PURPOSE
The Seattle Department of Transportation (SDOT) recently completed a comprehensive assessment
of the Levy to Move Seattle project delivery work plan and budget. This report summarizes key
findings and provides a framework for moving forward.
BACKGROUND
In Spring 2015, SDOT reached out to communities across Seattle to understand their priorities
for our transportation system. As a result of community feedback, SDOT and the former mayoral
administration developed the Levy to Move Seattle proposal and submitted a plan to the Seattle City
Council for consideration. In June 2015, the full Council amended and approved the Levy to Move
Seattle proposal and recommended Seattle voters consider the proposal in fall 2015.
In November 2015, Seattle voters approved the Levy to Move Seattle. The nine-year, $930 million
transportation levy funds safety improvements, street and bridge maintenance, and investments in
reliable, affordable travel options for a growing city. The levy includes three main funding categories
– Safe Routes, Maintenance & Repair, and Congestion Relief – and several tiers of specific
commitments. To deliver this program, SDOT assumed a total of $1.77 billion in funding, including
the $930 million in Levy to Move Seattle funding, $285 million in local funding, and $564 million in
regional and federal grants and partnerships.
November 2015 January 2016 May 2016 January 2017 October 2017 Early 2018
Seattle voters SDOT begins to First meeting of New federal Office of Move Seattle SDOT conducts
approve the Levy implement the Levy the Levy Oversight leadership formed to take a an assessment
to Move Seattle to Move Seattle Committee creates comprehensive view of the Levy to
uncertainty in of the levy program Move Seattle
federal funding and provide strategic project delivery
assumptions direction to SDOT
leadership
Process
With direction from Mayor Durkan and her new The assessment included a review of original
executive team, SDOT completed a comprehensive levy commitments; an evaluation of the scope,
assessment of the Levy to Move Seattle delivery schedule, cost and funding assumptions for
program as a result of delayed project delivery each levy commitment; and a consideration
in the first two years of the levy and funding of program management strategies
uncertainty created by the federal administration recommended by CDM Smith, a third-party
change in 2017. consultant, to improve project delivery.
Key findings
The assessment highlighted two key findings:
1. Parts of the original program need further 2. Program management structure, systems and
review and adjustment due to: tools need attention and investment.
Cost estimate increases The Office of Move Seattle was chartered in
Like other agencies in the region, costs have 2017 to help manage the size and complexity
increased due to rising local construction of Move Seattle, a program three times larger
costs, higher inflation than forecasted using the than the nine-year, $365 million Bridging the
Consumer Price Index, and more detailed project Gap levy. Working together with CDM Smith, the
scope and schedule information. Additionally, team identified several areas where additional
in several levy sub-programs, cost estimates strategies are needed to successfully deliver
included in the original budget were insufficient a program of this scale. These included:
to meet the levy commitment. streamlining and accelerating contracting and
procurement; ensuring consistent systems
Additional community transportation priorities and tools for scope, budget, risk and quality
Between the publication of the levy commitments management; and improving the process for
during levy outreach in 2015 and the time of this identifying and hiring resources.
assessment, additional citywide transportation
needs (e.g. Americans with Disabilities Act
consent decree, Sidewalk Assessment, Sound
Transit 3) have been realized and present
challenges and coordination constraints to
delivering the original levy.
Funding limitations
The recent federal administration change has
created uncertainty and limited the feasibility of
receiving some federal grants. While grant funds
have been secured and partnership opportunities
identified in the first two years, these funds are
restricted to specific sub-programs or types of
work.
CONGESTION RELIEF
Corridor Mobility Light Rail Partnership
Multimodal Improvements: Complete 7 transit Light Rail Connections: Provide city funding
plus multimodal (RapidRide) corridor projects, contribution for a new Link light rail station at
redesigning major streets with more frequent Graham Street in southeast Seattle
and reliable buses, upgraded paving, signals Northgate Bridge: Finalize design on this
and other improvements to improve connectivity project that will improve connections over I-5 for
and safety for all travelers, whether walking, pedestrians and bicyclists to the future light rail
biking, driving, or taking transit; complete the station at Northgate
Burke Gilman Trail Missing Link, Fauntleroy Way
Southwest Boulevard projects, develop plans Light Rail Connections: Implement early portions
and complete improvements to enhance the NE of the accessible Mt. Baker project
45th St Corridor for pedestrians and cyclists
between 4th Ave NE and Brooklyn Ave NE by the
Pedestrian and Bicycle Improvements
time University Light Rail opens in 2021, and plan New Sidewalks: Build 150 new blocks of
corridor improvements for Aurora Ave N sidewalks, filling in more than 75% of the
sidewalk gaps on priority transit corridors
Traffic Signal Timing Improvements: Optimize
citywide with an emphasis on creating accessible
traffic signal timing on 5 corridors throughout the
routes for those with disabilities and for the
city each year to improve traffic flow and serve
elderly
people in cars and trucks, on bicycles, taking
transit, and on foot Bicycle and Walking Facilities: Make residential
streets without sidewalks safer and more
Intelligent Transportation System
comfortable for walking, including through
Improvements: Implement Next Generation
partnership with Seattle Public Utilities in the
Intelligent Transportation System (ITS)
flood-prone Broadview neighborhood
Improvements to help all travelers move more
reliably around the city and provide improved Bicycle and Walking Facilities: Install 1,500
information for travelers new bicycle parking spots citywide and maintain
existing bike facilities. Install other biking and
Transit Corridor Improvements: Make bus
walking investments.
service more reliable through a comprehensive
transit improvement program to eliminate
bottlenecks in key locations and contribute to the
Freight Mobility Improvements
transit improvements on 7 transit plus corridors Partnership Improvements: Provide local money
including planning for access and egress to design and build the Lander Street Overpass
improvements to the West Seattle peninsula Heavy Haul Network: Build the East Marginal
Way corridor, a key route in Seattle’s Heavy Haul
Network
1 Bicycle Safety – Build approximately 50 miles The cost to meet levy commitments SDOT will work with the Seattle
Bicycle Master Plan of new PBLs and 60 miles is greater than originally anticipated. Bicycle Advisory Board and
(BMP) of greenways, completing Original estimates assumed bicycle stakeholders to prioritize
over half of the BMP citywide approximately $860 thousand as an a combination of bicycle facilities
network. average per-mile cost for bicycle (PBLs, greenways, trails, climbing
facilities. While costs vary significantly lanes, buffered bike lanes and bike
by location, most PBL and greenway lanes) that are consistent with
projects are now estimated to cost more guidance included in the BMP and
than the original figure. fit within the available funding.
SDOT will continue to research
The original levy deliverable and incorporate best practices to
commitments are not aligned with the implement bicycle facilities for all
BMP, adopted by City Council in 2014. ages and abilities.
2 Pedestrian Safety – Build 150 new blocks of The cost to complete the level of new SDOT will work with Seattle’s
New Sidewalks sidewalks, filling in more than sidewalk investment that aligns with Pedestrian Advisory Board and
75% of the sidewalk gaps this levy sub-program is greater than pedestrian stakeholders to
on priority transit corridors originally anticipated due to the addition determine how this deliverable
citywide with an emphasis on of levy deliverables without adequate will be measured within available
creating accessible routes for funding in 2015. funding, delivering a combination
those with disabilities and for of low-cost and concrete sidewalks
the elderly. throughout the city.
3 Multimodal Complete seven transit With current funding, SDOT can deliver SDOT will continue to plan and
Improvements- plus multimodal corridor investments on all seven RapidRide design projects while further
Transit-Plus projects, redesigning major corridors. However, the cost to complete evaluating funding opportunities
Multimodal Corridors streets with more frequent a level of investment that aligns with the and community priorities for each
(RapidRide) and reliable buses, upgraded higher mobility needs of our growing city corridor. A sub-program update and
paving, signals and other and meets community expectations is funding strategy are expected to
improvements to improve greater than available funding. be complete this summer and will
connectivity and safety for all be shared with the Levy Oversight
travelers, whether walking, Committee and key stakeholders to
biking, driving, or taking inform next steps.
transit…
4 Pedestrian Safety - Repair up to 225 blocks of SDOT has been counting “one block” as SDOT will work with the Levy
Sidewalk Safety damaged sidewalks in our equal to one full block face of a sidewalk, Oversight Committee to recommend
Repair urban centers and villages. or multiple small repairs totaling a how this deliverable will be
typical block face (i.e. 1,500 square measured within available funding,
feet). If it continues to be measured this such as measuring spot repairs
way, the funding allocated to this sub- made on block faces.
program will not be adequate.
5 Arterial Roadway Repave 65 targeted locations The cost to complete levy commitments SDOT will work with the Levy
Maintenance – every year, totaling about 70 is greater than originally anticipated. Oversight Committee to develop how
Arterial Major lane-miles of arterial street, This increase reflects rising construction this deliverable should be adjusted
Maintenance (AMM) with a repair and maintenance costs due to local market conditions and within available funding.
program run by city crews. added scope for replacing curb ramps as
part of this work. Additionally, SDOT will implement
strategies to reduce the cost for this
As this work is primarily done on a “spot sub-program.
repair” basis, a majority of this sub-
program budget needs to be allocated
towards spot repairs. On average, SDOT
completes approximately 38-65 spot
repairs per year.
6 Arterial Roadway Repave up to 180 lane-miles While not a formal levy commitment, SDOT will prioritize paving projects
Maintenance – of arterial streets. SDOT published a preliminary list of based on pavement condition
Arterial Asphalt & paving projects during the levy outreach and travel volumes to meet the
Concrete (AAC) period in 2015. commitment to repave arterial
streets within available funding. As
The original budget also assumed the project list is updated, SDOT
leverage opportunities which are not will share information with the Levy
available. Oversight Committee.
7 Bridge Replacement - Plan and design high-priority The original budget assumed leverage SDOT will prioritize available funding
Planning and Design bridge replacements to begin opportunities which are not available. to advance planning and design for
construction after 2024. Of bridges that are most vulnerable
the funds identified in this Cost estimates for planning and and in need of replacement. SDOT
element, up to $10 million design work are greater than originally will share this list with the Levy
of total funding (local, levy, anticipated and some bridges are no Oversight Committee and seek input.
leverage) may be used for longer the city’s top priorities.
implementing near-term SDOT will allocate $5 million in
pedestrian and bicycle safety funding to complete near-term
projects on bridges being bicycle and pedestrian safety
studied for replacement (in projects on bridges.
addition to funding provided
for pedestrian and bicycle
safety projects in other
elements).
8 Pedestrian Safety - Make curb ramp and crossing The cost to improve intersections is SDOT will implement strategies
Curb Ramps and improvements at up to greater than originally anticipated. to reduce the cost of designing
Crossings 750 intersections citywide This increase reflects a rise in the and constructing curb ramps and
creating accessible routes for cost for curb ramps, and that most intersections to deliver this sub-
those with disabilities and for intersections require multiple curb program within available funding.
the elderly. ramps as compared to other lower-cost
improvements such as curb bulbs and/or
pedestrian push buttons.
Public engagement
SDOT will engage the Levy Oversight Committee, key stakeholders and the public in developing a set of final
recommendations to be incorporated into an updated Levy to Move Seattle delivery plan.