Escolar Documentos
Profissional Documentos
Cultura Documentos
SECTION
No. Para DESCRIPTION PAGE
1 GENERATOR ASSEMBLY & ERECTION PRE-REQUISITES
1.1 Sub-assemblies 1.1
1.2 Auxiliaries 1.1
1.3 Erection pre-requisites 1.1
2 ERECTION SEQUENCE
2.1 General 2.1
2.2 Erection in service-bay 2.1
2.3 Erection in generator foundation pit 2.1
2.4 Slings 2.2
3 GENERATOR FOUNDATION 3.1
3.0 Reference drawings 3.1
3.1 Foundation: stator/bottom bracket 3.1
3.2 Sole plate and foundation bolts 3.1
3.3 Grouting
4 STATOR ASSEMBLY
4.0 Reference drawings 4.1
4.1 General 4.2
4.2 Stator frame 4.2
4.3 Stator core 4.2
4.4 Stator winding 4.3
4.5 Lifting of wound stator and lowering 4.5
4.6 Air coolers 4.5
5 GENERATOR SHAFTS AND ROTOR ASSEMBLY
5.0 Reference drawings 5.1
5.1 General 5.2
5.2 Spider and rim assembly 5.2
5.3 Mounting of poles 5.3
5.4 Fan assembly 5.4
5.5 Lowering of main shaft and rotor 5.5
5.6 Magnetic centering of stator and rotor 5.6
Fig. - 5.1 Developed view of rotor after pole mounting 5.8
Fig. - 5.2 Checking for magnetic centering 5.9
Fig. - 5.3 Greasing of rim keys and rim locking keys 5.10
Fig. - 5.4 Greasing of shaft and spider keys 5.11
SECTION
No. Para. DESCRIPTION PAGE
6 BOTTOM BRACKET, BEARINGS AND OTHER ASSEMBLIES
6.0 Reference drawings
6.1
6.1 General
6.1
6.2 Erection of bottom bracket
6.1
7 TOP BRACKET, BEARING AND OTHER ASSEMBLIES
7.0 Reference drawings 7.1
7.1 General 7.1
7.2 Erection of top bracket and other assemblies 7.1
7.3 Guide bearing and insulation 7.2
1.2 AUXILIARIES.
Hydrostatic lubrication system
Brake-jack system
Power pack
Anti-condensation heaters
Cooling water pipe lines for air/oil coolers
Fire extinguishing system (CO2 type)
Power house roofing completed and sides, windows and entries are covered.
Service-bay is concreted and embedding completed.
Concreting and curing of generator barrel completed.
Generator stator and bottom bracket foundations are checked, chipping
completed and pockets are clear.
3-phase, 4 wire electric power supply for construction and the tapping points
are available in power house and general Illumination is provided.
Ventilation and water supply arrangement.
EOT cranes commissioned and tested for loads and tandem operation.
Proper precautionary measures are ensured to avoid flooding of the power
house either from upstream or downstream of the POWER HOUSE.
1.1
SECTION – 2
ERECTION SEQUENCE
2.1 GENERAL
The erection procedure outlined below is a usual method adopted by BHEL. The
procedure is to be taken only as a guide and a preferred method of erection of
major component.
3.3 GROUTING
. The grouting of the sole plates shall be taken-up only after final levelling, centering,
bolting and dowelling. It is necessary to use non-shrinking cement/ compound to
produce a monolithic mass capable of transmitting loads from sole plates to
generator foundation.
The method of grouting shall be decided by the customer.
3.1
SECTION – 4
STATOR ASSEMBLY
4.0 REFERENCE DRAWINGS
(a) Stator frame and core assembly
4.1 GENERAL
The stator frame, punching and winding materials are shipped loose for their
assembly at site. The stator core shall be built as continuous ring at site. The
consolidation of the core, laying of winding, bus bars etc. including stage wise and
final H.V. testing shall be carried at site.
4.2
The core building shall be carried out as per the drawing, method of
core building, 3 251 06 23518 (6 sheets).
Weld the fingers on bottom plate of stator. Perform D.P. test to check
the welds. Check level of fingers and record the dimensions in log sheets
as per Quality Plan for Installation, document no. QPX-HG-027.
Conduct D.P. test on welded joints between key-bars and horse shoe
plates. Straighten the key bars as necessary. Record the dimensions in log
sheets as per Quality Plan for Installation, document no. QPX-HG-027.
The healthiness of RTDs shall be checked before and after their
installation in stator core/teeth and results shall be recorded in log
sheets as per Quality Plan for Installation, document no. QPX-HG-027.
The core consolidation and tightening shall be done as per drawing
and results shall be recorded in log sheet as per Quality Plan for Installation,
document no. QPX-HG-027.
After the core consolidation and final tightening, fish plates to be
welded on the flanged joints of stator frame as per drawing 0 251 06
23503.
4.4 STATOR WINDING
4.4.1 General
The stator winding is class ‘F’ insulated with consolidated straight portion and flexible
overhang. It consists of a double layer, single turn bar, wave winding, wound in open
slots. All the bars have been formed, insulated and tested at works before dispatch.
The bars have been provided with a 3600 Roebel transposition in the slot portion to
eliminate circulating current losses
Before proceeding with the winding work, minutely examine the stator core slot at
the top and bottom ends particularly at the glued packets for projection of punching
into the slot. Failure to remove any projection in the slot will lead to damage to bar
insulation and ultimately failure during HV test. Clean the core with compressed dry
air and apply conducting paint inside the slots.
4.4.2 Setting of support rings and trial winding bars
Assemble a few bars to ascertain the locations of support brackets. Assemble support
brackets and support rings as per drawing. A gap of 2 to 3 mm shall be maintained
between trial bottom bars and support rings for adjustability. The gap shall be filled
with thin bakelite strips wrapped with treated glass tape in the open spiral form. A
layer of polyester filler felt shall be placed between bottom bars and packing strips
for cushioning effect. Remove the trial bars and complete the assembly of support
brackets and support rings above and below the stator core.
4.4.3 Assembly of bars
(i) Template
While assembling bars in slots, it is necessary that the straight portion of bars extend
by an equal amount at both ends of core. It is convenient to prepare a template made
of pressboard or PLC fabric sheet or wood. The template may be made as follows:
4.3
Measure core length over clamping fingers at several points round the periphery and
determine maximum over all length. Construct the template to fit into the angle of the
bar between the straight portion and the end winding so as to clear core clamping
fingers.
(ii) Assembly of bottom bars
Refer drawing 12510523507 for item wise distribution of bottom and top bars in the
slots. Before assembling the bottom bar, a conducting packer of epoxy glass shall
be fixed at slot bottom. Ensure that the projection of straight portion of the bars is
equalised at the top and bottom ends. After assembly of bars, side clearance
between bar and slot wall shall be packed with conducting sheets as per drawing.
The bar shall be secured tight with the support ring using glass fibre woven tape as
per drawing. Each pair of bottom bars shall be bound together as per drawing.
Conduct HV test on bottom bars as per Annexure-I. Record the results in log sheets
as per Quality Plan for Installation, document no. QPX-HG-027.
(iii) Assembly of top bars
Fix the separator in correct position before assembly of top bars. Assemble the top
bar following the same procedure as in the bottom bars. Use conducting glass
laminates as needed to make the bar tight in width.
Brace the end winding with glass fiber woven tape after placing necessary
packers of epoxy glass laminate and conformal packing. Each pair of top bars shall
be bound together with four turns of glass tape and two reverse turns, maintaining
uniform clearance in the end winding.
The mouth of slot packing blocks shall be assembled and bound in position
with varnish treated heat polyester shrink sleeve. Additional conformal packing
may be used to obtain a tight fit. Refer wound stator drawing: 0 251 05 23501.
(iv) Slot wedge assembly
In each slot, 15 pairs of slot wedges shall be assembled. Each pair comprises of a
parallel piece and a taper piece. Refer item 8 of wound stator drawing 0 251 05
23501. Top most and bottom most wedges have the groove at the ends for tying
them with the top bars. Packing under wedge of epoxy glass laminate are to be
used essentially while fixing the slot wedges. The ripple springs and slot wedges
shall be assembled as per the Tech. Requirement 8 of drawing, 1 251 05 23507.
For assembly of slot wedges, use bar pressing device to drawing 1 251 51 23518.
Conduct HV test on bottom bars as per Annexure-I. Record the results in log
sheets as per Quality Plan for Installation, document no. QPX-HG-027.
(v) Brazing of winding bars, connectors and insulation
During stator winding, following types of brazed joints shall be made:
- Series joint between a top bars and a bottom bar using copper clips
- Jumper connection
- Winding bar to bus bar connection
- Bus bar to bus bar connection
Refer drawings: - Wound stator : 0 251 05 23501
- Insulating materials for complete stator winding : 1 263 04 23501
4.4
IMPORTANT : Neighbouring winding bars, connectors etc. should be protected from
heat while brazing by using asbestos putty/asbestos cloth.
(vi) Inspection of winding and HV test
It has been observed that generally the failure of winding in end winding region
during HV test or operation is due to mis-handling or presence of foreign materials
like nuts, bolts, metal chips, welding rods, tools, knife, blades, copper off cuts,
brazing material etc. etc. lodged in the cross over portion of bars during winding or
subsequent assembly and boxing-up. Therefore, best efforts must be made to
ensure removal of any foreign material before HV tests. Failure to do so result in
failure of winding during HV test or operation.
NOTE: The winding MUST be carried out in a clean and dust free atmosphere. If the
air is contaminated by cement dust etc. due to construction work in adjacent
locations, then it is necessary that the winding be carried out in an enclosed area.
DO NOT STEP ON WINDING.
4.4.4 Testing
The brazed joints after cleaning shall be subjected to ultrasonic test for joint
efficiency. Minimum acceptable joint efficiency is 50%. Record the results in log
sheets as per Quality Plan for Installation, document no. QPX-HG-027.
Check insulation resistance and carry out dry out of winding as per technical
instructions/standards.
Conduct stagewise H.V. tests on stator winding as called in Annexure-I. Record
the results in log sheet as per Quality Plan for Installation, document no. QPX-
HG-027. The stator winding insulation will be dried out before official H.V. test
and record the results in log sheet as per Quality Plan for Installation, document
no. QPX-HG-027.
4.5 LIFTING OF WOUND STATOR AND LOWERING
Lift compete stator as per the drawing, ‘Arrangement of stator lifting’, 0 251 51
23508 and lower it on leveled sole plates. Before lowering stator, apply thin coat of
molybdenum-disulphide grease on seating faces of sole plates. Refer Annexure-IV.
Check magnetic axis of stator core with respect to turbine flange top.
Position piano wire with plumb bob at the center of stator bore. Using stick
micrometer, centralise the stator with respect to the center of turbine shaft bore.
Record the results in log sheets as per Quality Plan for Installation, document no.
QPX-HG-027.
After alignment of rotor, centralise the stator again with respect to rotor on the
basis of stator form and rotor form (Refer Annexure-III). For this the weight of
stator can be taken on the crane without actually lifting it and using radial jacks to
move it in desired direction, as required.
4.6 AIR COOLERS
Carry out hydraulic testing of air coolers before their assembly on stator frame to
prove the healthiness of cooler tubes and joints. Record the results in log sheets
as per Quality Plan for Installation, document no. QPX-HG-027.
After lowering of stator assembly in generator pit, the air coolers shall be
installed on stator frame as per drawing, 1 251 04 23516.
4.5
SECTION – 5
GENERATOR SHAFTS AND ROTOR ASSEMBLY
5.0 REFERENCE DRAWINGS
(a) Rotor assembly
Rotor assembly 0 252 08 23509
Set of balance weights 3 252 51 23507
RIM assembly
Rim building instruction 3 252 03 01401
Rotor rim punching 0 252 03 23501
Rotor rim end plates 0 252 03 23503
Rim segment with spacer 1 252 03 23509
Rotor rim and spider stools 1 252 51 23508
Rotor rim stud and nut assembly 2 252 03 23502
Rotor rim building equipment 2 252 51 23506
Rotor rim assembly 0 252 03 23502
SPIDER
Spider center assembly (machining) 0 252 02 23504
Spider center and arm assembly 0 252 02 23505
Spider keys 2 252 02 23508
Spider cover assembly 1 252 08 23505
SPIDER and shaft
Fixing arrangement of generator shaft and spider 1 252 02 23511
Shaft and spider coupling stud and nut 3 252 02 23503
Set of items for coupling bolt tightening 2 252 08 23504
Spider, top shaft & main shaft tightening arrgt. 1 252 51 23516
BRAKE track, fan and collector
Arrgt. of brake track segments and spider assembly 1 252 07 23507
Fan segment and blade assembly 1 252 04 23512
Fan segment assembly 1 252 04 23513
Collector assembly (OD=1250 mm) 1 252 05 01003
ROTOR connections
Arrangement of rotor connection 0 252 06 23507
Shaft and lead assembly 1 252 06 23520
Rotor lead assembly (collector to shaft) 1 252 06 23521
(b) Pole and field coil
Fabricated field coil 0 253 02 23501
Details of fabricated field coil 1 253 02 23505
Wound pole assembly 1 253 02 23504
Pole keys 2 252 03 23501
Wound pole lifting gear assembly 1 253 51 23506
Pole fixing arrangement 1 253 03 23507
Pole key withdrawal gear 1 253 51 01001
5.1
(c) Generator shafts
Generator main shaft (machining) 0 254 01 23501
Top shaft (machining) 0 254 01 23502
Generator and turbine shaft tightening arrangement 0 254 51 23503
Top and main shaft fixing arrangement 1 254 01 23508
(d) Rotor lifting/turning
Rotor lifting Trunnion assembly 1 252 51 23522
Dummy shaft lifting arrangement 1 252 51 23523
Arrangement for rotor lifting 1 252 51 23524
Dummy shaft (machining) 1 252 51 23519
Arrangement of rotor turning 1 252 51 23517
5.1 GENERAL
The rotor spider is a fabricated assembly with detachable arms for their assemblies at
site. Generator has two forged shafts i.e. main shaft and top shaft. The main shaft has
integral thrust collar at top and a flange at the bottom for coupling with turbine shaft.
In this type of construction, rotor is assembled without main shaft in service-bay i.e.
spider, rim, fans, poles etc. are assembled. Generator main shaft and rotor spider are
coupled in the generator pit.
5.2
Ensure that all rim building pins are free after stacking every 15 layers of rim
punchings.
Also measure the width of pockets being formed on left hand and right hand of
master key at all key bar locations, except in one location where taper keys are
fitted. Minor variation in the width is expected, which can be taken care of by
the extra long rim keys.
Rim shall be tightened in 6 stages (including final stage) to achieve rim stud
elongation as per rotor rim assembly drawing. Record the results in log sheets
as per Quality Plan for Installation, document no. QPX-HG-027.
Molybdenum di-sulphide grease shall also be applied on the rim locking keys
under surface coming in contact with the slot of spider key bar, before their
assembly. Refer Fig. 5.3 at the end of this section.
NOTE:
(i) Carryout intermediate pressing of the rim at the intervals specified in the
drawing of rim assembly and check the following in tightened condition:
- freeness of rim building pins
- height at ID and OD, at least at eight locations. The variation in the
heights measured at ID and OD shall be maintained within 2 to 3 mm.
(ii) During rim building, the verticality of all poles seating faces shall be checked
using plumb line. The permissible error in verticality of each pole seating face
shall be limited to 0.3 mm. If required, grind the pole seating face. Too much
difference in verticality would cause undue variation of air gap causing
unbalanced pull couple, which will be difficult to balance.
(iii) After grinding pole seating faces, check the A/F of the pole seating faces on
rim. This can be done by dropping a plumb wire to rim face by a inside
micrometer. Difference in A/F of opposite faces should be within 0.3-0.5 mm.
(iv) Check the rim height and ensure that it is uniform both from ID and OD around
the circumference.
NOTE :(i) The pole body must be in tight contact with rim face, steel shim must not get
sand witched between pole body and rim.
(ii) During assembly of poles, the magnetic center of the poles has to be checked.
5.3.6 Apply a very thin coat of molybdenum-di-sulphide grease on taper face of pole key
and its opposite face.
Drive the pole key in their correct position taking care that taper surfaces are
properly matched. The drive key should project at least 2 to 3 mm beyond the
bottom rim end plate. Finally trim the keys to specified drawing dimension.
5.3.7 Record the verticality of pole as well as pole radius. If necessary, correct both
verticality and radius by grinding slightly the pole seating surface and rim. THE
VERTICALITY OF INDIVIDUAL POLE SHALL BE WITHIN 0.3 MM.
NOTE: Difference in radii of opposite poles shall be within 0.2 mm. Also refer Annexure
- V for rotor roundness check.
5.3.8 Again measure the impedance of pole and compare with the value obtained with
other pole. The impedance value of a pole shall not vary by more than 10 % of
average value of all poles. This value would be different from the impedance of the
pole when measured on ground. Record the results in a log sheet as per Quality
Plan for Installation, document no. QPX-HG-027.
5.3.9 Make pole-to-pole connection and assemble rotor leads on spider.
5.3.10 Conduct HV test on rotor winding & rotor leads as per Annex.-I. Record the results
in a log sheet as per Quality Plan for Installation, document no. QPX-HG-027.
5.4
5.4.1 Assemble fan segment as per drawing. Very light grinding of holes in fan
segments can be done for seating on rim nuts, if required.
(ii) The generator main shaft is supplied with oil retaining sleeve assembled round it.
Assemble spring plate around the shaft. Assemble springs, thrust pads, pad stops,
anchor plates etc. Lower main shaft (with assembled oil-retaining sleeve and
spring plate). After passing the flange of the main shaft through the bottom
bracket, keep the shaft in hanging position by the overhead crane, till spring plate
is assembled on to the bottom bracket.
.
(iii) Lower generator main shaft on thrust bearing.
NOTE : WHILE ASSEMBLING THE SPRINGS, ENSURE THAT THE SPRINGS ARE
FREE TO ROTATE AND DO NOT FOUL WITH SURROUNDING
SPRINGS.
5.5
IMPORTANT : The stator core/winding must be protected while lowering the rotor
through stator bore. For this purpose. atleast eight persons should stand equally
spaced on stator. While lowering the rotor, they should position planks (75 mm
x 2 m) on inner diameter of core.
5.5.3 Lowering of generator top shaft
(i) Bring top shaft in the service bay and remove temporary rusts preventive coating
and clean it up for assembly.
(ii) Make top shaft vertical using the lifting device provided and lower it on the main
shaft.
(iii) Bolt-up the top shaft with main shaft as per, ‘Top and main shaft fixing
arrangement’, drawing 1 254 01 23508.
5.6
For evaluation, average value of ‘T’ and ‘B’ shall be separately computed. Since
during erection, the rotor elevation is set higher to cater for the thrust bearing
deflection due to turbine runner and hydraulic thrust, the values of T&B will not be
equal. However half the difference of ‘B’ and ‘T’, i.e. (T - B) / 2 shall be equal to
the thrust bearing bracket and spring deflection. Refer clause 8.4.4, Section – 8 of
this manual. A variation of about 2 mm is permitted on this dimension.
The center line of stator and rotor shall match during normal operation. However
during standstill condition the rotor elevation is set a little higher than running
elevation, taken into account the thrust bearing bracket deflection and thrust
bearing spring deflection. This fact must be kept in mind while checking or
adjusting magnetic centre.
5.7
SECTION-6
BOTTOM BRACKET, BEARINGS AND OTHER ASSEMBLIES
6.0 REFERENCE DRAWINGS
Bottom guide bearing arrangement 0 257 02 23501
Bottom bracket centre and arm assembly 0 257 01 23504
Bottom bracket centre assembly 0 257 01 23505
Arrangement of air and oil vapour piping 0 257 02 23507
Arrangement of brake piping and conduit 0 257 08 23509
Arrangement of air guide and air baffle 0 257 05 23510
Air guide fixing support assembly 2 257 05 23510
Arrangement of pit air seal 0 257 06 23511
Baffle assembly 1 257 05 23506
Bottom guide pad 2 257 02 23503
Pivot bar (bottom) 2 257 02 23508
Pad stop 3 257 02 23505
Arrgt. of bottom bearing instruments & oil level switch 0 259 03 23503
6.1 GENERAL
The bottom bracket is supplied with detachable arms for their assembly at site. The
bottom bracket assembly comprising of thrust bearing, guide bearing, oil coolers
etc. rests on sole plates. The brake-jack units, oil vapour seal, pit air seal etc. are
assembled on bottom bracket.
6.2 ERECTION OF BOTTOM BRACKET
6.2.1 Lower bottom bracket and centralize it with respect to turbine shaft and also
check elevation. Refer clause 8.4.
6.2.2 Lower main shaft and measure bottom bracket deflection as per Section - 8.
6.2.3 Assemble interpad cooling piping inside the bottom bracket and outside piping
upto oil pump and motor unit provided for interpad cooling.
6.2.4 Commission brake-jack control panel and H.S. lubrication unit.
6.2.5 Lower the rotor and measure bottom bracket deflection as per Section-8.
6.2.6 Bedding of guide pads : Rub babbitt surface of a guide pad on respective
journal surface of generator shaft. Continue scraping of shining points of babbited
surface, which represent high points, till 80% contact area of the babbited surface
is achieved.
6.2.7 Assemble guide bearing pads. Set guide bearing clearances as per drawing and
record the clearances in log sheets as per Quality Plan for Installation, document
no. QPX-HG-027.
6.2.8 Assemble oil retaining sleeve on spring plate assembly and set it concentric to the
journal surface of main shaft.
6.2.9 Carry out hydraulic testing of oil coolers as per drawing and assemble them on
bottom bracket. Assemble oil vapour seal/pipes, bottom bearing instruments etc.
NOTE: Oil vapour seal should be assembled carefully for its effective functioning.
6.2.10 Clean the bearing housing thoroughly. Fill a few drums of oil and flush 2 to 3
times. Do not fill oil at this stage.
6.1
SECTION – 7
TOP BRACKET, BEARING AND OTHER ASSEMBLIES
7.0 REFERENCE DRAWINGS
DESCRIPTION DRAWING
Top bracket center assembly 0 256 01 23503
Top bracket center and arm assembly 0 256 01 23504
Arrangement of stator and top bracket fixing 2 256 01 23508
Top guide bearing arrangement 0 256 02 23501
Top oil vapour seal assembly 0 256 02 23505
Arrangement of air and oil vapour piping 0 256 02 23506 (2 sheets)
Top air guide and baffle arrangement 0 256 02 23507
Oil leakage collector assembly 1 256 02 23503
Guide bearing pad 2 256 02 23501
Pivot bar 2 256 02 23505
BOM for bearing protection brush arrangement 3 256 02 23511
Arrangement of floor plates 0 256 05 23510
Air guide assembly (top and bottom) 0 256 06 23508
Air baffle assembly 2 256 06 23510
Arrangement of D.C. connections 0 256 10 23509
Connector for D.C. connection 2 256 10 23512
Brushgear assembly 1 256 10 23505
Method of setting spring load for brushes 3 256 10 01401
Top oil cooler withdrawal arrangement 1 256 51 23507
Arrgt. of top bearing instruments and oil level switch 0 259 03 23501
7.1 GENERAL
The top bracket is supplied with detachable arms for their assembly at site. It
accommodates the guide bearing assembly, oil coolers etc. It provides support for
generator flooring, top casing, brushgear etc.
7.1
7.2.5 Assemble guide pads and other components and complete top guide bearing
assembly as per drawing.
7.2.6 Set oil retaining sleeve concentric to the journal surface of shaft.
7.2.7 Assemble oil leakage collector assembly underneath oil retaining sleeve.
7.2.8 Carry out hydraulic testing of oil coolers as per drawing to check healthiness of
cooler tubes and joints. Assemble oil coolers, oil vapour seal, instruments &
covers.
7.2.9 Complete laying, tack welding of cooling water and air pipe lines. Dismantle pipes
for final welding, cleaning and hydraulic testing as called in drawing. Install
cooling water pipes with supports and clamping arrangement as per drawing.
7.2.10 Assemble tubular shaft assembly and assemble collector, over speed device and
toothed wheel of SSG on it.
7.2.11 Check alignment of collector as given in Section - 8.
7.2.12 Fill up oil upto the specified oil level and close bearing housing.
7.2.13 Conduct High Voltage test on collector and rotor leads and record the results in log
sheets as per Quality Plan for Installation, document no. QPX-HG-027.
7.2.14 Assemble brushgear, OSD, SSG and DC connections on top bracket.
Assemble guide pads, oil vapour seal assembly, oil leakage collector assembly and
bearing protection brush. Measure IR values of following and record.
(i) Each guide pad to pivot bar before assembly in bearing housing
(ii) Guide pad to top bracket (earth)
(iii) Top oil vapour seal with respect to top bracket (earth)
(iv) Bearing protection (insulated) brush with respect to top bracket (earth)
(v) Oil leakage collector assembly with respect to top bracket (earth)
NOTE: Ensure that capillaries of RTDs, DTTs and thermostats do not touch the bearing
pads, keep plate etc. till they come on to the guide bearing support ring. For this
purpose capillary length inside top bearing housing should be insulated as per
drawing, 0259 03 23501.
7.2
SECTION – 8
LEVELS, CENTERING AND ALIGNMENT
(INCLUDING DOWELLING AND GROUTING)
8.1 INTRODUCTION
Levelling and alignment along with centralizing are the most important operation
in the erection of a Hydrogenerator. Trouble free operation of a machine depends
on satisfactory achievement of level, alignment and centralizing of rotor. These
operations must ensure that:
The thrust bearing is horizontal
The thrust bearing elevation is set to give correct turbine runner elevation during
normal operation
The axis of turbine shaft, generator main shaft, top shaft and collector shaft are in
one vertical line.
The turbine runner centre and generator rotor center coincide with centre line of
stay ring and stator bore respectively during normal operation.
The guide bearing clearances are set as per drawing.
8.1
8.4 SETTING OF THRUST BEARING ELEVATION
8.4.1 Check that the sole plates and bottom bracket holding down bolts are tightened.
8.4.2 After transferring load of rotor on thrust bearing, measure difference in magnetic
center of stator and rotor. Adjust the difference such that rotor axis, coincides
with that of stator, while the unit is under operation under full load.
8.4.3 Allowance must be made for deflection of the bottom bracket and thrust bearing
springs under full load i.e. weight of rotating parts and hydraulic thrust as
below:
a) Bracket deflection at full load (1015 T) 2.3 mm
b) Bracket deflection with generator rotor & gen. shafts (405 T) 0.92 mm
c) Spring deflection at full load (1015 T) 2.0 mm
d) Spring deflection with generator rotor & gen. shafts (405 T) 0.4 mm
8.4.4 It is to be ensured that the turbine runner will be at the desired level under
running condition on load. The turbine erector will advise the amount (T) by
which the turbine coupling is below the normal running position. The generator
shaft must then be set at a height above the turbine coupling by an amount equal
to T plus additional deflection of thrust bearing at full load. This equals to :
T + (2.3 – 0.92) + (2.0 – 0.4) = T + 2.98 mm.
8.4.5 It is essential that any adjustment of the bearing bracket shims provided to
obtain the correct coupling gap must be precisely the same (by micrometer
Measurement) at each bracket foot, otherwise the bracket will be thrown out of
level.
8.2
NOTE: The level gauge must be checked for zero error before use. H.S. lubrication should
be switched ON before giving any rotation to the rotor / shaft.
8.5.8 Rotate the rotor and note the level gauge readings at regular interval. It must be
ensured that the rotor is stationary, freely suspended, H.S. lubrication system is
OFF and no person or foreign material is on the rotor while taking the readings
8.5.9 While checking the level variation, H.S. lubrication pump should be switched off.
Adjust the bracket shims as necessary to get the resultant level reading within 1
division of level of 0.025 mm in 1 meter accuracy.
8.5.10 To obtain the required accuracy of the level, the shims under bottom bracket
feet are adjusted. The adjustment in the shims should be graded as far as
ispracticable to maintain an even loading on sole plates. Minimum number of
shims for a given adjustment should be used i.e. thicker shims are used wherever
possible
NOTE:
(1) It is advisable to measure total thickness of the shims used under each bracket
foot and then use a thick machined plate of same thickness as measured by
micrometer in place of many shims.
(2) All level gauge readings are to be taken after fully tightening the holding down
bolts after each adjustment of shims.
8.6 ALIGNMENT
IMPORTANT : DURING ALIGNMENT CHECKS, FOLLOWING POINTS
MUST BE ENSURDED:
(i) THE RETAINING PLATES OF THRUST PADS ARE NOT FOULING
WITH THRUST PADS PREVENTING FREE ROTATION OF ROTOR AND
SHAFT.
(ii) THE MOVEMENT OF DIAL GAUGE AT THE REFERENCE GUIDE
BEARING SHALL NOT EXCEED 1 TO 2 DIVISIONS.
(III) CLOSING ERROR SHALL NOT EXCEED 2 DIVISIONS AT THE
POINT OF MEASUREMENT OF THROW
(IV) THE FINAL ALIGNMENT READINGS SHALL BE TAKEN ONLY
AFTER FULL TIGHTENING OF THE BOLTS OF TURBINE AND
GENERATOR SHAFT COUPLING.
(v) TWO CONSECUTIVE FINAL THROW CIRCLE DIAMETERS
SHOULD BE
EQUAL IN MAGNITUDE AND DIRECTION.
8.3
8.7 ROTATIONAL CHECK ON GENERATOR MAIN WITH ROTOR AND
TOP SHAFT
8.7.1 Fully tighten the main shaft and top shaft coupling bolts.
8.7.2 Fit dial gauges at top and bottom, generator guide bearing journals in X and Y axis.
8.7.3 Rotate the rotor through 450, 900, 1350, 1800, 2250, 2700 , 3150 and 3600. Record the
dial gauge readings in a tabular form (as given below for ready reference) in line
with log sheet as per Quality Plan for Installation, document no. QPX-HG-027.
NOTE : The reading of 00 and 3600 should be the same within the tolerance of reading
accuracy. If these readings constantly show a difference, there is a possibility that the
shaft may not be rotating freely. The oil retaining sleeve or some such other component
may be touching the rotor. It is to be checked whether any jerk is produced while
rotating the rotor, which affects the initial readings. If so, the initial reading should be
taken after the cause of jerk is investigated and rotor made to rotate smoothly.
8.7.4 Plot the co-ordinates of ‘c’ on a graph paper to a suitable scale. Draw a circle with
minimum radius passing through any three points whereas enclosing remaining points.
THE THROW CIRCLE DIAMETER AT TOP GUIDE BEARING SHOULD BE
LIMITED TO 0.06 MM MAXIMUM.
8.7.5 The throw at the top guide-bearing journal shall be corrected, if it exceeds the
permissible limits defined above. In this case, the correction is possible by providing
shims between top shaft and main shaft.
8.7.6 Following points should be observed for shims:
(i) The shims should be graded in thickness and in steps of 200 to 250 mm i.e., if a shim
of 0.1 mm be needed at one end, thinner shims (say 0.08, 0.06, 0.04, 0.02 mm etc.)
shall be introduced additionally upto the diametrically opposite end as far as possible,
to maintain constant taper.
(ii) The shims shall be free from kinks etc. and must cover the full diameter of the flange.
(iii) Each piece of shim shall have at least one cutout for one fastener, i.e. bolts, dowels,
etc. ‘U’ cuts shall be provided for the purpose.
(iv) Shims shall be of stainless steel.
8.4
NOTE: The reading of 00 and 3600 should be same within the tolerance of reading
accuracy. If these readings constantly show a difference, there is possibility that
a shaft is not rotating freely. The oil retaining sleeve or some such other
component may be touching the rotor. It is to be checked whether any jerk is
produced while rotating the rotor, which affects the initial readings. If so, the
initial reading should be taken after the cause of jerk is investigated and rotor
made to rotate smoothly.
8.5
8.8.6 Plot the co-ordinates of ‘d’ and ‘e’ on a graph paper to a suitable scale. Draw a circle
with minimum radius passing through any three points whereas enclosing remaining
points. THE THROW CIRCLE DIAMETER AT TURBINE GUIDE BEARING
SHOULD BE LIMITED TO 0.08 MM MAXIMUM.
The throw at the top guide bearing should agree with the previous reading taken in
para 8.7.
8.8.7 The throw at the turbine-bearing journal should be corrected if it exceeds the
permissible limits defined above. The throw can be corrected by scrapping of end
surface of turbine or generator shaft or by placing stainless steel shims between
flanges. For shimming, the points mentioned in clause 8.7.6 shall be strictly followed.
8.12 DOWELLING
Only after completion of above operation, dowelling work shall be taken up. The
reamed holes shall be smooth and parallel to their axis. The hole diameter shall be
measured at top, middle and bottom. Dowel shall be machined and ground to give
clearance of 0.02 to 0.04 mm on actual measured diameters of holes.
All dowels (between bottom bracket and sole plates, stator and sole plates, top bracket
and stator etc.) shall be coated with molybdenum di-sulphide grease before putting in
place.
8.13 GROUTING
(i) Concrete surface for sole plate seating should be chipped/ground to get a levelled
and hard surface, before lowering sole plates on concrete.
(ii) AFTER FINAL LEVELLING, CENTERING, BOLTING AND DOWELLING OF
THE SOLE PLATES ARE OVER, the sole plates shall be grouted to the foundation
using non-shrinking cement/compound to produce a monolithic mass capable of
transmitting loads from sole plates to generator foundation. (Refer drawing 1 251
02 23502 for Arrangement of stator sole plates and drawing 1 257 07 23501 for
arrangement of bottom bracket sole plates).
(iii) The method of grouting shall be decided by the customer.
8.7
SECTION - 9
STARTING, TESTING AND COMMISSIONING
9.1 GENERAL
Clean the hydrogenerator of dust and dirt with the help of dry compressed air and
vacuum cleaner. Rub with cloth to clean internal surfaces of frame and air baffles
with cloth.
Remove foreign objects, if any from inner parts of hydro generator, specially the core
ducts, air gaps, inter polar gaps etc.
Check installation of dowels and tightening of fixing bolts of stator, bottom bracket,
top bracket, brake-jack assemblies etc. Check the locking of all the nuts, particularly
in rotating parts of generator and air baffles.
Check air guides and air baffles to ensure that they do not touch the rotating parts of
generator and the variation in airguide/baffle clearances are within limits specified in
the drawings.
Check that all cover plates are closed tightly.
The oil pot and pipelines are to be flushed by circulating oil for twelve hours. The
bearing housing shall then be filled with fresh oil up to the level shown in the
drawing. Again use the oil purifier for twenty-four hours for purification. Check for
any oil leakage.
In order to prevent entry of dirt and dust into the oil bath during first starting,
disconnect air piping from air baffle to vapour seal. HOWEVER, THE AIR PIPELINE
MUST BE CONNENCTED BACK AFTER FEW DAYS OF RUNNING.
9.1
9.4 FIRST RUN
In the first run, the machine is run without excitation and hence ensure that generator
excitation system is switched off. Start the hydro set and run it at low speed and make
sure that there is no jamming, unwanted noise/run-out of shaft and collector. If any
abnormal vibration is noticed at lower speed, balancing shall be done at that speed
before taking the machine to the next higher speed and upto finally rated speed.
OTHERWISE THE SHAFT MAY RUB THE OIL VAPOUR SEAL AND POSSIBLY
DAMAGE THE SEAL.
Provision is made on the rotor spider for fixing of the balance weight. By choosing the
proper size and location of balance weights, as required, the generator should be
balanced within allowable limits. The allowable bracket vibrations and shaft vibrations
(double amplitude) are as under:
Observe the oil level in thrust bearing oil bath. After starting, the oil level rises due to
centrifugal forces, heating and aeration. Check that the oil does not leak through the
bearing housing and oil retaining sleeves.
9.2
KNOCKING AND NOISE DURING SPEEDING UP. UNIT SHALL NOT BE
MAINTAINED AT OVER SPEED FOR A LONG TIME. INPECT GENERATOR
COMPONENTS AFTER OVERSPEED TEST, INCLUDING TIGHTENING OF ALL
HARDWARES, POLE/RIM KEYS ETC.
The voltage shall be built-up only after satisfactory condition of winding insulation
achieved by dry out. In order to build-up the voltage in stator winding, switch on the
excitation system and increase field current. Generator terminal voltage shall be
increased in steps of 2 kV and the unit shall be allowed to run for about 5 minutes every
time before increasing the voltage. Check the brushes for any sparking. Over voltage
protection check can also be done at this stage.
During the process of voltage build-up, monitor the vibration of shaft and bearing
brackets and if necessary, rebalance the machine before proceeding to the next higher
voltage. In this way, balance the machine under excited condition upto rated voltage.
Measure the vibration of the bracket and the shaft at top bracket and bottom bracket with
and without excitation and no load. If necessary, rebalance the machine before
proceeding to the next higher load. In this way, balance the machine under excited
condition upto rated load.
Conduct partial, full load and max. load throw off tests and check for satisfactory voltage
and speed rise.
9.3
(a) All balance weights are permanently welded/locked as per drawing, after removal of
temporary locking provided during balancing of a unit.
(b) Check carefully the tightness of fixing details of poles and keys, fan, rotor, air baffles,
stator, brackets, cover plates etc.
(c) Check carefully the stator winding for absence of any bulging of insulation or flow of
varnish.
(d) Check the interpolar joints of the rotor field winding. If necessary, tighten the holding
down nuts etc.
(e) Check the sealing of oil baths and vapour seal clearances.
(f) Check water and oil pipe lines for any leakage.
(g) Check working of braking system.
(h) Check the connections of current carrying leads and cables.
(i) Measure the insulation resistance of all the windings of the generator and compare them
with the measurements carried out earlier.
(j) Check the welding of rotor spider, top and bottom brackets, stator and other details.
(k) Blow the collector with dry compressed air as during starting period the most sensitive
wear of the brushes is observed.
(l) Check the oil levels in the bearing housings.
9.9 STOPPING
Following sequence shall be followed for stopping the unit when running on load.
(a) Reduce the output of generator till it is almost zero.
(b) Trip line circuit breaker.
(c) Reduce the field current till the terminal voltage is almost zero.
(d) Trip field circuit breaker.
(e) Allow the machine to decelerate to braking speed and apply brakes.
(f) Shut off cooling water supply to air/oil coolers, after machine comes to stand still. .
(g) Shut off H.S. Lubrication system and interpad cooling system.
(h) Release and reset brakes.
9.4
ANNEXURE – I
HIGH VOLTAGE TEST ON WINDINGS
1.1 SCHEDULE OF HV TESTS ON STATOR WINDING AT SITE
NOTES:
(1) H.V. tests specified are AC, rms voltage at 50 Hz for a duration of 60 seconds.
(2) IR value shall be recorded before and after each HV test.
(3) In case of failure during HV test, testing at any stage, the subsequent tests shall be
at the specified voltage, for 60 seconds duration irrespective of the duration of
application of voltage during failure.
(4) Impedance test of wound poles to at 60 to 100 V AC before conducting HV test:
(i) Before mounting the wound poles on rotor
(ii) After mounting the poles on rotor, but before connections
(5) Two terminals of each phase to be checked for electrical isolation by continuity test.
A - 1.1
ANNEXURE - II
INSULATION RESISTANCE TESTING AND DRYOUT
2.0 GENERAL
The insulation resistance of a winding is a function of the type and assembly of
insulating material. In general it varies directly with the thickness of insulation and
inversely with the conductor surface area. The value of insulation resistance also varies
inversely with the amount of moisture in the insulation and the amount of solvent left in
the bonding varnish of the winding connections. Insulation tests are carried out normally
using a megger. Where polarization index values are required, the megger must be
capable of supplying a steady voltage for 10 minutes. The results obtained using D.C.
test methods are affected by the general conditions of the surface of the windings as well
as by the leakage through the main insulation. Interpretation of the results may be
difficult if contamination is present; for this reason before carrying out the test, the
surface of the winding should be examined to make sure that they are clean and dry, and
not contaminated by moisture, oil, salt, carbon dust or other foreign matter.
A - 2.1
two minutes and thereafter the slope of the curve steadies of with time; for the next 10
to 30 minutes, the increase is a function of the absorption characteristics of the
insulation and hence of its general condition. On majority of the winding, the value
reached in 10 minutes will be greater than 90% of the final steady state reading. The
polarisation index of a winding is defined as the ratio of the insulation resistance after
10 minutes (R10) to the insulation resistance after 1 minute (R1) i.e.
Polarisation Index (P.I.) = R10/R1
On a clean dry winding, the polarisation index value should not be less than 2.0. If a
value below this is obtained, then a dry out should be carried out .
NOTE : If PI value tends to increase with successive readings the dry out should
be continued till nearly constant value is reached.
Values of ‘Ft’
Machine after
Winding New machine Machine after service for
Service, clean
Temperature Dry, unaged Several years with normal
0 and
C and clean Industrial Contamination
uncontaminated
10 32 16 8
20 16 8 4
30 8 4 2
40 4 2 1
50 2 1 0.5
60 1 0.5 0.25
70 0.5 0.25 0.125
80 0.25 0.125 0.0625
A - 2.4
(ii) Polarisation Index
The PI value shall be recorded in addition to IR. It is not uncommon on a clean, dry
winding to achieve a PI value of 2.0 & more after proper dry out. However, this may
not be achievable in some cases due to adverse atmospheric conditions such as
presence of moisture, dirt or dust etc. The minimum PI value acceptable for
satisfactory operation in such cases shall be taken as 1.5.
General Note:
The IR values recommended are for guidance. As stated in IEEE-43, it is impractical
to specify a definite minimum value of IR or PI of a rotating machine below which
the machine cannot be operated. It is recognized that it is sometimes possible to
operate a machine with value lower than the recommended minimum value, but it is
not considered a good practice in the majority of the cases.
A - 2.5
ANNEXURE – III
STATOR FORM AND ROTOR FORM
3.1 GENERAL
The purpose of checking stator and rotor forms is to minimize the inequalities in the
air gap all-round the circumference. This will ensure minimum possible unbalanced
magnetic pull with the built up stator and rotor, which will have a beneficial effect on
vibration performance of generator.
The stator and rotor must be built as circularly as possible, ensuring that the
difference in radius of diametrically opposite poles is within 0.2 mm. This can be
achieved by building the rim concentric to the spider (i.e. ensuring uniform gap on all
key bars) and properly grinding the pole seating surface and T-Slot groove in rim
while assembling the rotor poles.
The minimum air gap has been marked as AB in Fig. A 3.1. As explained above the
direction of stator shift is opposite to the maximum air gap i.e. in the direction B to
A as shown in Fig. A 3.1.
The decision regarding the amount of stator shift shall be taken only after carefully
analyzing the stator the stator form and rotor form reading. As mentioned above in
4.2 above half the difference of appositive air gap stator form reading, at location of
maximum air gap (i.e. Pole 14 & pole 6 in fig. A 8.1) is the amount of stator shift.
Since both the stator and rotor form are not truly circular the effect of stator shift on
air gap at adjacent pole may be different. Considering this factor and to get
optimum air gap reading, the average of half the difference of air gap readings of
adjacent poles are taken to decide the amount of stator shift, as explained in the
table below:
A-3.3
S.NO. AIR GAPS DIFFERENCE HALF THE AVERAGE AMOUNT
DIFFERENCE SHIFT OF STATOR
SHIFT
(1) (2) (3) (4) (5) (6)
Pole 15 Pole 7
Top 2.5 1.35 1.15 0.575
Bott. 2.95 0.30 3.25 1.625
NOTE:
(1) The readings given in column (1) & (2) are the difference in
Rotor form and stator form e.g. length of line AB for pole no. 14 in Fig. A 3.1 is
3.7 mm.
(2) The value is Col. 4 indicates the amount of stator shift
required as described in Para 3.4.
(3) The column 5 indicates the average of readings in column 4
for Pole nos. 15 & 14 and set of Pole 14 & 13. From the above it can be seen that
the stator has to be shifted by 0.9 mm (i.e. rounding off 0.915) to 1 mm (i.e.
rounding off 0.975) to achieve optimum air gap readings. This is decided after
careful study of complete set of readings. The bottom average air gap readings
1.525 and 1.326 have been ignored because shifting the stator by this amount
would have deteriorated the top air gap readings.
A 3.4
ANNEXURE - IV
APPLICATION OF MOLYBDENUM-DI-SULPHIDE GREASE
In the main body of this MANUAL, the location for greasing have been indicated in
respective sections. The following, however, summarises the locations where
MOLYBDENUM-DI-SULPHIDE GREASE has to be applied:
(i) a thin coat on top seating surface of stator sole plates before lowering the
stator. The grease should also be applied on the contact faces of holding down
bolts and dowels.
(iii) on rim keys before their assembly and seating surface of key-bar.
(iv) on rim locking key under surfaces coming in contact with top rim end plates.
Refer Fig. 5.3.
(v) on the radial keys for shaft and spider coupling. Refer Fig. 5.4, Section - 5.
(vi) on all dowels (e.g. top bracket and stator frame) before putting them in place.
A - 4.1
ANNEXURE – V
CHECKING ROUNDNESS OF ROTOR
5.1 It is necessary to check the roundness of the rotor in order to minimise the
variation in air gap. For this, radius of pole face shall be measured and it should be
ensured that the difference in the radii between any two diametrically opposite
poles is in the range of 0.2 to 0.3 mm.
5.2 The checking of rotor diameter shall be done on both rim A/F and pole O.D.
where the difference in radii is beyond permissible limits, the relevant poles shall
be taken out and rim-seating surface shall be ground to remove the high
spots/protruding punching and the poles re-assembled.
5.3 The measurement of pole face radius can also be carried out with the help of
stick micrometer. Readings are taken between the centralized piano wire and a
straight edge which is firmly pressed against the pole face at its tip center.
5.4 Minimizing the radii difference to reduce the air gap variation will reduce the
UNBALANCED MAGNETIC PULL in operation and will result in low vibration
of the rotor shaft system and bearing brackets.
5.5 While re-assembling the poles on the rotor after correcting the roundness, it is
necessary to ensure that the centre lines of all poles are matching for proper
checking of the magnetic center of the unit at a later stage. For this purpose, refer
to the detailed procedure on magnetic Centering.
5.6 After grinding operations are over, utmost care must be taken to clean all
surfaces free of iron filings, dirt and dust. Otherwise this may lead to a possible
earth fault at a later date.
NOTE :
It is necessary to check the pole face radius at top and bottom of each pole.
The verticality of each individual pole shall be within 0.3 mm, when measured after
assembly on rim. Any large variation could be due to
(i) Rim face not being vertical,
(ii) seating surface of pole on rim not being flat, and
(iii) protrusion of rim punchings or pole punchings.
The verticality can be corrected by grinding of the rim surface and/or seating surface of
pole body which will be in contact which rim.
A - 5.1
ANNEXURE VI
REPLACEMENT OF STATOR BAR AND FIELD COIL
6.1 PROCEDURE FOR CHANGING A FAULTY/ DAMAGED STATOR BAR
6.1.1 Fault location
In many of the cases, the fault can be located by visual inspection after opening the air
guides. Otherwise, the fault can be located by using 2.5 kV megger by sectionalising
the faulty branch.
A 6.1
slings to be passed under both ends of the coil. This can be done by driving wooden
wedges between the pole tips and insulation flange at intervals alongwith side of the
coil. The coil can now be lifted out by passing manila rope (not steel) slings over the
ends of the coil, care being taken to prevent damage to the copper turns from the
slings by interposing a thick sheet of press board. Thoroughly clean all deposits of
dust from the pole body and insulation packers by a clean cloth moistened with white
spirit or Lectraclean and dry by blowing compressed air. Retain the springs under the
field coils or reuse during reassembly.
Assemble the spare coil on the pole body after cutting of the unwanted leads,
flush to copper turns. The spare coil can be then be used in any position. Ensure that
the clearance is uniform on all four sides. The existing pole body insulation can be
used, if undamaged, otherwise new pole body insulation is to be used. First assemble
the corner angle and then epoxy glass laminate sheets. If any clearance is found
between pole body and field coil, this is to be filled epoxy glass fibre sheets. No
slackness is permitted between field coil and pole body. Assemble the steel washers
and the insulation flange of the coil. Check that the height that the height of the coil
assembly is as per drawing. Never lift the coil by slinging around projecting field
turns, as this may result in de- lamination of turns.
Check the IR value of the field coil and also measure its AC impedance.
Conduct HV test as per Annexure-I between the coil and the pole body. Next
assemble the pole on to the rotor. Measure the AC impedance of the coil again if
satisfactory, conduct HV test as per Annexure-I between the coil and pole body.
Finally, connect the pole leads to the adjacent pole and solder the joints using solder.
If a field coil is replaced at any p time, care should be taken to ensure that
the pole is polled hard down on the rotor rim. When the pole keys are driven in. This
can be checked by seeing that there is no gap between the pole body and the rim
seating surface. However, the spring allowance between the steel packers and rim
surface must be available around.
A 6.2