KITACON SDN. BHD. & PEMBINAAN KITACON SDN. BHD. FORM NO.

HAZARD IDENTIFICATION, RISK ASSESSMENT & DETERMINING CONTROL REV.


Rev. No.:________
Project / Location: Name of Job: Prepared By: Reviewed By:
R4 / BBR111, Bandar Bukit Raja 2, 2. Installation of Hoarding
Klang, Selangor. Date: Date:

2. Installation of Hoarding
HAZARD IDENTIFICATION RISK ASSESSMENT
Current Control Measures /
Responsibility
No Job Sequence Hazard Potential Risk Probability Severity Risk Recommendation

Mechanical -Minor injury (5) Machine operated by competent operator.


Delivery of Material Struck by moving part of -Damage to property / 2 3 6 - Workers stay away from moving machine.
Loading and machine utilities (6) To provide appropriate PPE.
1
unloading material Physical (5) Machine operated by competent operator.
-Serious injury
(Metal Decking) Falling object – during lifting 2 4 8 - Machine inspection before work commences.
-Damage to property (6) To provide appropriate PPE.
of material
(5) Supervised by designated person during stacking of Project Manager
Physical
material. Site Manager
Slip / fall / collapse of material
-Serious injury 2 4 8 - Routine checking to ensure stability of material.
due to poor material - To ensure material not obstruct any access way. Site Agent
Stacking / Storing arrangement (6) To provide appropriate PPE.
2 Site Engineer
material at site area (5) Machine must operate by competent operator.
Physical Site Supervisor
- Workers stay away from moving machine.
Struck / hit by moving part of -Minor injury 2 3 6 - Designated person to supervise lifting activity. SHO / SSS
material during lifting activity (6) To provide appropriate PPE.
EO
(4) Safety guard are in good condition.
Mechanical Scaffolder
-Serious injury 2 4 8 (5) Work carry out by skill workers.
Hand cut by cutting equipment (6) To provide appropriate PPE. Work Leader
Physical (5) Work carry out by skill workers. Machinery opr/
- Minor injury 2 3 6
Struck by flying object (6) To provide appropriate PPE.
-Minor injury Driver
(5) Work carry out by skill workers.
Noise exposure (long term can impair 2 3 6 (6) To provide appropriate PPE.
Signalman
Installation of workers hearing) Banksman
hoarding (5) Material handling should be carried out with correct
3. Physical (Ergonomic) Rigger
(Frame & Metal -Negligible injury 2 2 4
method.
decking ) Improper method of handling - Take a 2-3 minutes rest after every 2 ( two ) hours. Welder
(6) To provide appropriate PPE.
Workers
-Heat stress (low (4) Good / open ventilation at working area.
Psychological - To provide shelter/ rest area & drinking facilities
productivity) 2 3 6
Hot weather (5) Take a 2-3 minutes rest after every 2 ( two ) hours.
- Skin burn (6) To provide appropriate PPE.
Physical (4) To ensure hand-tool in good condition.
-Serious injury 2 4 8
Hit by hand-tool (6) To provide appropriate PPE.

Legend:
(1) Eliminate ; (2) Substitution; (3) Isolate; (4) Engineering Control; (5) Administrative Control; (6) Personal Protective Equipment (PPE)