Harga Satuan Jumlah Harga (Rp) No Uraian Kode Satuan Koefisien (Rp) A TENAGA Pekerja L.O1 OH 0.0810 96,000.00 7,776.00 Tukang batu L.O3 OH 0.1350 114,000.00 15,390.00 Kepala Tukang L.O3 OH 0.0135 120,000.00 1,620.00 Mandor L.O4 OH 0.0040 132,000.00 528.00 JUMLAH TENAGA KERJA 25,314.00 B BAHAN Pipa PVC Ø 4" M 1.2000 28,000.00 33,600.00 Perlengkapan 35% pipa 35% 28,000.00 9,800.00 JUMLAH HARGA BAHAN 43,400.00 C PERALATAN JUMLAH HARGA ALAT D Jumlah (A+B+C) 68,714.00 E Overhead & Profit 10% x D 6,871.40 F Harga Satuan Pekerjaan (D+E) 75,585.40