Você está na página 1de 1

1.

0 Equipment General Data and Information

Substation

Bay/Panel

2.0 Mechanical Check and Visual Inspection


Item Description Done Date Remarks
1. Mechanical Check and Visual Inspection of panels
2. Check main and riser buses for correct phasing connections.
3. Perform mechanical check and visual inspection on all voltage transformers.
Perform mechanical check and visual inspection on all disconnected and
4.
grounding switches.

3.0 Electrical Test

Item Description Done Date Remarks

1.
Bus continuity and phasing test.

2. Main circuit resistance test with the switchgear erected but not yet
connected to the cables.
3. Insulation resistance test at 5 kV DC on all main circuit between phase
to phase and phase to ground (before HV test).

4.
Primary Injection Test

5.
High voltage test