Escolar Documentos
Profissional Documentos
Cultura Documentos
INTRODUCTION
This presentation provides general criteria for designing living quarters. Although the
emphasis is on living quarters for offshore platforms, some of the concepts discussed
are equally valid for living quarters at other remote locations. Design Considerations
subject contains a broad overview of design considerations that must be taken into
account before a detailed quarters design can be developed. To some extent, these
considerations may affect quarters layout and the location of the quarters within the
facility.
In the Layout Selection subject some guidelines are presented for initially selecting
an overall quarters size and making an approximate allocation of plan area among
the different areas within the quarters. Included in this subject are items to be
considered when laying out individual rooms. Example room layouts are presented in
the last subject.
General
Quarters buildings are designed to house people comfortably and safely, regardless
of the surrounding environment. However, the variety of environments, number and
type of personnel, and function of the quarters leads to many different designs.
Design problems presented by the Middle East are different from those encountered
in Alaska. A building in the North Sea, where work-shifts are longer than in the Gulf
of Mexico, requires different considerations. A building designed for Africa may need
to reflect cultural differences. Quarters that house drilling personnel may have
different requirements than quarters that house production personnel (i.e., a change
room). Quarters may be multipurpose and may, for example, contain generator
packages or may incorporate a helicopter pad.
A. Live Loads
2 2
Area (kg/m ) (lb/ft )
Actual
C. Wind Loads:
Wind loads depend on location, but they are based on the formula, P = 0.0625 V 2 C s C h (metric), or P
= 0.0256 V 2 C s C h (customary), where P is the wind generated pressure in kg/m 2 (lb/ft 2 ), V is
velocity in m/s (mph), C s is a shape factor, and C h is a height above water factor.
* When the surface is flat and height is less than 15 m (50 ft) above the water.
** Building surface is flat and height is 15 m (50 ft) to 30 m (100 ft) above the water.
D. Other
Loads
Handrails 90 kg (200 lbs) applied to the rail at any point in any direction
Quarters are much different from the normal architectural structures such as schools
and houses. Quarters design resembles ship-building, where space and fit are a
problem. Air conditioning ducts, pressure and gravity pipes, as well as electrical
conduit/wiring, all compete for limited space. Window locations may well be
determined by furniture location, especially in bedrooms. Redesign of an entire floor
might be required because sufficient space was not allowed for the specified washers
and dryers. Equipment must be moved through passageways, and turns must be
able to accommodate the furnishings.
Machinery and fixtures must get in and fit together. The quarters must function; it
must be safe, long lasting, and please a multitude of people.
Kitchen design is something of a specialty. The best and most interested source is
the caterer who might be using the facility. The layout of the work floor of a kitchen
is very important. See Appendix for examples. Workers and material should travel
minimum distances, proceeding in a logical sequence with a minimum of criss-
crossing and backtracking. Delays in storage of materials, in processing, and in
Figure 1
A wall must bear wind loads (see Table 1) and act as diagonal bracing in the
quarters frame. Wall plates may be flat or crimped and are normally 4.8 mm (3/16
in) thick.
The section modulus of crimped plate may be substituted for angle or channel
stiffeners with flat plate. Crimped plate is generally considered more attractive due
to its texture. However, the exterior wall is thickened and may therefore introduce a
space problem. Not all manufacturers can crimp plate, and few can handle plate over
3 m (10 ft) in width. Thus, available plate width may be a consideration in selecting
floor-to-floor heights.
Light gauge siding, shown in Figure 3 (Exterior of quarters with light gauge metal
siding.), is not as tough or durable as plate.
It is easier to replace and lighter. However, the use of such siding makes it difficult
to pressurize the building. In an area where high wind loads are present, the
structure needed to transmit those loads from a light skin to the frame may increase
in cost due to additional diagonal bracing. This may make the light gauge alternative
uneconomical.
The geometry of shape affects cost. A square building uses less wall material to
contain the same square footage of floor area as a rectangular building.
A top lift is preferred since lifting from the skid requires the use of a spreader bar. A
well-designed roof or heliport will absorb the horizontal forces exerted by slings
during lift. For larger buildings where padeyes are farther apart, the need for
diagonal bracing should be investigated.
Padeyes are generally the most critical aspect of the structural design. Rooftop eyes
must accommodate the sling angle. The smaller the angle the more the horizontal
load that is introduced into the roof. Therefore, the angle should be 45 degrees or
greater from the horizontal, with 60 degrees being preferred. A very heavy pin must
be inserted in the sling and padeye, and sufficient space must be allowed. Unless the
building has a centrally positioned center of gravity, the load will not be equal on all
slings. The sling length can sometimes be adjusted with shackles to level the load.
However, an additional safety factor must be included for the effect of the eccentric
load.
Drains in the padeye wells should be provided. The padeyes should be spaced to
balance the lift load. However, the lift columns must carry the major downwind loads
to the platform and must be located appropriately. Small adjustments may be
necessary to miss windows and doors.
Structural floors may be wood, steel plate, or poured concrete. Wood was more
common in the past than it is today. If wood is selected for floors, consider sandwich
panels for span and strength. A structural semi-lightweight concrete floor is cheaper
and faster to place than steel, allows the sloping of floors to drain, and does not "oil
can" (develop an uneven appearance). The disadvantage is that the concrete floor is
73 kg/m2 (15 lbs/ft2) heavier than 6.3 mm (1/4 in plate).
Heliports can be raised or incorporated as the roof. Heliports without air gaps are
more susceptible to turbulence and should therefore be larger. The Federal Aviation
Administration publishes a design guide for heliports. The API RP 2L on planning,
design, and construction of heliports.
Walkways, stairs, and handrails, both internal and external, should be given close
attention. These fixtures are closely related to personnel evacuation routes and
contribute to the overall safety of the quarters. Handrails should be designed for
loads as shown in Table 1.
Figure 5
and Figure 6 (Example handrail and grating detail) show examples of external and
internal handrail details.
The maximum angle for stairs should be less than 45 degrees from the horizontal.
Treads should be non-skid design and large enough not to present a trip hazard in an
emergency. A typical exterior stairway design is shown in Figure 7 (Exterior
stairway).
Some guidelines for stairway arrangements are presented in Figure 8A and Figure 8B
(Recommended stairway arrangements).
Figure 8B
The coating system is the chief protection of a building in a harsh environment. Blasting and
recoating of buildings or structures on location is an extremely expensive procedure. Therefore,
the quality of the original job is of the utmost importance. Normally a coating system similar to
that used to protect the other structures will be chosen. Interior painting in a quarters building,
while limited, should be of good quality and easy to clean. The full coating system should be
applied to the steel before windows and aluminum doors are installed, if possible.
Galvanizing protects steel in some of the more exposed locations such as exterior
grating and handrails. Galvanized surfaces may be painted for extra protection or
aesthetics, but painting is an additional expense. Handrails should be checked after
galvanizing for drips and sharp edges. Imperfections should be buffed off.
Sandblasting
Sandblasting provides the anchor pattern to hold the paint to the surface to be protected. The key
to a proper paint job is a good surface preparation. There are three common grades of
sandblasting specified by standards set by the Structural Steel Painting Council. The least
effective preparation is "sweep" blasting, then "commercial" blast, with the best preparation being
"white" blast. "White" blasting is usually required for all exposed surfaces.
Exterior Openings
In the offshore environment an architectural window is not sufficient. The usual
marine window is 0.6 m by 0.9 m (2 ft by 3 ft). Aluminum is the most commonly
selected material. Windows may be fixed or operable. Where the building is
pressurized, consider fixed windows. Where the building has a controlled interior
environment, windows are seldom opened. Windows must be considered in designing
heating, ventilation, and air-conditioning systems
Screens on operating windows are optional, but some sort of shade should be
provided inside. Complete black-out shades are normally used in sleeping areas, with
venetian blinds being used in other areas. Opaque glass may be called for in certain
locations. Aluminum windows must be insulated from the steel to control electrolysis.
Hardware for the windows is generally furnished by the window manufacturers.
Exterior doors are usually of hollow metal steel or aluminum. Aluminum is preferred
except where fire ratings are required. Steel doors and frames should be galvanized
before coating, and all doors should be insulated. Small vision panels should be
provided. Codes may restrict these to 64,500 mm2 (100 in2). Fire rated and labeled
Exterior openings should be caulked with top quality silicon sealant and water-tested
under a firehose to duplicate wind-driven rains in storm conditions.
Interior Finishes
General
Interior Finishes should be chosen for safety, durability, comfort, and aesthetics.
Partitions
Metal studs are normally used. These are usually 20 gauge galvanized and
perforated in 92 mm (3 5/8 in) and 143 mm (5 5/8 in) widths. Gypsum board back-
up is then applied. By using 16 mm (5/8 in) fire coded sheetrock on both sides of the
stud, a one-hour fire protection rating can be achieved. A typical partition is shown in
Figure 9 (Typical interior partition).
Plywood may also be used as a back-up, but it does not have the same fire rating.
Some treated lumbers and plywoods are fire retardant, but their specifications must
be checked closely, especially with regard to humidity. Treatments designed for
exterior use (high humidity) contain formaldehyde, which may pose a smoke risk to
the occupants in the event of fire. The treatment for interior usage has humidity
limitations. Exceeding these limitations may cause leaching of the treatment, which
may cause damage to any metal it contacts. Care should be exercised to assure that
proper application of the interior products is made.
Ceramic tile is popular in showers and baths. Other options are covered in the
mechanical section.
Floor Coverings
Floor coverings fall under two major classifications: hard and soft. There are a
number of types of grouts used between the tiles after they are in place. An epoxy
grout is best for galleys and other locations of hard use and frequent cleaning. Hard
floors include ceramic tile, quarry tile, and terrazzo. Ceramic and quarry tile floor can
be "thin set" (glued down), or "mud set" (seated on a bed of sand and cement
grout). Mud set is preferred because it allows for sloping to drains. Generally, it is a
good idea to use hard floors in wet areas such as kitchens and bathrooms and to use
soft tiles in other areas.
Soft floors are the various resilient tiles such as vinyl and reinforced vinyl, sheet
goods, carpets, and several poured finishes.
Sheet goods have fewer seams than tiles and are preferred. Carpets may be used if
a little more luxury is desired.
The base trim, the strip at the bottom of the wall, is designed to protect the wall
during mopping and floor cleaning. 100 mm (4 in) high extruded aluminum base is
popular in quarters. A vinyl base may be used with vinyl floors but may tend to come
unglued. Against wood paneling, a wood base may be used and ceramic or quarry
may be used to match the floor.
Ceilings
Ceilings, or "overheads" as they are called on ships, should be selected for fire
protection, lack of smoke development, sound attenuation, cleanability, and access
to the attic spaces. The priority is dictated by the use of the particular spaces.
Kitchens and baths need a hard, scrubbable surface easily removed for cleaning.
Sleeping and public areas need more sound absorption. No ceiling should ever be
inflammable. An unfaced fiberglass batt over the ceiling helps with sound control.
Figure 11
Some ceilings carry a fire rating. In normal buildings, the grid is hung with a 9 gauge
wire, in accordance with a recognized industry standard. However, quarters buildings
are constructed to be transported and lifted, and may be dropped. Extra caution,
therefore, must be taken with a ceiling. Light fixtures must be securely attached to
the structure surface, not the ceiling. Rods at all four corners are preferred for this
purpose. If a building is dropped or landed hard, the fixtures could bring down the
ceiling.
Interior doors may be wood or hollow metal steel. Wooden doors may be solid core
or hollow core. Solid wood doors are preferred over hollow core. See Table 2 for
example door widths.
Galley 910 mm 3 ft 0 in
Cabinets
Cabinets must be heavy-duty and durable and mounted on a structural surface. The
design should reflect the function, and as much storage space as is practical should
be provided. Kitchen cabinets and shelving in larger quarters should be stainless
steel. Wood cabinets should be of solid plywood and not those generally chosen for
residential use. Wood cabinets clad in a laminated plastic are preferred over painted
wood surfaces in quarters buildings.
Accessories
Choose brass or stainless steel with a heavy duty finish. Attach the fixtures to the
wall with screws because factory attachments do not stand up. Provide an ash
receptacle at each exterior door unless smoking is prohibited. There should be
adequate coat hooks throughout the building. Except in a private bath, towel bars
are seldom used. Towel hooks are Preferred Near Shower Stalls.
Furnishings
Furnishings are a matter of individual choice provided they are functional and heavy-
duty. Adequate shelf space and file drawers should be provided for all documentation
required to operate the facility properly. Bunks need to be large and comfortable.
Provide as much private locker space as is possible. Bunks and lockers should be
securely attached to the wall. Provide adequate bunk lights and bunk shelves at each
bed space. Bunk curtains are a good idea. They block the light from a bunk light if
one person wants to read and the other wants to sleep. Figure 12 (4-man bedroom
with bunk beds) shows bunks installed in a four-man bedroom.
Consideration should be given to including lockers, a desk with a chair, and a waste
basket in each bedroom. More luxurious spaces including lounge chairs and
televisions may be provided. Areas provided for reading, TV watching, card playing,
pool, or even workouts are furnished according to their use. More elaborate and
comfortable quarters may be required in those areas where work shifts are extended
or where the isolation of the location allows few diversions.
Food Service
The food service should be sized according to the number of people eating rather
than the number sleeping. The following items are normally required:
In some parts of the world cultural and religious dietary considerations may dictate
two separate kitchens. Storage capacity for frozen food and dry storage depends on
the number of personnel and frequency of supply. A typical galley is shown in
Figure 13 (Galley.
Figure 13
Thermal Insulation
Fiberglass thermal insulation such as that shown in Figure 14 (Fiberglass insulation
installed in exterior wall) is most commonly used in walls and roofs.
Floors are more difficult to insulate. A concrete deck requires less insulation than a
steel deck. One approach is to install a fiberglass board on pins welded to the
underside of the floor. Another is to use spray-on insulation. Cost/benefit ratios
should be discussed with a specialist.
Adhesion may be a problem with spray-on insulation applied to the underside of floor
structures with smooth coating systems. Tapes are available to measure adhesion
and should be used to assure a quality job. Most spray insulation, whether applied
vertically or horizontally, requires a layer of wire reinforcing for thicker applications.
Check the manufacturer's literature for exterior use under offshore conditions.
Excessive noise may significantly affect comfort. The use of acoustical tiles and
carpets helps to deaden sound. It may be necessary to provide sound-attenuating
walls in mechanical equipment rooms or to install sound-attenuating enclosures
around the equipment itself to keep sound from spreading to other areas of the
building.
In some offshore quarters designs the heliport is located on the roof of the quarters.
Helicopter traffic can be a source of both noise and vibration. While the duration of
the nuisance may be short (only during take-off and landing) and will not affect
those who are awake, it can be very disturbing to those who are asleep. An effective
way to minimize the disturbance to sleepers is to elevate the helideck 2.5 to 3.0 m
(8 to 10 ft) above the roof of the quarters and to isolate its structural support from
the skid of the building, as shown in Figure 15 (Quarters building with elevated
helideck being placed on barge).
Figure 15
Mechanical
In buildings, the term "mechanical" refers to plumbing, heating, ventilation, and air
conditioning equipment. Figure 16 (Underside view of quarters building showing
structure, plumbing, and electrical components) shows the underside view of a
quarters and its plumbing and electrical components.
The water supply may be split between potable and salt water. Potable water is
piped to showers, lavatories, drinking fountains, and sinks. Piping is usually copper
for potable water, both hot and cold. Plastics can be used as well. If plastic is used
on the hot water system, the temperature specifications should be checked. Salt
water may be used to flush toilets and urinals. Plastic piping is usually used for salt
water.
Fresh water may be supplied by a public utility and transported to location by ships,
or else it may be made on-site by a vacuum distillation or reverse osmosis water
maker. It is a good idea to filter either the entire potable system or the fixtures
supplying water for internal consumption. Treatment for bacteria is required.
Fresh water systems are normally designed for 375 to 475 l (100 to 125 gal) of
water per person per day. The amount of storage required for potable water depends
on the source of potable water. Many small platforms in the Gulf of Mexico get their
water from supply boats. Depending on the supply boat schedule, five to ten days of
storage may be provided. If water makers are installed to desalinate seawater,
storage should be sufficient to supply normal need if the unit must be repaired. On
large platforms, two or more water makers can be installed to minimize the need for
potable water storage. On large platforms in the North Sea where weather conditions
may preclude shipments of potable water, it is common to install stand-by water
makers as well as 7 to 14 days of storage. The design of the watermakers is beyond
the scope of this tutorial.
Wastewater piping is usually plastic, with special high temperature pipe used for a
distance of about 1.5 m (5 ft) from the dishwasher. Dishwashers normally use 82°C
(180°F) water. Cast iron, steel, and copper are sometimes used, but not with salt
The hot water system should be insulated to minimize heat loss. The cold water
systems should be insulated to prevent condensation if run in the ceilings. Exposed
water piping (both hot and cold) must be insulated for freeze protection if there is
that possibility.
Toilets and urinals are usually made of vitreous china. Sinks can be any material
from cast iron to stainless steel. Figure 17 (Porcelain sinks installed in gang shower)
Figure 17
and Figure 18 (Stainless steel sinks) show examples of porcelain and stainless steel.
Figure 19
Tile is desirable for individual showers as it is stiffer and more durable than
fiberglass, and it costs less than stainless steel. Group showers are usually ceramic
tile. Showerheads are usually sized for 9.5 l (2.5 gal) per minute flow.
Except for private or semi-private baths, usually one toilet is provided for each eight
people, one lavatory for each four, and one shower for each eight. Consideration
should be given to provide one drinking fountain per floor.
Hot water heaters are usually electric with high recovery capacity to provide
adequate hot water. The heater should be sized considering peak usage rates. Total
capacity calculated on daily use will be inadequate for the one hour peak usage at
shift change. For safety reasons, gas is not widely used for heating water or cooking
in offshore quarters.
It is not unusual to locate the hot water heaters on the roof of quarters. Check
valves should be provided for the supply side of each heater to prevent a loss of
pressure from draining the heater. The electrical submersion elements will burn out if
draining occurs.
There are two basic types of Western toilets (also called water closets), tank type
and flush valve type. Either type uses about 1.3 l (3.5 gal) per flush. The flush valve
type takes about 7 kg (15 lbs) of pressure to operate properly. Thus an operating
pressure of at least 9 kg (20 lbs) must be maintained at the highest level of the
building. Since storage vessels most likely will be at a lower level, a pump system
will probably be required. Flush valves require water that is free of debris that can
catch in the valve and hold it open. Urinals are usually flushed and equipped with
flush valves. Toilets are normally in a compartment and urinals are protected by
screens. Porcelain or stainless steel is best for these toilet compartments and
screens. In the Middle East and part of Africa, an Eastern type of toilet may be used
by native personnel.
There are two basic types of air conditioning used in most buildings: direct expansion
(usually a split system) and chilled water. Figure 20 (Schematic arrangement of a
chilled water system)
Figure 21
It is generally a good idea to design a zoned system, one for each floor. Sometimes
a system will have all bedrooms on one zone and all common areas on another. The
air supply flow of a central system is often more important to a well functioning
system than the refrigeration side. Attention to the duct design is essential. Since
humidity is the major key to sensible cooling, it may be a good idea to dry the air by
sub-cooling and then to reheat the air to a comfortable temperature.
One method used to conserve conditioned air is the use of air locks such as the one
shown in Figure 22 (Partial layout with air lock).
Figure 22
An air lock is formed by a second exit door set in a corridor four ft or so behind the
door to the outside. If both doors are not open at the same time, the volume of
Ventilation
Because of the odors generated in the building from cooking, bath use, and from
normal human occupancy, there must be an induction of fresh air. A certain amount
of fresh air enters through doors or open windows, but some must be brought in with
the air conditioning system. This fresh air is not to be confused with pressurization.
The kitchen is the largest generator of heat and odor. A hood over the range and
fryer is a necessity, but an exhaust hood also pulls out sizable amounts of
conditioned air. Some hood designs use a supply fan as well as an exhaust fan. The
two fans are balanced so that about 80 percent of the volume of the extracted air is
supplied back to the hood by the intake fan. This short-circuits the air over the
cooking surfaces and extracts odor and moisture without pulling too much air from
the building. Such a hood is known as an "energy saver" hood and is very cost
efficient.
Baths should have positive exhaust, and each bath should be independently ducted
to the exterior. Most guidelines call for a ventilation capacity of 1.4 m 3 (50 ft 3 ) of
air per minute per toilet. The method of supplying air to the room from the air
conditioning system and allowing for an equal amount of air to escape through fixed
vents does not work well. Air from an odor-generating area must not be allowed to
enter the return air flow because this causes odors to be distributed throughout the
building. Exhaust systems should not be combined. It is too easy for odors from one
area to escape to another.
Pressurization
While a well-designed air conditioning system provides a minor amount of positive
pressure in a tight building, certain locations may require an interior pressure
sufficient to insure that contaminated or potentially explosive air cannot enter the
building even through open windows and doors. To achieve this pressure, a separate
pressurizing system consisting of intake fans, pressure relief vents, and a duct from
the fans to a location of non-contaminated air for intake will be required. If this
pressurizing air is to be conditioned, there will be a requirement for extra heating
and cooling capacity. If, however, the need of such positive pressure is on an
emergency basis only, there is little benefit in spending the money necessary to treat
this extra air.
The standard requirements for a positive pressure air system are that it should (1)
be capable of maintaining a pressure of at least 25 Pa (0.1 in of water) in the area to
be pressurized with all openings closed and that it should (2) be capable of providing
a minimum outward velocity of 0.3 m/sec (60 ft/min) through all openings. All doors
and windows capable of being opened should be considered as open, and an
allowance for other openings should be included. Air lock/exterior doors should be
automatically closing to minimize air losses. The pressurizing ability of the air
conditioning system may be included in the calculations.
Light fixtures for normal lighting indoors are mainly the recessed fluorescent type.
Limited use of incandescent fixtures for bed lamps and other needs is common.
Fixtures for outdoor lighting on stairs and perimeter walkways should be similar to
the type used in the facility. Usually the majority of the external fixtures are high
intensity discharge (HID) fixtures. HID fixtures include those using mercury vapor
and sodium vapor lamps. Sodium vapor fixtures are usually more expensive than
mercury fixtures, but they are more efficient in electricity usage. At locations where
power cost is low and where many fixtures are required due to equipment
shadowing, mercury vapor fixtures are often preferred because of their low initial
cost, lower replacement lamp cost, and better color rendition.
The low profile of fluorescent fixtures often dictates their use in areas of low
headroom. A relatively short life, low efficiency, and susceptibility to vibration
exclude incandescent lamps from serious consideration for most applications. In
areas free from vibration and easily accessible for maintenance, such as
entranceways, incandescent fixtures may be acceptable.
Emergency lighting fixtures are often incandescent types. They should provide
sufficient light for personnel evacuation. Normally, 11 lumens/m 2, or one footcandle
(FC), at the floor level of all exit and interior stairs is considered to be sufficient.
Emergency lights could be powered from individual battery packs that are
automatically charged by the normal electrical system. They can also be powered by
a separate emergency power system that receives its power from a central
uninterruptible power supply (UPS).
Minimum design lighting intensities should be specified for the different rooms or
areas. Some examples of design intensities are as shown in Table 3. Design
voltages and cycles should be specified in accordance with local standards.
Room (lumen/m 2
) Illumination (FC) *
Bedrooms 375 35
Kitchen 540 50
Recreation/Lounge 430 40
Video 430 40
Corridors 270 25
Fixtures in baths and galleys should be vapor tight. Special fixtures are used in
showers.
Electrical systems provide power for heat and air conditioning, fans, and kitchen
equipment. They also provide power to convenience outlets (base outlets) and any
dedicated outlets that may be required for clocks, televisions, drinking fountains, or
special tools.
Normally a duplex outlet is provided on each wall of each room and spaced
approximately every 6 m (20 ft) along the walls. An outlet is also provided at each
bunk and over each lavatory for shaving. All outlets are usually ground fault
interceptors, especially in the lavatory/shower areas. An outlet should be provided in
the vicinity of equipment for trouble lighting or power tools. Outlets on the exterior
of the building must be water-tight and may need to be explosion-proof.
Circuiting should be laid out with an eye to failure. A whole area should not go dark
because of a single circuit outage. The outlets and lights in a room should be on
different circuits. The lights should be split on two circuits in large rooms. Circuits
should be limited to 1,600 full load watts for 110 v systems. It is a good idea to have
a separate distributing panel for each floor.
Circuit characteristics vary in different parts of the world, but most quarters are
operated on platform generated electricity. The proper size and type of service must
be provided for all equipment items. A three-phase air conditioner will not work on
single-phase wiring. The same thing is true for a 220 v hot water heater connected
to a 440 v supply.
Fire detection equipment is used to detect the start of a fire or those conditions in
which a fire could begin. Examples of detection equipment include heat detectors,
smoke detectors, and gas detectors. Some of these are shown in Figure 23
(Examples of detection equipment (courtesy of Pyrotronics, Cedar Knolls, NJ)).
Figure 23
These systems normally trigger alarms and can be made to initiate certain
emergency shutdown systems and extinguishing systems. On larger quarters
buildings, the triggering of these detectors can be made to close off the HVAC
dampers to prevent fire, smoke, or gas from spreading to other areas of the building
through the HVAC system.
Fire fighting systems consist of hand extinguishers, automatic sprinkler systems, and
fire suppression systems such as Halon and dry chemical. Hand extinguishers should
be wall-mounted in accessible locations throughout the building. Extinguishers
should be located near the exterior exits and points of possible combustion such as
the kitchen and mechanical rooms. There are several types of hand extinguishers,
which can be specified: (1) dry chemical, (2) carbon dioxide, and (3)
monoammonium phosphate, depending on the type of fire anticipated. The all-
around ABC extinguisher is readily serviceable and can be used on any of the three
classified fires.
Automatic sprinkler systems can be either permanently pressured (wet pipe) or pressured on
actuation (dry pipe). Potable water does not have to be used. Offshore, seawater is normally
used in sprinkler systems, but a means for flushing with potable water is normally provided to
keep the system clean of sediment and rust.
Firewalls are sometimes used to protect internal stairwells and other critical exit
paths. They may also be used to contain equipment fires within mechanical
equipment rooms. Use of fire walls in certain rooms dictates the use of ceiling
systems of similar fire rating to prevent fires from spreading to other levels.
(Steel plate, no openings)). All fire ratings are based on actual testing of the
partitions installed as nearly as possible to actual situations for the tests. The testing
is done by recognized organizations such as Underwriters Laboratories or Factory
Mutual.
Openings of any type should be avoided in a fire wall. Plumbing vents and ventilation
outlets can usually be arranged to penetrate other walls. If it is necessary that a
window or door be installed in a fire wall, then that opening must be rated or
protected. That is, if a fire rated window or door and frame is not used, an
automatically closing fire shutter must be installed over the opening.
Modular Construction
Quarters are sometimes composed of a number of separate truck-transportable
modules. Most often these modules are rectangular in shape with doors on the ends.
Separate modules are available for bedroom/bathroom, kitchen/galley, office,
recreational rooms, and any combination. Modules can be laid side by side on the
deck and/or stacked one above the other to provide any amount or desired
accommodation of floor space. Communication between modules is through external
walkways and stairs.
Modular construction is particularly well suited for small or temporary quarters. Often
these are standard models that can be leased or purchased and may even be
A main drawback is that the modules' narrow width does not allow for large common
areas. It is also difficult to arrange standard modules so that it is possible to go from
one to the other without going outside. A variation of separate module construction
involves laying out the quarters so that it can be constructed on the platform by
installing "building blocks" of prefabricated modules one next to each other, with
openings in the walls for passageways and larger common areas. Using this
approach, any layout is possible. The building blocks concept has the disadvantage
that it requires more offshore hookup time and additional structural cost. In addition,
there is a potential for leaks to develop where the building blocks are joined.
Examples of modules and building blocks are provided in the Example Layouts
Subject.
Gulf of Mexico
The next step is to lay out the different areas in more detail within the confines of
the "box" determined in the first step. Table 2 can be used to help in this effort.
Important decisions include determining the number of people to be accommodated
in each bedroom and the arrangements for bathrooms. For example, a Gulf of Mexico
quarters may have private rooms for the foremen, while other company personnel
are housed two per room. The contract and catering personnel may be
accommodated four to a room. Although not recommended, some bedrooms have
been designed to sleep six or more persons. The one-man room may have a private
bathroom, and the two-man rooms may share a bathroom with adjacent two-man
rooms. The four-man and larger rooms may have one large common bathroom on
the same floor level. Another quarters may have only one-or two-man rooms, with
each room sharing a bathroom with the adjacent bedroom. Where both women and
men must be accommodated, it may be necessary to provide two sets of common
bathrooms or to physically separate the rooms that share bathrooms from those that
share a common bathroom.
Kitchen, m 2
/person and ft 2
/person 0.6- 6-21 1.4 15 Undefined Undefined
1.9
* Requirements for undefined areas are not given on an area per person basis, but are clearly specified otherwise.
Another important decision is determining the number of kitchens and dining rooms
required. In most locations only one kitchen and one dining room is required.
However, certain religions such as Islam, Hinduism, and Judaism have dietary
restrictions. If the quarters are designed to accommodate people of a religion that
has dietary restrictions as well as one that does not, it may be necessary to have
separate kitchens and dining rooms. Alternately, all personnel may have to observe
dietary conditions that satisfy all religions present.
The number and size of special purpose rooms such as offices, recreation rooms,
auditoriums, and clinics must be considered in the layout. In Moslem countries it
may be necessary to provide a prayer room. The areas allocated for each room type
should be somewhat larger than required for that room type, to allow for corridors,
entrances, and wall thickness.
Practical considerations, such as locating all bedrooms on one level, grouping office
space together, etc., may require that either the initial allocation to each room type
be adjusted slightly or the preliminary quarters dimensions be changed. It may be
desirable at this stage to try several different layout concepts with varying length to
width ratios to see which one results in a more nearly optimum layout from the
standpoint of lowest cost (usually this means smallest area) while still meeting the
layout and preliminary sizing objectives.
1. Isolate bedrooms on floors by themselves to reduce the noise level in these rooms.
2. Place the food storage areas near a door leading to a crane laydown area.
3. Place the HVAC units on the roof to save deck space, reduce energy losses, and allow
onshore commissioning.
4. Check that equipment and machinery can be removed for servicing from any mechanical
equipment rooms and that furnishings and other equipment can be moved in and out.
5. In mild climate areas, place external walkways at each level on the ocean sides to
promote human relaxation.
6. While the quarters must be as compact as possible, providing enough space for proper
function, especially in the kitchen and common areas.
7. Use extra spaces for storage. Do not waste space.
In laying out the quarters it is absolutely necessary to provide two escape routes
from every location in the quarters. For offshore facilities the layout of the quarters
relative to potential locations of fires within the facility must be considered. It is not
sufficient to provide two routes from the building if both lead to a common path for
abandoning the platform. Where possible, each escape path should be independent
of others and should lead to a different final location of platform abandonment (e.g.,
boat landing, survival craft, etc.). It may be necessary to provide fire walls to shield
personnel from radiation from a potential fire location.
The final layout must be checked to assure there is room for furnishings. It is always
a good idea to leave extra space in the preliminary layout stage. There is always
need for extra space. Walls have thickness, and they consume floor space. They may
be thicker than normal because of piping such as vents at each toilet or because of
flush-mounted electrical panels. If these things are not considered during preliminary
planning, they can cause the designers serious problems during final planning. Even
the swing of a door can be a problem in the final design.
The Appendices provide example layouts of the individual room types. However, the
designer is limited only by safety considerations, available deck space, and the need
to provide sufficient space for the furnishings. Architectural reference books such as
Architectural Graphic Standards contain detailed dimensions of individual items of
furniture and other fixtures. Some of the more common dimensions are shown in
Table 3.
Bunk 91 cm x 213 cm
Locker 46 cm x 46 cm
Swivel Chair 69 cm x 71 cm
Lounge Chair 76 cm x 76 cm
Fryer 38 cm x 81 in
Washer/Extractor 91 cm x 122 cm
(commercial)
Dryer/Extractor 91 cm x 122 cm
(commercial)
NOTE: Allow 122 cm in front of washer and dryer equipment for door-swing
and operator.
Locker 18 in x 18 in
Office Desk 60 in x 30 in
Swivel Chair 27 in W x 28 in D
Sofa (3 person) 90 in W x 32 in D
Lounge Chair 30 in x 30 in
Fryer 15 in x 32 in
Washer/Extractor (commercial) 36 in x 48 in
Dryer/Extractor (commercial) 36 in x 48 in
NOTE: Allow 48 in. in front of washer and dryer equipment for door-swing and
operator.
3 Compartment Sink 57 in x 22 in
Maximum Size
Class A Openings: In walls separating buildings or dividing a single building into fire areas.
Class B Openings*: In enclosures of vertical communication through buildings such as entrances to
stairs.
1) Made of approved non-combustible material.
2) Prevents flame from passing through it for 30 minutes if subjected to a
standard test.
Class C Openings: In corridor and room partitions.
Class D Openings*: In exterior walls that are subject to severe fires from outside the building and
smoke for 60 minutes, if subjected to a standard fire test.
Class E Openings: Inexterior walls subject to moderate or light fire exposure.
* Most commonly required ratings in offshore quarters buildings.
Class ALO: 1) Is Class A.
2) Is insulated with approved insulation, panels or covering.
3) If subjected to the standard fire test for 60 minutes has an average
temperature rise on the unexposed side of the insulated surface of less than
121°C (250 °F) above the temperature before the test and a rise of less than
162.8 °C (325 °F) at any point on the unexposed surface including joints.
Partitions
1 hour Metal stud with 15.9 mm (5/8 in) thick fire code sheet rock each side.
2 hour Metal stud with 2 layers of fire code sheet rock each side with staggered
Ceilings
Exterior Walls
U.S. Coast Guard requirements for walls, ceilings, and floors for marine applications:
A "Standard Fire Test" is described as one in which the sample is exposed in a test
furnace to a series of temperature relationships approximately as follows:
1. Beds -Provide a steel or wood single bed with mattress, bed lamp, lockable drawer(s),
and curtain for each person accommodated. Use a two-tier system and include a
bookshelf.
2. Lockers -Provide individual lockers with drawer(s) for each person accommodated, with
adequate space to hang clothes.
3. Desks -Provide at least one desk with chair, waste basket and ashtray per bedroom.
4. Miscellaneous -Some rooms may contain mirrors, window curtains, sofa, chairs, table,
bookcase, television, refrigerator, etc.
Kitchen
The dry storage room should be sized based on re-stocking requirements. Dry
storage areas are normally fully shelved with approximately six heavy duty shelves
from floor to ceiling.
Mess Hall
1. Dining Tables -Dining tables are normally laminated plastic, with sufficient chairs to seat
at least half the number of people being accommodated.
2. Eating Utensils -Settings for approximately twice the number of people being
accommodated are normally required. A setting should include knife, fork, spoon, iced
tea spoon, dinner plate, saucer, salad bowl, soup bowl, cereal bowl, coffee cup, 10 ounce
glass. Serving trays are normally provided for about the total number of people being
accommodated.
3. Tray Slide -Usually a four bar stainless steel tray slide along the entire length of serving
tables is specified.
4. Coat and Hat Rack -Consideration should be given to providing a rack to accommodate
hard hats for total number of people who can be seated.
1. Clothes Washers -automatic, multi-cycle, commercial quality washing machines with total
capacity of about one pound per person are normally provided.
2. Clothes Dryers -Clothes dryers are normally vertically stackable and of commercial
quality, with a total capacity equal to that provided by the clothes washers.
3. Ironing Boards -Can be standard size collapsible with steam-type industrial irons and
spare covers and pads.
4. Folding Tables -Folding tables are normally commercial, marine quality with laminated
plastic tops.
5. Cabinets and Shelves -As much overhead capacity of cabinets and shelves should be
provided as can fit in the space allocated.
6. Sinks -Stainless steel sinks with hot and cold water service are normally provided.
Recreation/Lounge/Video
In the video room, seating for about one-third the total number of people being
accommodated is normally provided. Furnishings for recreation areas are arbitrary
and can include the following as examples:
1. Pool tables -With 1 in thick slate top and ten cues, racks, balls, chalk, and cue repair kit.
2. Sofa And Lounge Chairs.
3. Ping Pong Tables -Folding, with extra nets and paddle sets.
4. Stereo Console -Similar to home units.
5. Televisions -635 mm (25 in) or larger color screen.
6. Video Cassette Recorders/Players -Specify tape format (e.g., VHS)
7. Dart boards -Include darts.
8. Games -Chess, Checkers, etc., with game tables and chairs.
Medical Clinic
For small quarters buildings the medical area may consist of a first aid cabinet only.
All quarters should have as a minimum a first aid kit, splints, and a burn kit.
Following are examples of items that may be contained in the medical wards of
larger buildings:
Corridors
Offices
Desk, swivel chairs, side chairs, wastebaskets, file cabinets, hanging file, tables,
bulletin board, and chalk board.
Figure 1
Figure 6 Office/Galley/Dining
Figure 18
(B) FALSE
3. A square building uses ______ wall material to contain the same square footage of floor
area as a rectangular building.
(A) less
(B) equal
(C) more
(B) 15 degrees
(C) 30 degrees
(D) 45 degrees
(E) 60 degrees
5. Which of these is NOT among the materials used for structural floors?
(A) Wood
(B) Fiberglass
6. The maximum angle for stairs should be ___________ from the horizontal.
(A) less than 25 degrees
7. Which of the following is NOT a type of sandblasting technique specified by the Structural
Steel Painting Council?
(A) Hose blasting
9. What type of exterior doors should be used if the risk of fire is very high?
(A) Fiberglass
(C) Copper
(D) Aluminum
10. What is the most common type of thermal insulation material in walls and roofs?
(A) Aluminum
(B) Fiberglass
(C) Plywood
(D) Plastic
(B) Steel
(C) Aluminum
12. What is the typical design assumption for water consumption per person per day?
(A) 200 to 245 l [50 to 65 gal]
13. The drain water from sinks and showers is NOT required to be treated before disposal.
(A) TRUE
(B) FALSE
14. What are the main types of air conditioning systems used in most buildings?
(A) Liquid nitrogen and chilled water
15. The purpose of a positive interior pressure is to insure that contaminated or potentially
explosive air would not enter the building even through open windows and doors.
(A) TRUE
(B) FALSE
(B) FALSE