Escolar Documentos
Profissional Documentos
Cultura Documentos
such cases, only one copper removal process needs to be utilized and it is
advantageous to use it after iron removal. Furthermore, it may be possible
to divide in half the chemical concentrations of sodium bromate and citric
acid, the pH still, however, being adjusted to 9.5. Work has shown that
sodium nitrite is a less acceptable alternative to sodium bromate for the
oxidizing agent in copper removal, despite its apparent advantage for the
secondary purpose of short-term passivation. If gas-induced circulation is
being used, air is an acceptable medium during copper removal, but does
not obviate the need for sodium bromate.
1.5.4.7 Passivation After Cleaning
To minimize deterioration of the active surfaces produced by acid cleaning,
a final passivation stage is an essential part of the overall cleaning process.
Details are included in Appendices 1A, 1D, 1E and supplementary notes
are given in Sect. 1.8, ‘Protection of Plant After Cleaning’.
1.5.4.8 Protection of Plant When the Cleaning Process is Interrupted
Special situation could arise if it were necessary at any stage to curtail
or suspend a cleaning. Guidance on the available courses of action in
such circumstances is given in Appendix 1G.
1.6 Practical Considerations
1.6.1 Planning
1.6.1.1 Coordination
Experience has shown the need for full consultation between the
Engineering, Design and Construction, Plant Engineering, and
Operation Services before carrying out pre-operational chemical
cleaning.
1.6.1.2 Operational Water Requirements
During cleaning, there is a requirement for very large quantities of
clarified and DM water. Careful programming of the installation and
commissioning of the water treatment plant and water storage tanks is,
therefore, required before commencing pre-commissioning cleaning.
For post-operational cleaning, application of the complete Appendix 1D
may use up to 12 boiler volumes of DM water.
1.6.1.3 Effluents
It is essential that all statutory requirements covering effluent disposal
from the station are established and met. In some circumstances, citric
acid waste can be disposed of by burning in an adjacent boiler.
Appendix A: The Operational and Safety Aspects of Chemical Cleaning … 153
dictate that both pre- and post-operational cleaning are carried out with
most of the drum internals in place.
1.6.3.6 Stagnant Areas
Particular attention must be given to stagnant areas, instrument
connections, and similar items to ensure that they are properly cleaned
and flushed. Temperature measurement points should be installed to
show uniformity of circulation, although an infra-red TV camera is
preferable for this purpose. Adequate sampling facilities should be
available to check reagent strength and circulation.
1.6.3.7 Water-Plugging of Super heaters
To prevent cleaning solutions entering the super heater while only the
boiler circuit is being cleaned, the super heater shall be water-plugged
before any circulation of cleaning solution commences and
back-flushed between the various stages of the process. Care must be
taken to ensure that the super heater can be adequately back-flushed. In
addition, as discussed in Appendix 1H, a constant head overflow device
shall be fitted to the boiler drum, and suitable arrangements made to
indicate drum level during cleaning. Make-up water should be adjusted
to a Ph OF 8.8–9.2, and ammonia should be used for this purpose.
1.6.3.8 Venting
While chemical cleaning operations are in progress, venting of the
boiler, including the vent from the constant head overflow, should be to
the outside of the building into an area inaccessible to personnel.
1.6.3.9 Inspection
Thorough inspection of the plant, as far as practicable, shall be carried
out at the end of the cleaning process, giving due regard to the
precautions given in Sect. 5, ‘Safety Aspects’.
1.6.4 Chemical Aspects
Given that there have been problems of degradation of inhibitors in
storage, it would be advisable to check the age and batch number of the
chemical used. Apply the inhibitor efficiency test before use.
1.6.4.1 Chemical Requirements
As some cleanings require additional amounts of chemicals (principally
for iron removal), a sufficient reserve should be available locally to
minimize delay to the program. This is particularly important for the
first cleaning in a boiler’s history or after a change of operating regime
(e.g. from base-load to two-shifting).
Appendix A: The Operational and Safety Aspects of Chemical Cleaning … 155
Notes:
1. This procedure may be unsuitable for large vessels (e.g., DC heaters) because
of weight support limitations.
2. After water flushing has been completed, the plant shall either be dried out or
put in wet storage, unless the flushing immediately precedes a further stage of
cleaning.
3. Water flushing shall be carried out using deionized water if austenitic
components are present or for once-through boilers. If any other plant is given
a preliminary flush with filtered water, it shall be thoroughly flushed out
afterward with deionized water, except where it is to be followed by a chemical
cleaning process.
1.8 Protection of the Plant After Cleaning
1.8.1 The Need for Passivation
After the steel surfaces have been chemically cleaned, they are very
‘active’ and subject to rapid rusting. It is, therefore, necessary to passivate
the cleaned metal surfaces to prevent their deterioration. Operation
immediately after passivation is the best means of establishing the
protective oxide film.
Appendix A: The Operational and Safety Aspects of Chemical Cleaning … 157
Notes:
1. Experience shows that provided the system has been lagged, the temperature
should not have fallen below 75 °C before cleaning has been completed, when
using ammoniated citric acid, or 50 °C with hydrofluoric acid/hydrochloric
acid.
2. The reasons for raising pH above 5.0 are:
(i) To minimize corrosion of the plant after cleaning, but before displace-
ment of acid.
(ii) To avoid corrosion in discharge points and culverts.
160 Appendix A: The Operational and Safety Aspects of Chemical Cleaning …
1A-III. 1.4 Citric acid rinse is carried out using 0.1 % W/W citric acid with
a of pH 3.5–4.0. The second rinse with citric acid is done at a
temperature of 65 °C. This step is to ensure a more thorough
iron removal.
1A-III. 1.5 Drain the citric acid solution under nitrogen capping.
1A-III. 1.6 Carry out neutralization using a neutralizing solution contain-
ing 8000 ppm of trisodium phosphate, (Na3PO4 12H2O) and
4100 ppm of disodium phosphate (Na2HPO4 7H2O) at a
pressure of 7 kg/cm2. Hold the pressure for about 2 h
Neutralization can also be done using 1 % soda ash solution at
85–90 °C for about 6 h.
1A-III. 1.7 Switch off the fires. Allow boiler to cool gradually. Open the
drum vents when the drum pressure drops to 1–2 kg/cm2. Drain
the boiler when the drum temperature drops to below 100 °C.
full load steam flow. ASME PTC 4.1/BS-2885 gives a method for
calculating sizes of pipework, and pressure and temperature
conditions necessary for steam purging the super heater, reheater,
and steam pipework together with the necessary chart. Because
there is now a computer program available for carrying out the
required calculations, practical guidance, based on experience on
steam purging at many stations, is also included.
1B-2 During steam blowing, there is an increased risk of water carryover
because the pressure drop which occurs is higher than during
normal operation. To minimize the risk of stress corrosion, sodium
hydroxide must not be added to the boiler water during steam
blowing. The boiler is initially filled with 50 mg/kg hydrazine and
50 mg/kg ammonia. No further additions of hydrazine are required,
but 50 mg/kg hydrazine and 50 mg/kg ammonia should be added to
the make-up water to the boiler to react with dissolved oxygen.
Before commencing the steam blowing process, it must be proved
that all cleaning chemicals have been thoroughly flushed from the
boiler water circuit. The boiler water should not contain more than
0.1 mg/kg chloride (as Cl−) or 0.2 mg/kg sodium (as Na+).
2.4.1.3 In the on-load method, the pH of the cooling water entering the
condenser is decreased by acid dosage to about 2–2.5. The buffering
capacity of the cooling water, together with the large volume of the
system restrict the change of pH elsewhere in the circuit.
2.4.2 Choice of Acid
While in principle any of a large number of acids may be used to
remove the scales found in condensers, hydrochloric and sulfuric acids
are recommended because in addition to being inexpensive and readily
available, they were used satisfactorily in investigational studies of this
subject. Of these two, hydrochloric acid is recommended only when the
whole condenser is isolated, (i.e., in an off-load cleaning). Where there
is any possibility of contamination of the feed water by the cleaning
solution, as in reduced-load or on-load methods, then only sulfuric acid
is to be used. For SS tubes, sulphamic acid, although costly, is also
being used.
2.4.3 Inhibition
2.4.3.1 The three basic methods of cleaning impose quite different requirements
for inhibition and these are influenced by the materials of construction
of the plant and by the estimated long-term frequency of cleaning. By
the use of inhibitors, acceptable conditions can be achieved in respect of
the corrosion of water boxes and tubes, as well as restraint of galvanic
attack and copper deposition and dezincification. The use of either
recommended inhibitors. Armohib 28 or Armohib 533 or equivalent
suppresses copper deposition in the water box and also counteracts
galvanic corrosion. Recommendations for inhibitor requirements are
given in Appendix 2D.
2.4.3.2 The degree of risk to condenser integrity is related to the frequency of
cleaning.
2.4.4 Selection of Cleaning Processes
To aid in the selection of a suitable cleaning process, logic is given in
Appendix 2E.
2.4.5 Practical Considerations
2.4.5.1 Terminal Points
Suitable terminal points can be made as branch connections, so that
rigging can be carried out on-load and subsequent flushing can take
place without delay.
2.4.5.2 Circuitry
Where appropriate, the water boxes should be connected in series into a
circuit containing a tank and pump, the water box vents being fitted
with temporary connections back to the chemical mixing tank.
Appendix A: The Operational and Safety Aspects of Chemical Cleaning … 173
2.5.3.3 Experience to date has shown that a solution containing Na4EDTA and
0.7 % oxalic acid has sufficient capacity to cope with most of the
condenser steam side deposits encountered. If oil is present, 10 % v/v
degreasant and 1 % v/v ethomeen S25 has been found to be adequate.
2.5.4 Exclusion of Oxygen
2.5.4.1 Corrosion inhibitors are unnecessary provided air (oxygen) is excluded
from the cleaning circuit.
2.5.5 Practical Considerations
Experience has shown the need for full consultation between cleaning
contractors, stations and if appropriate, specialist advice should be
sought prior to cleaning. Among the factors to be considered are:
2.5.5.1 Water Requirements
2.5.5.1.1 During the cleaning, there will be a requirement for large quantities of
high quality demineralized water for preparing solutions and rinsing.
Water containing a significant concentration of calcium must not be
used, as this would cause a precipitation of calcium oxalate and a
subsequent rise in solution pH.
2.5.5.1.2 Although the clean is carried out at ambient temperatures, if possible, a
supply of high quality hot water (e.g., blow-down) should be available
to facilitate more rapid dissolution of oxalic acid crystals when the
cleaning solution is being prepared.
2.5.5.2 Temporary Holding Tanks
Sufficient temporary holding tanks must be provided to hold the
pre-mixed solution prior to transferring it to the condenser, and to hold
the effluent when the cleaning is completed.
2.5.5.3 Mixing Procedure
2.5.5.3.1 Prior to mixing is necessary to prepare a concentrated (approx. 10 %
v/v) solution of oxalic acid and to add the surfactant to the degreasant.
To save process time, both these procedures may be carried out off site
by the cleaning contractor prior to the cleaning.
2.5.5.3.2 If the degreasant/surfactant mix is prepared on site, this mixture must be
continuously agitated prior to use to ensure complete dispersal of the
much denser surfactant.
2.5.5.3.3 Mixing shall be carried out in the following order:
1. Dilute Na4EDTA concentrate.
2. Carefully add, with further dilution, concentrated oxalic acid
solution.
176 Appendix A: The Operational and Safety Aspects of Chemical Cleaning …
The system is refilled with raw water and circulated at 4–5 kg/cm2
pump pressure and drained. Mass flushing is finally done with CW
pumps in service.
4.2.5 Fluoride
Determine using a fluoride ion selective electrode and an epoxy bodied
reference electrode.
4.2.6 Alkalinity
Take a 100-mL sample, add pH 4.5 indicator and titrate with 0.1 M nitric
acid.
g/kg NaOH = Titre × 0.4.
4.2.7 Sodium
Sodium may be measured flame photometrically. Instruments giving a
full scale deflection for 5 mg/kg or less of sodium will be satisfactory, and
should be operated in accordance with the manufacturer’s instruction.
4.2.8 Total Iron in Citric Acid, Hydrochloric Acid, or Hydrofluoric Acid
4.2.8.1 Dilute the sample to give a final iron concentration in the range
0–60 mg/kg (3 % citric acid saturated with iron will have an approximate
iron concentration of 8500 mg/kg). For most analysis, a hundred-fold
dilution will be adequate. With hydrofluoric acid, dilute with 2 % boric
acid to protect glassware.
4.2.8.2 Determine the total iron by atomic absorption directly on the diluted
sample or take 50 mL of the diluted sample, add 0.5 thioglycollic acid
and 5 mL excess of 0.880 ammonia. Make up to 100 mL. Measure the
colour using a 10 mm cuvette and a 605 filter. Read off the total iron
concentration from a calibration graph prepared under identical
conditions
Total iron and total copper may also be determined by titration method.
For iron 5 mL of filtered sample and dilute with 25 mL of DM water.
Add 2 % KMnO4 solution dropwise till permanent pink colour appears.
Add 15 % hydrazine sulphate solution dropwise till pink colour
disappears. Add 2 drops in excess. Add 5 g of KI crystals and stopper
the flask. Allow to stand for 5 min. Titrate the liberated iodine with 0.1 N
sodium thiosulphate solution using starch indicator.
The method for copper determination is same as for iron except that
before the addition of KI crystals 5 g of ammonium bifluoride is to be
added and mixed well.
4.2.9 Ferric Iron in Citric Acid or Hydrochloric Acid
4.2.9.1 Take 25 mL sample and adjust the pH to 2.5 with approximately normal
Na2C03 solution
4.2.9.2 Dilute the solution to 100 mL and add five drops of 5 % sulphosalicylic
acid solution. Titrate with 0.1 M EDTA until the pink colour just
188 Appendix A: The Operational and Safety Aspects of Chemical Cleaning …
disappears. Add a further five drops of indicator and continue the titration
until the pink color disappears
g/kg Fe 3+ = Titre × 223.
4.2.10 Nickel
Place 2 mL of the sample in a separating funnel, add four drops of 10 %
hydrogen peroxide solution, and two drops of phenolphthalein solution.
Then, add 5 mL of 10 % sodium potassium tartrate and mix the contents.
Add 2.5 N sodium hydroxide solution drop-wise until the phenolph-
thalein just turns pink and then add 0.1 N hydrochloric acid drop-wise
until the colour is just discharged. Add 5 mL of 0.15 %
furil-alpha-dioxime followed by 25 mL of 2 N ammonia solution. Swirl
the contents of the flask to mix, and add 15 mL of the chloroform through
a filter paper and measure the absorbance in a suitable size cuvette.
Determine the nickel content from a calibration curve.
4.3 Methods of Analysis to be Used During the Post-operational Cleaning
of Condensers
The iron, copper, zinc, and nickel content of samples of the chemical
cleaning liquor can be determined by atomic absorption
spectrophotometry/suitable equipment available at site using standard
instrument operating conditions.
4.3.1 Instrument Calibration
4.3.1.1 Prepare separate series of calibration standards by appropriate dilution of
1000 mg/kg stock containing:
(i) Iron: 0, 10, 20, 30, 40 and 50 mg/kg Fe
(ii) Copper: 0, 5, 10, 20, 30 and 40 mg/kg Cu
(iii) Zinc: 0, 0.5, 1, 2, 3 and 4 mg/kg Zn
(iv) Nickel: 0, 2, 4, 6, 8 and 10 mg/kg Ni
in 2 % v/v ‘AR’ nitric acid
4.3.1.2 Measure the absorbance of each standard, using the manufacturer’s
recommended instrument conditions, at the following wave lengths:
(i) Fe: 372.0 nm
(ii) Cu: 217.9 nm
(iii) Zn: 213.9 nm
(iv) Ni: 232.0 nm
and construct calibration curves for reference purposes.
4.3.1.3 When used in conjunction with the following analytical procedure, the
above concentrations will correspond to 0–2500 mg/kg Fe; 0–2000 mg/kg
Cu; 0–200 mg/kg Zn, and 0–500 mg/kg Ni in the original cleaning liquor.
Two procedures are available, one for determining total metal removed in
Appendix A: The Operational and Safety Aspects of Chemical Cleaning … 189
a clean and the other for following the progress during the chemical
cleaning operation
4.3.2 Determination of the Total Amount of Iron, Copper, Zinc, and Nickel
Removal in a Cleaning
Mix the final cleaning liquor sample well. Transfer 5 mL of the sample to
clean dry 50 mL conical flask. Add 5 mL concentrated nitric acid (AR).
Heat to boiling on a moderate hot plate and gently reflux for 15 min with
occasional swirling of the flask. Allow to cool and add approximately
30 mL deionized water. Warm the solution on a hot plate and transfer the
contents of the flask quantitatively to a clean 250 mL graduated flask.
Dilute to the mark with deionized water and mix the solution well.
Determine the Fe, Cu, Zn, and Ni content solution by atomic absorption
spectrophotometry using the instrument operating conditions and cali-
bration procedure previously described.
4.3.3 Rapid Method for Following the Progress of the Chemical Cleaning
Operation
Transfer 5 mL of the chemical cleaning liquor (free from suspended
matter) to a clean 250 mL graduated flask. Add 5 mL ‘AR’ concentrated
nitric acid, dilute to the mark with deionized water and mix well.
Determine the Fe, Cu, Zn, and Ni content of the sample by atomic
absorption using the instrument conditions and calibration procedure
described above.
(continued)
Determinant Solution Method
Armohib 28 Acid cleaning Colorimetric
Bromate/copper Alkali cleaning Titration
Nitrite Copper stripping Colorimetric
Nitrite Flushing Colorimetric
Copper Alkali cleaning Colorimetric
Trisodium phosphate Alkali boil-out Titration
Phosphate Cleaning Colorimetric
Phosphate Alkali boil-out Colorimetric
Hydrazine Water Colorimetric
consult with the medical service (normally the Nursing Officer) with
respect to first-aid facilities. Supervision of the required safety precau-
tions by the Station Chemist shall also include supervising the chemical
cleaning contractor’s employees and any failure to comply with the safety
requirements shall be notified immediately to the Project Site Manager or
Location Manager as appropriate. The Supervising Officer or his deputy
shall be present at the scene of operation whenever chemicals are being
received or are in the cleaning system or during subsequent inspection
5.2.1.2 The Station Chemist shall ensure that chemicals are introduced in the
correct manner to the cleaning circuit and that the ventilation and
temperature requirements before entry into the plant for inspection or
working have been complied with (see 5.2.6)
5.2.2 General Philosophy
5.2.2.1 The manual handling of chemicals should be avoided as far as practicable
and wherever possible, mechanical methods should be used for
transporting, dispensing, and transferring chemicals
5.2.2.2 Protective clothing for skin and eye protection must be worn and if not
adequately ventilated, breathing apparatus must be worn when:
(i) Mixing chemicals
(ii) Dealing with leaks, spillages, splashes and
accumulated vapors
(iii) Approaching the plant
(iv) Post-cleaning inspection is carried out
5.2.3 General Precautions and Personal Hygiene
Wherever and whenever there is danger of contact with chemicals, all
personnel must:
(i) Be warned of the nature of the potential hazards and the necessary
precautions and be instructed in the correct use of protective
clothing and equipment by the Supervising Officer
(ii) Observe a high standard of personal hygiene avoiding contact with
chemicals, their vapors or contaminated residues
(iii) Not eat, drink, or smoke
(iv) Avoid wiping nose, eyes or face other than with clean paper tissues
(v) Place all debris and chemical residues removed from the plant in
clearly labeled polythene bags for subsequent disposal
(vi) On leaving the plant, remove their protective clothing for cleaning
before re-use, and clean themselves and their equipment, using
disposable materials
(vii) Wash thoroughly as soon as possible after leaving the operational
area (see 5.2.8)
192 Appendix A: The Operational and Safety Aspects of Chemical Cleaning …
5.2.5.3 Whilst chemical cleaning operations are in progress, venting of the boiler,
including the vent from the constant head overflow, must be to the outside
of the building, inaccessible to personnel and well away from other vents
or intakes to avoid the possibility of vapor reentering the building
5.2.6 Approach to the Plant (Excluding Bodily Entry) After any Stage of
the Cleaning Process
5.2.6.1 When the plant is to be opened up after the passivation stage or after any
acid stage during the process, the precautions given in 5.2.6.2–5.2.6.6
shall be observed
5.2.6.2 The chemical cleaning circuits must be drained to the approved disposal
point taking care to minimize spillage, splashing of solutions or
accumulation of vapor. If chemicals are drained into a holding vessel,
care must be taken that mixing of chemicals from different stages does not
occur in the vessel. It is particularly important to avoid acidifying
solutions containing nitrite or bromate, or mixing strong acids and alkalis
or strong oxidizing and reducing agents
5.2.6.3 Vapors issuing from plant openings should be dispersed by blowing clean
air through the access point using the best possible ventilation to obtain a
high dilution rapidly. The breaking open of access points should be
carried out by personnel wearing an approved type of overall and gloves
and breathing apparatus incorporating a hood to give a full protection to
the head. Suitable equipment is given in Appendix 5B. Contact with
surfaces which are or have been wetted by chemicals should be avoided
as far as is reasonably practicable
5.2.6.4 Components which are contaminated with chemicals should be placed on
impervious sheets for cleaning prior to replacement
5.2.6.5 Personnel should not expose themselves to risk by making a quick
observation of the plant interior (without bodily entry) when the access
points are first opened
5.2.7 Entry of Personnel into Plant That has been Chemically Cleaned
5.2.7.1 The precautions given in 5.2.7.2–5.2.7.5 are necessary if entry is to be
made into the plant after any acid cleaning or passivation stage in the
process
5.2.7.2 Entry to the plant shall be restricted to the minimum number of people
necessary. During the time that personnel are inside the plant, a stand-by
man must be positioned at the point of entry
5.2.7.3 Before entering the plant after chemical cleaning, either after the
passivation stage at the end of the process, or after any acid stage during
the process, or to carry out reinstatement work such as the removal of
flow restrictors, there must be an absolute minimum delay of 3 h after
194 Appendix A: The Operational and Safety Aspects of Chemical Cleaning …
opening all entry points, unless full protective clothing is worn and an
air-line breathing apparatus is used. During this period, ventilation of the
plant should be carried out at a rate of at least ten air changes/h using a
filtered air supply. It is essential that this 3-h delay period is observed,
even if a higher ventilation rate is adopted. Ventilation of the plant at a
rate of at least 10 air changes per hour should be continued while
personnel are in the plant for inspection or to carry out reinstatement work
such as removal of flow restrictors
5.2.7.4 Additionally before personnel enter plant, the temperature should be
ambient temperature. If the conditions above in 5.2.2 and 5.2.5 have been
fully complied with personnel can enter the plant wearing coveralls,
gloves, and carefully fitted eye-goggles as detailed in Appendix 5B.
Where such conditions have not been fully complied with, personnel
entering the plant must wear overalls, PVC gloves, rubber boots, a
breathing apparatus, and hood attachment giving full protection to the
head as detailed in Appendix 5B
5.2.7.5 Removal of debris or chemical residues from the plant must be carried out
by personnel wearing full protective equipment and in such a manner as
to avoid contamination of external surfaces. The residues should be
extracted into impervious containers which are then passed to persons
wearing gloves and goggles, as detailed in Appendix 5B
5.2.8 Exit of Personnel and Materials from Plant Containing Hazardous
Residues After Chemical Cleaning
5.2.8.1 The personnel collecting debris and chemical residues must place them in
clearly labeled polythene bags within the plant
5.2.8.2 For disposal, debris and chemical residues must be washed into a system
where considerable dilution can be achieved. Equipment used for
handling chemicals and the inhibitor must also be cleaned after use by
washing into a disposal system where considerable dilution can be
achieved (see 5.2.9)
5.2.8.3 The same personal clothing should be used until the end of the work
period on which a particular operator is engaged and then thoroughly
cleaned. Upon leaving the plant, the operator should remove the
protective clothing for subsequent cleaning before re-use and proceed
directly to the showers, paying particular attention to washing the hands
and face
5.2.9 Disposal of Chemical Waste
Disposal of all surplus solutions and chemical waste must be by an
approved route. The appropriate waste disposal and water authorities
should be consulted.
Appendix A: The Operational and Safety Aspects of Chemical Cleaning … 195
Notes:
1. Where Emergency Action is Required For Dealing With Spillage Or
Escape Of Chemicals, Maximum Ventilation and Water-Washing
Facilities Must Be Used
2. Personnel using self-contained and air-line breathing apparatus must
be properly trained and experienced in the use of such apparatus
3. The standard procedure outlined in documents with regard to the
removal of protective clothing must be strictly observed
4. Particular care must be exercised when opening drums of 0.880
ammonia solution, particularly where these have been in a warm
atmosphere, because the contents are likely to be under pressure
5.3 Boilers, Super Heaters, Reheaters, and Feed Systems
Where there is a choice, preference should be given in using inhibitors
having a lower perceived risk.
5.3.1 In addition to the safety considerations given for all items of plant, the
following specific provisions apply to the chemical cleaning of boilers,
super heaters, reheaters, and feed systems
5.3.2 The substituted thio-ureas present in some inhibitors specified in
Appendix IF can lead to the formation of carbodiimides, which cause
temporary blindness and sensitivity to light. To minimize the risk of eye
toxicity, it is essential to adhere to the recommendations in Sect. 5.2, ‘All
Items of Plant’, particularly regarding the addition of the inhibitor to the
cleaning solution (5.2.5) and approach and entry into the plant (5.2.6 and
5.2.7). The recommendations on supervision (5.2.1) handling, storage,
and disposal of chemicals (5.2.2, 5.2.4, 5.2.5 and 5.2.9) must be strictly
observed
5.4 Condensers
5.4.1 Cooling Water Side
5.4.1.1 The provisions given in Sect. 5.2 also apply to the chemical cleaning of
the CW of the condensers
5.4.1.2 While it is believed that eye toxicity due to carbodiimide is not possible
with the inhibitors currently specified for condensers in Appendices 2D
and 2E, it is nevertheless essential to flush out all traces of inhibitor using
the full flow of the main CW pumps for at least 3 h before entering the
plant. The precautions during cleaning (5.2.5) and the approach and entry
into the plant (5.2.6 and 5.2.7) must be strictly applied
196 Appendix A: The Operational and Safety Aspects of Chemical Cleaning …
5.4.1.3 The health precautions stated in the IS Safety Code of Practice on the
maintenance of cooling water and other auxiliary water must be followed
to minimize the risk of infection from Legionella
5.4.2 Steam Side
Inhibitors are not used in current practice for cleaning the steam side of
condensers, therefore, no special precautions are required in this respect.
5.4.2.2 However, large volumes of acid cleaning liquids and solvents are used
and the provisions given for supervision (5.2.1). Handling storage and
disposal of chemicals (5.2.2, 5.2.4 and 5.2.9) must be applied. Some
solvents are flammable and/or toxic, and precautions must be taken to
ensure that no explosion hazard or toxicity risk can arise. Ventilation
equipment should be selected and positioned taking into account risks to
personnel and explosion risks in accordance with ‘National Power Safety
Rules Code of Practice in Confined Spaces’
5.5 Feed Heaters
The provisions given for supervision (5.2.1); the addition of inhibitors to
the cleaning solutions (5.2.5); approach and entry into the plant (5.2.6 and
5.2.7), and the handling, storage, and disposal of chemicals (5.2.2, 5.2.4
and 5.2.9) must be strictly observed. Solvents are also used and
precautions must be taken to ensure that no explosion hazard can arise
and that the plant is suitably ventilated to prevent risks to personnel (see
5.4.2.2).
(continued)
Chemicals OEL (note 1) Main hazards Special storage
requirements
Citric acid Powder and solution can cause eye Store away from
injury oxidizing agent
Chromic acid 0.05 mg/m3 Can cause severe burns Store away from
(as Cr) Can cause violent oxidizing agents and
explosion in contact with reducing any fire risk
agents
Dipotassium hydrogen Produces toxic, irritant fumes when
phosphate heated
Disodium hydrogen Produces toxic, irritant fumes when
phosphate heated
Ethomean S25 – Skin and eye irritant (See Supplier's
data sheet)
Formic acid 5 ppm Corrosive. Can cause severe burns Store in a
well-ventilated area
Inhibitors (Armohib 28, Can cause skin and eye irritation –
Hibron armohib 533, (some severe). Some combus-
Stannine LTP, Dodigen Tible/toxic/corrosive
95, etc.) Rodine, Lith
solvent, coronil. etc.
Hydrazine 0.1 ppm Strongly caustic. Irritant Store separately. See
May cause damage to liver and national safety code of
kidneys practice GS-C1 0.15
Hydrochloric acid 5 ppm Corrosive and irritant. Store in a
well-ventilated area
Hydrogen peroxide 1 ppm Oxidizing and corrosive Store separately, and
Can cause severe damage to eyes away from all
and skin combustible materials in
May explode in contact with dust a cool area
Hydrofluoric acid 3 ppm Toxic and corrosive. Can cause Store in a
severe burns well-ventilated area
Nitric acid 2 ppm Oxidizing and corrosive can cause Store away from acetic
severe burns acid, ammonia and
combustible materials
Oxalic acid 1 mg/m3 Corrosive. Avoid breathing dust or Store away from
vapor oxidizing agents
Potassium hydroxide 2 mg/m3 Highly corrosive. Irritant. Inhalation Severe store away from
(caustic potash) (Note 2) of dust or mist causes intense acids
irritation
Potassium or sodium – Eye/skin irritant, with acid solutions Store away from acids
dichromate toxic gases can be produced and combustible
materials
Possible explosion hazard on contact
with organic materials
(continued)
198 Appendix A: The Operational and Safety Aspects of Chemical Cleaning …
(continued)
Chemicals OEL (note 1) Main hazards Special storage
requirements
Potassium or sodium – Oxidizing agent. Eye/skin irritant. Store away from acids,
bromate With acid solutions toxic gases are combustible materials
produced and ammonia
Possible explosion hazard with
ammonia and contact with organic
materials
Potassium or sodium – Eye/skin irritant. With acid solutions Store away from acids
chromate toxic gases can be produced. and combustible
Possible explosion hazard on contact materials
with organic materials
Potassium or sodium Eye skin irritant with acid solutions Store away from acids
nitrite nitrons fumes are produced. Possible and combustible
explosion hazard on contact with materials
organic materials
Sodium carbonate (soda Skin irritant. Dust or mist, irritating Store away from acids
ash) to upper respiratory tract
Sodium fluoride 2.5 mg/m3 If heated or in contact with acids, Store away from acids
(as F) emits highly toxic fumes and combustible
materials
Sodium hydroxide 2 mg/m3 Highly corrosive. (note 2) irritant. Severe store away from
(caustic soda) Dust acids
or mist can cause irritation to upper
respiratory tract
Sulphamic acid – Emits toxic fumes when heated. Store away from heat
Irritant
Sulphuric acid 1 mg/m3 Extremely irritant and corrosive. Store away from alkalis
Cause severe burns
Tetra sodium ethylene – Concentrated solution is caustic. Store away from acids
diamine tetra Skin
acetate and eye irritant
Tripotassium phosphate – Skin irritant. If heated highly toxic –
fumes
Trisodium phosphate – Skin irritant. If heated emits highly –
toxic fumes.
Wetting agents – May cause eye and skin irritation –
(Dissapol, Teepol, etc.)
Notes
1. OEL—Occupational Exposure Limit (8-h TWA value)
2. Confirm by reference to the most recent HSE Guidance Note eH 4016
Appendix A: The Operational and Safety Aspects of Chemical Cleaning … 199
(continued)
Conditions Protective equipment
5B-3 (i) For entry into plant after chemical a. Compressed air-line breathing apparatus
cleaning in which the requirements for b. One-piece cotton/polyester overall with
inhibitor additions and ventilation and hood or one-piece disposable PE-coated
temperature have been fully complied with tyrek
c. PVC gloves
d. Rubber boots (molded)
(ii) When breaking open access points a. Compressed air-line breathing apparatus
after chemical cleaning (if entry also required).
b. Open-circuit self contained breathing
apparatus (if entry not required)
c. One-piece cotton/polyester overall with
hood or one-piece disposable Tyrek
d. PVC gloves
e. Rubber boots (molded)
(iii) Where contact with vapor and As per 5B.3 (ii)
merging from drains or vents during a
chemical process is unavoidable
(iv) Where severe spillage or escape of the a. Open-circuit self-contained breathing
following chemicals has taken place: apparatus
Sodium bromate, Nitrous fumes, b. Compressed air-line breathing
Stannine LTP and Armohib 28
c. PVC gloves
d. Rubber boots (molded)
e. One-piece cotton/Polyester coverall
with hood or one-piece disposable overall
in PE-coated tyrek (alternatively, PVC
chemical splash suit)
5D-2.3.3 Place the test vessel in a constant temperature bath and allow it to
equilibrate to the test temperature.
5D-2.3.4 Weigh the coupon to the nearest tenth of a milligram. The coupon
should not be added to the test vessel containing the solution until
the solution reaches the test temperature. Totally immerse the
coupon in the test solution. Any supports or hangers used should
be electrically nonconductive material.
5D-2.3.5 The duration of test should be 6 h.
5D-2.3.6 Duplicate tests must be performed to confirm results and to
minimize the possibility of random errors. Duplicate tests should
be conducted separately so that any errors made in one test will not
be repeated in duplicate.
5D-2.3.7 After completion of the test, rinse the coupons in DM water and
then rinse them with acetone or methanol to remove the inhibitor
film. Scrub the test coupons using a nylon brush and soap solution.
Rinse with DM water and follow with an acetone or alcohol rinse
to replace the water and dried in oven at a temperature of about
105 °C for about 15 min. Store the coupons in a desiccator for a
minimum period of 1 h prior to re-weighing.
5D-2.3.8 Calculation of Corrosion Rate
After cleaning, the coupon should be re-weighed to the nearest
tenth of a milligram. The corrosion rate, as on average penetration,
based on weight loss should then be calculated in the units of
mg/cm2/h.
5D-2.3.9 Criteria for Acceptance
The weight loss should not be more than 0.1 mg/cm2/hr at 65 °C
for carbon steel and mild steel sample.
5D-3 Field Test Method
A small ball of steel wool (about 0.1 gm) is degreased with
acetone and added to a sample of inhibited acid solution in the acid
tank solution during cleaning process.
5D-3.1 Criteria
Inhibitor efficiency is judged to be adequate if the wire wool ball
does not float after 1 min in ammoniated citric acid or after 2 min
in hydrochloric acid.
204 Appendix A: The Operational and Safety Aspects of Chemical Cleaning …
5D-4 Notes:
1. The expiration date of the inhibitor is to be checked before
starting use.
2. In the event that the test fails, the test is to be conducted at a
higher concentration so as to conclude at what concentration
the efficiency is acceptable and accordingly concentration of
inhibitor in acid cleaning procedure is to be adopted.
Appendix B
Fire Protection of Power Stations
1.0 Introduction
Plant is exposed to onerous operating conditions and the combinations of
flammable material in large quantities and ignition sources which can lead to
the incidence of fires. This Guidance Note applies the principles and gives
specific recommendations to achieve a satisfactory level of protection,
methods to prevent fires, and routine checks/maintenance jobs for operational
station at risk from fire.
2.0 Any previous Guidelines
Nil
3.0 Scope
This Guidance Note is specifically geared at fixed fire detection and
protection systems. The provision and use of portable equipment, such as
hose pipes/reels and extinguishers by a fire fighting team is covered by the
TAC/CISF Fire Manual.
Recommendations are made for prevention/detection/protection against fire,
for inspection, for testing and maintenance, and for operational needs
pertaining to the fire detection and protection equipment.
4.0 Fire Hazards and Prevention
The various hazards in a power station and the methods to prevent these are
given in the following table.
(continued)
S. No. Area Fire hazard Fire prevention
4.4 Coal bunkers 1. Feeding of hot coal from 1. Residual, compacted coal should
stockyard, which may be about be avoided in bunkers and bunkers
to burn should be emptied and cleaned
2. Residual coal sticking to thoroughly during overhaul of unit
bunker walls for a long periods 2. Bunker gates to be maintained to
resulting in self-ignition ensure that they close properly
3. Any draught of air through when bunker is not in use
the coal in bunkers, particularly 3. Hot coal should not be fed into
compressed air from air blast the bunkers from stockyard
equipment 4. System of hot work permit to be
4. Low bunker level coupled followed during welding/cutting job
with unsatisfactory isolation in bunker floor
from feeder/mill with 5. Availability of bunker level
subsequent pressurization of indication along with annunciation
furnace causing hot gases to for low bunker level to be ensured
pass through the bunker
5. Bunker conveyor fires
4.5 Coal feeders 1. Hot or burning coal passing 1. Routine cleaning of feeder from
from coal bunkers inside to reduce extent of residual
2. Fires in mills particularly coal left compacted in dead spaces
during start-up or shut-down within the feeder
periods 2. Bunker gates and mill dampers to
3. Friction due to mechanical be maintained to prevent passage of
failure combustion products from fires into
4. Welding/gas cutting etc. the feeders or elsewhere in the
5. Residual coal in pockets of system
feeder 3. The system of hot work permit to
be strictly followed during
welding/gas cutting jobs
4. Periodic checking of feeder
protection on “No coal on belt” to
be ensured
4.6 Coal mills and P. 1. High mill outlet temperature 1. Appropriate fire detection system
F. piping due to coal flow interruption to be maintained in both running
2. Low level of coal in ball and standby mills
mills 2. Instrumentation of
measuring/maintaining level of coal
in ball mills and of measuring
sound level to be maintained
3. Proper start-up and shut-down
procedures to be maintained
4. Mill inerting system to always be
kept in service
5. Auto closing of HAG from mill
outlet temperature high protection
is to be kept in service
(continued)
208 Appendix B: Fire Protection of Power Stations
(continued)
S. No. Area Fire hazard Fire prevention
4.7 Boiler burner 1. Ignition of preheated fuel oil 1. Steam pipes for oil atomization
fronts on hot boiler casing/steam pipes are to be thoroughly insulated
2. Rupture of flexible hoses 2. Prompt attention to defects on
3. Leakage of PF pipes burner connecting hoses and pipe
4. Faulty ignitors coupled with work
leaking oil 3. No spillage of oil around burner
area during removal of burner
carrier for tip cleaning. In case of
oil leakage, soaked insulation to be
removed and re-insulation to be
completed
4. Minimum electrical
equipment/cables/junction boxes
near burners to be located
5. Ignitor faults to be immediately
attended
6. Oil waste, rag, and combustible
materials should not to be allowed
to accumulate
7. Periodic checking of igniter
effectiveness to be done
4.8 Fuel oil storage 1. Greater risk during venting, 1. Precautions to be taken during
tanks gassing, and filling operations tank emptying, cleaning, tank
of light fuel oil inspections, vent inspections, and
2. Leakage of tank other maintenance work (including
3. Dry grass around tanks electrical/lighting work).
4. Oil spillage Welding/cutting to be avoided. If
5. Unclean surroundings carried out, all precautions must be
6. Soaked insulation taken
7. Electrical tracing 2. Entry to bunded area to be
restricted to authorized persons
only
3. Filling lines to be purged and
road tanker connections should be
kept secure when not in use
4. Recycled oil to be cooled to
below the flash point before
returning to storage tanks
5. Excess temperature safety
systems and alarms to be installed
on heater banks
6. All areas within the bund walls
must be free of vegetation and other
combustible materials
(continued)
Appendix B: Fire Protection of Power Stations 209
(continued)
S. No. Area Fire hazard Fire prevention
4.9 Fuel Oil unloading 1. Oil spillage or leakage due to 1. There should be adequate
and transfer pump failure of joints or of venting ventilation in the enclosed pump
house due to overheating or house to keep the concentration of
restrictions in system oil vapors within safe levels
2. Heaters 2. Proper smoke vents and
3. Loosely laid electrical adjustable louvers at high and low
cables/welding cables level
4. Drain oil stagnant in 3. Proper earthing of all electrical
unloading pipe trenches and systems
surface drains 4. Use of flame proof
lighting/electrical appliances only
in the pump house
5. Trenches to be filled with sand
and PCC on top to prevent
contamination with oil
6. Oil waste, rag, other combustible
materials not to be allowed to
accumulate
7. No spillage of oil
8. Prompt attention to defects on oil
pipes and heaters etc.
9. If used, oil absorbing granules
should be removed immediately
after use. Wood dust not to be used
as it is an oil-absorbing medium
4.10 Naphtha tanks and 1. Leak in the system, whether 1. Gas leak detection system to be
piping from bulk storage, the kept operational
distribution network, control 2. Entry to storage areas should be
valves, or naphtha pipelines at restricted to authorized persons
combustion chambers only
2. Venting or leaking Naphtha 3. Areas around tanks to be kept
gas getting ignition due to free of vegetation and any other
discharge of static electricity combustible materials
during tank filling 4. Earthing of tanks, other
equipment to be checked regularly
5. Filling lines to be purged and
road tanker connections to be kept
secure when not in use
6. Prompt attention to leakage
defects
4.11 Regenerative Air 1. Carry over of unburnt liquid 1. Frequent inspection and water
Heaters fuel onto the internal heat washing of air heater
exchanger surfaces during cold 2. Soot blowing of air heaters
start-up specially during start-up
2. Slow build-up of deposits of immediately after bringing boiler
unburnt fuel in the absence of into service and cleaning regularly
soot blowing for a period of at least once per shift at a minimum
time 3. Oil to be burnt with maximum
attainable efficiency in the furnace
by appropriate cleaning and
adjustment of burners to minimize
the quantity of unburnt particles,
elimination of tramp air, and
consequent chilling of the flame and
(continued)
210 Appendix B: Fire Protection of Power Stations
(continued)
S. No. Area Fire hazard Fire prevention
by ensuring that combustion
chambers are gas tight
4. Air heaters can be put under
observation during light up with the
help of digital camera
5. Regular cleaning, maintenance
and testing of oil burners
6. Thermo-couple type fire
detection system which has been
found to be more reliable to be kept
in service for monitoring air heater
temperatures
7. Infra-red fire detection system,
wherever provided, also to be
maintained for prompt hot spot
detection
8. Burner flushing and testing for
their sprayer leakage and
atomization to be done
4.12 Turbine-generator 1. Minor leakage of lubricating 1. Oil leaks, if any, should be
and control fluids into collected nearest to the leak
inaccessible areas, lagging, 2. Prompt attention to oil leakages
drain trenches and coming in 3. Good housekeeping.
contact with hot surfaces Accumulation of rubbish should be
2. Heavy oil leakage in the form avoided
of spray onto bare hot metal 4. Dispensing point of flammable
caused by bursting of liquid to be kept away from turbine
pipe/flange hall
3. Leakage of hydrogen to 5. Seepage of oil into insulation
atmosphere should be avoided
4. Leakage of hydrogen into 6. Any increase in consumption of
bus duct coupled with choking hydrogen to be thoroughly
of vents of bus duct investigated and rectified
5. Cables laid near hot 7. Adequate ventilation of TG hall
equipment 8. Any welding/gas cutting work to
6. Looseness of current carrying be done only after issue of hot work
bolts, carbon brushes permit
9. Steam pipes to be thoroughly
insulated
10. In case of oil leakage, soaked
insulation to be removed and
re-insulation to be done
4.13 Mineral oil filled 1. Electrical faults inside the 1. Oil leakages to be promptly
transformers transformers including tap attended to
changer failures 2. Vegetation, rags, etc. should not
2. Oil leakage from be allowed around transformer
transformers 3. Routine checking of cooling fans
3. Bushing failure and pumps, operational parameters
4. Rupture of transformer tank 4. Soaking pit to be inspected
body caused by internal faults regularly and cleared as necessary
so as to avoid saturation
5. DGA (dissolved gas analysis) to
be done regularly for transformers,
(continued)
Appendix B: Fire Protection of Power Stations 211
(continued)
S. No. Area Fire hazard Fire prevention
and any defect indicated should be
attended to as early as practicable
6. Condition monitoring of
transformers by thermo-vision
cameras, acoustics methods should
be done
4.14 Cable 1. Overheating of cables/cable 1. Cable galleries/vaults to be kept
(a) galleries/vaults joints up to temperature clean and free of all extraneous
conditions high enough to bring combustible materials and not to be
the plasticizers of PVC used as storage and office areas
compound into a volatile state Regular inspection of cable
2. Short-circuit creating galleries
sufficient heat 2. Access to cable galleries to be
3. Accumulation of coal dust, restricted
flammable debris, cardboard 3. Proper ventilation to be provided.
packages, fuel and lubricating 4. All cable entry points to cable
oils gallery to be fire sealed
4. Welding/cutting inside cable 5. Fire barrier walls to be provided
gallery between cable tunnels of units and
5. Heating during installation of fire doors to be kept closed
heat-shrinkable cable joints 6. Loosely laid wires to be avoided
7. Lighting fittings, lighting wires to
be inspected regularly
8. No welding work to be done in
cable galleries
9. Any leakage of fuel/lubricating
oil into cable gallery to be
immediately attended
10. Ingress of coal dust from boiler
side must be avoided
11. Any overheated joint should be
repaired at the earliest
12. Proper illumination in the cable
gallery to be maintained
4.14 Cables in trays in 1. Accumulation of coal dust, 1. Cable trays to be covered with
(b) boiler area flammable debris, cardboard aluminum sheet from top
packages, fuel, and lubricating 2. Cable trays to be regularly
oils inspected and cleaned
2. Welding/cutting inside cable 3. Loosely laid wires to be avoided
gallery 4. Care to be taken during gas
3. Hot flue gas/ash from boiler cutting/welding near/above cable
furnace during furnace trays
pressurization 5. Any leakage of fuel
4. Heat radiation/high oil/lubricating oil on cables to be
temperature due to vicinity of immediately attended
furnace, p.c. pipes, hot air ducts
(continued)
212 Appendix B: Fire Protection of Power Stations
(continued)
S. No. Area Fire hazard Fire prevention
4.14 Cables in trays 1. Accumulation of coal dust, 1. Cable trays to be covered with
(c) near bottom ash flammable debris, cardboard aluminum sheet from top
hoppers packages, fuel, and lubricating 2. Cable trays to be regularly
oils inspected and cleaned
2. Welding/cutting inside cable 3. Loosely laid wires to be avoided
gallery 4. Care to be taken during gas
3. Hot flue gas/ash from boiler cutting/welding near/above cable
furnace during furnace trays
pressurization 5. Any leakage of fuel
4. Heat radiation/high oil/lubricating oil on cables to be
temperature due to vicinity of immediately attended
furnace, p.c. pipes, hot air ducts 6. Cables trays can be insulated
5. Hot bottom ash falling on with refractory material for limited
cables during abnormal lengths keeping in view derating
operation factors as per cable manufacturers
(Cables may have to be replaced by
higher size)
4.15 Switch-gears 1. Insulating oil of circuit 1. Switchgear rooms to be kept
breakers clean and free of flammable debris
2. PVC cables, epoxy resin 2. Regular inspection of switchgear
based and paxolin/melamine rooms to be done
insulating material, PVC 3. Switchgear rooms not to be used
wiring, solenoids, and plastic as storage areas or office space
encased relays 4. Proper maintenance of
switchgears and regular testing of
protection relays
5. Proper ventilation of switchgear
rooms
4.16 Gas turbines 1. Leakage of gas, Naphtha 1. Gas leak detectors to be kept in
from joints, covers etc. service always and to be regularly
2.Improper burning of liquid tested
fuel leading to its accumulation 2. Gas/liquid fuel leak should be
in the duct promptly given attention
3.Leakage of 3. Lubricating oil/jacking oil leak
lubricating/jacking oil should be attended at the earliest
possible time
4. No flammable materials should
be allowed to be stored in the
turbine hall
5. Liquid fuel should be fired to
maximum attainable efficiency
6. Good housekeeping.
Accumulation of rubbish to be
avoided
7. Dispensing point of flammable
liquid to be kept away from turbine
hall
8. Any welding/gas cutting work to
be done only after issue of hot work
permit
9. Seepage of oil into insulation to
be avoided
10. Adequate ventilation of TG hall
(continued)
Appendix B: Fire Protection of Power Stations 213
(continued)
S. No. Area Fire hazard Fire prevention
4.17 Diesel Generators 1. Leakage of fuel oil 1. Permanent natural ventilation
and Diesel 2. Lubricating oil getting should be provided in the diesel
Engines Driven overheated and leaked engine room at high and low levels
Fire Pumps 3. NRV of diesel return line to to disperse vapors and fumes
tank not working 2. Exhaust pipes should be suitably
insulated to prevent ignition of
flammable materials
3. Fuel, lubricating oil leakages
should be immediately attended to
4. Fuel tanks should preferably be
positioned outside the building
5. Instrumentation and controls of
diesel engine to be regularly
checked and maintained
6. Overloading should be avoided
7. NRV of diesel return line to tank
to be checked regularly
8. Engine oil sample to be tested
regularly
9. Battery and diesel tank should be
sufficiently apart
(continued)
SN Area Detection system Protection system Remarks
c. (i) Unit Turbine lube oil Quartzoid bulb type Automatic HVW
tanks, coolers, and heat detectors (with spray system and fire
purifiers hydraulic detection extinguishers
(ii) Turbine lube oil tank pipe network)
assembly in auxiliary
compartment of gas
turbines (design without
GT enclosure)
d. Central lube oil tanks - do - - do -
assembly and purifiers
e. Turbine lube oil pipes (in - do - (optional) Automatic HVW Feasibility to be
oil canal) spray system checked as per
(optional) layout for each
project
f. Lube oil system (tanks, - do - Automatic HVW
piping if any) of TD- spray system and fire
boiler feed pump extinguishers
g. Generator seal oil system - do - - do -
h. Cable galleries/cable vault (a) Linear heat (a) Automatic MVW (b) Not being
sensing cable type spray system and fire provided in new
heat detectors; extinguishers projects
ionization and (b) TES type water
photoelectric type spray system
smoke detectors
(b) - do - plus TES
type
sprinkler bulbs (for
local/auto spray)
i. Cable vault (above false Linear heat sensing Fire extinguishers; Indicator of the
roof and below false cable type heat automatic carbon photo-electric
flooring of unit control detectors; ionization dioxide gas and ionization
rooms) and photoelectric extinguishing system type smoke
type smoke detectors or automatic inert gas detectors to be
extinguishing system mounted at false
roof
j. Battery rooms (C&I and Electrical spot type Fire extinguishers
electrical) heat detector and
ionization type
smoke detectors
k. Steam turbine bearing (a) Quartzoid bulb (a) Manual HVW To be provided in
housing, turbine type heat detectors spray system and fire consultation with
enclosure (with hydraulic extinguishers manufacturer
detection pipe (optional)
network) (optional) (b) Automatic inert
(b) Flame detectors, gas extinguishing
gas detectors system
(continued)
Appendix B: Fire Protection of Power Stations 215
(continued)
SN Area Detection system Protection system Remarks
l. All MCC and Switchgear Ionization type Fire extinguishers
rooms (LT/HT) smoke detectors
m. UCB and its adjoining Ionization and photo Automatic Inert gas
office space, Control electric type smoke (‘INERGEN’ or
equipment rooms, UPS, detectors ‘ARGONITE’)
inverter rooms, extinguishing system;
marshalling cabinet area automatic inert
system
n. SWAS rooms – Fire extinguishers
o. Service building/facilities Smoke detection Sprinkler system, fire
building system extinguishers
p. Along the periphery – Hydrant system Hydrant valves
and individual
hose boxes/hose
reels
q. Stair cases – Hydrant system and Landing valves
fire extinguishers and individual
hose boxes
5.2 Main plant boiler/WH RB block
a. Electro-static-precipitator – Hydrant system, Landing valves
water monitors and individual
around ESPs and hose boxes, hose
WHRB reels
b. Gas turbine fuel syst. Quartzoid bulb type Automatic HVW
skids heat detectors (with spray system and fire
(gas/Naphtha/NGS/HSD) hydraulic detection extinguishers
for metering/filtering etc. pipe network)
c. Boiler burner front Quartzoid bulb type Automatic HVW
heat detectors (with spray system and fire
pneumatic detection extinguishers
pipe network) or
electrical spot type
detector
d. All control rooms, MCC Ionization type Fire extinguishers
and switchgear rooms smoke detectors
(ESP/VFD, ash handling
plant and other buildings)
e. Cable galleries (ESP and Linear heat sensing Automatic MVW
VFD building) cable type heat spray system and fire
detectors; ionization extinguishers
and photoelectric
type smoke detectors
f. Boiler staircases – Hydrant system, Landing valves
water monitors on and individual
either side of boilers hose boxes
and fire extinguishers
(continued)
216 Appendix B: Fire Protection of Power Stations
(continued)
SN Area Detection system Protection system Remarks
g. Coal Bunkers – Bunker inerting by
CO2/inert gas/steam
(optional)
h. Along the periphery – Hydrant system Hydrant valves
and individual
hose boxes
5.3 Transformer yard area
a. All transformers Quartzoid bulb type Automatic HVW Hydrant valves
heat detectors (with spray system hydrant and individual
hydraulic/pneumatic system and fire hose boxes
detection pipe extinguishers
network)
b. Along the periphery – Hydrant system Hydrant valves
and individual
hose boxes
c. DG set/black start DG Quartzoid bulb type Automatic MVW
area heat detectors (with spray system and fire
hydraulic detection extinguishers
pipe network)
d. All control rooms, MCC Ionization type Fire extinguishers
and switchgear rooms smoke detectors
(compressor house, DG
set area or any other local
MCC/switchgear rooms)
5.4 Coal handling plant
a. Coal Conveyors (a) - (a) Hydrants/monitors Hoses to be
(b) LHS cable type (b) (i) Sprinkler provided in
heats detectors and system central hose
infrared type heat (ii) Solenoid operated houses
detectors automatic MVW
(c) Linear heat spray system and
sensing cable type hydrant system
heat detectors, (c) Automatic MVW
quartzoid bulb type spray system and
heat detectors (with hydrant system
hydraulic/pneumatic
detection pipe
network) and
infra-red type heat
detectors
b. Transfer points and Quartzoid bulb type (a) Automatic MVW
crusher houses heat detectors spray/sprinkler
system and hydrant
system (landing
valves and/or water
monitors)
(b) Hydrants
(continued)
Appendix B: Fire Protection of Power Stations 217
(continued)
SN Area Detection system Protection system Remarks
c. Coal handling plant Ionization type (a) Fire extinguishers
control rooms, MCC and smoke detectors (b) Hydrants (outside)
switchgear rooms
d. Cable galleries in CHP Linear heat sensing (a) Automatic MVW
control/switchgear rooms cable type heat spray system and fire
(if any) detectors; ionization extinguishers
and photoelectric (b) Hydrants (outside)
type smoke detectors
e. Transformers of rating 10 Quartzoid bulb type Automatic HVW Hoses to be
MVA and above within heat detectors (with spray system and fire provided in
the plant premises hydraulic detector extinguishers hydrant central hose
pipe network) system houses
5.5 Fuel oil handling
a. Fuel oil tanks Linear heat sensing Foam injection
(NAPTHA/NGL/HSD) cable type heat system and
HFO/LDO detectors, quartzoid automatic/manual
bulb type (with MVW spray system
pneumatic detection (for uninsulated
pipe network) heat tanks)
detectors
b. Fuel oil dyke – Hydrant system Hoses to be
(hydrants and water provided in
monitors); central hose
foam water houses
hydrants/monitors
c. Fuel oil pump house ‘Quartzoid bulb’ (a) Automatic
equipment type heat detectors MVW/foam spray
(with hydraulic system
detector pipe (b) Fire extinguishers,
network) foam hydrants
d. Control rooms, Ionization type Fire extinguishers
MCC/switchgear rooms if smoke detectors
any
e. Transformers of rating Quartzoid bulb type Automatic HVW Hoses to be
10 MVA heat detectors (with spray system and fire provided in
hydraulic detector extinguishers hydrant central hose
pipe network) system houses
5.6 All Other off site area
a. All pump – Hydrant system Hoses to be
houses/permanent (hydrants and/or provided in
structure such as WTP, water monitors) fire central hose
PT Plant etc. (other than extinguishers houses
cooling towers)
(continued)
218 Appendix B: Fire Protection of Power Stations
(continued)
SN Area Detection system Protection system Remarks
b. Miscellaneous Ionization type Hydrant system
switchgear/MCC and smoke detectors (hydrants and/or
control rooms water monitors) and
fire extinguishers
c. Transformers of rating 10 Quartzoid bulb type Automatic HVW Hoses to be
MVA and above within heat detectors (With spray system, hydrant provided in
the plant premises hydraulic detector system and fire central hose
pipe network) extinguishers houses
d. Administration building – Hydrant system Hydrant valves
(periphery) and individual
hose boxes
e. Administration building – Hydrant system and Landing valves
(staircases) rire extinguishers and individual
hose boxes
f. Communication Ionization type Fire extinguishers
building/SATCOM smoke detectors
building if any switchgear
room, control/cubicle
room
g. Communication – Hydrant system Hydrant valves
building/SATCOM and individual
building (periphery) hose boxes
(continued)
Frequency Checks
Weekly 1. All hydrant valves and monitors to be examined systematically to ensure that
all valves and spring catches are maintained in good condition along with
hand-wheels, couplings, lugs, etc.
2. Inspect hydrants for any obstruction of approach to these due to vehicles, etc.
3. Open randomly selected valves one by one and observe flow of water for a
short time. Close the valves. The whole operation of valves should be smooth
and there should not be any leakage
4. Inspect all hose boxes to ensure that these contain the required number of
hoses, branch pipes, and nozzles
5. Open air release valves on the main pipes in order to expel trapped air
6. Inspect hose reel installations and ensure that their isolating valves are closed
7. Inspect isolating valves for valve position and for any leakage
8. Check valve pit for proper cleanliness and ensure that it is not flooded and is
in good repair, readily operable condition
Frequency Checks
9. Check level and specific gravity of electrolyte in the batteries of diesel
engines
10. Check that automatic start sequence of diesel engine-driven pump is
operative. Run each diesel engine for about 30 min under load (not less than
60 % operating load) until the time operating parameters such as exhaust
temperature, closed circuit water temperature, lubricating oil temperature,
lubricating oil pressure, etc. are stabilized. Check whether operating parameters
are within recommended range
Check exhaust pipes of each diesel engine for leakage, chokage, and
overheating when the pump is running
11. Check battery charger panels for proper functioning
12. Check fire pumps control-cum-annunciation panel for proper functioning
and alarm/annunciation
13. Check temperature of pump house
14. Check all auxiliary equipment such as battery charger, compressor, water
pumps, and diesel fuel level
15. Carry out flow test as detailed below:
(a) Select hydraulically most remote hydrant and place a pressure gauge
mounted on a blank cap adjacent to it
(b) Connect two or more hose pipes with nozzles each 30 m long at
hydraulically most remote hydrant and adjacent valves
(c) With a pump running at its maximum pressure, with other hydrant valves
closed, flow water through the hose reels with valves fully open. Note down
readings of pressure gauges mounted adjacent to hydraulically most remote
hydrant valve and in the pump house. The running pressure should be between
3.5–5 kg/cm2. This test should be repeated with different pump next week by
rotation. (Alternatively, the pressure gauge can be mounted at the hydraulically
most remote hydrant also instead of adjacent one). Test should be rotated for
different locations which are hydraulically far or are hazardous
16. Change over to other pumps as per ‘Change Over Schedule’
(continued)
220 Appendix B: Fire Protection of Power Stations
(continued)
Frequency Checks
Monthly 1. Clean strainers of spray pumps (in case of clarified fire water site may change
the frequency of cleaning the strainers)
2. Check that connectors of battery are clean and free from corrosion and
properly connected. Smear a little petroleum jelly on them and on the battery
terminals
3. Top up cells with distilled water, if required
4. Carry out monthly maintenance of diesel engine as per manufacturer’s
recommendation
5. Measure vibrations of pumps and gear boxes
Quarterly 1. Clean and examine pump coupling for signs of wear, general damage,
looseness, and misalignment
2. Carry out quarterly maintenance of pump and motor and diesel engine as per
manufacturer’s recommendations
3. Inspect fan belts of diesel engine for slackness and wear. Adjust/replace if
necessary
4. Clean crankcase breather (use clean fuel for cleaning) by using air
Frequency Checks
5. Remove air filter element and shake out excess dirt by gently tapping on a flat
clean surface
6. Inspect exhaust pipe work for any damage, leakage, or choking and clean it
thoroughly.
7. Check and clean terminals of electric motors. Tighten connections, if required
8. Reassemble air compressors using new gaskets
9. Inspect compressor delivery filter
10. Carry out quarterly maintenance of air compressors as per manufacturer’s
recommendations
11. Adjust the gland assembly by tightening the gland adjusting nuts on either
side of split gland collar. Replace gland packing if it has hardened
Yearly 1. Overhauling of pump and motor to be performed per manufacturer’s
recommendation
2. Yearly maintenance of diesel engine to be done per manufacturer’s
recommendations including:
(a) Inspection and cleaning of fuel injectors
(b) Thorough checking of diesel engine cooling system for leaks, blockages
(flushing, if required, to be done with clean water)
(c) Inspection of starter motor and replacement of carbon brushes, if necessary
(d) Inspection and cleaning of engine exhaust manifolds and pipes and
replacement, wherever necessary
(e) Inspection of air filter and replacement of air filter element, if required
3. Painting of stand posts, overground pipes, and risers is recommended
4. Carry out hydraulic test of pipelines to detect leakages
5. Remove suction filter, cylinder head and valve plate assembly of air
compressors and clean. Inspect valve plates and counter plates. Replace, if
necessary
Every 2 1. All isolating valves to be dismantled and thoroughly overhauled
years 2. Various pressure/temperature switches/gauges to be calibrated
Every 5 Drain, clean, repair, and return to service all pump suction tanks for the systems
years
Appendix B: Fire Protection of Power Stations 221
(continued)
Frequency Checks
Monthly 1. Check for proper functioning of solenoid valves for
remote/manual operation and local/manual operation by energizing
solenoid valves but not allowing spray to take place
2. Check quartzoid bulbs and spray nozzles for proper
positioning/orientation
Quarterly (in addition to 1. Check that water supply arrangements (including back-up
weekly requirements) supplies) are in order and operate valves and carry out a valve
discharge test
2. Operate main stop and zone isolating valves over full range.
A non-hardening packing should be used in valve glands. Restart
valves. Trip and reset deluge valves
3. Test the deluge system by doing actual spray. Where plant
operations prevent routine testing of fixed water sprays,
consideration should be given to conducting a trial of the equipment
during a plant overhaul
4. Check back-pressure valves for correct function. Inspect all
sprays and nozzles for freedom from corrosion and correct
orientation. Painted detector heads should be replaced
5. Examine piping to ensure that it is corrosion free, is properly
supported and is painted
6. All electrical and hydraulic alarms and their initiation devices
should be checked
7. Check spray nozzles for proper orientation
8. Operate water spray system by releasing pressure from detection
line after taking precautionary measures. Observe the spray
coverage and nozzles for any choking, wrong directional mounting
In the case of spray system of transformers, check that the top of
spray cones are below turret of bushings. Reset deluge valve
9. Clean strainers after the spray
Annually 1. Overhaul all control valves, isolating valves and deluge valves
2. Alarm valves, isolating valves to be dismantled and overhauled
3. Various pressure/temperature switches/gauges to be calibrated
4. Flush detection and spray lines and clean all nozzles
5. Carry out hydraulic test of pipelines to detect leakages
Every statutory outage 1. Pressure vessels should be examined internally and the
opportunity taken to repaint with rust-resisting paint
2. Test the deluge system by doing actual spray. Where plant
operations prevent routine testing of fixed water sprays,
consideration should be given to conducting a trial of the equipment
during a plant overhaul
3. Carry out a full flow pump test for a minimum of 6 h
4. Adequate steps should be taken to prevent vulnerable items
suffering damage from water ingress and to ensure that spray
pipework is completely drained afterward
Every 15 years Drain, clean, repair and return to service to service all pump suction
tanks for the system
Appendix B: Fire Protection of Power Stations 223
1.0 Purpose
The directive specifies the system for modifications in plant/equipment at
the power station.
2.0 Scope
2.1 This directive shall be applicable to all modifications (or design change)
to plant/equipment/systems/components of existing power stations after
the date of issue of the directive. For modifications made prior to issue of
this revision, procedure described at clause no 5.7 should be followed
2.2 In the case of power stations set up after the date of issue of this directive,
the directive shall apply from the date the PG test is conducted or date of
completion of warranty of the contractor, whichever is later
2.3 The directive shall not be applicable to modifications/design change to be
carried out under contractual obligations of the contractor under the
contract irrespective of the period when such modification is carried out.
However, in such cases where modification is necessary to be carried out
before expiry of the warranty period or before PG Test, whichever is later,
written consent of the contractor for such proposed modification should
be obtained before carrying out the modification. In all such cases, an
approval from the Engineering Department must be obtained, which shall
be routed through Operation Services (OS)
2.4 The reference design or datum for each plant/equipment/system/
component of the power station shall be as per the last document
approved by Engineering or the original design drawings
2.5 The directive shall not be applicable to ‘defects’ or ‘repairs’ which require
equipment to be reinstated to the original condition
2.6 For the purpose of this directive, system, or component shall also include
load-bearing structures
Station Code:
Purpose of Modification
Component / System: (State justification)
Manufacturer :
Any identified safety hazard / Environment impact on account of the Plant Modifications
Date
232 Appendix C: System for Plant Modifications
3. APPROVALS
4. IMPLEMENTATION
(After work has been completed, record the means by
which modification has been achieved. State Contract Signature:
Number, etc.) Concerned Dept. I/C
Date:
5. COMMISSIONING
Note:
1. This Directive applies only to modifications; it does not apply to `defects' or
repairs which require equipment to be reinstated to the original condition.
2. Section 2 `Categorization'-The selection of Assessment Category is the
responsibility of the Appropriate authority.
Appendix C: System for Plant Modifications 233