Escolar Documentos
Profissional Documentos
Cultura Documentos
PII:SO958-9465(98)00005-5
ELSEVIER
Application
--
of Steel Fibre Concrete for
Underwater Concrete Slabs
H. Falkner” & V. Henke
Institute for Building Materials, Concrete Construction and Fire Protection (iBMB),
Technical University of Braunschweig, Germany
Section I - I
Plan - view
Fig. 1. Section through the building pit ‘Potsdarner Platz’.
For depths of up to lo-12 m, it is possible to pumping out of the building pit, after hard-
construct a ‘dry building pit’ with an artificial or ening of the underwater concrete slab;
natural sealing layer and deep sheet piling or if necessary, local defects have to be sealed
slotted walls. For greater depths a different con- by injection with cement grout.
struction method has to be used; underwater
excavation after the erection of the sheet piling The underwater excavation took place with
or slotted walls with the subsequent placement large floating dredgers in the construction sec-
of a back-anchored underwater concrete slab tion B of d&is. This first artificial lake created
(see Fig. 2). here covered an area of approximately
For construction of a dry building pit with an 20000 m2. This lake is enclosed by 1.2-m thick
underwater concrete slab according to Fig. 2c, slotted walls or sheet pile walls with a steel
the following construction steps are necessary: section depth of 1.0 m. The underwater con-
crete slab, with a thickness of 1.2 m, is anchored
driving of the sheet piling or construction of
by approximately 2000 tension piles; each pile
the slotted wall;
with a length of 17 m carries a tension force of
excavation of the building pit to the ground-
up to 1500 kN. The overall buoyancy force for
water level;
this building pit amounts to 3000 MN. Figure 3
setting of the anchors for the surrounding
shows this artificial lake.
walls. Additional anchors below the outside
ground-water level would affect the very
stringent watertightness requirements;
further underwater excavation down to the STEEL FIBRE REINFORCED CONCRETE
required level; SLABS
driving of the tension piles from a pontoon,
in this case steel profiles as vibration-injected For the time being, the verification of such an
piles; underwater concrete slab is based on a simple
concreting of the underwater concrete slab; computational model. It is normally assumed
for the first time steel fibre concrete was used that the external loading is carried by spatial
for such an extensive slab instead of plain arches within the slab towards the anchoring
concrete points of the tension piles, whereas the resulting
Application of steel fibre concrete for underwater concrete slabs 379
(a) (b)
t - 19,0
t - 36,0
Sealing marl layer --l
Anchored underwater
Naturally sealing layer Injected soil layer concrete slab
Fig. 2. Construction principles for deep building pits.
horizontal force is balanced by the external sidered to be fixed (see Fig. 4). The verification
earth and water pressure on the surrounding of the serviceability and overall stability is
walls. These anchoring points are normally con- assumed to be fulfilled if the concrete compres-
Anchoring -1
Prestressing bar 0 36
t A-
.-.-.
-+
8 --
8
c.-*.
0
8
4
cork layer _1
8
0
F
8
u)
A.
---I--
I P
+.
t
&i F 1.1
m F 2.1 - F 2.4 jacks with &en oil pressure
q F 3.1 - F 3.4
Fig. 5. Test set-up for plain and steel fibre reinforced concrete slabs.
382 H. Falkneq K Henke
the risk of sudden failure. Other tests, carried From this yield line pattern a simple model was
out with a single load in the middle of the slab developed for the dimensioning of these slabs.
(not included in this paper), led to a deform- The slab UB3 (40 kg/m3) in comparison to
ability which was 10 to 15 times higher than slab UB2 (60 kg/m3) showed better load-carry-
with a plain concrete slab. ing behaviour, which can be explained by the
These results showed clearly that steel fibre- higher total amount of the finer steel fibres,
reinforced concrete slabs have an inherent even if the mass of the fibre was reduced. Based
additional redundancy and therefore possess a on these findings, it was finally decided to use
higher degree of safety performance in practice. this amount and kind of steel fibres for the
The fibre reinforced slabs did not break into underwater concrete slabs.
several pieces; on the contrary, they could be
lifted as a whole from the test floor. One of the
fibre reinforced test slabs can be seen in Fig. 8, APPROVAL FOR SPECIAL CASES
where the yield lines are clearly recognizable.
Under German building regulations, building
materials or construction methods which are
600 not covered by the normal building regulations
Fi Wf UB3
and/or codes have to be approved under the so-
called ‘special case approval regulations’. This
400 procedure makes sure that these new building
materials or methods conform with the regula-
tions in existing codes.
In this context, and as there was no previous
2oa experience about the handling of steel fibre
, , _-_ -r_____
__.._._.. concrete under such extreme conditions (most
UB2:fibreamc?ete6okgIm’ of the concreting took place in winter and early
It t ti, UB3:tibreconcrete4OkgIm’
I I I spring 1995/96), it had to be proven in this con-
2 4 6 8 10 text in a large-scale test under building site
As = Deformation difference A - B (tIIm) conditions that steel fibre concrete could be
Fig. 7. Results of test loading slabs with plain and steel produced and placed underwater, satisfying all
fibre concrete. concrete technology and procedural engineering
Application of steel jibre concrete for underwater concrete slabs 383
conditions. This large-scale test was carried out cross-section of these steel containers was
in late autumn 1995. The following conditions 1.2 x 1.2 m, with a total length of 4 m.
for a special case approval had to be met: Altogether, six of these underwater concret-
ing tests, together with an additional four
The long pumping distances of over 150 m pumping tests, had to be carried out. The six
and the placing underwater enable proper underwater concreting tests were necessary as,
concreting of the underwater slab, especially even though these tests were planned on the
with regard to the enclosure of the tension basis of extensive preliminary laboratory tests
pile heads. with regard to the concrete properties, composi-
The material properties of different concrete tion and slump, some of the first mixes showed
mixes used had to be checked in such a way an extremely high retarding time. Even if these
that a decision about the final concrete mix concretes reached their intended strength (C
can be carried out with regard to the con- 20/25) in the end, such unpredictable behaviour
crete material and workability properties. could not be tolerated.3 Therefore, these tests
The tests had to be carried out for steel fibre proved to be extremely valuable, as they showed
concrete as well as for a normal concrete, the behaviour of the different concrete mixes
used as a reference concrete. under building site conditions in comparison to
For each concrete mix one large test speci- defined laboratory conditions.
men including two pile heads had to be For the underwater concrete slab the follow-
concreted underwater and recovered after ing mix (see Table 1) was finally chosen, as it
the concrete had hardened. showed a tolerable heat of hydration and an
These test specimens had to be sawn apart, in intended regarding time of 24 h.
order to check for proper enclosure of the As mentioned already, it had to be proven
pile heads. that the heads of the tension piles were totally
The concrete mix should show a very low encased by the steel fibre concrete and that
heat of hydration and take the sulphate con- there was an even steel fibre distribution over
tent of the ground water into account. the cross-section. Therefore, the test specimens
had to be cut through the pile head with a
Figure 9 shows the steel container of one test diamond bandsaw. Figure 10 shows the cross-
specimen with the two heads of the tension section through such a test specimen. Close
piles prior to lowering into the building pit. The inspection showed that the pile head was
384 H. Falkner; K Henke
Fig. 9. Steel container with two pile heads for the large-
scale test.
Grade c2012.5
Cement 32.5 R, 280 kg/m”
Aggregates O-16 mm
Fly ash 220 k
Water 197 l/,5/y
w/c ratio 0.7
w/(c+f) 0.39
Fibres DRAMIX 50/0.6, 40 kg/m3
Fluidifer Fk88, 1.5%
Regarder Retard 360, 0.4%
Spread 67 cm (on ‘German Table’)
Fig. 10. Cross-section of a test specimen.
Application of steel jibre concrete for underwater concrete slabs 385
successfully completed dry building pit. During The final result, a dry building pit which ful-
the whole construction process, each phase was filled all requirements, shows that the use of
monitored by an extensive measurement pro- steel fibre concrete for such an underwater con-
gramme. crete slab provides a new concept which, as
more and more buildings have to be founded
far below the ground-water table, will contri-
CONCLUSIONS bute to the overall building safety. If
dimensioned properly, such a steel fibre-rein-
For the first time an underwater concrete slab forced concrete slab can be constructed for the
of such dimensions has been constructed. The same cost as a thicker, plain concrete slab.
positive test results in the laboratory as well as
on the building site convinced all parties REFERENCES
involved in this project (planning engineers,
construction companies and building authori- Falkner, H., Huang, Z. & Teutsch, M., Comparative
ties) that the use of steel fibre concrete would study of plain and steel fibre reinforced concrete
contribute considerably to the overall safety of ground slabs. Concrete International, January 1995.
Falkner, H., Teutsch, M. & Klinkert, H., Untersuchun-
this construction measure. gen des Trag- und Verformungsverhaltens
The large-scale test on the building site rtickverankerter unbewehrter und stahlfserbewehrter
proved to be especially valuable, as it provided Unterwasserbetonsohlen. Forschungsbericht des IBMB
der TU Braunschweig, (Test report on the load carry-
the opportunity to study the behaviour of dif- ing and deformation behaviour of underwater concrete
ferent concrete compositions under building site slabs, unpublished), May 1995.
conditions. In addition, these tests allowed the Falker, H. & Henke, V., Steel fibre concrete for under-
water concrete slabs. In Proceedings (32) of the
verification of the stringent quality control pro- International RILEM Conference on Production Methods
gramme which had to be established in order to and Workability of Concrete, Paisley Scotland, 3-5 June
control all stages of the concreting, starting with 1996, p. 79.
the aggregate supply and finishing with the Faklner, H., New technology for the ‘Potsdarner Platz’
- steel fibre concrete for underwater concrete slabs.
properties of the fresh concrete arriving on the In Proceedings of the 3rd Eurolab Symposium, Berlin,
concreting pontoon. 5-7 June 1996.