannot be
effectively achieved by the simple periodic maintenance and
ABSTRACT
inspection through check-list evaluation. To achieve the goal
Currently, fault diagnosis of reservoir facilities relies mostly of the preventive maintenance, an effective fault diagnosis
on check-list evaluation. The results and qualities of evalua- system is required. In recent years, fault diagnosis receives a
tion are limited by experience and ability of the evaluators, lot of attention and emphasis for the maintenance and the
which may not achieve the goal of systematic assessment in a safety evaluation of reservoir facilities [27].
consistent manner. To overcome the limitation of the tradi- Currently, faults diagnosis methods of reservoir facilities
tional approach, this research develops a fault diagnosis and include three types: qualitative analysis, semi-quantitative
evaluation system for reservoir facility by utilizing multi-state analysis, and quantitative analysis. Due to the complexity,
Fault-Tree Analysis (FTA) technique, in conjunction with uncertainty and variability of the hydro-power system, limited
Bayesian Networks (BN) which incorporate expert experi- maintenance data are collected for quantitative analysis. Quali-
ences through lateral linkages among BN nodes and weighting tative analysis only provides rough maintenance status and
factors. The system has been used to analyze and verify cannot support the sound maintenance plan. Therefore, several
against three hydro-power systems currently in operation. It hybrid approaches are developed for the fault diagnosis that
was found that through BN analysis the fault trend is consis- combine limited objective data and experts’ experiences. Some
tent to that from historical data analysis via Weibull distribu- popular hybrid approaches are Event-Tree Analysis (ETA),
tion. This indicates that the transformation of a multi-state Fault-Tree Analysis (FTA) and Bayesian Networks (BN).
Fault-Tree (FT) and BN is reasonable and practical. Based FTA is a common diagnostic tool used to assess the reli-
upon the analysis of BN by inputting prior information of the ability of a system. However, FTA has some limitations in
hydro-power systems, the probabilities of fault occurrences modeling, such as lack of lateral links and limited definition
are effectively computed based on which proper preventive of event states and logic gates. To overcome the limitations of
maintenance strategies can be established. FTA, BN has been proposed and widely applied for un-
certainty analysis. However, the establishment of BN for
practical applications could be quite difficult and tedious,
I. INTRODUCTION
especially for complicated ones. This study combines the
All reservoir facilities become aged over time which result advantage of FTA and BN to propose a more effective BN
in degradation of total performance [27]. Due to limited development process by transforming a multi-state FT into a
suitable sites for new reservoirs in Taiwan, high quality BN framework. The process was then used to build a hydro-
maintenance of existing reservoir facilities, such as spillways, power plant fault diagnosis system. Model validation and
outlet structures and power generation systems, becomes one sensitivity analysis are performed to further assess the appli-
of the main concerns in the reservoir management. Recently, cability of the diagnosis system.
and the regular maintenance, based on the system types, Data Collection
component characteristics and operational environments [25].
Since facilities are only regularly maintained or replaced, the
desire of early fault prevention cannot be achieved without Select Top Event Transform into BN Event Symbol
prior diagnosis of the faulty states and fragile conditions. That Framework Transformation
may lead to unnecessary waste of manpower and resources in
Select Intermediate & Add Lateral Input Expert
maintenance. Base Event Linkage Opinion
Since 1990, risk and fault diagnosis evaluation have been
included in dam safety assessment and hydro-power system Decide Logic Logic Gate
Construct CPT
management programs around the world. US Federal Energy Relationship Transformation
Regulatory Commission (FERC) implemented Potential-
Failure-Mode Analysis by adopting core-group discussion to Construct FT Compute Probability
Framework Event
conduct qualitative evaluation [9]. Failure Mode Effects and
Criticality Analysis (FMECA), a semi-quantitative analysis, is Fig. 1. Flow Chart for Transformation from FT to BN.
also widely applied in fault diagnosis. Furthermore, several
quantitative probability analysis models were developed for
risk and fault diagnosis, such as statistical deduction, reliabil-
III. RESEARCH APPROACH AND PROCESS
ity analysis and model simulation. For statistical deduction,
common techniques used are the relative frequency method The construction of BN could be quite complicated and its
and BN [14]. Reliability analysis makes use of probability network structure is problem specific. It is more advantageous
density function (PDF) to deduce the requirement and the to construct BN hierarchy by following the concept of FTA
probability for the system to stay within safety margin. Moni- and then transforming basic FT into BN framework. Finally,
toring data over the years are used to determine parameters for lateral links among BN nodes and conditional probability table
the model. Nevertheless, limited maintenance data can be (CPT) were introduced to incorporate experts’ experiences.
collected during the life cycle of the dam facilities. The life Fig. 1 depicts the proposed transformation process. In the
time of the dam facilities is generally much longer than that following, FTA, BN and the transformation processes are
of electronic facilities and rarely maintenance data are col- explained in detail.
lected for the fault diagnosis. Because of that, some semi-
quantitative analysis methods were proposed for the system 1. Fault Tree Analysis (FTA)
diagnosis, such as FTA [7, 15, 20, 22]. FTA is graphical deduction method by selecting an event
FTA assumes an event to be either fault or normal state (i.e., which a system does not wish to occur as the top event and
two states). In FTA two logic gates are commonly used to link from top-down searches for intermediate events till the very
the events in hierarchy and they are “OR Gate” and “AND bottom events. FTA generally uses “OR Gate” and “AND
Gate”. Due to the limited expression only for two states of the Gate” logic to link basic events, intermediate events and top
original FTA, multi-state fault-tree quantification technique is event in an inverted tree diagram called FT diagram. Through
proposed to transform FT into BN for fault analysis [13]. The a logic tracing of the developed tree diagram, FTA qualitatively
use of BN allows incorporating expert knowledge with or quantitatively analyzes defect and weaknesses of a system.
Bayesian probability theory for more effective fault diagnosis. It is a common analytical tool for system and mechanical re-
The main techniques make use of “OR Gate” and “AND Gate” liability and for safety and fault diagnosis [7, 15, 20, 22]. With
logic transform into BN to perform probabilistic analysis of the popular application of FTA software packages, FTA has
event occurrence [2-4, 6, 12, 17, 18]. Most of the transfor- been widely applied to fault analysis and risk evaluation of
mation methods convert both event nodes and logic gates in large systems. However, Generally FTA defines only two
FT into corresponding physical nodes in BN. However, logic states (either fault or normal) in the events, and two logic gates
gates are used to describe the relationship between events in (OR Gate and AND Gate) to link the events in a hierarchy. It is
sequence. It is meaningless to convert the logic gates into not powerful to handle the situation of complicated multi-
physical BN nodes. Moreover, under the multi-state situation, state systems. FTA is more applicable to a system analysis
it is difficult to define its conditional probability by using FTA problem in which fault mechanism and logic relationship are
[1, 8, 11, 24]. clearly defined. For complex and uncertain systems, prob-
In this research, a more reasonable transformation process abilistic network approach should be a better choice.
from FT to BN is proposed and investigated. A systematic
BN-based reservoir facility fault diagnostic system was then 2. Bayesian Network (BN)
developed for a more objective diagnosis and evaluation. BN combines probability theory with graphic theory and is
Three hydro-power systems currently in operation were used consisted of tree major parts: node, connecting arrow and CPT.
to analyze and verify the applicability of the BN-based fault It is a directed acyclic graph (DAG) and can display interre-
diagnostic system. lated variables in a network by means of their cause and effect
C.-G. Jong and S.-S. Leu: Transform Fault Trees to Bayesian Networks for Hydro-Power Diagnosis 369
E
1. All FT events are transformed into BN base nodes.
D C T F E Repeated events in FT are represented only by a BN base
T T 0.95 0.05 node.
B A T F 0.7 0.3 2. The probability of occurrence of basic event in FT can be
F T 0.87 0.13
F F 0.2 0.8
directly applied as the prior probability of a BN base
node.
3. The arrows among BN nodes follow the definition of
(b) event relationships in FT.
Fig. 2. Conventional Transformation Process from FT to BN: (a) Condi- 4. If there are some meaningful relationships among basic
tion with Certainty, and (b) Condition with Uncertainty. BN nodes that are not well defined in FT, arcs and ar-
rows should be inserted into basic BN to indicate the
mutual influences among the nodes. Those arcs can be
relationships. The technique can make qualitative and quan- defined by experts based on the problem scope.
titative deduction for uncertain outcomes by inferring the
conditional probabilities in BN. BN has a higher efficiency • CPT Determination
and accuracy in uncertain inference, especially for compli- In a BN framework, if a node has several parent nodes, or
cated systems with highly correlated elements [2, 17, 18, 21]. if each parent node and child node has several states, the
In recent years, BN has been widely applied in various fields, CPT structure will become complicated. In addition, the
such as medical diagnosis, industrial design, financial in- values of CPT are generally defined by experts based on
vestment, ecology, etc. their experience, the probability values could be inconsis-
However, it is generally difficult to establish mutual rela- tent especially under the condition of complicated CPT
tionship among nodes in the network by directly incorporating stated above. In this study the software, AgenaRisk, was
the views of experts. Therefore, several transformation proc- used to eliminate the above-mentioned difficulties (Agena
esses from FT to BN have been proposed [2-4, 6, 12, 17, 18]. 2008). Through parameters defined in the software, cou-
In general, the transformation of logic gates in FT into BN is pled with weighting factors filled by experts among nodes,
also one-to-one; i.e., logic gates in FT are converted into cor- one can calculate probability values in CPT rapidly.
responding physical nodes in BN (shown in Fig. 2). However,
there are differences in meanings of an event node in BN and a When AgenaRisk is used to define CPT, the definition of
logic gate in FT. An event node is used to represent a variable the expression function in the software is a key step. As stated
in the problem domain, whereas a logic gate is to describe the above, there are two main logic gates in FT: “AND” and “OR”.
logical relationship between the nodes. For the transformation In the selection of the expression function items, minimum is
between FT and BN, the event nodes and the logic gates selected if the corresponding logic gate in FT is “AND”,
should be treated differently. In the transformation process whereas maximum is selected if the logic gate is “OR”.
370 Journal of Marine Science and Technology, Vol. 21, No. 4 (2013 )
Through deduction, it can be proven that the fault probabilities BN are identical. Furthermore, in AgenaRisk, the output is
of top event by FTA and BN are identical. For simplicity, identical to the “AND” logic gate in FT if the minimum value
assuming that there are two independent events: A and B, and of the expression function item is selected. Also, the output is
their top event C, they have two states: A1 and B1 belong to identical to the “OR” logic gate in FT if the maximum value of
normal states, A2 and B2 fault states, as well as C1 normal the expression function item is selected. After the minimum
states, C2 fault states. or maximum value has been selected in function types, the
Based on the logic of AND gate, the fault probability can be weighting factors should then be selected in the software. The
calculated as weighting factors can be determined through the opinion poll
of experts based on the contribution of parent nodes to the
P(C2 ) = P(A2 ∩ B2 ) = P( A2 ) × P( B2 ) (1) subsequent nodes. The score ranges from 1 to 5 in which 1
means that the parent node has the least effect on child node
Based upon the concept of BN, the fault probability can be and 5 means the most effect. Based upon the above-mentioned
derived as inputs, CPT can be calculated by AgenaRisk.
P(C2 ) = C2 A1 B1 × A1 × B1 + C2 A1 B2 × A1 × B2
IV. BN-BASED HYDRO-POWER
+ C2 A2 B1 × A2 × B1 + C2 A2 B2 × A2 × B2 DIAGNOSIS SYSTEM
= 0 × A1 × B1 + 0 × A1 × B2 + 0 × A2 × B1 (2)
Based upon the proposed BN construction process, a
+ 1× A2 × B2 BN-based hydro-power diagnosis system was developed. In
= A2 × B2 order to obtain the sound knowledge support, nine experts
were invited to construct BN. Their background information
Based upon the logic of OR gate, the fault probability can is listed in Table 1. The detail of the system development is
be defined as: explained below.
1. Construction of FT Framework
P(C2 ) = P( A2 ∪ B2 ) = P( A2 ) + P( B2 ) − P( A2 ∩ B2 )
(3) First, a top event indicating the condition that the hy-
= 1 − [(1 − P( A2 )) • (1 − P( B2 ))] = 1 − P( A1 ) • P( B1 ) dro-power system fails to produce power is defined. Based
upon the components of the hydro-power system and their
Based upon the concept of BN, the fault probability can be conditions, eight intermediate events in the second level; 27
derived as intermediate events in the third level; and 84 basic events were
further defined. Based upon the discussion with the experts
P(C2 ) = C2 A1 B1 × A1 × B1 + C2 A1 B2 × A1 × B2 (as shown in Table 1) and the examination of past maintenance
+ C2 A2 B1 × A2 × B1 + C2 A2 B2 × A2 × B2 records, it was found that the occurrences of any intermediate
= 0 × A1 × B1 + 1× A1 × B2 + 1× A2 × B1 or basic event can disable power production. Therefore “OR
(4) Gate” is used as logic linkage among the events. The FT
+ 1× A2 × B2
frameworks after careful deliberation with the experts are
= A1 × B2 + A2 × B1 + A2 × B2 shown in Figs. 3-6 each of which, respectively, are FT dia-
= 1 − A1 × B1 grams describing the causes making the system unable to
produce power, disabled turbine, malfunction generator, and
It is seen that the fault probabilities of top event by FTA and failed transmission system for delivering power.
C.-G. Jong and S.-S. Leu: Transform Fault Trees to Bayesian Networks for Hydro-Power Diagnosis 371
Hydropower System
Failing to Produce Power
A C D E
B Transmission
Waterway Cannot Malfunction Tailrace Cannot
Disabled Turbine System Unable to
Supply Flow Generator Deliver Power Discharge Flow
H
Operational Error
B C D
E1 E3
Tailrace Malfunction
Erosion Gate
E2 E4
Air Vent Clogging
Damage of Silt
F G
Disabled Cooling Faulty Control
System System
G2 G3 G4
F1 F3 G1
Insufficient Insufficient F5 Loss of Control Control Software Disabled
Disconnection
Generator Upper Generator Thrust Insufficient
of Control Power not Operational Control
Guide Bearing Bearing Cooling Shaft Seal Hardware
Cooling Water Water Cooling Water Module Signal
F2 F4
Insufficient F6
Insufficient Insufficient Shaft
Generator Lower Generator
Stator Cooling Bearing Cooling G5 G6
Guide Bearing
Water G7 G8
Cooling Water Water Interrupted Interrupted Mismatch of
Direct Mismatch of
Alternate Control Firmware
Current Current Software
A1 A2
Intake Gate Penstock Cannot
Cannot be Open Diliver Flow
A6 A7
A3 A4 A5 Insufficient Oil A10 A11
Disabled Pressure for A13
Gaterframe Clogging by Trashrack Filling A8 A9 Damage of Main Valve Cannot A12
Siltation Damage Opening Shaft be Opened Damage of
deformation
Valve Clogging by Expansion Penstock Internal
rnal
Manhole
Deformation Siltation Joint Water Erosion
Cover
Seal
Disabled
Turbine
B2
B1
Faulty Guidevane B5
Clogging of
Spiral Case Excessive Shaft
B3 B4 Vibration
Runner Shaft Shaft Cover
Seal Leakage Leakage
B8 B9
Hydraulic
Broken
B6 B7 System Cannot
Guidevane Operate
Faulty Governor Malfunction Server Shear Key Guidevane
B10 B11
B12
Broken Linkage Faulty Shaft Bearing
Turbine Runner
between Shaft
Jammed by Drift
and Turbine
Wood
Runner
B20
Faulty B21 B22
Mechanical Motor Damaged Power Failure
Components
Malfunction
Generator
C1 C2 C3 C5
Faulty Parallel Excitation Rotor Failure Bearing Failure
Control System System Failure
C22 C27
C21 C26
Low Pressure High Pressure
Loosening of Oil Leak Due
Compressed Air Lifting Pump
Brake Shoe Broken Pipe
System Failure Failure
C18 C19 C20
Coil Connector Coil Grounding Coil Internal
Open Circuit at Two Points Short Circut
C4
Stator Failure
C28 C29
Burned and Mechanical C30
Damaged Component Power Failure
Motor Damage
C14
C12 Air Heat
C11 C13
Stator Core Exchangers
Stator Frame Stator Coil
Failure Cannot
Failure Failure Dissipate
Heat
C24 C25
C23
Steel Core Steel Core
Steel Core
Insulation Fastener
Failure
Failure Failure
Failed Transmission
System to Deliver
Power
D1 D2 D3
Transformer Switch Equipment Transmission
Failure Failure Equipment Failure
D10 D12
Breaker Failure D11
Isolation
Insulator
Switch Gear
Failure
Failure
D18
D16 D17
Potential and
Compressed Air SF6 Degrading
Current
Equipment or Lowering of
Transformer
Failure Pressure
Abnormal
D4 D7 D14 D15
D6 Protection
Pressure D5 Insulation D8 D9 D13 Transmission
Steel Core System Failure
System Coil Damage Oil Pipe Damage Fan Failure Transmission Line
Damage
Damage Degrading Tower Failure Thundering
Damage
D20
D19
Control
Loss of Control
Component
System Power
Damage
After the completion of FT frameworks, a total of 18-year The analysis was performed on an hourly basis for three
fault and maintenance data are analyzed statistically for separate states. The state classifications are made in accor
Shihmen units 1 & 2 and Yihsin unit, excluding the period dance with FMEA fault rate occurrence scoring standard
from 2004 to September 2007 during which typhoon had ranking 3 (see Table 2). The fault duration of 1/15,000 of the
caused severe interruption of the system operation. The total total period of analysis, that is 8 hrs, is used as a state classi-
analysis periods are 126,312 and 131,400 hours, respectively. fication interval. Thus, the system has three states: (1) normal
C.-G. Jong and S.-S. Leu: Transform Fault Trees to Bayesian Networks for Hydro-Power Diagnosis 375
D17
SF6
Degrading or D18
Lowering of Potential and
Pressure Current
Transformer
Abnormal D19 A14 A15
Loss of Degraded Disabled or
D16 Oil
Compressed Control D20 Interrupted
Air System Control Power to
Equipment Power Component Motor
Failure
D10 D11 D13 Damage
Breaker Insulator Transmission A6
Failure Failure Tower Disabled A4 A10
Failure Filling Clogging Damage of
D14 Valve by A9 Expansion
Transmission Clogging by Joint Water
D12 Line Siltation
D6 Isolation Thundering A7 Siltation Seal
A16
Steel Core Damage
A5 Insufficient
Switch Gear Trashrack Guide Vance
Damage Failure D15 Oil Pressure
Water
Protection Damage for Opening
C20 Liakage too
Coil Internal System
D8 Failure A12 A11 Large
C19 Short Circut
Coil D7 Pipe Penstock Main Valve
Damage D2 Internal Cannot be
Grounding Insulation Switch D3 A3 Erosion
at Two Oil Transmission Gaterframe Opened
Points
D9 Equipment
Fan Failure Degrading Failure Equipment Deformation
Failure A17
C18 A13 Malfunction
A8 A2 Damage of Bypass
Coil Shaft A1
Connector D5 D1 Deformation Penstock Manhole Valve
Transformer Intake Gate Cover
Open Coil Cannot be Cannot
Circuit C8 Damage Failure
Open Diliver
Rotor Poles D4 Flow
Failure Pressure D F6
Failed H Insufficient
System Shaft Bearing F5
Damage Transmission Operational
System to Error A Cooling Insufficient
C21 C10 Waterway Water Shaft Seal
C30 Loosening Deliver
Cannot Cooling
Power Failure Ventilation Power
of Brake
Fans Failure C3 Supply F Water
Shoe Flow Disabled
Rotor
Cooling F3
C7 Failure T Insufficient
Rotor Rim System
Hydropower Generator
C28 failure
System Failing Thrust Bearing
Burned and C22 C to Produce Cooling
Damaged Low Pressure C6 Malfunction Power Water
Motor Compressed Air C9 Rotor/Spider Generator F1
System Failure Brake Failure C4 Insufficient F4
Ringfailure Stator Generator Upper F2 Insufficient
C1 Guide Bearing Insufficient Generator
Failure Faulty Parallel Cooling Generator Lower Stator
C29 C25 C12 Control Water Guide Bearing Cooling
Mechanical Steel Core Stator Core C5 System G Cooling Water Water
Component Fastener C11 Bearing Faulty
Damage Failure
Failure Stator Failure C2 Control E E1
Frame Excitation System Tailrace Tailrace
Failure System Cannot Erosion
Failure Discharge
C23 C15 Flow
Steel Core Top Guide B E2
Failure Bearing C16 Disabled Air Vent
C13 C14 Failure Bottom Turbine Damage
Stator Coil Air Heat Guide
C24 Failure Exchangers Bearing B4 E4 E3
Steel Core Cannot Dissipate Failure Shaft Cover Clogging of Malfunction
Insulation Heat Leakage Silt Gate
Failure
C17
Thrust
Bearing G4
Failure Disabled
B1 Control
C27 Clogging of Hardware
High Pressure
B3 B5
Runner Excessive Spiral Case G3
Lifting Pump Shaft Seal Control
Failure C26 Shaft
Software not
G8
Oil Leak Leakage Vibration G1 Mismatch
Operational of
Due Broken Disconnection
Pipe of Control Firmware
B2 Module
B26 B12 Faulty Signal
Power Turbine Runner Guidevane
Interruption of Jammed by
Lubrication Drift Wood G2
Oil Pump Loss of G7
B25 Control Mismatch
Lubrication B9 Power G6 of Control
Oil Pump B11 Hydraulic Software
Motor Faulty Shaft System Cannot
B6 Interrupted
Damaged Bearing Faulty Direct
Operate Governor Current
B23 Guidevane
Faulty
Lubricant B10 G5
B24 System Broken Linkage B7
Mechanical between Shaft B8 Malfunction
Interrupted
Broken Alternate
Failure of and Turbine
Guidevane
Server B13 Current
Lubrication Runner Hydraulic
Oil Pump Shear Key System
Output Signal
B22 Malfunction
B27 Power B19 B16
Failure B15
Faulty Faulty Faulty Faulty
Components Compressed Hydraulic Distributor
Air System Valve B14
Equipment Interruption of
Governor
Power Source
or Speed
B21 B17
Motor Leakage of
Damaged Hydraulic
B20 B18 Line
Faulty Pump Unable
Mechanical to Rise
Components Pressure
condition - the state is ″0″; (2) faulty state with duration less Table 3. Key features of three hydro-power plants.
than 8 hrs - the state is ″1″; and (3) faulty state with duration Plant
longer than 8 hrs - the state is ″2″. Through discussions with a Yihsin Shihmen 1 Shihmen 2
Item
panel of the site experts (as shown in Table 1), it was con- Storage Regulation Reservoir Reservoir
cluded that the state classification matches the 8 hrs daily work Facility Pool Type Type Type
requirement. Based upon the state classification, the fault Turbine type Francis Francis Francis
durations of all basic events over the years were analyzed. The Head 146.8 m 59~109 m 59~109 m
ratios of the fault duration over the total operation duration are
Installed
used for the prior probabilities of basic events. 40 mw 45 mw 45 mw
Capacity
Annual 1.80 × 108 1.10 × 108 1.10 × 108
2. Construction of BN from FT
Output kwh kwh kwh
Based upon the transformation process described in Section 12 km Downstream Downstream
3, all the FT diagrams were transformed to BN. Overlapping Location upstream from Reservoir from Reservoir
nodes were combined into one. Furthermore, some lateral arcs from Reservoir on Right Bank on Right Bank
among the BN nodes were added based upon the experts’ Waterway, Turbine, Generator, Transmission and
Main
experiences. The complete BN framework is shown on Fig. 7 Transformer Facility, Cooling Facility, Control
Facilities
which will be used in the follow-up analysis and in-depth System and Tailrace, etc.
investigation.
3. CPT Development of rotation. The type of turbine is suitable for head in the
AgenaRisk was used to calculate CPT based on the con- range of 30 to 500 m, and is referred to as medium head tur-
structed BN framework. Since FT logic gates are all “OR bine. The basic features of the three hydro-power units are
Gate”, maximum values were selected in the expression summarized in Table 3.
function types. The relative weighting factors of parent nodes
to their child nodes were discussed and defined in the panel of 2. System Reliability Analysis
nine experts. Based upon the above-mentioned input data, the In this research, actual fault and maintenance records of
CPTs for all the arcs in the BN were then calculated. Finally, Shihmen Unit 1 and 2 (1965~2008) and Yihsin Unit (1991~
the posterior probabilities of the BN nodes (including both top 2008) were collected and analyzed. The goodness-of-fit test
event and the intermediate events) were inferred along BN. by Chi-Square test indicates that the historical failure data
The sum of probabilities in states ″1″ and ″2″ yields the fault reveals that time-to-failure of the three turbines fits the
probability of the system. Weibull distribution. The Weibull distribution is a commonly
used probability distribution in reliability analysis and may be
used to model both increasing and decreasing failure rates
V. MODEL VERIFICATION AND
[7, 8, 10, 12, 13]. The three parameters are: shape parameter
SENSITIVITY ANALYSIS
β, scale parameter θ (characteristic life) and location pa-
The results of BN inferences were validated by comparing rameter τ. If there existed faulty condition at the beginning of
with the reliability analysis of historical data. The sensitivity the system use, the location parameter can be set to zero [7, 8,
analysis was further performed to identify key subsystems and 10]. Because faulty conditions had occurred to all three hy-
components for system fault diagnosis. The results from the dro-power units, location parameter is not considered in
sensitivity analysis may be used as an important reference in Weibull distribution.
future diagnostic analysis and maintenance strategies. Based on the available maintenance data, Weibull distribu-
tion parameters β and θ were estimated by the least square
1. Background Data of the Systems method and the resulting coefficient of determination (R2)
The Shihmen Reservoir, located in Northern Taiwan, is were greater than 0.9. Table 4 shows the statistic data and the
formed by an embankment Dam. Since reservoir filling in good-of-fit test results. As can be seen that β values for
May, 1963, it has been in operation for 47 year. It is a multi- Shihmen Unit 1 and 2 range between 1 and 3 and the corre-
purpose reservoir for irrigation, power generation, water sup- sponding probability density function (PDF) are skewed. For
ply, flood control and recreation. Unit 1 and 2 hydro-power Yihsin unit, β is larger than 3 and its PDF is close to the normal
units are located at right bank downstream from the dam. distribution and is symmetrical. Fig. 8 depicts the PDF curves
Each installed capacity is 45 MW, with average annual output for the time-to-failure of the three turbine units. From Table
of about 1.1 × 108 KWH. The Yihsin hydro-power unit is 4 it is observed that all three systems shape parameter β > 1
located 12km upstream from the dam and has an installed have a trend of increasing failure rate and exhibit wear-out
capacity of 40 MW with an average annual output of 1.80 × failure period in a form of bathtub curve. Increased inspection,
108 KWH. Vertical type Francis turbines are installed for all monitoring and maintenance are needed for these three hy-
three units. Thus the flow direction is perpendicular to the axis dro-power units.
C.-G. Jong and S.-S. Leu: Transform Fault Trees to Bayesian Networks for Hydro-Power Diagnosis 377
Table 4. Chi-Square goodness-of-fit test for weibull distribution and parameter estimation.
System
Yihsin Shihmen 1 Shihmen 2 Shihmen 1 & 2
Item
Sample size 33 60 64 124
χ2 Goodness-of-fit Test on H0: Weibull Distribution
Equally Spaced Intervals K 7 7 7 8
Length of Interval (hr) 1200 1700 2300 2000
Freedom 4 4 4 5
Critical values @5% 9.5 9.5 9.5 11
Test statistic values 9.31 9.08 7.26 10.69
H0: Weibull distribution accepted accepted accepted accepted
Weibull Parameter Estimation
Regression Line 4.885x-41.716 1.637x-14.24 2.373x-20.535 1.959x-16.994
Critical values @5% 9.5 9.5 9.5 11
Test statistic values 9.31 9.08 7.26 10.69
H0: Weibull distribution accepted accepted accepted accepted
Weibull Parameter Estimation
Regression Line 4.885x-41.716 1.637x-14.24 2.373x-20.535 1.959x-16.994
β 4.885 1.637 2.373 1.959
θ 5115 hr 5986 hr 5727 hr 5859 hr
R2 0.943 0.937 0.946 0.944
Mean-time-to-failure (MTTF) 4,692 hrs 5,358 hrs 5,248 hrs 5,308 hrs
Characteristic Life (θ ) 5,115 hrs 5,986 hrs 5,727 hrs 5,859 hrs
Median time-to-failure (R = 0.5) 4,745 hrs 4,787 hrs 4,908 hrs 4,859 hrs
Although the mechanism of transformation from FT to BN on Knowledge and Data Engineering, Vol. 19, No. 10, pp. 1420-1432
has been well examined, the use of BN, nevertheless, relies on (2007).
12. Franke, U., Flores, W. R., and Johnson, P., “Enterprise architecture de-
the inputs of expert experiences for the linkages and CPTs. pendency analysis using fault trees and Bayesian Networks,” Computer
Data provided by different experts will directly affect the ac- and Information Science, Miscellaneous Paper, Procedings of the 2009
curacy and the assessment quality of BN. Special attention Spring Simulation Multiconference, pp. 209-216 (2009).
should be paid to expert elicitation in the future study. In ad- 13. Graves, T. L., Hamada, M. S., Klamann, R., Koehler, A., and Martz, H. F.,
dition, BN can be learnt from raw data. If complete and sound “A fully Bayesian approach for combining multi-level information in
multi-state fault tree quantification,” Journal of Reliability Engineering
maintenance data are available, an objective BN can be estab- and System Safety, Vol. 92, pp. 1476-1483 (2007).
lished. Finally, there are other important facilities in a reser- 14. Hartford, D. and Baecher, G. B., Risk and Uncertainty in Dam Safety,
voir, such as spillway, water intake structure and silt-sluiceway. Thomas Telford, Ltd., London (2004).
There is a need to extend the reliability analysis of this type to 15. Kales, P., Reliability for Technology, Engineering, and Management,
these systems and make use of BN for faulty diagnosis to en- Pearson Education Taiwan, Ltd. (2006).
16. Leemis, L. M., Reliability Probabilistic Models and Statistical Methods,
hance the reliability of the entire reservoir system. Prentice-Hall International, Inc., London (1995).
17. Liu, X., Li, H., and Li, L., “Building method of diagnostic model of
Bayesian Networks based on fault tree,” Proceedings of SPIE, Seventh
REFERENCES International Symposium on Instrumentation and Control Technology:
1. Benedict, E. K., “Elicitation techniques for Bayesian Network models,” Sensors and Instruments, Computer Simulation, and Artificial Intelli-
Stockholm Environment Institute, Working Paper WP-US-0804 (2008). gence, Vol. 7127, 71272C-1 (2008).
2. Bobbio, A., Portinale, L., Minichino, M., and Ciancamerla, E., “Com- 18. Marsh, W. and Bearfield, G., “Representing parameterised fault trees
paring fault trees and Bayesian Networks for dependability analysis,” using Bayesian Networks,” Proceeding of the 26th International Con-
Computer Safety, Reliability and Security, Lecture Notes in Computer ference on Computer Safety, Reliability and Security, SAFECOMP,
Science, Vol. 1698, pp. 310-322 (1999). Springer-Verlag (2007).
3. Bobbio, A., Portinale, L., Minichino, M., and Ciancamerla, E., “Im- 19. Meeker, W. Q. and Escobar, L. A., Statistical Methods for Reliability
proving the analysis of dependable systems by mapping fault tree into Data, A Wiley-Interscience Publication, John Wiley & Sons, Inc., USA
Bayesian Network,” Reliability Engineering and System Safety, Vol. 71, (1998).
pp. 249-260 (2001). 20. O’Connor, P. D. T., Newton, D. W., and Bromley, R. C., Practical Reli-
4. Boudali, H. and Dugan, J. B., “A discrete-time Bayesian Network reli- ability Engineering, 4th Edition, John Wiley & Sons, Ltd., England
ability modeling and analysis framework,” Reliability Engineering and (2005).
System Safety, Vol. 87, No. 3, pp. 337-349 (2005). 21. Qian, G., Zheng, S., and Cao, L., “Bayesian Network based on a fault tree
5. Cooke, R. M. and Goossens, L. H. J., Procedures Guide for Structured and its application in diesel engine fault diagnosis,” Proceedings of SPIE,
Expert Judgement, published by the European Union as EUR 18820, ICMIT: Control Systems and Robotics, Vol. 6042, 60421P-1 (2005).
European Commission, Brussels, Belgium, Luxembourg (2000). 22. Rao, S. S., Reliability-Based Design, McGraw-Hill International Edi-
6. Doguc, O., Jose, E., and Marquez, R., “An efficient fault diagnosis tions, Taiwan (2002).
method for complex system reliability,” 7th Annual Conference on Sys- 23. Ross, S. M., Probability Models, Academic Press, An Imprint of Elsevier
tem Engineering Research (CSER) (2009). Science, Eighth Edition USA (2003).
7. Ebeling, C. E., An Introduction to Reliability and Maintainability Engi- 24. Sigurdsson, J. H., Walls, L. A., and Quigley, J. L., “Bayesian belief nets
neering, McGraw-Hill International Editions, Singapore (1997). for managing expert judgement and modeling reliability,” Journal of
8. Fabian, C. and Hadipriono, F., “Expert systems for construction safety. I: Quality and Reliability Engineering International, Vol. 17, No. 3, pp.
Fault-tree models,” Journal of Performance of Constructed on Facilities, 181-190 (2001).
Vol. 6, No. 4, pp. 246-260 (1992). 25. Taiwan Electrical Power Company, Water Power Generator System
9. Federal Energy Regulatory Commission, Dam Safety Performance Moni- Operation and Maintance Manual and Shihmen Water Power Generator
toring Program, Federal Energy Regulatory Commission, Washington, Operation Standard Manual, Taiwan Electrical Power Company, Minis-
DC, USA (2005). try of Economic Affairs, Taiwan (2008).
10. Fenton, N. E. and Neil, M., “Combining evidence in risk analysis using 26. Tobias, P. A. and Trindade, D. C., Applied Reliability, Second Edition,
Bayesian Network,” Safety Critical Systems Club Newsletter, Vol. 13, No. International Thomson Publishing, Europe (1995).
4, pp. 1-6 (2004). 27. Water Resource Agency, The Establishment of the Optimal Inspection
11. Fenton, N. E., Neil, M., and Caballero, J. G., “Using ranked nodes to Scheduling and Frequence for Dam Safety, Water Resource Agency,
model qualitative judgments in Bayesian Networks,” IEEE Transactions Ministry of Economic Affairs, Taiwan (2004).