No Deciplines to be Audited
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1 Engineering
Adequacy Audit
System Audit
Product Close out and Final
Documentation Audit
2 Procurement
Adequacy Audit
System Audit
3 Construction
Adequacy Audit
System Audit
Product Close out and Final
Documentation Audit
4 Commissioning
Readiness Audit at 30% Progress
Readiness Audit at 30% Progress
APPROVAL:
1 Engineering
1.1 Adequacy Audit
1.2 System Audit
1.3 Product Close out and Final
Documentation Audit
2 Procurement
2.1 Adequacy Audit
2.1 System Audit
3 Construction
3.1 Adequacy Audit
3.2 System Audit
3.3 Product Close out and Final
Documentation Audit
4 Commissioning
4.1 Readiness Audit at 30% Progress
4.2 Readiness Audit at 30% Progress
APPROVAL:
(HUSSIN BIN ALI) (WAN RUI)
Quality Manager Project Manager
PETRONAS RAPID PROJECT, PENGERANG
(P30A - EPCC OF RAPID ADDITIONAL OLEFINS STORAGE FACILITIES)
01 12 Jan 2018 to 17 Jan 2018 CCEM work progress at 50% (System Audit) 1 audit
02 12 Jan 2018 to 17 Jan 2018 IJB work progress at 25% (Adequacy Audit) 1 audit
04 12 Jan 2018 to 17 Jan 2018 MMHE ATB foundation at 50% (System Audit) 1 audit
05 16 April 2018 to 20 April 2018 IJB work progress at 50% (System Audit) 2 audit
06 16 April 2018 to 20 April 2018 DESB foundation at 50% (System Audit) 2 audit
07 16 April 2018 to 20 April 2018 MMHE ATB foundation at 75% (Handover and FD Handover) 2 audit
08 4 June 2018 to 8 June 2018 IJB work progress at 75% (Handover and FD Handover) 3 Audit
09 4 June 2018 to 8 June 2018 DESB work progress at 75% (Handover and FD Handover) 3 Audit
4 June 2018 to 8 June 2018 WHYY- Fabriation & Eretion of 4 nos of Propylene Sphere Tanks .
10 3 Audit
MMHE foundation at 25%
12 Nov 2018 to 16 Nov 2018 WHYY- Fabriation & Eretion of 4 nos of Propylene Sphere Tanks .
11 4 Audit
MMHE work progress at 75% (Handover and FD Handover)
PETRONAS RAPID PROJECT, PENGERANG
(P30A - EPCC OF RAPID ADDITIONAL OLEFINS STORAGE FACILITIES)
01 3 Nov 2017 - 6 Nov 2017 Engineering - Adequacy Audit at 50% Works Phase 1 audit
02 29 Jan 2018 - 2 Feb 2018 Engineering - Project Close out & Final Documentation Audit at 75% 2 audit
03 29 Jan 2018 - 2 Feb 2018 Procurement - System audit at 30% of work phase. 2 audit
04 29 Jan 2018 - 2 Feb 2018 Construction - Adequancy Audit at 25% Works Phase 2 audit
05 21 May 2018 - 25 May 2018 Procurement - System audit at 80% of work phase. 3 audit
06 21 May 2018 - 25 May 2018 Construction - System audit at 50% Works Phase 3 audit
07 12 Nov 2018 - 16 Nov 2018 Construction - Product Close out ad final documentation Audit at 75% 4 audit
08 12 Nov 2018 - 16 Nov 2018 Commisioning - Readiness Audit at 30% Progress 4 audit
PETRONAS RAPID PROJECT, PENGERANG
(P30A - EPCC OF RAPID ADDITIONAL OLEFINS STORAGE FACILITIES)
03 12 Jan 2018 to 17 Jan 2018 CCEM work progress at 50% (System Audit) 1 audit
04 12 Jan 2018 to 17 Jan 2018 IJB work progress at 25% (Adequacy Audit) 1 audit
06 12 Jan 2018 to 17 Jan 2018 MMHE ATB foundation at 50% (System Audit) 1 audit
07 29 Jan 2018 - 2 Feb 2018 Engineering - Project Close out & Final Documentation Audit at 75% 2 audit
08 29 Jan 2018 - 2 Feb 2018 Procurement - System audit at 30% of work phase. 2 audit
09 29 Jan 2018 - 2 Feb 2018 Construction - Adequancy Audit at 25% Works Phase 2 audit
10 16 April 2018 to 20 April 2018 CCEM work progress at 75% (Handover and FD Handover)
11 16 April 2018 to 20 April 2018 IJB work progress at 50% (System Audit)
13 16 April 2018 to 20 April 2018 MMHE ATB foundation at 75% (Handover and FD Handover)
14 21 May 2018 - 25 May 2018 Procurement - System audit at 80% of work phase. 3 audit
15 21 May 2018 - 25 May 2018 Construction - System audit at 50% Works Phase 3 audit
16 4 June 2018 to 8 June 2018 IJB work progress at 75% (Handover and FD Handover)
17 4 June 2018 to 8 June 2018 DESB work progress at 75% (Handover and FD Handover)
4 June 2018 to 8 June 2018 WHYY- Fabriation & Eretion of 4 nos of Propylene Sphere Tanks . MMHE
18 foundation at 25%
19 12 Nov 2018 - 16 Nov 2018 Construction - Product Close out ad final documentation Audit at 75% 4 audit
20 12 Nov 2018 - 16 Nov 2018 Commisioning - Readiness Audit at 30% Progress 4 audit
PETRONAS RAPID PROJECT, PENGERANG
(P30A - EPCC OF RAPID ADDITIONAL OLEFINS STORAGE FACILITIES)
Electrical / Instrumentation
Piping / Tank / Mechanical
Friday, 2 Feb 2018 ENGINEERING Lunch (Lead Electrical / Instrumentation
(Lead Piping / Tank / Mechanical Engineer) Engineer)
Monday, 5 Feb 2018 PROCUREMENT Expediting / Logistic / Material Management Lunch Closing Meeting
Friday, 12/1/2018