Substation
Bay/Panel
1.
Bus continuity and phasing test.
2. Main circuit resistance test with the switchgear erected but not yet
connected to the cables.
3. Insulation resistance test at 5 kV DC on all main circuit between phase
to phase and phase to ground (before HV test).
4.
Primary Injection Test
5.
High voltage test