Você está na página 1de 18

इंटरनेट मानक

Disclosure to Promote the Right To Information


Whereas the Parliament of India has set out to provide a practical regime of right to
information for citizens to secure access to information under the control of public authorities,
in order to promote transparency and accountability in the working of every public authority,
and whereas the attached publication of the Bureau of Indian Standards is of particular interest
to the public, particularly disadvantaged communities and those engaged in the pursuit of
education and knowledge, the attached public safety standard is made available to promote the
timely dissemination of this information in an accurate manner to the public.

“जान1 का अ+धकार, जी1 का अ+धकार” “प0रा1 को छोड न' 5 तरफ”


Mazdoor Kisan Shakti Sangathan Jawaharlal Nehru
“The Right to Information, The Right to Live” “Step Out From the Old to the New”

IS 7784-1 (1993): Design of cross drainage works- Code of


practice, Part 1: General features [WRD 13: Canals and
Cross Drainage Works]

“!ान $ एक न' भारत का +नम-ण”


Satyanarayan Gangaram Pitroda
“Invent a New India Using Knowledge”

“!ान एक ऐसा खजाना > जो कभी च0राया नहB जा सकता ह”


है”

Bhartṛhari—Nītiśatakam
“Knowledge is such a treasure which cannot be stolen”
( Reaffirmed 2012 )

Indian Standard
DESIGNOFCROSSDRhNAGEWORKS-
CODEOFBRACTICB
PART 1 GENERAL FEATURES

( First Revision )

UDC 626-861-1 : 006.76

%I
8 BIS 1993

BUREAU OF INDIAN STANDARDS


MANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARG
NEW DELHI 110002

July 1993 Price Group 6


Cross Drainage Works Sectional Committee, RVD 17

FOREWORD

This Indian Standard was adopted by the Bureau of Indian Standards, after the draft finalized by the
Cross Drainage Works Sectional Committee had been approved by the River Valley Division Council.
Cross drainage works are structures which are constructed to negotiate an aligned carrier channel/
canal over, below or at the same level of a drainage or another carrier channel/canal.
The code of practice for design of cross drainage works is formulated in two parts, Part 1 dealing with
general features and Part 2 with specific requirements, for various types of cross drainage works.
This standard was first published in the year 1975. Based on the experience of various departments
including Central Water Commission and Irrigation Department, a need was felt to make its
provisions up-to-date, and hence, this revision has been prepared. The principal modifications are in
respect of correcting the terminology of some of the terms and covering it separately [ see IS 4410
( part lS/Sec 5 ) : 1992 ] categorizing the various cross drainage works as is being done in practice,
arriving at design flood, loss of head etc. The modifications made in this standard are based on the
suggestions received from various states thus making the provisions more clear and in line with the
practice being followed in this country by major states.
For the purpose of deciding whether a particular requirement of this standard is complied with, the
final value, observed or calculated, expressing the result of a test or analysis, shall be rounded off jn
accordance with IS 2 : 1960 ‘Rules for rounding off numerical values ( revised)‘. The number of
significant places retained in the rounded off value should be the same as that of the specified value in
this standard.
IS 7784 (Part 1) : 1993

Indian Standard
DESIGNOFCROSSDRAINAGEWORKS-
CODEOFPRACTICE
PART 1 GENERAL FEATURES

( First Revision )
1 SCOPE before deciding upon the site and type of crossing. As
a general guide, for deciding upon the type of the cross
1.1 This standard (Part 1) covers general features
drainage work, important considerations are as given
pertinent to the design of various types of cross
drainage works and incorporates investigations and below:
studies connected therewith. a) Full supply level and functions of canal -
vis-U-L&high flood level of the drainage channel,
2 REFERENCES
b) Topography of terrain,
2.1 The Indian Standards listed in Annex A are neces-
Cl Regime of the stream?
sary adjuncts to this standard.
d) Foundstion strata,
3 TERMINOLOGY
e) Dewatering requirements,
3.0 For the purpose of this standard, the definitions
given in IS 4410 (Part ll/Sec 5) : 1977 and IS 4410 9 Ratio of design flood to be provided in drainage
channel to the discharge in the canal, and
(Part lS/Sec 5) : 1992 will apply.
fit) Envisaged head loss.
4 CATEGORIES OF CROSS DRAINAGE WORK!3
51.1 FullSupplyLevels ofcanadvis-a-vis High Flood
4.0 Cross drainage works can be classified under the Level (HFL) of Draitrage Channel
three broad categories listed at 4.1 to 4.3, based on the The choice of any particular type of cross drainage
type of the structure to negotiate a canal over, below or work is dependent on the high flood level (HFL) in the (
at the same level of the drainage channel. drainage channel to be negotiated. Aqueducts are
4.1 Stru’ctures for Canal Over a Natural Drainage generally proposed when the bed level of canal is well
Channel above the HFL of the drainage channel. Superpassages
The structures falling under this category are are generally proposed when the full supply level (FSL)
aqueducts, syphon aqueducts and culverts. Main- of the canal is well below the bed level of the drainage
tenance of structures in this category is relatively more channel. When the bed level of the canal is at, or below,
convenient, as these are generally above the ground and the HFL of the drainage channel, the depression of the
hence open for inspection. bed of the drainage channel is often a mop economical
proposal and in such cases syphon aqueducts may be
4.2 Structures for Canal Underneath a Natural considered.
Drainage Channel ‘.
i ’ 5.1.2 Topography of Terrain
The structures falling under this category are superpas- Detailed examination of the topography of the terrain
sages and syphons including well syphons. In case of is essedtialtg locate a stable reach of the drainage
syphons the maintenance is diffhzult as these run below channel’with good foundations permitting, preferably,
the natural drainage channel and are, therefore, not a right-angle crossing. Topography of the terrain may
easily accessible-to inspection. also permit diversion of one channel into another and
4.3 Structures for Canal Crossing a Natural locating the cross drainage work below the confluence
Drainage Channel at the Same Level of the two channel for greater economy.
Structures falling under this category are level cross- 5.1.3 Regime of Drainge Channel
ings and inlets, with or without escapes. The regime of a drainge channel requires careful ex-
NOTE -Wherever the word ‘canal’ is used, it should amination. For drainage channel carrying high sediment
be meant as ‘canal/carrier channel’. charges or drift materials, the possibility of choking up
5 SELECTION OF THE TYPE OF CROSS of the syphon and the effect of fluming of the drainage
DRAINAGE WORK channel should be kept in view.
5.1.4 Foundatioli Strata
5.1 While aligning the canal, the type of c?oss drainage
work envisaged should always be kept in view. The The selection of the most suitable site and a good
economics of various types of cross drainage works design, for any cross drainage work is intimately re-
vi.s-a-vb alternative aligmnents should be considered lated to the engineering properties of the foundation

1
IS 7784 (Part 1) : 1993

sub-strata at various alternative sites. These properties site selected and extending upstream and downstream,
have, therefore, to be determined by site explorations. of the centre line of the proposed crossing and covering
Where an alternative site, meeting other criteria, is its approaches to sufficient distances, so as to demar-
available, the final choice would obviously depend 011 cate levels, cadestral survey plot numbers, important
the location where the sub-strata available close to the topographical features like depressions near the
- bed of the stream is firm. proposed alignment of canal, general sub-soil water
5S.S Dewatering Requirements levels (with slope, if possible), etc.
In the executibn of foundation works for cross drainage 6.5.1 The other requirements for the plan at 6.5 are:
structures dewatering of foundations may pose serious a) reference to the position of the bench-mark used
problems. An accurate estimate of the cost and proce- as datum with its full description and reduced
dure of dewatering requires to be carefully worked out level;
when designs involve laying of foundations below the
ground water table.
b) the lines and identification numbers of the cross
sections and longitudinal sections of drainage
5.1.6 Ratio of Design Flood in Drainage Channel to chamiel taken within the scope of site plan and
the Discharge in Canal exact locations of their extreme points;
Negotiating a canal below the drainage chamlel is 4 the locations of the various trial pits and/or.
generally more difficult and involves more head loss. borings with tlteir identification numbers;
However, if the topography and other features warrant
a choice to be made between canal syphon and syphon
dj The contour of the drainage channel at intervals
between 0’5 m to 1’5 m depending upon the
aqueduct, then canal syphon may be preferred, only if terrain. This interval r!iay be greater in mour-
the ratio of canal discharge to the design flood is tainous regions;
substantially low.
e) The direction of flow of water;
5.1.7 Envisaged Head Loss
0 The angle of direction of crossing; and
The choice of ani particular type of cross drainage
work is also dependent on the head loss that can be g) Cross alignment of canal further upstream for
some distance beyond the limits of cross
pennitted in the canal. Whereas higher head loss can
drainage works.
throw some area out of command, restriction on head
loss may necessitate provision of wider sections 6.6 A cross section of the drainage cham~el at the
making the structure costly. proposed site of the crossing to appropriate vertical
and horizontal scales indicating the following informa-
6 DATAREQUIREMENT tion:
6.1 For any type of cross drainage work some data is
a) Cross section covering the bed and banks ofthe
required which is common to all types of cross drainage channel portion and the ground levels beyond
works. A location map for the work with results of the banks covering the entire flood plane, or
subsurface exploration conducted at site, cross sections from ridge to ridge at close intervals to suffi-
of the stream, upstream and downstream of the cient distances on either side showing all un-
proposed site, should be prepared, as given in 6.2 to 6.9. even features and habitations, if any;
6.2 An index map to a suitable scale showing the
b) Nature of the soil in bed, banks and approaches,
recotnmended location of the cross drainage structure, with trial pit or bore-hole sections showing the
the alternative sites of crossings investigated and levels and natures of the various strata down to
rejected, the existing communications, the general
stratum suitable from foundation considera-
topography of the country and the importa?& habita-
tions and front considerations of safe bearing
tions in the vicinity. .J 1
capacity of soil;
6.3 A catchment area map to a suitable scale, with c); Low-water level; and
contour markings at suitable intervals showing the
main drainage channel front its sources together with d). *%%-&n flood level.
all its tributaries. The map should also show the various 6.7 Longitudinal section of the drainage charulel
locations of raingauge stations, gauging sites, etc, as covering a reasonable reach to suitable scale, showing
also the general soil types and land use (that is forests, the location of the cross drainage work, with levels of
cultivated and uncultivated areas). The hydrological the observed flood, the low water and the bed levels at
observation sites should also be marked. Existing, suitably spaced intervals along the line of the deep
under construction or proposed embankments and water channel.
flood management measures should also be shown. 6.8 Anotegiving the salient features relating to the
6.4 A detailed survey plan of the drainage chamlel to catchment area, the meteorological conditions ex-
suitable scale showing important topographical fea- perienced thereon, besides the following other
tures extending considerable distances, downstream points:
and upstreatn, of the proposed site of crossing and
either of its banks. I a) Any predictable (future) alteration in the land
use;
6.5 Asite plan to a suitable scale showin& details of the
b) Storages in the catchment (artificial or natural)

2
IS 7784 (Part 1) : 1993

and embankment breaches that have occurred 6.10.2 Drainage Channel


in the past; 1. Extent and nature of drainage area (catchment’
4 Short duration intensity and frequency data in area);
respect of rainfall in the catchment; 2. Maximum annual rainfall and the period
4 Liability of the site to seismic disturbances; (years) of data;
e) Likelihood of heavy sediment charge or floating 3. Maximum intensity of rainfall with year;
timber, 4. Maximum observed flood discharge at the
f) Particulars of foundation exploration data in- site;
cidental to design requirements; and 5. Maximum flood level;
g) Recuperation tests, where foundation depth is 6. Water surface slope;
more than 3 m below the water table and where
7. Site plan of proposed crossing including contours;
the strata are pervious.
8. Log of borehole or trial pit data;
6.9 A note giving the salient design features of structures
9. Type of bed load of drainage chamtel;
existing upstream or downstream of the proposed site.
10. Longitudinal section of the stream for
63.1 Presence of dams, barrages, weirs, etc, on the
suitable distance ups&ream and downstream
natural drainage chamtel in the vicinity either upstream
of the canal depending upon site conditions;
or downstream, may affect the hydraulic charac-
teristics of the natural drainage channel, like obli- 11. Cross section of the drainage chamrel for a
quity and concentration of flow, scour, silting of bed, distance 100 m to 300 m upstream and
change in bed levels, flood levels, etc. These effects downstream, at intervals of 10 m to 50 m;
should be considered in the design of the cross 12. Waterways provided in road and railway
drainage work. bridges or other hydraulic structures on the
6.10 For preparing the design of a cross drainage drainage channel;
structure, the following specified hydraulic data should 13. Spring water level at the crossing site in May
-- also be made available. and October; and
6.10.1 Canal 14. Silt factor.
1. Full supply discharge, Q; 7 DESIGN FLOOD FOR DRAINAGE CHANNEL
2 Bed width; 7.1 Design blood for drainage chamtel to be adopted
3. Full supply depth; for cross drainage works should depend upon the size
4. Water surface slope; of the canal, size of the drainage channel and location
5. Bed level; of the cross drainage. A very long canal, crossing a
drainage channel in the initial reach, damage to which
6. Bed slope; is likely to affect the canal supplies over a large area
7. Full supply level; and for a long period, should be given proper
8. Top of bank level; weightage.
9. Cross section of canal showing Natural Ground 7.2 Cross drainage structures are divided into four
Level; categories depending upon the canal discharge and
10. Subsoil water level; and drainage discharge. Des&n flood to be adopted for
11. Nature pf bed material and value of ‘n’ these four categories of cross drainage structures is
(rugosity coefftcient in Manning’s formula). given in Table 1.
i’
Tible 1 Design Flood Values
(Clauses 7.2 an&TA). -
cstegory Canal Discharga in rn?sce *Estimated&&age F=qu~;;$Duisp
of Srructu~ Diiarge in m’/sac
A O-O.5 Ail discharges 1 in 25 years
B 05-15 O-150 1 in 50 years
Above 150 1 in 100 years
C 15-30 O-100 1 in 50 years
Above 100 1 in 100 years
D Above 30 O-150 ~1inlOOyears
Above 150 As per Note 2
NOTES
1 XX desigo flood IO be adopted as mentioned ia this table should in no case, be less than the observed flood.
2 la case of very huge cross drainage StNCIUfeS where estimated drainage discharge is above 150 cumecs and canal design discharge
is more than 3Octonecs, the hydroloe should be examined in detail and appropriate &sign flood adopted, which should in no case
be less than 1 in 100 years flood.
*This refers IO the discharge estimated on the t)asis of river parameters curresponding to maximum observed flood level.

3
Is 7784 (Part 1) : 1993

7.3 Where possible, the discharges determiued by dif- where


ferent methods mentioned in IS : 5477 (Part 4) :1971
PW = wetted perimeter in m;
’ should be compared to see if any large variations are
exhibited and the most reasonable value, giving c = a coefficient varying from 4’5 to 63 accord-
weightage to the one based on observed data, should be ing to local conditions, the usual value
adopted. Where there are cross drainage works already adopted being 4’8 for regime channel; and
existing on the same drainage channel, full data regarding Q = design flood in m3/s.
the observed flood should be obtained and the new cross
drainage works designed, with such modifications in the 8.1.2.1 The value of wetted perimeter obtained
design flood as may be considered necessary. from 8.1.2 is the total waterway between the two faces
7.4 To safeguard against unforeseen nature of flood of the abutments.
intensities the foundation of the cross drainage struc-
ture should be checked for a check flood discharge of 8.1.2.2 In works ‘with rigid floors, however, waterway.
value twenty percent higher than the design flood given can be further flumed within the permissible limits of
in Table 1. velocity negotiated through the available ventages.
Ordinarily such velocities should be limited to the
8 HYDRAULIC DESIGN ASPECTS
values given in Table 2
8.1 Waterway
8.13 For sub-vountaiuous and mountainous terrains with
8.1.1 Waterway.for a cross drainage wfirk is fixed from flashy flows, the waterway is provided within the width of
hydraulic and economic considerations with particular the existing stream. Where the slope of the natural drainage
reference to: channel is quite steep suitable methods may be adopted to
a) design flood, bring the velocity within the desired limits.
b) topography of the site, 8.1.4 The minimum dimension of openings should be
c) existing and proposed sectiou aud slope of the such as to permit, as far as possible, manual clearing of
drainage channel in the vicinity of the crossing, deposits therein.
d) peimissible amux, and 8.2 Clearauce for Aqueducts
e) construction and maintenance aspects. 8.2.1 Rectangular Openings
8.1.2 ..Ih plains, the drainage channels are generally in The clearance will depend upon the relative levels of
alluvium and the waterway usually provided in works the canal bed and high flood level of the draiuage
without rigid floor is about sixty to eighty percent of channel. Values given in Table 3 are suggested
the perimetei, given by Lacey’s formula: as suitable minimum clearances (taking iuto account
allowable afflux) for purposes of design, where
Pw = C [Q]“’ available.
Table 2 Maximum Permissible Velocities.
( Clause 8.1.2.2 )
SI No. ljpes of Floors Maximum Penuissihle Velocity

(1) (2) (3)


m/s
I? Metals face (steel and cast iron lined) 10

ii) Face of concrete grade M 30 and above ’ 6


i**
- grade &elow M 30 4

iii) Stone masonry face with cement pointing . 3


%LIW =

iv) Stone masonry face with cement plaster 4

v) Brick masonry face with cement plaster 25

vi) Brick masonry with cement pointing 2

vii) Hard rock 4

viii) Murum 15-2

W Soil silt 07-l

NOTES
1 Whe*_flow carries abrasive materiai$ with it, the permissible valuea may be further reduced by 25%.
2 Hard steel troweling, power floating, sqotb surface finish and conCnuous long curing can have higher abrasion resistance, and
higher velocities than that given in this table can be permitted, for surface using cemen!.

4
IS 7784 (Part 1) : 1993

Tuble 3 Miuimum Vertical Clearances for Rectangular Openings

SI No. Design Flood Minimum Vertical Clearance

(1) (2) (3)


m3h mm
9 Below 3 450
ii) 3 and above but below 30 600
iii) 30 and above but below 300 900
iv) 300 and above but below 3 WO 1200
v) 3 000 and above 1500

8.2.1.1 Ifthe minimum clearances specified in Table 3 8.4.3 The efzect of afflux on the submergence of the
are not available; safety of the superstructure should be surrounding coantry should be specially studied.
ensured against likely repercussions. 8.4.4 The afflux may be calculated by either of the
8.2.2 Arch Openings methods given at 8.4.4.1 and 8.4.4.2.
Minimum clearance measured to the crown of the arch 8.4.4.1 Rational formuiae
should normally be given as recommended in Table 4. Broad crested weir discharge formula or orifice dis-
8.23 In the case of drainage channels, wbere a bed rise charge formula depending upon the flow conditions
due to progressive silting is anticipated, the permissible through the cross drainage work openings, may be
clearance specified in Table 4 should be increased to applied for calculating afflux. When the performance
allow for such aggradations depending upon the extent of the cross drainage work openings remains unaf-
of silting. fected by the depth downstream of the obstruction,
83.4 Free Board that is, a standing wave is formed, weir formula is
applicable, otherwise the orifice formula holds good.
On aqueduct structures, the free board is reckoned horn
Approximately, when the downstream depth D,
the high good level (including afflux) in case of
drainage channel and from the full supply level in case above the crest is more than eighty percent of the
of canals, to the formation level of guide bank or canal upstream depth D, the weir formula does not hold
embankment. The free board should not be less thau good.
900 mm. Wherever heavy wave actions are au- a) Weir formula :
ticipated, the free board should be suitably increased.
Q = 1’70 C, LH3R
8.3 Clearance for Superpassages
where
83.1 Clearance
Q = discharge through the openings iu m3/s;
Clearances of about fifty percent of those recom-
c w= coefftcient of discharge accounting for
mended in 8.2.1 and 8.2.2 mutalk mutandis may be
losses in friction; the values may be taken as
provided in case-of superpassages.
under :
83.2 Free Board Condition Value
Free board recommended in 8.2.4 may be provided. I) Narrow openings with 0’94
or without floors
8.4 Alflux
2) Wide openings with floors 0’96
8.4.1 The afilux to be adopted in the designsllduld be
3) Wide openings without floors 0’98
that which would correspond to the design flood.
L = ~ I&ar_waterway in m;
8.4.2 The afflux should be restricted to such a value
H.2 total energy head upstream of the obstruc-
that the resulting velocity does not cause serious bed
scour in the drainage or does not create submergence tion in m, that is, D, + V2/2 g
which cannot be permitted. D, = depth of flow upstream in m; and

Table 4 Minimum Cleannces for Arch Opeuiugs


( Clauses 8.2.2 and 8.2.3 )
SI No. Arch Opening Clearrace

(1) (2) (3)


m
9 Less than 3 Rise or 0% m whichever is more
ii) 3 and above but less than 6. T, 2/3 rise or 10 m whichever is more
iii) 6 and above but less tban 21 2/.3 rise or 125 m which’ever is more
iv) 21 and above 2/3 rise or 15 m whichever is more

5
IS 7784 (Pert 1J : 1993

v*/2g = velocity head where v is the average


velocity in the approach section worked out
from the known width (W) of unobstructed
section.
w= width of unobstructed section.
b) Orifice formula

, O*’
Q = CoP dn LD,
where 0.6

Q= discharge through the opening in m3/s, I


c, = coefftcient of discharge, 0) 0*4

g = acceleration due to gravity in m/s’,


L = linear waterway in iii, 0.2
Dd = depth downstream of the obstruction in m,
h = afflux in m, 0
e = a factor accounting for recovery of some 0:5 0.6 O-7 0.6 0.9 t.(
velocity as potential head on emergence
from the cross drainage work openings, and -fOR+--
V = average velocity in approach section in m/s.
The value of ‘C,’ and ‘e’ to be adopted are given in
FIG. 2 COEWWENT‘e’ INTHEORLFKEFORMULA
Fig. 1 and 2 The afflux can be calculated knowing
(a) the discharge, (b) the unobstructed width of the If the value of Vvaries considerably in the unobstructed
stream, and (c) the average depth downstream of the cross section of the drainage channel, as in the case of
cross drainage work opening. a drainage chamtel which spills over its banks, Vfor the
purposes of this formula may be taken as the average
velocity in the main chamtel and correspondingly the
value of A should be determined by dividing the total
discharge by V.
8.4.4.3 In case of readily erodable beds, fi~ll afflux as.
calculated from 8.4.4.1 or 8.4.4.2 may not occur.
8.5 Depth of Scour
8.5.1 Mean De&t ofScour
The mean depth of scour in metros below the check/high
flood level may be calculated from the equation :
0.5 0.6 0.7 0.6 0.9 1.0

[I
2 In
d,,,, = 1’34 %
sf
FIG. 1 COEFFKJENT‘C,’ INTHEORIFKEFORM&A where
.
8.4.4.2 Empirical formula Di yt&%charge in cumecs per metre width. The
When the area of obstruction is not very large compared value of Di should be the maximum of the
to the original unrestricted area, the following formula following:
gives reasonably good results : 9 the design flood divided by the erfective
linear waterway between abutments or
h guide bunds, as the case may be.
ii) The value obtained should take into ac-
where count any concentration of flow through
h = afflux in m, a portion of the waterway assessed from
V = velocity in the unobstructed drainage the study of the cross section of the
channel in m/s, drainage channel. Such modifications of
A = the unobstructed se:tional afea of the the value may not be deemed applicable
to minor cross drainage structures with
drainage chamtel in m , and
overall waterway less than 60 m.
a = sectional area of the drainage channel
provided in the construction in m2. iii) Actual observation, if any.

6
IS 7784 (I’M 1) : 1993

KSF = the silt factor for representative sample of is representect*as the sum of these losses as applicable.
the bed material obtained up to the level of Thus, if the toTal loss of head is denoted by H then :
the deepest anticipated scour and given by H = h, + h2 + la, + h,
the expression 1’76 [C&J’”
where
‘c&’ being the weighted mean diameter in
millimetres. IQ = losses at the inlet and outlet (for syphon),
NOTES /I: = losses at elbows or bends (for barrel),

1 d, may be taken as thegrain sizeat 50% passing from 113 = losses due to transitions (other than syphon),
grain size distribution curve. and
2 The above method of estimating & is based on 114 = losses due to skin friction (for barrel and
Lacey’s theory for regimeconditions in alluvial beds. trough).
8.5.2 Maximum Depth of Scour for Design of 8.6.1 Lass ofHead at the Inlet and at the Outlet of Syplms
Foundation
The formula for the losses at the entrance may be taken as:
The maximum depth of scour below the Highest Flood
Level (H.F.L.) at obstructions and configurations of the
11, = [l +jJ $
channel should be estimated from the value of ‘d,,’ on
the following basis :
where
For the design of piers and abutments located in a
hi = loss of head at entrance or at exit in m;
straight reach and having individual foundations
without any floor protection works : fi = a coefficient which provides for the loss of
head on entry. It may be taken, for all prac-
i) In the vicinity of piers 2’00 d tical design purposes, as 0’08 for a bell
ii) Near abutments I,27 dll approach mouth entrance and as 0’505 for cylindrical
retained entrance with sharp edges (unshaped mouth
2’00 d,, scour all of the same sectional area of the barrel);
around- V = velocity in syphou iu m/s; aud
For the design of floor protection works, for raft foun- g = acceleratiou due to gravity h m/s*.
dations or shallow foundations, the following scour 8.6.2 Loss of Head Due to Elbows or Bends in Barrels
values should be adopted:
The loss of head due to elbows or bends It,, may be
i) in a straight reach 1’27 d sm computed in accordance with the procedure given iu
ii) at a moderate bend 1’50 d sm IS 2951 (Part 2):1965.

iii) at a severe beud 1’75 d sm 8.6.3 Well designed inlet aud outlet transitions are
necessary at the upstream and downstream approaches
iv) at a right angled bend 2’00 d sm of cross drainage works. Following estimates of losses
NOTE - The values of scour depth obtained as above in the transitions I13 generally hold for normal dcsigu
may be suitably modified where actual observed data is and installatiou conditions. These are not applicable to
available. syphons as for them this aspect is covered in 8.6.1.
8.6 Loss of Head (Energy Loss) These losses exclude losses covered by introduction of
trash racks OII upstream approaches.
When water flows through any structure there are head
losses due to various factors mentioned in~‘8.6.1 8.6.4 Loss of Head due to Skin Friction in the Barreki
to 8.6.4. The total loss of head occurring for a flow and Troughs

%I_ -

SI NO. Type of Transition ‘. Losses

Inlet
1 Streamline warped J-vz”
0’1
1-I 2g
2 Slraight ‘warped
yz- 4
o-2 -
i 2g 1
3 Straight warped with I;- vj
J-VI
bottom corner fillets 03 - -
{ 2g I 0.4 1 2s 1

where
‘1
~1 = velocity of flow before [he transition in m/s
~2 = velocity of flow atier the transition in ~~/s, and

8 = acceleration due to gravity in m/s*.

7
IS 7784 (Part 1) : 1993

8.6.4.1 The.loss of head due to skin friction in the To choose the value of ‘n’ refer to IS 2912 : 1964.
barrels ‘hb’ may be computed in accordance with the Depending upon the smoothness, hardness and
procedure given in IS 2951 (Part 1) : 1965. rendering of surfaces of the structure (concrete,
8.6.4.2 Loss of head due to friction in troughs h, plaster or masonry, etc), planeness, workmanship
should be calculated by the Mamling’s formula namely: and quality control the value of rugosity coefficient
‘n’ may be reduced for design purposes from the
v = i RV3,.SV2 typical value, so as to achieve reliability in head loss
estimates.
where
Manning’s constant depends upon the characteristics of
v = means velocity in m/s, the material and the surface roughness. In absence of
R = hydraulic means radius in m, actual investigation or established norms being avail-
S = slope, and able, value of Maiming’s constant as given in Table 5
n = Mann&g’s constant. may be assumed.

Table 5 Values of Manning’s Coeflicient

Qpe ofSurface Material Value of II

Range Normal Design Value

(1) (2) (3)


Concrete

0 Hard, smooth fmisb, troweled 0011 to 0014

2) Float fmish 0013 to 0015

3) Uofmished (oat properly floated) 0015 lo 0.022

4) Neat cement smootb finish 001 to 0012 0012

5) Steel shuttering finish 0012 to 0018 0016

a) Wooden planks shuttering tioish 0014 lo 0020 0018

-0 Large panel plywood shuttering finish 0013 LO0016 0016

8) Large panel smooth form finish, rich concrete 0011 to 0014 0013
@I30 grade and above) with joints grounded
smooth, and all defects rectified

9) Gunited (rough job) 0018 to OU25 0.022

10) Guoited (go&i plane job) 0016 to 0’023 0019

11) Smooth concrete surface with epoxy oU09 IO0012 0’011


or polymer treatment
Ma.lonty

1) Glazed brick, good workmanship very fine joints *’ 001 I lo 0’015 0013
.J 8
2) Good quality brick masonry in cement mortar 0012 to 0018 0018

3) Rubble masonry in cement mortar 0017 to$rk3Q I dU25


4) Dry rubble 0023 IO 0’035 0032

5) Dressed ashlar masonry 0013 IO0’018 0016

8.7 Wu~sition Walls percent may not be adopted. For the purpose ofcomputing
the Uuming ratio of canal, the width at mid depth may be
Transition walls as seen in plan, should at their ends,
taken as one hundred percent. In drainage channel when
turn nearly at right angles to the flow in the chamlel and
the course is undefined, a fluming ratio from seventy to
should extend for a minimum length of 0.6 m into the
ninety percent of the Lacey’s wateMray may bc adopted.
earth bank. Suitable pitching may be provided to the
slopes, beyond the trausitiou end. 8.9 Structure alid Earth Work Connection
8.8 Fluming Ratio ‘il The earth mass in vicinity of the rigid structure is tile
connection between rigid structure aud flexible
Except when dictated by conditions particular to a
earthwork. The rigid structure is nou settling, relative
specific structure, a fluming ratio less than seventy

8
IS 7784 (Part 1) : 1993

to the earthwork. The deflectious, settlements and other 1 mat exit point. This allowance iu height is the length
movements in the rigid structure are comparatively over which creep coefficient is to be assumed as zero.
very small. The rigid structure may consist of masonry, 8.9.2.3 From the plot of tlow net, the differential
PCC, RCC, etc. The connection between rigid struc- desigu pressure (soil aud hydraulic) on the rigid struc-
tures and’ earthwork is to be desigued so as to reduce ture cau be estimated.
the differeutial settlement, and to avoid the possibility
of formation of a separatiou (cleavage) betweeu the 8.9.3 The bottom slabs of box (or barrel) or culverts
two. The conditiou of counectiou between the rigid should be checked for safety against the uplift force in
structure and the earth work affects the seepage, creep a severe combinatiou of forces chosen. CBecks should
coefficient arid piping and thus affects the stability of coiisist of:
the earthwork. a) safety against movement or flotatiou during
For the couuection, soil of proper qualities should be construction and in service, and further
chosen. The method and the amount of compaction b) check for design stresses with severe combina-
should be as required. tiou of uplift.
8.Y.l The. canal embaukment adjoining the cross 8.9.3.1 For safety against flotation or movement, if
drainage structure should have adequate provisious to required, the gravity loads cau be increased by increas-
avoid possibility of auy breach aud to minimize iug thickucss of members, providiug additioual cou-
seepage. The outer slope of the embankment should Crete or masonry for weight, or anchoring the members
have a clear cover of 600 mm over the desigucd iuto the fouudatiou strata or deeper. The sum of down
phreatic line (see IS 7894 : 1975) for the worst com- ward equilibratiug forces should be at least 1.2 times
biuation of desigu flood in natural draiuage chaancl and the upward buoyancy force. For checking the stress
aiuiual low water level. couditiou in -the members, the dead loads or the
High earth bauks (say over 5 m above ground) should dowuward equilibratiug force (such as anchorage)
be checked for stability of slopes and provisiou of should be reduced by dividing these by 1.2. Anchorages
rock-toe with tilter should be made. Rip-rap or pitching aud parts of auchorage system should be checked for
should be doue up to a level 0.5 m above HFL plus stresses uuder full load required for safety against -
afflux as applicable (see IS 10751:1983, IS floating.
11532:1985, IS 12094:1987, IS &X37:1985). For large 8.Y.4 Whcu tlow is through multi barrel, at the
drainage channel properly desigued guide banks may upstream aud dowustream ends, stop-log grooves may
be required. be provided by extcndiog the partition wall, so as to
8.9.2 The water Uow through various soil strata should facilitate isolating oue or more barrels for maiutcuauce
be engineered. Flow uet through earth work aud foun- or repair. Euds of the partitious of multi-barrels should
datiou strata is to be estimated. Exitgradieutofseepage be provided with cut aud ease water shapes so as to
water should be limited withiu the permissible limit. minimize the energy loss.

Adequate fouudatiou depth or cut-off or curtaiu walls 8.10 Abrasion Resistance


may be provided of suitable depth so as to get scfe exit Structural members in the bed of the flow should be
gradient, which may be worked out iu accordauce with safe against abrasion loss. Depending ou the velocity
Khosla theory for two dimeusioual flow. In large struc- of llow aud the abrasiou causing debris (stone gravel,
tures three dimeusioual seepage flow may be cou- saud silt, ctc) it may hold, the structural mcmbcr iu the
sidered for estimatiug exit gradient. bed should be hard euough aud of suf[icicntly high,
8.9.2.1 The permissible creep coefficieut (head loss streugth or it should be giveu a treatmcut or wearing
per unit length) through soil may depeud upou degree coat to enhauce the abrasion resistauce. Fitchiug of
of compaction, whether it is rebilled, actions &soil- heavy weight stoues, stoue masonry or high grade
StNChIrC counectiou or interface, relative movtmeuts coucrete overlays may be provided.
between soil aud rigid structure, probable settlements, Apart froitLthc&e.d of llow, the mcmbcrs ou the sides
etc. may also,be suhjectcd to abrasion, though the material
Generally the permissible value of exit gradicut for causing abrasion may be less effective OII the sides thau
flow through dirfereut types of soils cau be adopted as at the bottom. Hence due cousidcratiou for durability
below : of sides, alougwith the llow should be givcu.
Clay 1 in 4 9 FOUNDATION
Shingle 1 in4to5 9.1 Fouudatious of a cross drainage work should be
Coarse sand 1 in 5 to 6 dcsigucd to satisfy the rcquircmcuts of allowable bcar-
Fine sand 1 in 6 to 7 iug capacity of the fouudatiou strata uudcrcritical loads
iucludiug positive pressure couditious (i.e. IIO uplift or
8.9.2.2 At cutry,tiud of seepage path, au allowance, as tcrrsion), seismic effects, antiripatcd scour and settlc-
discount, should be assumed for settlemeut aud iuetfi- 111ent.
cieut maiuteual,ce, scparatiou, cracking, c$c. At exit
end a discouut or allowauce should be assuulcd against 9.1.1 The sub grade at the fouudatiou lcvcl lbr knowu
erosion, scour or settlement. In absence of au estimate, shape aud size of fouudalious, depth below ground
the allowance may be 0.6 m high at entry point aud level, expected sub-soil water lcvcl and cugiuceriug

9
IS 7784 (Part 1) : 1993

properties should be safe in bearing capacity. Compara- tested on models. These studies should infer ulia.
tively lower pressures are allowed on foundations ou taken into account the impact of ancillary com-
sub-grades prone to appreciable settlement. poncnts of the structure, namely, the approaches,
9.1.2 As far as possible, the foundation should bear on end connections, aftlux bun&, Hnors, p:otectioii
arrangements and any upstream Or dowmtream
homogeneous, undisturbed and unifonn sub-grade of
fairly dense type. Where foundations have to be structures on either the canal or the drainage chan-
provided on sub-grade of different types suitable joints nel.
should be provi’dcd to avoid cracks due to differential 11 MISCELLANEOUS DETAILS
settlement, the tolerance limit has to be evaluated for
11.1 Waterstops
each case.
Waterstops, also referred to as water seals, are
9.13 The permissible maximum differential settle-
generally of three types, namely : (a) rubber water
ment of the foundation strata estimated should not
seals, (b) metal water seals, and (c) synthetic
exceed 1 in 400. In case of structures sensitive to material seals. The waterstops are used in and
differential settlement, the tolerance limit has to be
across all joints where leakages are detrimental to
evaluated for each case.
structural safety or the water needs are to be con-
9.1.4 When the seismic effect is considered, higher served. The locations where waterstops are
bearing capacity may be adopted in accordance with provided in various types of cross drainage works
IS 1893 : 1984. arc described below:
9.1.5 The foundations should be taken sufficiently
a) Aqueduct - In R.C.C. through side walls
deep to secure firm strata from considerations of settle- and bottom slab over each pier in a continuous
ment, overall stability and avoidance of undermining length and at the junction of transition and
due to erosion. The depth of foundation of various R.C.C. trough, both in the floor and wing
members should be such that these are safe against walls.
scour or are protected against it. If sound rock is met Syplron-At expansion joints and at the junc-
with, at the higher levels than the anticipated scour, b)
tion of ea’ch of the sloping limbs in a con-
scour criteria will not be applicable. Tension (i.e. nega- tinuous form and at the junction of the
tive contact pressure) can be allowed only if foundation transition walls and floors with the barrel,
strata consists of hard rock, however, such negative both at the entry and exit in a continuous
contact pressure should be neglected in the design form.
calculations.
4 Sirperpassage -At the junction between the
9.1.6 Maximum depth of scour should be computed for drainage trough wing walls, namely, trough
stream as in 8.5 from check high flood level (CHFL). wall of R.C.C. and wing wall of masonry and
Either the foundation or cut-off wall if provided, under all the expansion joints in a continuous
the foundation should be taken to a depth 1.333 times length.
the scour depth estimated below CHFL or 1.05 times
the scour depth estimated for probable maximum tlood 11.2 Weep Holes
(PMF). Either depth of foundation, or depth of cut-off Weep holes are small openings in the retaining walls,
if provided,‘should also be governed by permissible like wings (i.e. transitions of natural stream). These are
gradient of seepage water in 8.9.2. In case of canal to facilitate the drainage of backfilis and avoid build up
having erodablc bottom (i.e. unlined) similar checks of pressure. Weep holes may be provided above the
should be done for full supply discharge. ; flow net line of zero water pressure, under the condition
9.1.7 Where concrete or masonry fltio%!Is provided of canal llowing full and natural stream with lowest
under the works, scour condition is not applicable and am!ual llow.
the foundatio,ns are usually taken to about 1.5 m below W&?daleS if provided, should have filters with
the floor levels with suitable cut off for the concrete or gfgded material suitably provided to avoid piping of
masonry floors. However where such a floor is not earth fill behind the wall and also to avoid choking
provided, foundations are taken to provide a margin of the holes.
below the anticipated scour level (usually called grip The provision of weep holes should be so, as to not
length) of about 0.33 times the maximum depth of render the creep coefficient of seepage unsafe, and.
scour. should also not contribute to enhanced loss of canal
water.
10 MODEL STlJDlES
11.3 Ikurings
10.1 Owing to a number of complex factors in the
For safe transfer of load from superstructure to sub-
design of hydraulic structures and specially when the
structure suitable bearings should be provided between
designs are based on empirical fqrmulae, adequate
the trough bottom and pier abutment to cater for the
answers cannot be obtained through a$ialytical methods
various movCments occurring in the superstructure
only. Therefore, it would be in the best interest, if the
under different combinations of load.
designs for major cross drainage works are first

10
IS 7784 (Part 1) : 1993

ANNEX A
( Clause 2.1 )

LIST OF REFERRED INDIAN STANDARDS

IS No. Title IS No. Title

1893 : 1984 Criteria for earthquake resistant design 4410 Glossary of terms relating to river valley
08 structures Cfoiirth revision) (Part 151 projects : Part 15 Canal structures, Sec-
Set 5) : tion 5 Cross drainage workds (/ht
2912 : 1964 Recommendations for liquid flow 1992 revision)
measurement in open channels. by
slope area methods (approximate 5477 Method for fixing the capacities of
methods) 1’9”;: 4) : reservoirs : Part 4 Flood storage

Recommendations for estimation of


flow of liquids in closed conducts : Part 7894 : 1975 Code of practice for stability anyalysis
of earth dams
1 Head loss in straight pipes due to Cric-
tion resistance. 8237 : 1985 Code of practice for protection of slope for
reservoir embankments (first revision)
2951 Recommendations for estimation of
flow of liquids in closed conduits : 10751 : 1983 Criteria for design of guide banks for
@aPa;2) :
Part 2 Head loss in pipes and fittings. alluvial rivers
11532 : 1985 Guidelines for construction of river em-
4410 (Part Glorssary of terms relating to river val- bankments (levee)
ll/Sec 5) : ley projects : Part 11 Hydrology, Section
12094: 1987 Guidelines for planning and desgin of
1977 S.Floods
river embankments (levees)

11
Standard Mark
The use of the Standard Mark 1s governed by the provisions of the Bureau of Indian
Standards Act, 1986 and the Rules and Regulations made thereunder. The Standard Mark on
products covered by an Indian Standard conveys the assurance that they have been
produced to comply with the requirements of that standard under a well defined system of
inspection, testing and quality control which is devised and supervised by BIS and operated
by the producer. Standard marked products are also continuously checked by BIS for con-
formity to that standard as a further safeguard. Details of conditions under which a licence
for the use of the Standard Mark may be granted to manufacturero or producers may be
obtained from the Bureau of Indian Standards.
Bureau of Indian Standard0

BIS is a statutory institution established under the Bureau of Indian Standards Aci, 2986 to promote
harmonious development of the activities of standardization, marking and quality certification of
goods and attending to connected matters in the country.

Copyright
BIS has the copyright of all its publications. No part of these publications may be reproduced in any
form without the prior permission in writing of BIS. This does not preclude the free use, in the course of
implementing the standard, of necessary details, such as symbols and sizes, type or grade designations.
Enquiries relating to copyright be.addressed to the Director ( Publications ), BIS.

Review of Indian Standards

Amendments are issued to standards as the need arises on the basis of comments. Standards are also
reviewed periodically; a standard along with amendments is reaffirmed when such review indicates that
no changes are needed; if the review indicates that changes are needed, it is taken up for revision.
Users of Indian Standards should ascertain that they are in possession of the latest amendments or
edition by referring to the latest issue of ‘BIS Handbook’ and Standards Monthly Additions’.
Comments on this Indian Standard may be sent to BIS giving the following reference:

Dot : No. RVD 17 ( 56 )

Amendments Issued Since Publication

Amend No. Date of Issue Text Affected

BUREAU OF INDIAN STANDARDS

Headquarters:
Manak Bhavan, 9 Bahadur Shah Zafar Marg, New Delhi 110002 Telegrams : Manaksanstha
Telephones : 331 01 31, 331 13 75 ( Common to all offices )
, .
Regional Offices : _,‘! Telephone

Central : Manak Bhavan, 9 Bahadur Shah Zafar Marg ; 331 01 31


NEW DELHI 110002 L-w.
,,- . I 331 13 75
Eastern : l/14 C. I. T. Scheme VII M, V. I. P. Road, Maniktola 37 84 99, 37 85’61
CALCUTTA 700054 I 37 86 26, 37 86 62
Northern : SC0 445-446, Sector 35-C, CHANDIGARH 160036 53 38 43, 53 lb 40
1 53 23 84
Southern : C. I. T. Campus, IV Cross Road, MADRAS 600113 235 02 16, 235 04 42
I 235 15 19, 235 23 15
Western : Manakalaya, E9 MIDC, Marol, Andheri ( East ) 632 92 95, 632 78 58
BOMBAY 400093 ‘i 632 78 91, 632 78 92
t
Branches : AHMADABAD. BANGALORE. BHOPAL. BHUBANESHWAR.
COIMBATORE. FARIDABAD. GHAZIABAD. GUWAHATI. HYDERABAD.
JAIPUR. KANPUR. LUCKNOW. PATNA. THIRUVANANTHAPURAM.

Printed at New India Printing Press. Khurj~. ~no~a

Você também pode gostar