Employer Design

straight Forward
Contractor Design

Project
Book
S.No Condition Of Contract
Plant and /or high
unforeseen Risks

Condition Of Contract For


1 Red No Yes N/A
Construction
Condition Of sub Contract For
2 Red No Yes N/A
Construction
Condition Of Contract For plant &
3 Yellow No No Yes
deign Build

Condition Of Contract For


4 brown No No N/A
Deign,Build & Operate Projects

Condition Of Contract For EPC


5 Orange No No N/A
/Turn Key Projects

6 Short Form Of Contract Green Yes Yes N/A


Sum Little employer

Major Unforeseen
Fixed Price-Lump

Involvement No
Contractor Design

risks
Remarks
Plant and /or high
unforeseen Risks
Maintenance

N/A N/A

N/A N/A

N/A N/A

Yes N/A

N/A Yes

1.If the price for the contract is relatively small, say under
US$ 500,000, or the construction time is short, say less than 6
months, or the work involved is relatively simple or
repetitive - dredging work might be a good example: then
consider using the Short Form of Contract, which is a
completely new FIDIC Book specially prepared for such
projects.
N/A N/A
2.It does not matter whether the design is provided by the
Employer (or his Engineer/Architect if he has one) or by the
Contractor,

3.It does not matter whether the project involves


construction, electrical, mechanical, or other engineering
work.