Escolar Documentos
Profissional Documentos
Cultura Documentos
GENERAL :
(i) All costs relating to or arising out of carrying out the tests and
submission of test reports and or samples to the client /
consultant for approval during the entire tenure of the work
shall be borne by the contractor and included in the quoted
rates.
1.0.0 CEMENT
1.1.0 SUPPLY
1.2.1 Cement bags shall be stored dry, leak proof, moisture proof and
well ventilated godowns at the cost of the contractor.
Cement of different types shall be stored in separate
godowns or separate compartments of a godown.
1.2.2 The floor of the godown shall be raised and shall consist of wooden
planks testing on the base prebared with dry bricks laid on
edges. Stacking of cement bags shall have a clearance 150
to 200 mm above the floor and 450 mm from the wall.
1.2.3 Cement shall be stored in stacks, which are not higher than 10
bags to avoid lumping due to pressure and in such a manner
as to permit easy access for inspection and identification.
1.2.4 The bags shall be kept close together in rows of two bags to reduce
circulation of air as much as possible. The bags shall be
arranged in header and stretcher fashion so as to lessen the
danger of topping.
1.2.5 ‘First in’, ‘First out’ rules shall be applied while removing the
bags for use.
1.2.7 No stored cement bag shall be used after three months from the
date of manufacture. Generally, stacking and storing of
cement shall be in accordance with clause 3.2 of IS : 4082.
1.3.1 The manufacturer shall satisfy himself that the cement conforms
to the relevant Indian standards and if required, shall
furnish a certificate to this effect to the purchaser or his
representative within ten days of the despatch of the cement.
1.3.2 The contractor shall be fully responsible for the quality of cement
brought to work site. In case the contractor has any doubt
regarding the quality of cement brought to work site, it is
upto him to have it tested at his own expense and make sure
that the cement is of acceptable quality.
1.4.0 TESTING
1.4.1 The contractor shall submit test certificates furnished by the
manufacturer to client / consult. Where the client/
consultant is not convinced about the quality of cement, he
can ask the contractor to have the cement tested or he can
take samples in the presence of contractor from cement bags
stored at work site and forward them to government
approved laboratory for testing. Expenses towards such
tests shall be the contractor.
1.5.0 SAMPLING
1.5.1 For one lot of 50 tonnes of cement, 2% of bags shall be picked out
of random, from which one samples of 15 kg shall be taken.
1.5.3 When it is not possible to test samples within one week, the
samples shall be backed and stored in airtight containers till
testing.
2.0.0 AGGREGATES
ABSORPTION :
6% maximum by weight for ordinary construction and 2%
maximum for water proof construction.
SALT
1% maximum (equivalent anhydrous calcium percentage by weight
of cement)
SHELL
8% maximum by weight
CARBONATES
10% maximum by weight.
(b) The sand shall be free from adherent coatings and shall not
contain harmful materials such as iron pyrites, coal, mica,
slit, clay, alkali, sea shell, organic impurities, loam etc.,
2.1.2 GRADING
Fine aggregate with a fineness modulus value less than ‘2’ shall
not be used for reinforced concrete work. The natural sand used
for R.C.C work shall have a grading conforming to one of the three
grading zones given in the following table (Table B). Fine aggregate
conforming to grade IV as per IS : 383 shall not be used for R.C.C
works.
2.2.3 STORAGE
(c) If the aggregates are stored at site for a long time, it shall be
sieved before use, to remove dust, if directed by the
consultant.
3.1.0 SUPPLY
3.3.0 TESTING
3.4.0 SAMPLING
4.0.0 WATER
Water used for various works shall conform to IS : 456
Water for use in mixing with cement shall neither be hotter than
250 C nor colder than 5 0 C at the time of mixing. Whenever
temperature controlled concrete is specified, the contractor may
establish an ice making plant of required capacity at site.
Water used for curing shall not produce any objectionale stain or
unsightly deposit on the surface. If shall be free of elements that
significantly affect the hydration reaction. Presence of tonnic acid
or iron compounds in water is objectionable.
The sample of water taken for testing shall represent the water
proposed to be used, with due account being paid to seasonal
variation. The samples shall not receive any treatment before
testing other than that envisaged in the regular supply of water
proposed for use. The sample shall be stored in a clean container.
Test shall be carried out only once for one particular source.
4.4.0 STORAGE
5.0.0 ADMIXTURES
5.3.0 SAMPLING
5.3.1 Sampling for testing shall be done in accordance with clause 4.1 of
IS 9103 for liquid admixtures and clause 4.2 of IS : 9103 for
non – liquid admixtures.
5.4.0 TESTING
5.5.0 STORAGE
6.0.0 FORMWORK
6.1.2 Form work shall be of marine plywood, timber, steel and fibreglass
of suitable thickness capable of resisting damage to the contact
faces under normal conditions of erecting forms, fixing steel
and placing concrete. For designated areas prominently in
public view the choice of material shall be decided by the
Engineer – in – charge.
6.1.3 The forms shall be true to dimensions and sizes. The props used
on the work shall be of such type. Which can afford finer
adjustments for levels etc., and ensure fully stability.
Hot rolled rivet bars shall conform to IS : 1148 and high tensile
steel rivet bars for structural purposes shall conform to IS
1149.
ST–42S :
If shall be used for all types of structures (riverted and bolted) including
those subjected to dynamic loading and where fatigue, wide fluctuations
of stresses, reversal of stresses and great restraint are involved. It shall
be suitable for welded structures provided that the thickness of the
material does not exceed 20 mm.
ST–42W :
Structural steel tubes (ERW) used for building construction shall be hot
finished tubes conforming to IS : 1161/IS : 1239/IS : 806, tubes shall
be designated by their nominal bore and shall be classified as light,
medium and heavy as per IS : 1161, tubes of thickness lower than light
tubes shall not be permitted.
Unless mentioned otherwise, fusion welding quality steel ST–42w shall
be used for all the structural steel works and tubes shall be YST 21
conforming to IS : 806.
Over 10 mm
upto 20 mm
Over 20 mm
Bars Below 10 mm 26 23
(round, only bend 42 to 54
square and test shall be
Hexagonal) required. 10
mm and
above
7.2.1 When the steel is supplied by the Contractor, test certificate of the
manufacturer shall be obtained according to IS : 2062 and
other relevant Indian Standards. Notwithstanding the
manufacturer’s certificates, the Consultant / Architect may ask
for testing of material in approved test laboratory. The test
results shall satisfy the requirements of the relevant Indian
Standards. Whenever quality certificates are missing or
incomplete or where material quality differs from standards
specifications, the Contractors shall conduct all appropriate
tests as directed by the consultant / Architect at his own cost.
Materials for which test certificates are not available or for
which test results do not comply with relevant IS standards
shall not be used.
7.3.0 STORAGE
8.1.1 The asbestos cement sheets used for roofing and cladding shall be
plain, corrugated or semi – corrugated sheets from Everest or
approved make conforming to IS : 459
8.1.5 All fixing accessories shall conform to IS : 730 and IS : 1626. The
diameter of the bolts shall not be less than 8 mm. The J – bolts
shall be atleast 90 mm longer at lap points of sheets and 75
mm longer at other points than the depth required to hook the
bolt to the purlin. The galvanised iron washers shall be 25 mm
in diameter and 1.6 m thk. The bitumen washer shall be 35
mm in diameter and 1.5 mm thk.
8.1.7 The sheets shall have rectangular shape, corrugations true and
regular, edges straight and clear smooth surface on exposed
side and free from cracks and visible defects holes deformation,
chipped edges or otherwise damage.
8.1.8 All the AC sheets shall be painted with 3 coats of lime wash on the
underside unless otherwise specified.
8.3.0 STORAGE
9.1.1 G.I. sheets used for roofing and cladding shall generally conform
to the requirements prescribed in IS : 277 and shall be of the
best quality duly approved by the client / consultant.
9.1.2 The base metal for galvanised sheets and coils shall be hot or cold
rolled mild steel conforming to IS : 513. The sheets shall be
free from cracks, split edges, twist, surface flaws etc., They
shall be clean, bright and smooth. The galvanizing shall be
uninjured and in perfect condition. The sheets shall show no
signs of rust or white powery deposits on the surface. The
corrugation shall be uniform in depth and pitch and parallel to
the side.
9.3.0 STORAGE
10.1.0 GENERAL
10.1.1 Colour coated sheets shall be made out of cold or hot rolled MS
sheets conforming to IS : 513 glavanised as per IS : 277 and
shall be of the best quality.
10.1.3 The sheets shall be free from cracks, twist, surface flaws, split
edges and any other defects which could impair the strength
and quality of the material.
10.1.4 The profile of the sheets shall be uniform, smooth, regular and
true to shape.
10.1.5 The colour shades shall be consistent and free from visible
defects.
10.2.0 SAMPLING
10.3.0 STORAGE
11.0.0 STONES
For specific use (e.e exposure to chemical fume, fire hazard etc.,)
type of stone shall strictly conform to the recommendtions of table
2 of IS : 1597 (part 1) or as directed by the Client / Consultant.
One through stone shall be provided for every half a square metre
of facing, evenly distributed in a staggared pattern.
They shall have about 0.03 sq.m in face area and shall have a
failing for the full width of the masonry when the width of masonry
is 600 mm or less.
The length of the interior headers shall not be less than 450 mm
and their average cross sectional area shall not be less than 0.025
sq.m
11.1.5 SAMPLING
11.1.6 TESTING
12.1.2 MARKING
Each type of stone blocks, slabs and tiles supplied at site shall
bear the manufacturer’s identification marks or initials.
(a) Samples shall be selected and tested separately for each lot for
determining its conformity or otherwise to the requirements of
the specifications.
Stone slabs not conforming to the size, colour, texture and other
criteria mentioned above shall be rejected by the Client /
Consultant.
13.0.0 BRICKS
13.1.0 BRICKS FOR MASONRY
(b) They shall be free from cracks, flaws and nodules of free
lime.
(d) They shall give a clear metallic ringing sound when struck by
a mallet and shall not break when dropped on the ground on
their flat face in a saturated condition from a height of 600
mm.
First class bricks are those, which strictly conform to the standard
size of module bricks and such that ten layers of brick laid in
mortar shall form masonry of 1 m height. These bricks shall be
manufactured from good quality plastic earth, which is free from
saline deposits. They shall have straight edges and even surfaces.
When immersed in water for an hour they shall not absorbed
water more than 1/6 th of their weight. On drying they shall not
show any sign of efflorescence.
13.1.6 HANDLING
The contractor shall provide all labour and plant required for the
inspection nd conduct of such tests as shall be required by the
consultant without additional charges.
13.1.8 STORAGE
Same as that of ‘Coarse aggregate’.
14.0.0 SAND
(c) Clay fine slit & fine dust in natural sand, crushed gravel or
stone sand shall not be exceed 5% by mass when determined
in accordance with IS 2386 (Part – 2)
14.1.3 STORAGE
Same as that of ‘Fine Aggregate’.
(a) Sand used for external, internal wall surfaces and ceiling
plaster shall conform to IS : 1542 and shall be procured
from approved sources.
(b) `Unless otherwise specified, sand for plaster shall imply
natural river sand.
(c) The sand shall be hard, strong, dense, durable, clean and
free from veins, adherent coatings and shall not contain
deleterious materials such as iron pyrites, coal, lignite, mica,
slit, clay, alkali, sea shell, organic impurities, loam or any
other harmful materials in such quantities so as to adversely
affect the strength or durability or plaster.
(d) Presence of clay, fine slit and fine dust in sand shall not be
more than 4$ by weight as stated in clause 3.0 or IS : 1542.
Organic impurities shall also be within limits as per Table
1.0 or IS : 383
14.2.2 GRADING
(a) The grading of sand for internal wall and ceiling plaster shall
be within limits specified in the following table of IS : 1542.
(b) The grading of sand for external plaster coat and renderings
shall be within the limits specified in Table B.
Class a sand shall be used generally for plaster work but where they are
not available , class B sand may be used after getting the approval from
Client / Consultant.
14.2.4 STORAGE
Same as that of ‘Fine aggregate’.
15.1.0 SAND
15.1.1 Sand used for filling shall be clean river sand hard, gritty, dry
and coarse, free from earth, silt organic matter, clay and
other deleterious materials.
15.2.0 MOORUM
15.2.2 FILLING
MOISTURE CONTROL
Water shall be always sprayed and not poured. Ponding shall never be
allowed. In wet weather the work may have to be suspended. Care shall
be taken to see that moisture is uniformly spread throughout the layer
and where necessary mixing with harrows and rakes shall be done.
MEASUREMENTS
15.2.3 CINDER
(e) Fixing lugs shall have a head made of 25 wide x 1.6 mm thk.
Steel strip of specified length and a split end tall 40 mm wide
x 1 mm thk. And 200 long. There shall be a minimum of
three lugs to each jamb.
(f) Hinges shall be made of 2.5 mm thk. Mild steel with a zinc
coated removable pin of 6 mm diameter (conforming to IS :
1341)
(i) For side – hung door there shall not be less than three
buffers of fubber or other suitable material inserted in holes
in the rebate and one shall be located on the centre line of
the lock – strike plate lock – strike plate. For double –
shutter doors there shall be two buffers of rubber or similar
suitable material inserted in holes in the rebate in the lock
jamb only at the head and spaced 15 cm at either side of the
centre line of the door.
(b) The sliding door shall be in one leaf. The doors shall be
hung from the top by supporting wheels fitted in steel
hangers of substantial design, extending at least 400 mm
down the door unless designed with a double strap in which
case they need not extend more than 300 mm. Hangers
shall be riveted to the door and if the door exceeds 1.5 m in
width not less than three hangers each with a wheel shall be
fitted. Supporting wheels and pins shall be of steel and
wheels of low friction type shall be used. The rail upon
which the supporting wheels run shall be a flat bar of steel
at least 75 x 50 x 8 mm in section or an angle at least 65 x
65 x 8 mm in section on which a steel runner bar 16 x 16
mm in section is fixed by rivets at 225 mm centres to carry
grooved supporting wheels.
(f) Ball bearings provided for rolling shutters shall be two – row
self – aligning type with special cast iron catnips at the
extreme pulleys at either end. The pulleys shall be
interconnected with a cage formed out of mild steel flats of at
least 32 x 6 mm and spaced at 15 cm.
16.1.5 SUPPLY
16.2.2 SUPPLY
Same as for steel joinery.
16.2.4 SAMPLING
17.2.0 HINGES
These shall be mild steel but Hinges (medium), brass butt Hinges
(light / ordinary), brass butt Hinge (heavy), brass oxidised butt V
(light / ordinary), brass oxidised butt V (heavy), extruded
aluminium alloy butt V or as specified. Brass and MS butt Hinges
shall generally conform to IS : 205 and IS : 1341 respectively.
Brass barrel tower bolt with cast brass parallel and rolled or
drawn brass bolt.
Brass barrel tower bolt with brass sheet parallel and rolled or
drawn brass bolt.
Mortise lock with pair of lever handles shall have steel casing and
brass bolts and shall be right or left handed as shown in the
drawing or as directed by the Client / Consultant. It shall be of
the approved quality and shall conform to IS : 2209. The shape
and pattern shall be approved by the Client / Consultant. The
size of the lock shall be determined by its length. The lock for
single leaf door shall have a rebated face. Lever handles with
springs shall be mounted on plates and shall wigh not less than
0.5 kg per pair. These shall be of brass, finished bright chromium
plated or oxidised.
17.8.0 FLOOR DOOR STOPPER
These shall be made of cast brass or C.P. steel and shall generally
conform to IS : 1837. The base and socket plate shall be made
from minimum 3.15 mm thk. Brass or CP steel plate and projected
shall not be less than 12 mm in diameter and 12 mm cast in
single pieces with the base plate.
18.0.0 GLAZING
18.1.1 The glass used for glazing works shall be of the best quality
transparent and free from blisters, specks, bubbles, stones,
scratches, veins, air holes and other defects also as to give a
clear visibility through the glass.
18.1.2 All glass shall be procured from a reputed manufacturer and
duly approved by Client / Consultant. The glass supplied at
site shall conform to the requirements indicated in the
schedule of items and the following Indian Standards listed
below.
18.2.1 GENERAL :
Unless otherwise specified sheet glass shall weigh 7.5 kg/sq.m for
panes upto 600 x 600 mm. For panes larger than 600 x 600 mm
and upto 800 x 800 mm glass weighting not less than 8.7 kg/sq.m
shall be used. For bigger panes upto 900 x 900 mm glass
weighting not less than 11.25 kg/sq.m shall be used.
Sheet glass shall be patent flattened glass of best quality and for
glazing and framing purposes shall conform to IS : 1761.
18.2.2 TESTING
Any glass, found to suffer from defects beyond allowable limits (as
per Table – 2, IS : 2835) shall be rejected.
18.2.3 SAMPLING
18.3.2 The wire mesh used in the wired glass or wired figured glass
should be made of steel wire 0.46 to 0.56 mm in diameter.
The pattern of mesh shall be square or diamond with wired
welded or hexagonal with wires twisted. The wire mesh shall
be embedded completely in the glass sheet at least 1 mm
from the surface and shall not be exposed at any place. Wire
mesh shall to contain more than 3 broken wires per square
metre of glass.
18.6.0 PUTTY
Putty may be prepared by mixing one part of white lead with three
parts of finely powdered chalk or then adding boiled linseed oil to
the mixture to form a stiff paste and adding varnish to the paste at
the rate of 1 litre to varnish to 18 kg of paste.
19.0.0 TILES
19.1.0 TERRAZZO TILES
(a) All tiles to be used shall be heavy duty flooring tiles only,
conforming to clause 3 of IS : 1237.
However, special shapes and sizes of tiles can be asked for by the
client. In such as case, the manufacturer / supplier shall ensure
to supply the tiles only in the specified shape and size.
(g) The wearing layer of the tiles shall be free from projections,
depressions, cracks, holes cavities and other blemishes.
19.1.2 PHYSICAL REQUIREMENTS
(a) Client can ask for any physical test to verify the acceptability
of the tiles. All physical tests shall be carried out as per
Appendex A to F of IS : 1237 as applicable, depending on the
tests to be done.
19.1.3 SAMPLING
19.1.4 MARKING
All tiles shall be legibly marked on the back with the name of
the manufacturer or his trade mark. Heavy duty tiles shall
be marked ‘H’
The tiles shall be vitreous were shall and shall be free from
deleterious, substances. The finished tile, when fractured shall
appear fine grained in texture dense and homogeneous. The shall
be sound, true to shape, flat, free from flaws and other
manufacturing defect affecting their utility.
FLOOR TILES
These tiles should have high strength, good resistance to wear and tear,
low water absorption and sufficient anti – skid properties and all shall
conform to IS :13755. Based on the properties of the glaze and
hardness, floor tiles are categorized abrasion resistant -–wise as group II
to V. According to the intensity of foot traffic the tile group shall be
selected and used.
WALL TILES
These tiles shall be single fast fired having medium water absorption
and high strength characteristics. These tiles shall have high glaze and
better adhesion to wall and shall conform to IS : 13753. Wall tiles shall
be glossy / semi – glossy, matt glaze finish, white or coloured, plain or
printed special printed and premium printed.
These tiles are of different shades having monolithic body that is pressed
in very high tonnage press and fired to high temperature. The tiles shall
be homogeneous. And compact through out the entire body with very
high strength, low porosity and extreme surface hardness, high
resistance to abrasion by chemicals and shall conform to IS : 4457. The
tiles shall be with smooth surface or textured anti – skid finish surface.
Polished vitrified ceramic floor tiles shall be homogenous heavy and
tough with highly reflective polished surface but non – slippery.
19.2.3 STORAGE
The tiles shall be free from any flaw, fissure, crack or any other
manufacturing defect that may adversely affect their utility. They
shall be flat, square, true to shape and sound.
20.0.0 PAINTS
Paint shall not show excessive setting in freshly can and shall
easily be mixed with paddle to smooth homogeneous state.
20.1.2 PRIMER
Primer shall be zinc phosphate
20.1.4 SAMPLING
20.1.5 STORAGE
(c) The paint for use, shall meet the requirements of IS : 5411
(part – 1) on testing . The paint for exterior use shall comply
with the requirements of IS : 5411 (Part – 2)\
20.2.3 SAMPLING
20.2.4 TESTING
20.2.5 STORAGE
20.3.2 SCAFFOLDING
Where ladders are used, pieces of old gunny bags shall be tied at
top and bottom to prevent scratches to the walls and floors.
20.4.1 MATERIALS
Lime used for whitewashing shall be freshly burnt fat line (also
classified as class ‘C’ lime) conforming to IS : 712. It shall be
white in colour.
(1) Yellow and red ochre – The ochres shall conform to IS : 44.
The solid lump shall be crushed to powder.
20.4.2 SCAFFOLDING
Same as for ‘Cement part’
20.5.0 DISTEMPER
The specifications and condition for this shall be the same as that
applicable for dry distemper, except that oil bound distemper of
approved make, shade and colour shall be used after applying
priming coat of petrifying liquid or other primer as may be
recommended by the manufacturer / supplier. It shall conform to
IS : 428.
20.5.3 SCAFFOLDING
Same as for ‘Cement Paint’
20.6.0 HERITAGE WALL FINISH :
The density shall be 288 kg / cu.m and the weight shall vary from
8 – 12.8 kg / sq. m depending on the thickness. It shall be
available in thickness of 9.5, 12.5 and 15 mm.
Standard sizes are 610 x 610 mm, 1220 x 1220 mm and 1220 x
610 mm
21.2.0 TESTING
The levels shall be recorded in field books and plotted on plan before
starting the excavation.
BACK FILLING
CUTTING
MEASUREMENT
Where ordinary rock and hard rock is mixed, the measurement of the
excavation shall be carried out by stacking both the types of excavated
rock separately. The quantity of rock shall be arrived at by applying
reduction of 50% for looseness in stack. If the sum of net quantity of
two kinds of rock exceeds the total quantity of excavated material then
the quantity of each type of rock shall be in the ratio of quantities in
stack measurements of the two types of rocks.
QUALITY OF MOORUM
Pieces of hard rock which do not get crushed under the roller shall not
exceed 50 mm size.
FILLING
Filling shall be done in 20 cm thk. Layers and every layer shall be power
rolled with 8/10 ton roller so as to achieve maximum compaction and
till such time that no further movement is observed under the wheels of
the roller.
After filling is completed the modified procter density shall be 92% with
OMC.
Before start of work the contractor shall supply the samples of moorum
from each quarry to cover the variations expected in the supply. The
samples shall be tested for the following in a recognized laboratory in
accordance with IS 2720 for the following.
MOISTURE CONTROL
Water shall be always sprayed and not poured. Ponding shall never be
allowed. In wet weather the work may have to be suspended. Care shall
be taken to see that moisture is uniformly skpread throughout the layer
and where necessary mixing with harrows and rakes shall be done.
MEASUREMENTS
SOAKING OF BRICKS
LAYING
The walls shall be taken up truly plumb. All courses shall be laid truly
horizontal and all vertical joints shall be truly vertical. Vertical joints in
alternate course shall come directly one over the other. The thickness of
the brick courses shall be kept uniform.
All hold fasts of doors, windows, etc., which are required to be built in
walls shall be embedded in cement mortar or in cement concrete as
specified in their correct position as the work proceeds.
JOINTS
Bricks shall so laid that all joints are full of mortar. The thickness of
joints shall not exceed one for brickwork of any class designation. All
face joints shall be raked to a minimum depth of 10 mm by a raking tool
during the progress of work where the mortar is still green so as to
provide proper key for the plaster or pointing to be done. Where
plastering or pointing is not required to be done the joints shall be
struck flush and finished at the time of laying.
CURING
SCOPE
Hand operated pressure pumps shall be used for uniform spraying and
proper check shall be maintained to ensure that specified quantity of
chemical is used for the required area.
TIME OF APPLICATION
PROCEDURE
The bottom surface and sides (upto 300 mm) shall be treated with
chemical at the rate of 5 litres / sq.m
The portion of the column foundations and the retaining walls coming in
contact with the backfill. The structure shall be treated at the rate of 15
litres / sq. m of the vertical surface. If water is used for ramming the
earth fill then treatment shall be carried out after the ramming
operation is completed by rodding the earth at 150 mm c/c close to the
structure surface and spraying the required quantity of chemical. For
R.C.C framed structures using 1:2:4 or richer concrete the treatment
shall start from a depth of 500 mm below ground level and there is no
need to start the treatment from the bottom of excavation for columns
and plinth beams. The earth from 500 mm below the ground level and
above shall be treated as described in previous paragraph. However, for
R.C.C frame structure, there shall be no chemical treatment for column
foundations.
The top surface of filled earth within plinth walls shall be treated with
chemical emulsion of the rate of 5 litres / sq. m before the subgrade of
floor is laid. Holes upto 80 – 70 mm deep at 150 mm centers shall be
made to facilitate saturation of the soil with chemical emulsion.
TREATMENT OF JUNCTION OF WALL AND FLOOR
After the building is complete, rod holes shall be made along external
perimeter at 150 mm centers and 300 mm deep and these holes shall be
filled with chemical emulsion at 5 litres / running metre of perimeter.
GUARANTEE
MEASUREMENT
SCOPE
IS 3596 : Safety code for scaffolds and ladders (Part I & II)
IS 1200 : Method of measurement of building works.
Engineer shall have the right to inspect the source/s of material/s, the
layout of operations of procurement and storage of materials, the
concrete batching and mixing equipment and quality control system.
Such an inspection shall be arranged and approval of Engineer – in –
charge shall be obtained prior to starting of concrete work.
GENERAL
Engineer shall have the right to inspect the source /s of material /s, the
layout and operation of procurement and storage of materials, the
concrete batching and mixing equipment, and the quality control
system. Such an inspection shall be arranged and Engineer’s approval
obtained, prior to starting of concrete work.
CEMENT
The use of bulk cement will be permitted only with the approval of
Engineer. Changing of brands or type of cement within the same
structure will not be permitted.
CONTRACTOR will have to make his own arrangements for the storage
of adequate quantity of cement. If supplies are arranged by owner,
cement will be issued in quantities to cover work requirements of one
month or less, as deemed fit by the engineer and it will be the
responsibility of contractor to ensure adequate and proper storage.
Cement bags shall be stored in a dry enclosed shed (storage under
tarpaulin will not be permitted), well away from the outer walls and
insulated from the floor to avoid contact with moisture from ground and
so arranged as toprovide ready access. Damaged or reclaimed or partly
set cement will not be permitted to be used and shall be removed from
the site. Not more than 12 bags shall be stacked in any tier. The
storage arrangement shall be approved by engineer. Consignment of
cement shall be stored as received and shall be consumed in the order of
their receipt at site.
Cement held in storage for a period of Ninety (90) days or longer shall be
tested. Should at any time Engineer have reasons to consider that any
cement is defective, then irrespective of its origin, date of manufacture
and / or manufacturer’s test certificate, such cement shall be tested
immediately at Contractor’s cost at a national Test such tests are found
satisfactory, it shall not be used in any work. Contractor shall not be
entitled to any claim of any nature on this account.
CONSISTENCY
The consistency of the concrete shall be such that it flows sluggish into
the forms and around the reinforcement without any segregation coarse
aggregate from mortar. The slump tests are mandatory and shall be
carried out at regular intervals so that the consistency concrete can be
monitored.
PLACING OF CONCRETE
COMPACTION
Surface defects on a minor nature may be accepted and the same shall
be rectified as follows.
(b) Honey combed and other defective areas much be chipped out,
the edges being out as straight as possible and perpendicular to
the surface. Shallow patches are first treated with a coat of
thin grout (1 cement : 1 sand) and then filled with mortar
similar to that used in concrete. Large and deep patches shall
be filled up with concrete held in place by forms and shall be
reinforced.
(c) Holes left by bolts shall be filled carefully with mortar. Holes
extending right through the concrete shall be filled with mortar
with a pressure gun.
(d) The same amount of care to care the material in patches should
be taken as with the whole structure.
Minimum of six sample cubes shall be taken for all concreting work
(periodicity as specified in 9.6 of section III) and three cubes shall be
tested after 7 days curing and balance after 28 days curing.
7 DAYS TEST
(b) If the average comp. Strength of the three cubes is less than
specified but not less than 75% of the specified strength , the
concrete shall be accepted at reduced rates at the discretion of
EIC. The reduced rate shall be calculated on proportionate
basis. I.e. for every percent decrease in the specified strength
the rate shall be reduced by the same percentage.
(e) Measurement
PLASTERING
PREPARATION OF SURFACE
The following surface preparation shall be made for both single and
double coat plasters. The surface shall then be thoroughly washed with
water, cleaned and kept wet before plastering is commenced.
APPLICATION
Plastering shall be started from the top and worked down towards the
floor. All holes shall be properly filled in advance of the plastering as the
scaffolding is being taken down. To ensure even thickness and a true
surface, plaster of about 15 x 15 cm shall be first applied horizontally
and vertically, at 3 metres intervals over the entire surface to serve as
gauges. The surfaces of these gauged areas shall be truly in the plane of
the finished plaster surface. The mortar shall then be laid on the wall,
between the gauges with trowel. The mortar shall be applied in a
uniform manner slightly more than the specified thickness and brought
to true surface by working a wooden straight edge reaching across the
gauges with small upward and sideways movements at a time.
Horizontal joints in plaster shall not occur on parapet tops and copings
as these invariably lead to leakages. Good quality lime neroo shall be
applied to plastered surface with steel trawel to a thickness slightly
more than specified and rubbed down to give overall thickness of 12 mm
and polished to a perfectly smooth and even finish working from top to
bottom
Apply 12 mm thk. Coat of CM 1:4 mixed with CICO / ACCO proof water
proofing compound mixed as per manufacturer’s specifications as 1 st
coat leaving the surface rough.
When the plaster has been brought to true surface with a wooden
straight edge the surface shall be left rough with 2 mm deep follows
shall be made with a scratching tool to form key for the finishing coat.
The surface shall be kept wet till the finishing coat is applied.
The finishing coat shall be applied after the undercoat has sufficiently
set but not dried and in any case within 48 hours of laying the first coat.
WATER PROOFING
All water proofing works to be carried out in this scope of work shall be
through the following approved agencies / any other reputed approved
local agency.
CEMENT PAINTING
SCOPE
This covers the laying and finishing of cement concrete flooring tiles in
floors, wall, staircases etc.,
MATERIALS
LAYING
Subgrade concrete or the R.C.C. slab on which tiles are to be laid shall
be cleaned, wetted and mopped. The bedding of the tiles shall be either
with the mortar 1:3 (1 lime putty : 3 sand) or cement mortar 1:3 or as
specified. The average thickness or mortar shall be 30 mm and
thickness at any place shall not be less than 10 mm.
Lime mortar bedding shall be spread, tamped and corrected to proper
levels and allowed to harden for a day before the tiles are laid. Over this
bedding, neat grey cement slurry of honey like consistency shall be
spread at the rate of 4.4 kg/sq. mt over such an area that would
accommodate 20 tiles.
Before laying, the tiles shall be soaked in water for at least 20 minutes
and then allowed to dry to about 10 minutes. It is necessary to have
tiles damp but not wet when they are laid. Tiles shall be fixed by gently
tapping with a wooden mallet till they are properly bedded and in level
with the adjoining tile. The joints shall be kept as thin as possible not
exceeding 1.5 mm. Where full – size tiles cannot be fixed tiles shall be
cut to the required size and their edges rubbed to ensure a straight and
true joint. Tiles which are fixed in the floor adjoining the wall shall
enter not less than 12 mm under the plaster, skirting or dado. After
the tiles have been laid, excess cement coming out through the joints
upto the surface shall be immediately wiped clean.
The day after the tiles are laid all joints shall be cleaned of the grey
cement with a wire brush. The joints shall after 24 hours be filled with
matching cement paste and allowed to set. The same cement slurry
shall be applied to the entire surface of the tiles in a thin coat with a
view to protect the surface from abrasive damage and fill the pin holes
that may exist on the surface.
The floor shall then be kept wet and protected for a minimum period of
seven days before starting the polishing. No one shall be allowed to
walk on the floor during the first 24 hours immediately after the tiles are
laid.
The surface shall thereafter the grounded evenly with machine fitted
coarse grade grit block. Water shall be used profusely during grinding.
It shall then be covered with a thin coat of cement mixed with colouring
pigment to match the topping of the wearing surface of the tile sand
second grinding shall then be carried out with machine fitted with the
grade blocks.
The final grinding with machine fitted with the finest grade grit blocks
shall be carried out after 24 hours of completion of second grinding or
before handing over the floor. The entire surface shall be finally washed
with weak solution of soft soap in warm water.
TILES IN SKIRTING
PREPARATION OF SURFACE
LAYING
Joints shall be cleaned off grey cement grout with wire brush or trowel
to the depth of 2 to 3 mm and all dust and loose mortar removed.
Joints shall then be flush pointed with white cement added with
colouring pigment if required to match the colour of the tiles. The wall
shall kept wet at least for seven days. The finished wall shall not sound
hollow when tapped with a wooden mallet.
MEASUREMENTS
MATERIAL
APPLICATION
PRECAUTIONS
Old brushes shall not be used. Oil based Putties for filling in cracks,
depressions etc., shall not be used splashes if any shall be cleaned
immediately as they will be difficult to remove afterwards. Washing of
the surface shall not be done within 3 to 4 week of application. Other
details shall be as detailed in Oil Bound Distemper.
ELECTRICAL INSTALLATION
Wiring for power and light / fan circuit shall be separate. Entire wiring
shall be done by flexible PVC insulated copper conductors of specified
(in the job schedule) size.
POINT WIRING
Fans : 5 A SP switch.
Lights : Amps SP Switch
Power Plug : Amps 3 pin plug combined SS type.
Phase or live conductors shall be looped at the switch box and natural
conductor can be looped either from the switch box or from the light fan
or socket outlet.
WIRING TERMINATION
IDENTIFICATION OF WIRES
The phase conductors shall be of any of the RYB colours and the neutral
conductor shall be of black further the phase conductors in one line
shall be of only one colour i.e., either red. Earthing conductor shall be
green.
(b) Insulation test between phases, phases and neutral, phase and
earth with 500 V meggar.
(c) Operational Test
SAFETY EARTHING
(a) All earthing circuits shall be checked for continuity. The earth
resistance of all identifiable electrical equipment shall be
measured and recorded.
TECHNICAL SPECIFICATION ELECTRICAL
SCOPE OF WORK
The scope of work covered by this specification shall include supply and
installation of all electrical equipment and materials including testing
and commissioning.
Any variation or changes to be carried out at site shall be done with the
approval of the Engineer.
The scope of work shall include, but not to be limited to the supply,
storing, installation, testing and commissioning of following
(17) All tools, tackle, ladders etc., and the contractor shall but all
testing and measuring instruments as required.
(18) Storing of material at site and watch & ward of it till handing
over.
The design shall include all reasonable precautions and provisions for
the safety of operation and maintenance personnel.
The electrical contractor executing this work shall have a valid licence
issued by the State Government for carrying out installation work of the
voltage class involved under the direct supervision of a person holding a
certificate of competence for the same voltage classes, issued, of
recognized by the State Government.
The tenderer shall furnish with this tender the particulars of the licence
for carryingout the installation work against this specification.
All necessary safe holding for working at various heights shall be the
responsibility of the Contractor. The contractor shall be responsible for
compensation in case of any accident to his workmen at site. The
contractor shall fulfill and bear all statutory charges for their workmen.
Then tenderer shall indemnity owner / consultant of any charges for
workmen compensation.
2. SAND
Tests to be conducted
PERIODICITY OF TESTING
REMARKS
1. Slit content should not exceed 8%
2. For sand pad foundation no need of particle size
distribution. Only slit & bulk content to be carried out.
Same as above test shall be repeated for minimum qty. 500 sq. m of
plastering.
REMARKS
3. COARSE AGGREGATE
Tests to be conducted
REMARKS
4. CEMENT
Tests to be conducted.
REMARKS
5. CEMENT CONCRETE
Tests to be conducted
PERIODICITY OF TESTING
REMARKS
6. REINFORCEMENT STEEL
Tests to be conducted
Minimum qty. 250 kg tests shall be repeated for every 10 mt of each size
(dia) or part thereof
REMARKS
7. BRICKS
Tests to be conducted
PERIODICITY OF TESTING
2 samples tiles to be rested for minimum quantity of 80 sq. m
QUANTITIES
GENERAL
The switch board and the mounted equipment shall comply with the
latest edition of the following Indian Standards.
IS : 4047 : Heavy duty air break switches and fuses for voltage not
exceed 1000 V
IS 5 : Painting
GENERAL REQUIREMENTS
Switch gear shall be indoor, floor mounting, free standing type enclosed
in sheet steel cubicles and shall be dust, weather and vermin proof.
Enclosures shall conform to IP – 54 and shall be cold rolled sheet steel.
Gaskets shall be used between all adjacent units and underneath all
covers to render the joins effectively dust proof. Steel sheets shall not be
less than 2.00 mm (14 S.W.G.) in thickness. Switch gear should be of
single front type design.
The switch board shall be totally enclosed, dust, weather and vermin
proof. If necessary, openings for natural ventilation shall be provided.
Gaskets of durable materials shall be provided for doors and other
openings. Switch Boards specified for outdoor installation shall be
housed in outdoor type kiosks to make it weatherproof. The
switchboards shall be suitable for the ambient and site conditions
specified. Suitable hooks shall be provided for lifting the boards. These
hooks when removed shall not leave any openings in the boards.
Access from the back shall be limited to bus bars and cables only for
415 V main switch boards and DG panels. For all other panels, all
equipment shall be mounted on the front side and shall be accessible
from the from through hinged doors. Switches, ammeters, voltmeters
and lamps etc., shall preferably be mounted on fixed portions.
Individual switch fuse units. MCCBs bus bar and cable entrance alleys
shall be housed in separate enclosed compartments separated from each
other by metallic or any other resistant insulating material barriers.
Barriers and automatic safety shutters shall be provided such that bus
bars and other live parts are accessible even with breakers completely
drawn out. Opening of bus bar chambers shall be possible with special
tools only.
PAINTING
INSTRUMENT TRANSFORMERS
The voltage transformers shall have an accuracy class 3.0 from 50% to
110% of normal voltage and class 1.0 from 80% to 120% of normal
voltage with burdens varying between 25% to 100% of the rated value at
0.8 PF lagging.
The primary of the voltage transformers shall be rated for 415 volts and
the secondary for 110 volts. Unless otherwise stated, 2 single phase V –
connected VTs shall be used.
MEASURING INSTRUMENTS
AMMETERS
Ammeters shall be moving iron or moving coil type. The moving part
assembly shall be with jewel bearing. The jewel bearing shall be
mounted on a spring to prevent damage to pivot due to vibrations and
shocks. The ammeters shall be manufactured and calibrated as per the
latest edition of IS : 1248. The ammeters shall be instrument
transformer operated and shall be suitable for 5 A secondary of
instrument transformer. The scales shall be calibrated to indicate
primary current unless otherwise specified. The ammeters shall be
capable of carrying sustained overloads during fault conditions without
damage or loss of accuracy.
VOLTMETERS
Voltmeters shall be of moving iron or moving coil type. The range for
415, 3 phase voltmeters shall be 0 to 500 V. Suitable selector switch
shall be provided for each voltmeter to read voltage between any two
lines of the system. The voltmeter shall be provided with protection fuse
of suitable capacity.
The load break switches shall be heavy duty air break type and shall
have quick make / break manual operating mechanism. The operating
handle shall be mounted in the door of the compartment having the
isolator. It shall be possible to padlock the switches in the ON & OFF
position. Door interlock shall be provided so that it should not be
possible to open the door with the switch in the “closed” position.
Normal it shall not be possible to close the switches with the door open
but for testing purposes it shall be possible to defeat this interlock.
Switches shall be able to carry full load current continuously without
overheating. Barriers shall be provided to prevent inter – phase arcing.
The live terminals shall be avoid accidental contact. Motor feeder
switches shall be adequately for motor duty.
Fuses shall be HRC carriage link types. Diazed fuses will not be
acceptable.
All equipment and installation covered under the scope of work shall be
designed for electricity supply of the following specification.
DRAWING
The drawings enclosed with this specification are only for the guidance
of the tenderer. The exact routing of conduits, cables and wires and the
exact location of the equipment shall be as per construction drawings or
as decided at site by the Engineer. (Any field corrections shall be shown
in five (5) copies of each drawing and such as – built drawings shall be
handed over to the owner by the contractor after completion of the
installation.
The contractor shall submit for the approval of the owner / Consultant,
drawings of switch boards / tailor made equipment etc., as required in
four (4) sets before commencing the manufacture and / or supply. The
equipment shall submit four sets (4) of as built certified drawings after
complete fabrication of the equipment.
LOCAL CONDITIONS
The tenderer shall visit the site, ascertain the local conditions, entry,
traffic restrictions, and obstructions if any and also site conditions.
Whether the tenderer visits the she or not, he is deemed to have visited
the site and ascertained all the site conditions. The tenderer shall allow
in his tender for an extras likely to be incurred due to site conditions.
No claim will be allowed on this account under any circumstances.
STANDARDS
The equipment and the installation work shall generally conform to the
requirements of the Indian Electricity rules with its latest amendments
and all relevant standards and code of practice of the Bureau of India
Standards.
SAFETY
The tenderer shall include and take adequate precautions as per the
Indian standard codes to ensure safety for personnel and prevention of
accidents at site. The tenderer shall be responsible for compensation to
their workmen due to accident, if any.
STATUTORY REQUIREMENTS
The contractor shall obtain the approval of the State electricity board
and electrical inspectorate and carryout charges as called for by the
Electrical inspector at no extra cost to the owner. He shall also obtain
the drawing approvals and final safety certificate from CEIG. Only the
statutory fees payable to electricity authority shall be reimbursed by the
owner on production of valid vouchers.
INSPECTION
TIME SCHEDULE
CO – OPERATION
The contractor shall coordinate work with those of the other agencies at
the site and shall avoid any interference and interruption with the
progress of the MCCBs shall be certified, in accordance with EIC
standards and shall have the following performance characteristics.
Rated short circuit breaking capacity – not less than 25 KA for lateral
submain installation or the prospective fault current at the point of
installation whichever is greater. Short circuit current withstanding
duration shall not be less than 1 second.
This shall operate correctly at all values of supply voltage between 70%
and 120% of the nominal supply voltage under all operating conditions
of the MCCB. MCCBs incorporating shunt release shall be provided
with block terminals and shunt release lead cables.
CONTROL SWITCHES
All control switches shall be rotary, back connected type, having a cam
operated contact mechanism. Preferably phosphor bronze contacts shall
be used on the control switches. They shall have pistol grip handles.
Number of ways, locking system etc., shall be as stated on these
switches. Ammeter selector switches shall have make generally have 4
positions for reading 3 phase currents and the neutral current. The
voltmeter selector switch has to also have 4 positions. Three shall be
used to measure phase to phase voltage and fourth shall be off position.
Remote / Trip / Off selector switch for the motor feeders shall be
lockable in OFF position.
PUSH BUTTONS
Push button colours shall be as follows
INDICATING LAMPS
PROTECTIVE RELAYS
The fuses shall be non – deteriorating type and shall have an operation
indicator, which will be visible without removal of fuses from service.
Fuses shall be pressure fitted type and shall have ribs on the contact
blades to ensure good line contact. It must be possible to handle fuses
during off – load conditions although full voltage may be available on the
terminals. Fuse – pullers shall be provided.
GENERAL
MCCBs shall comply with and be type tested to EIC 157–1, 157–A, 157–
1B.
All MCBs to be used for serving pump motors, fan motors, and other
motor equipment shall be of motor type and shall be capable of handling
the starting currents.
All MCCBs shall be completed with dust – proof metal enclosures with
all the live terminals totally enclosed.
OPERATION CHARACTERISTIC
The overload trip setting can be adjusted on site from 60% to 100% of
breaker rated current in 10% steps.
PERFORMANCE CHARACTERISTIC
Wherever used ,all protective relays shall be back connected, draw out
type, suitable for flush mounting and fitted with dust tight covers.
Alternatively, plug-in typw of relays shall also be acceptable. The relay
cases shall bave provision for inslulation of tesft plug at the front for
“testing and calibration” using an external power supply without
disconnection the permanent wiring. It shall be possible toshort the CTs
through the test plugs.
TRIPPING RELAYS
All, tripping relays shall be lockout with hand reset contacts and shall
be suitable to operate off the specified DC voltage. These relays shall
have self coil-cut-off contacts and shall be provided with hand reset
operation indicators. Tripping relays will be acceptable in non- draw out
cases. The number of contacts shall be as shown in the schematic
drawings.
The panels shall be completely assembled, wired and tested as per IS-
8623-1977 at the factory in the presence of purchaser’s engineer or his
authorised person.
The test shall include wiring continuity test, insulation resistance tests,
high voltage tests ( 2.5 KV AC for 1 min.) and functional tests to ensure
operation of control scheme and individual equipment.
manufacturer’s test certificates in respects of all meters, switchgears,
contactors etc. prior to inspection of panels shall be produced to the
purchaser’s engineer at vendors works.
Along the offer, the contractor shall submit the following documents.
Arrangement of compartments.
Before manufacturer of the panels, the supplier shall have to take the
approval for the design and drawings in writing. Any manufacturing
done prior to approval of drawing shall be rectified in accordance with
the approved drawings by the supplier at his own cost and the
equipment shall be documents shall be enclosed separately.
GUARANTEE
The switch board shall be guaranteed for trouble free operation for a
period of 12 months form the date of commissioning or 18 months from
the date for arrival at site whichever is earlier. Any defects discovered
during this period shall be rectified free to charge.
GENERAL
BUSBARS
The ELCB shall be provided with a test Button to simulate leakage and
to test the ELCB. The ELCB shall operate and switch off the circuit
within 30 milli seconds in case of a fault.
The enclosures of the ELCB shall be molded from high quality insulating
materials, which shall be fire retardant, anti- tracking, non-
hygroscopic, impact resistant and shall withstand high temperature.
GROUNDING
The DBs shall be provided with two nos. brass earthing stud
terminals with suitable nuts, washers etc. for connection too earth bus
outside the DB.
PAINTING
All routine and acceptance tests as per the relevant IS shall be carried.
Out in presence of the purchaser or his representative.
PACKING
Along the offer, the contractor shall submit the following documents:
General arrangements drawings of DBs showing the various
constructional features etc.
After awardof the contract, the manufacturer shall submit the following
documents for approval.
Arrangements of compartments .
Single line diagram.
Complete technical particulars of all equipment.
Commissioning and maintenance instruction for all equipment.
Set of re-produceable for all the the above drawings.
Before manufacturer of the DBs, the supplier shall have to take the
approval for the design and drawings in writing. Any manufacturing
done prior to approval of drawing shall be rectified in accordance with
the approved drawings by the supplier at his own cost and the
equipment shall be supplied within the stipulated period. Time
schedule for drawing documents shall be enclosed separately.
GENERAL
The cables shall comply with the latest edition of the following standards
:
IS : 1554 (PART – I) - PVC insulated (heavy duty) electric cables –
working voltage unto and including 1100 V
IEC :540 & 540A - Test methods for insulation and sheaths of
electric cables and cords.
GENERAL CONSTRUCTION
The cables shall be suitable for laying in trays, trenches, ducts and
conduits and for under ground buried installation with uncontrolled
backfill and possibility of flooding by water and chemicals.
Outer sheath of all PVC and XLPE cables shall be black in colour and
the minimum value of oxygen index shall be 29 at 27 plus or minus 2 oC.
In addition, suitable chemicals shall be added into the PVC compound of
the outer sheath to protect the cable against rodent and termite attack.
The overall diameter of the cables shall be strictly as per the values
declared in the technical information furnished along with bids subject
to a maximum tolerance of 2mm.
PVC / Rubber end caps shall be supplied free of cost for each drum with
a minimum height of eight per thousand meter length. In addition, ends
of the cables shall be properly sealed with caps to avoid ingress of water
during transportation and storage.
The core insulation shall be with PVC compound applied over the
conductor by extrusion and shall conform to the requirements of type `A’
compound as per IS:5831. The thickness of insulation and the
tolerance on thickness of insulation shall as per table 2 of IS:1554 Part-
1. Control cables having 6 crores and above shall be identified with
prominent and indelible Arabic numerals on the outer surface of the
insulation. Colour of the numbers shall contrast with the colour of
insulation with a spacing of maximum 50mm between two consecutive
numbers. Colour coding for cables unto 5 crores shall be as per Indian
standard.
The inner sheath shall be applied over the laid up cores by extrusion
and shall be of PVC conforming to the requirements of TYPE ST1 PVC
compound as per IS:5831. The minimum thickness of inner sheath
shall be as per Table 4 of IS:1554 – Part-1.
The outer sheath form cables shall be applied by extrusion and shall be
of PVC compound conforming to the requirements of type ST-1
compound as per IS:5831. The minimum thickness of outer sheath
shall be as per column – 3 for both armoured and unarmoured cables.
SPECIFICATION FOR XLPE CABLES
The conductor shall be stranded and compacted circular for all cables.
All cables rated 1.1 / 3.8 / 6.6 Kv and above shall be provided with both
conductor screening and insulation screening. The conductors shall be
provided with non-metallic extruded semi conducting shielding.
The conductor screen, XLPE insulation and insulation screen shall all
be extruded in one operation by `Triple Extrusion’ process to ensure
perfect bonding between the layers. The core identification shall be by
coloured strips or by printed numerals.
The inner sheath shall be applied over the laid up crores by extrusion
and shall conform to the requirements of type ST2 compound of
IS:5831. The extruded inner sheath shall be of uniform thickness. For
multicore cables, the armouring shall be by galvanized steel strips. If
armouring is specified for single core cables in the data sheet, the same
shall be with H grade hard drawn aluminium round wire of 2.5 sq.mm
diameter.
The outer sheath of the cables shall be applied by extrusion after the
armouring and shall be of PVC compound conforming to the
requirements of Type of IS:5831. The thickness of outer sheath shall be
as per amendment No. 1 to Table 5 of IS:7098 part 2 (column 3 & 5 for
both armoured and un armoured cables).
The termination and straight through jointing kits for use on the
systems shall be suitable for the type of cables offered as per this
specification.
The accessories shall be supplied in kit form. Each component of the kit
shall the manufacture’s mark of origin.
The kit shall include all stress grading, insulating and sealing materials
apart from conductor fittings and consumable items. An installation
instruction sheet shall also be included in each kit.
TERMINATING KITS
JOINTING KITS
All routine tests, acceptance tests and tests shall be carried out an
cables as listed in IS:1554 Part-1.
The inner and outer sheath of XLPE cables shall be subjected to all the
tests applicable for PVC cables. The test requirements for insulation and
sheath of PVC cables shall be as per latest revision of IS:5831.
Following are the special tests to be performed on the cables and test
results for similar type of cables shall accompany the offer.
The test shall be carried out as per ASTMD 2863 or applicable Indian
Standard specification.
The vendors shall furnish the test details to analyse the property by
chemical method.
CABLE ACCESSORIES
Type tests should have been carried out to prove the general qualities
and design of given type of termination / jointing system. The type tests
shall include the following tests conforming to VDE 0278/IS
specification. The type test certificates shall be submitted along with
the offer.
Medium voltage power cables from 10 sq.mm unto and including 300
sq. mm – 500M
GENERAL
GENERAL REQUIREMENTS
For each type of light fitting the MANUFACTURER shall supply the
utilization factor to indicate the proportion of the light emitted by the
bare lamp which falls on the working plate.
All mercury vapour and metal halide fittings shall be complete with
accessories like lamps, ballasts, power factor improvement capacitors,
starters / igniters wherever applicable etc.,
Outdoor type fittings shall be provided with outdoor type control gear
box the fittings shall be power factor corrected to 0.95 lagging
(maximum).
Each fitting shall have a terminal block suitable for loop –in, loop-out
and T-off connection. The internal wiring shall be complete by the
MANUFACTURER by means of stranded copped wire and terminated on
the terminal block.
EARTHING
Each light fitting shall be provided with an earthing terminal suitable for
connection to the earthing conductor.
All metal or metal enclosed parts of the housing shall be bonded to the
earthing terminal so as to ensure satisfactory earth continuity
throughout the fixture.
PAINTING / FINISH
The finish of the fittings shall be such that no bright spots are produced
either by direct light source or by reflection.
LIGHT FITTINGS
High / MID / LOW bay fixture suitable for HPSV / HPMV / MH lamps
consists of reflector made out of high purity aluminium and anodized.
The integral control gear shall be housed in a cast aluminium housing
which will have cooling fins. It shall have a strong MS bracket with an
anti vibration eyebolt.
Street light fixture suitable for hpsv / hpmv lamp consists of cast
aluminium housing, stove enameled grey outside and white with an
anodized aluminium reflectors and highly transparent clear acrylic sheet
cover with hinge and toggle fastening, neoprene gaskets and integrated
prewired ballasts etc.,
The luminaries shall have die cast aluminium spigot complete with
integral copper wound control gear PF Correction capacitor mounted in
canopy, lamp holder and suitable rated lamps. The diffuser / cover
shall be apal acrylic HDP in double conical shape.
It shall be suitable for GLS lamp unto 100W and comprises of die cast
aluminium alloy body, prismatic heat resistant glass cover held with a
weatherproof gasket in a MS galvanized wire guard. It shall be painted
in while stove enamel inside and grey outside.
REFLECTORS
Reflectors shall be readily removable from the housing for cleaning and
maintenance without disturbing the lamps and without the use of tools.
They shall be securely fixed to the housing by means of positive
fastening device of captive type.
Lamp holders shall comply with relevant standards. They shall have low
contact resistance, shall be resistance to wear and shall be suitable for
operation at the specified temperature without deterioration in
insulation value. They shall hold the lamps in position under normal
condition of shock and vibration met within normal installation and use.
Lamp holders for the fluorescent lamps shall be of the spring loaded bi-
pin rotor type. Live parts of the lamp holder shall not be exposed during
insertion or removal of the lamp. The lamp holder contacts shall provide
adequate pressure on the lamp cap pins when in working position.
Lamp holders for incandescent, mercury vapour & metal halide lamps
shall be of Edison screw (E.S.) type. Starter holders for fluorescent
lamps shall conform to the relevant standards. All material used in the
construction of the holder shall be suitable for tropical use.
BALLASTS
Separate ballast for each lamp shall be provided in case of multi lamp
fittings.
The ballast for metal halide lamps shall not be constant wattage type.
STARTERS
Starters shall have bimetal electrodes and high mechanical strength.
Starters shall be replaceable without disturbing the reflector or lamps
and without the use of any tool. Starters shall have brass contacts and
radio interference capacitor.
CAPACITORS
LAMPS
The fluorescent lamps shall be “Cool Day Light” type unless otherwise
specified and shall be provided with features to avoid blackening of lamp
ends. The lamp shall have triple coil electrode with an anode ring and a
triband phosphor coating.
Mercury vapour lamps shall be of high pressure, colour corrected type,
with a high luminous efficiency. The discharge tube shall be made of
high grade quartz.
Metal halide lamp shall be provided with internal diffuse coating and the
average lumen output shall be 19000 lumen for 250W and 32000
lumens for 400 W and the lamp voltage shall not exceed 100v for 250W
and 128 v for 400 W. The colour rendering index of the lamp shall be 93.
The lamp shall be suitable for universal burning position and for use in
open type luminaire.
CEILING FANS
EXHAUST FANS
WIRES
The type and size of wires to be used shall be as indicated in the Bill of
quantities & Drawings.
Neutral : Black
Earth : Green
No joint is permitted in the run of wires.
SWITCHES
RECEPTACLES
OUTLET BOXES
Outlet boxes for sockets, switches, fixtures and fan regulators etc., shall
be of minimum 16 gauge or as specified. M.S.Sheet 2.5” deep.
Junction / outlet boxes shall be used in roof slab where concealed
wiring has been adopted. Front cover plate shall be of sheet steel in
areas where surface wiring has been adopted. For concealed wiring the
front cover plate shall be of Formica or modular front plate of approved
equivalent with colour to suit the walls. Outlet boxes shall be electro-
galvanised after fabrication. Cover plate shall be fixed by cadmium
plated brass screw and suitable C.P.Brass cup washers. Samples of
these shall be approved by Engineer-In-Charge.
Care shall be taken to see that all conduit ends have no burrs and ends
are neatly reamed to avoid damage to wires. All metal conduit
accessories shall be only of threaded type. In grip or clamp type
accessories are not acceptable. Samples of these shall be furnished for
approval by Engineer-in-charge at site, before installation.
The maximum number of PVC insulated wires which can be drawn in
conduits of various sizes shall be as given below :
Nominal Cross sectionals Sizes of Conduits
area in Sqmm
20 mm 25 mm 32 mm 40 mm
1.5 5 10 12 -
2.5 5 8 12 -
4.0 3 6 8 -
6.0 2 5 7 -
10.0 2 4 5 8
16.0 - 2 3 6
GENERAL
The contractor shall provide the complete bonding & earthing of the
neutral point of power system & non current carrying metal parts of all
electrical equipments & apparatus.
In all cases, the electrodes shall be driven such that the zones of
earthing do not overlap.
EARHTHING CONDUCTORS
All three pahse switches & distribution boards unto 60 amps, rating
shall be earthed with 2 nos. distinct & independent 3mm dia GI wires.
All three pahse switches & distribution boards unto 100amps. Rating
shall be earthed with 2nos, distinct & independent 4mm dia GI wires.
All 200 amp & above switches shall be earthed with min. of 2nos.
separate & independent 40mm x 6mm GI strip.
EARTH PIT DETAILS
RESISTANCE TO EARTH
GENERAL
The main / sub distribution frame shall be enclosed type made out of
CRCA sheet steel of suitable thickness (2 to 3.15mm). This shall house
necessary number of terminations with tags as specified with provision
for terminating incoming and outgoing cables. The terminations and the
frame shall be of standard make.
The frame shall be suitable for outdoor application with IP55 protection.
8. INSTALLATION
The portion of the trenches which is not covered by the switch board
shall be covered with 6 mm thick checkqured steel plates with suitable
reinforcemnt if required.
All unused cable shall be closed with suitable blind plugs or plates
made from 4mm thick sheet steel bolted t the gland plates.
MCB Distribution board shall be fixed with bolts and nuts grouted to the
wall concealed in the cupboards / niches provided or flushed /
semiflushed directly into the wall.
WIRING
The wires of a circuit shall not run through the conduits switch / socket
boxes of another circuit. A common drawbox with hylam barrier
separating individual circuit wires may be adopted to minimize the
number of draw boxes.
Wire shall be terminated at the switch boxes with suitable crimping type
tinned copper lugs.
The wiring shall be carried out by looping the phase conductors at the
switch box and the neutral conductors at the lights, fans and sockets.
For coping of wires in switch boxes, shrouded type multiway 10A / 20A
rated connectors shall be used.
CIRCUIT WIRING
The circuit wiring shall be from MCB distribution boards to first switch
box and looping to the consecutive switch box in the circuit including
conduits and accessories.
POINT WIRING
(e) Modular range of plate type cover plate, control switch, box
etc.,
(h) Ceiling rose / angle holder / battern holder for light points
(k) Cutting and chasing the wall for conduit & boxes installation
and making good the same in original finish after installtion
complete as required.
TELEPHONE WIRE
The Telephone wire shall be drawn in the conduits provider for the
purpose. It shall be terminated with standard termination accessories at
the end of socket pin and Telephone junction boxes.
Switch / socket boxes shall be concealed in the wall and the mounting
height of the boxes shall be as indicated in the drawings. Generally the
lighting switch box will be +1350mm from FFL and soxket will be at
450mm from FFL.
The switch and socket front plates shall project beyond the switch /
socket box. In the case of concealed conduit wiring, the joints between
the box and the surrounding plaster is covered by the cover plate. The
cover plate shall be fixed with brass cup washers and full threaded
brass screws.
CEILING FANS
Concealed type fan hook boxes shall be provided for mounting of the
ceiling fans.
The fan shall be fixed to the hook in such a way that the canopy covers
the opening of the fan hook box. Necessary down rods and other
accessories shall be included as required for complete operation.
EXHAUST FANS
The boxes shall be covered with 3mm thick hylam sheet of approved
colour. In the case of concealed flush mounting, the hylam sheet shall
project 6mm beyond the box so that the joint between the box and the
surrounding plaster is covered by the sheet. The hylam sheet hsall be
fixed to the box with brass cup washers and full threaded brass screws.
LUMINAIRES
CABLES
The under ground cable shall be laid in excavated trenches outside the
building. The trenches shall be excavated to a depth at not less than
800mm dand the cables shall be laid at a depth of 750mm.
The cables shall be laid over a 50mm thick sand cushion at bottom and
250mm on top of cable and shall be with bricks at either ends of trench
and protected at top by slab / bricks. The gap between the cables and
the bricks shall be filled with sand. Above the brick, for 150mm the
cable trench shall be filled with sand, after that for 400mm (i.e.,) unto
formed ground level the cable trench shall be back filled suitably with
soil.
Cable markers shall be installed at every 30m internal along all straight
lines and at bends. The cable markers shall be of cast iron and shall
have a clear and legible inscription “LT CABLE”.
Wherever cables are required to enter the building the cable shall be
drawn through hume pipe or GI pipe. Suitable packing shall be made at
both ends of the pipes. Cables inside building shall be run in cable
trays.
Where cables are required to cross the roads, cables and pipes of other
services the cable shall be drawn through hume pipe or GI pipe.
Suitable sealing shall be made at both ends of the pipes.
Vertical runs of cables along the wall shall be laid through GI pipe of
suitable diameter unto a height of 900mm above finished floor level. The
GI pipe shall be clipped to the wall with GI clamps and GI screws. The
distance between the clamps shall not exceed 400mm.
The cable laying shall be done in such a way that there is no damage /
injury to the cable. Adequate care shall be taken while pulling cable
from drum and while laying.
Sharp bends shall be avoided in the cable runs. The bending radius
shall not be less than 12 times the diameter of the cables.
No joint shall be permitted in the runs of the cables unto a run of 500
Meters.
Where more than on cable has to be laid along the same route, the
cables shall be laid horizontally touching each other and not one above
the other.
Poles for external lighting shall be installed along the road / pathway
edges as indicated in the drawing and shall be provided with cement
concrete foundation below the ground level and above the ground level.
The concrete used for the foundation shall be fixed in 1:2:4 proportions
with stone aggregate of 20mm nominal size. Concreting shall be done
solidly to avoid honeycombing using shuttering.
The depth and height of the concrete work shall be as per requirement
of the pole heights.
The luminaire shall be installed at the locations indicated over the poles.
The lamps shall be fixed after the luminaries are installed.
1 BOX FRAME
BACKSIDE
TOP OF BOX
16G Aluminium Bottom cover with white powder coated and interlocked
at the rear side with Aluminium runner (MFR) and is securely held in
the front of the box with the help of 2mm thick Aluminium Extruded
profile (FTRD) with rain water dripping arrangement to protect the sign
face from rain water dripping.
BOTTOM OF BOX
16G Aluminium Bottom cover with white powder coated and interlocked
at the rear side with Aluminium runner (MFR) and securely held in the
front with the held of 2mm thick Aluminium profile (FTRC).
Top and bottom runner (MFR) and tensioning (FTR) are supported by
vertical 2mm thick aluminium profile (VSP) and zinc coated M.S.
Brackets (SB) at every 3 to 4 feet distance maximum.
OR
NOTES
iii. Contractor must attach documentary proof (in form of invoice copy
or import documents) certifying the quality and make of fabric and
reflector. In the absence of above, bills will not be processed by
HPCL.
FOR
TECHNICAL SPECIFICATION
1. ER BLOCK MANUFACTURING
FACILITIES
2. RAW MATERIALS
7. LAYING OF PATTERNS.
SCOPE OF WORK
1.1 Verification of the existing site condition and advising our project
incharge to lay suitable base course if required. Contractors are
required to satisfy themselves with quality of sub-grade, sub-base
coarse before the paver blocks are laid and suggest strengthening
if required.
1.2 Clearing the site by removing all obstacles such as stones, debris
etc., for laying of paver blocks.
1.6 Testing of paver blocks through reputed Govt. / Non Govt. test
house and submission of test results as per requirements in
technical specifications. HPCL reserves the right to carryout tests
at random. Cost of such tests to be borne by party.
1.7 The contractor shall guarantee that all material and components
designed, fabricated, supplied and laid by him shall be free from
any type of defect due to faulty material and / or workmanship /
erection for a period of one year from the date of completion of
work at individual sites. However, free maintenance for two years
shall be rendered by the contractor.
1.3 CURING
ii. Other tools and equipment for testing raw materials and
paver blocks.
- The pavers are to be skirted all round with kerbing using solid
concrete blocks of size 100mm x 200mm x 400mm. The kerbing
should be embedded for 100mm depth. The concrete used for
kerbing shall be cured properly for 7 days minimum.
TECHNICAL SPECIFICATIONS
THICKNESS 80 MM
Shape irregular (Uniform shape with no
follow or cracks)
Chamfer 4 mm to 6 mm along top edges
Colour Natural cement grey colour without
use of any pigment
Dimenstional Tolerance (+/-) 2 mm for length & width (+/-)
3 mm for height (thickness)
The bedding sand shall consist of a clean well graded sand passing
through 4.75 mm sieve and suitable to concrete manufacture. The
bedding should be from either a single source or blended to
achieve the following grading.
All work further than one metre from the laying face shall be left
fully compacted at the completion of each days laying.
The joining sand shall be broomed to fill the joints. Excess sand
shall then be removed from the pavement surface and the jointing
sand shall be compacted with not less than one (1) pass the plate
vibrator and joints refilled with sand to full depth. This procedure
shall be repeated until all joints are completely filled with sand.
No traffic shall be permitted to use the pavement until all joints
have been completely filled with sand and compacted.
Both the sand and paving units shall be dry when sand is spread
and broomed into the joints to prevent premature setting of the
sand.
The surface course should not be vibrated until the edge restraint,
together with any bedding or concrete haunching, has gained
sufficient strength. It is essential that edge restraints are
adequately secured.
SAMPLING OF PAVER BLOCKS
1. METHOD OF SAMPLING
2. COMPRESSIVE STRENGTH
3. ABRASION RESISTANCE
4. FLEXURAL STRENGTH
1. TESTING MACHINE
The testing machines shall be of suitable capacity for the test and
capable of applying the load at the rate specified. It shall comply, as
regards repeatability and accuracy with the requirements of relevant ISI
specs.
2. PROCEDURE
The sample specimens shall be tested in wet condition after being stored
for at least 24 hours, in water maintained at a temperature of 20 0 C +50
C before the specimens are submerged in water, the necessary area
shall be determined by the method described in Appendix A.
The plates of the testing machine shall be wiped clean and any loose
grit or other material removed from the contact faces of the specimen.
Plywood nominally 4mm thick, shall be used as packing between the
upper and lower faces of the specimen and the machine plates, and
these boards shall be large than the specimen by a margin of at least
5mm at all points. Fresh packing shall be used for each specimen
tested. The specimen shall be placed in the machine with the wearing
surface in a horizontal plane and in such a way that the axes of the
specimen are aligned with those of the machine plates. The load shall
be applied without shock and increased continuously at the rate of
approximately 15 N / Sq.mm per minute until no greater load can be
sustained. The maximum load applied to the specimen shall be
recorded.
APPENDIX - C
Method for Determining of wet Transverse Strength
(Flexural strength)
1. The Pavers shall be tested wet after soaking in water for 24 hours.
6. The load ‘P’ which caused the breaking of the paver shall be
recorded.
The grinding path of the disc of the abrasion – testing machine shall be
evenly strewn with 20 g. of the abrasive powder. The specimen shall
than be fixed in the holding device with the surface to be ground facing
the disc, and loaded at the center with 300 N (30 kg) The grinding disc
shall than be put in motion at a speed of 30 rev/min and the abrasive
powder is continuously fed back on to the grinding pat so that it
remains uniformly distributed in a track corresponding to the width of
the test piece. After every 22 revolutions, the disc shall be stopped the
abraded tile powder and the remainder of the abrasive powder shall be
removed from the disc, and fresh abrasive powder in quantities of 20 g
applied each time. After every 22 revolutions the specimen shall be
turned about the vertical axis through an angle of 90 0 in the clockwise
direction and it should be repeated 9 times thereby giving total number
of revolutions of 220. the disc, the abrasive powder and the specimen
shall be kept dry throughout the duration of the test. After the abrasion
is over, the specimen shall be reweighed to the nearest 0.1 g. It shall
then be placed in the thickness measuring apparatus once again in an
identical manner and the reading taken with the same position and
setting of the dial gauge as for the measurement before abrasion.
T = (W1 – W2) V1
W1 x A
Where,
T = Average loss in thickness in mm,
W1 = Initial mass of specimen in g,
W2 = Final mass of abraded specimen g,
V1 = Initial volume of specimen in mm3,
A = surface area of the specimen in mm 2
APPENDIX – E
METHOD FOR THE DETERMINATION OF WATER ABSORPTION
iv. Visible surfaces water being removed with a damp cloth, and
immediately weighed.