Escolar Documentos
Profissional Documentos
Cultura Documentos
T
he Dhamra Port developed by vessels up to 180,000 DWT with a to Larsen & Toubro covering a
Dhamra Port Company Limited total capacity to handle 25 million wide gamut of operations such
(DPCL) in Orissa is a 50:50 tons per annum of cargo. The as civil, mechanical and electrical
joint venture between Larsen & master plan for the overall port when works as well as construction of
Toubro and Tata Steel. The Dhamra- completed provides for 13 berths, the railway network which will
Chandbali Port is located near capable of handling more than 100 connect the port with the Indian
village Dhamra on the North of the million tons per annum of dry bulk, Railways’ network at Bhadrak on the
river Dhamra, about 68 km from liquid bulk, break bulk, containerized Howrah-Bhubaneswar route. Various
Bhadrak District in Orissa, situated and general cargo. The location of operating companies (OCs) and
between Haldia and Paradip. This Dhamra is in close proximity to the Business Units within L&T took up
signature port is being developed mineral belt of Orissa, Jharkhand different construction activities under
by DPCL on Build, Own, Operate, and West Bengal and its deep draft phase-I and completed the same on
Share and Transfer (BOOST) basis suitable for large vessels will make schedule. Scott Wilson Kirkpatrick
and the company has been given a the port one of the most cost-effective India Pvt. Ltd, the Indian arm of
concession to operate the port for a and efficient on the Eastern coast of the UK-based Scott Wilson
period of 34 years including a period India. Kirkpatrick, has been appointed the
of 4 years for construction. project management consultant.
Integrated Port Project L&T’s scope of work for the
This is one of the deepest ports in
construction of Dhamra Integrated
India with a draft of 18 meters and DPCL entrusted the contract for
Port Project included the following
it can accommodate super cape-size Phase-I construction of the port
facilities:
Coal conveying system at Dhamra. Inset : coal being conveyed through the conveyor
Superstructure - 121 span (700 m long) Railway overhead electrification for total length of
110 Tkm ( 62.5 Rkm)
Material Handling System Signaling & Telecommunication length or nos.
Ship Un-Loader for Coal (2800 TPH) - 2 nos
132 KV Transmission Line
Ship Loader for Iron Ore (5000 TPH) - 1 no
Length from Bhadrak to Port - 65 km
Wagon Tippler (25 tips/hr.) - 1 no
Number of transmission towers - 261nos
Reclaimer & Stacker Cum Reclaimer for Iron Ore
- 2 Nos 132 KV Switch Yard
¾¾ (Stacking - 3750 TPH & Reclaiming - 5000 1 No at Bhadrak End.
TPH)
1 No at Dhamra End.
Stacker cum Reclaimer for Coal - 2 Nos
¾¾ (Stacking - 5500 TPH & Reclaiming - 3500 Township
TPH) E-Type Block - 120 Flats
Conveyors - 7.24 km (5500/3500 TPH) Bachelor Hostel – 30 Rooms
to meet the stringent deadlines lighting system was adopted in such place to meet exigencies during
set by the client. Following are a manner that turtles would not get cyclonic storm. This envisaged a
some of the many constraints they attracted towards source of the project well-defined evacuation plan for
had to face during the period of construction lighting. This was a labour, staff and materials and the
construction: conditional requirement and project resources were reinstated at the
authorities including all contractors end of the season.
Site Access – The most critical
had to abide by the same in order not
problem everyone faced during the There was a shortage of skilled
to disturb the nesting and hatching
construction of the project was the manpower too; however, local
habits of Olive Ridley Turtles. For this
long temporary single lane access workmen were trained to mitigate
purpose, sodium vapour lamps with
road. Since there was a delay in this situation.
protective covers were used in place of
land clearance, settlement and
halogen and metal halide lamps
handing over of the land for road Plant & Machinery
construction, everyone had to use this Bulk Materials Scarcity – The project
Following plant & machinery were
only source, which was a real ordeal continuously faced bulk materials
deployed for executing the work
for every staff and vendor visiting scarcity throughout its construction
expeditiously under inclement
the site. In order to avoid everyone phase. Hence alternative materials
weather condition on the sea
congesting the road during the day were constantly tried out. For
front:
time, it was decided to transport all example, extensive use of Ordinary
goods and materials only during Portland Cement was replaced with Batching Plant 30 cu.m 1
night with adequate safety and Slag Cement. Crusher dust and Boom Placer 1
security measures. weather rocks were used for plant 150 t capacity P&H crane 1
road construction work 80 t capacity Fushun crane 1
Turtle Friendly Lighting – As per
environment protection guidelines A proper Disaster Management 75 ton Cranes 4
issued by IUCN, turtle friendly Plan was prepared and kept in 18 ton cranes 6
Treatment Philosophy
19m DIA 800 cu.m capacity clariflocculator
The Hydraulics of the treatment plant is designed
in such a way that water flows by gravity from the from the centrifuge is then collected and disposed in an
cascade aerator (first unit of the WTP) to the clarified environment friendly way. The entire water treatment
water reservoir. From the clarified water reservoir plant is designed for a hydraulic overloading of 20 %
it is then pumped to the pressure sand filters for and for a turn down capacity of 50%.
potable water requirements and also pumped for Broadly the water treatment scheme comprises
dust suppression applications at various locations in Cascade aerator, Parshall flume, Flash mixer,
the Port operation area . The sludge generated from Clariflocculator, Clarified water sump and pump
the clariflocculator is then treated through sludge house, Pressure sand filters, Potable water sump and
thickener and centrifuges. The final dewatered sludge pump house, Sludge Thickener, Centrifuge
remaining16 months. Therefore A special gang was engaged for of sleeper laying and rail threading
L&T employed Sleeper Layer doing foundation using boom to reduce deployment of workmen
and Rail Threader machines for pressure in gape location due to substantially.
erection of mono block sleeper delay in cess handover and land
For Rail joint automatic flash butt
and rail laying. dispute. The entire stretch of the
welding machines were deployed
railway route was divided in to
OHE work in DPCL project was by subcontractors in addition to
small sections for advance feeding
different in many ways compared departmental and dedicated FB
of required material such as Mast /
to the regular CORE / RVNL machine. On an average the site
Portal, Bracket etc. and expediting
railway contract works that L&T achieved a production of 70 Joints
installation work as soon as the
executes. This in fact called for per machine per day.
foundations are cast.
advanced techniques in OHE
Centre line of track was done on
erection methods to mitigate Outsourcing of P&M and back-to-
the cess by coordinate for marking
stringent time schedule, working back arrangement with specialized
the OHE foundation. Thus the
in cess without a track and major agency not only helped to meet
problem of non-availability of
P&M like erection crane, tower the scarcity of captive P&M and
track was eliminated. Excavation
wagon etc normally supplied by staff, but also ensured better
of OHE foundation was done both
Railways. quality of work.
by manual as well as excavator.
The entire 2500 (15000 cu.m) of For the permanent way construction Concrete was supplied from site
OHE foundations were cast on cess work both manual and mechanized through concrete mixture. In
without having a track or any other linking methods were used. In both critical area and inconvenient
facility within a short period of 7 methods, usage of Hydra Crane for locations Boom placers were used
months. A dedicated survey team handling of Rail, sleeper, Dumper for to avoid delay. All mast erection,
provided for marking of error free ballast spreading, Roller for ballast boom erection was done with
center line to avoid rejection of compaction were employed in Hydra Crane and stringing of
foundation. addition to the mechanized method contact wire and catenary were
132 kV switchyard
The 132 kV switchyard specially
built at Dhamra port, draws its
power from Bhadrak substation
of Orissa Power Transmission
Corporation Limited (OPTCL) Another view of the switchyard at port
and this meets the complete One bus section aliser 6.6 kV bus duct. The switchyard
power requirements of the port consists of the following major
electricals. The switchyard consists Single main transfer scheme is equipment:
of the following bays: adopted for this 132 kV switchyard
wherein the main busbars are 20 MVA 132 / 6.9 kV YNyn0,
One Line feeder ONAN transformer
rated for 1250 A, 3 phase, 31.5
Two 20 MVA 132 / 6.9 kV kA for 1s. The secondary 132 kV 1250 A SF6 circuit breaker
transformer feeders transformer is connected to 6.6
1250A Isolators
One bus transfer kV indoor switchgear through
Illumination
The illumination system implemented
at Dhamra Port is designed to
ensure the best of environmental
practices worldwide. The Lighting
management has been identified as
one of the key measures to mitigate
light pollution from the port lighting
system which has an adverse impact
on the Olive Ridley turtles, one of the
rare species of its kind, prevalent in
this part of the world. In principle,
L&T is strictly adhering to the Lighting
missions advocated by IUCN (The
International Union for Conservation
of Nature) lighting experts. They
have helped DPCL to choose and
select the specific lighting fixtures
which would minimize light spillage
and does not misguide or migrate
the turtles.
L&T completed the 65 km long 132 kV and as such, it is considered as the route for this Bhadrak – Dhamra
Transmission Line tower construction Life Line to Dhamra Port and the transmission line mostly passes
work from Grid Substation at entire project was executed in a through fertile agricultural fields,
Bhadrak to Dhamra and linked it period of 32 months. along the Orissa coast. The soil
with the 132 kV / 6.6kV Substation conditions in many places were
at the Port complex. This is the only Unlike the normal transmission not suitable for normal open cast
source of power to this mega port lines built across plain terrain, the foundations and L&T had to build
them on pile foundations, which movement of operations. However, practices in the store management
came as a real challenge. these issues were amicably settled even at isolated locations
by the Construction Manager, attracted the attention of our clients
Out of the total 260 foundations, Site Engineers, Accounts and and they acclaimed the same in
171 were built on pile foundations. Administration team right from the many forums.
Nearly 1316 cast-in-situ piles commencement of the project.
were cast along the entire stretch Similarly safety has been accorded
accumulating to 23786 m in length. Being a project on the move, the highest priority and accordingly
In addition, the topography of the transmission line projects call for the site clocked one million lost
entire stretch of the line was low proper Stores Management. Keeping time injury free man-hours upto
lying which made the construction stock of good inventory is essential November 2009 and the project was
all the more difficult, particularly for the progress of the project without awarded the certificate of merit for
in the monsoon period and the any delay. This fact is well known its EHS activities.
post monsoon months. Water to our engineers, but the greatest
Thus the project was successfully
logging continued even beyond challenge was in meticulous planning
commissioned to its rated Voltage on
the offset of monsoon and the and keeping stock of inventory at
14th January’ 2010 and was handed
able Site Engineers worked out strategic locations to meet the timely
over to Orissa Power Transmission
various innovative approaches requirements of the project. Beating
Corporation Limited (OPTCL) during
to ensure an uninterrupted work all the odds, our engineers carried
March 2010.
schedule at site. out the task in the most efficient
Compiled by
manner, thanks to the Project
There were protests and agitations Management Team for their expert K. Sridharan with inputs from project
by disgruntled local land owners planning, mobilization of resource team – Pabak Mukhopadhyay,
which had an impact on the Right- and implementation techniques. Sutanu Ganguly, Deepak Kumar,
Of-Way clearance and speedy Ramkumar, Debashis Ghosh and
Our strict adherence to ISO certified Kuntal Pakhira
I
ndia is one of the most fortunate the second largest steel producer RashtriyaIspat Nigam
countries to have an abundance in the world by the year 2015. Limited -
of Iron ore which is the raw Abetted with the growing global
Visakhapatnam Steel
material for making steel. The demand and the increasing
per-capita consumption of steel domestic consumption, domestic Plant
in a country is one of the most steel producers are expanding L&T in consortium with Paul Wurth
important barometer for measuring production capacities in order to Italia bagged the EPC order for
development and economic capitalize on this opportunity. the Blast Furnace # 3 with a Hot
growth. Steel is crucial to sustain metal capacity of 2.5mtpa.Once
Rashtriya Ispat Nigam Limited
the development and growth of commissioned, this furnace will fulfill
(RINL), the holding Company of
all infrastructural needs, be it VSP’s phased expansion planned
Visakhapatnam Steel Plant is also
construction of roadways, railways, target of liquid metal production.
in a similar fray of expansion and
ports, dams, power plants, water L&T’s scope of work includes
supply systems, housing, etc. has set its mission to attain 16
million ton liquid steel capacity complete detail engineering based
Presently in 2010, the steel through technological up- on basic design and engineering
industry in India is the fifth gradation, operational efficiency inputs by Paul Wurth and the major
largest in the world and given the and expansion. The existing portion of indigenous manufacturing
vibrancy with which it is growing, capacity of Visakhapatnam Steel and supply, erection of equipment
the Steel Ministry estimates that Plant (VST) stands at 3.4 million including the associated civil and
the India is poised to become tons per annum. structural works. Apart from this there
then screened and weighed as per which can change angles allowing
Technical Features of operator defined charging sequence more flexibility in precise material
Blast Furnace and transported to the top of the distribution inside the furnace.
Working Volume : 3,230 cu.m furnace using a conveyor system.
Blast Furnace Proper: The blast
Inner Volume : 3,814 cu.m Main Charging Belt Conveyor: furnace is a tall steel structure
Hearth Diameter : 13 m Main Charging belt conveyor is with varying shell thickness that is
divided into two parts MB1 of length internally lined with refractory. The
Tuyeres : 34 nos
138m (from stock house to transfer refractory is cooled by water - cooled
Peak Production : 7,850 tpd tower) and MB2 of length 369.5m metal components called staves,
Average Production : 7,150 tpd (from transfer tower to top of the which are embedded between the
furnace). The height of trestles for shell and the refractory.
Furnace Top Pressure : 2.5 bar g
the conveyor varies from 4 to 57m.
Fuel Rate : 535 kg/HMt BF Shell - The furnace body or
The conveyor gallery including
profile consists of five parts:
technological structures in assembled
using DEMAG CC1800-1. The civil condition of length 54m weighing 1. Hearth, at the bottom of the
works for stock house was handled 130 Mt was erected in single lift furnace, which is a straight
by RINL through other agencies. using DEMAG CC2800 crane. cylinder
All the 5 parts mentioned above were panels which were assembled at Down comer: Down comer erection
supplied by Paul Wurth from China ground in order to reduce the of a blast furnace is one of the
in 22 rings, each ring comprises 6 number of lifts. toughest jobs due to the intricacy
segments. The circular BF shell rings involved in terms of the weight to
got erected in 11 lifts. Staves & Refractory: Staves are be handled and the configuration.
flat cooling members provided The down comer design at VSP was
Normally the fit up of Tuyere holder parallel to the furnace shell. This different from other similar furnace
rings and making the opening for will act as the heat exchanger, and designed by Paul Wurth, as two down
outlet nozzle for off-take pipes are consists of embedded pipes which comers are provided in the place
carried out in shop floors due to the carry water and are connected to the of one down comer. Down comer
criticality of job and level of accuracy main cooling circuit of the furnace. connects the furnace to the dust
required. In VSP, these jobs were Erection of stave and refractory catcher and carries the BF gas to gas
carried out successfully at site by works were taken up simultaneously cleaning plant. Down comer erection
developing the necessary templates, by providing safety deck at two along with the refractory at VSP were
jigs and fixtures. different levels and one moving completed in a shortest period of
platform in-between to facilitate men two days (including welding) for
Tower Structure: The blast
and material movement. each down comer. Such complicated
furnace being a free standing
structure, all the platforms and Carbon blocks which forms the part erection would normally take many
other structures need to be of Hearth refractory were pushed into weeks due to the intricacy involved in
supported on a tower structure the furnace using roller arrangement joint matching.
which is categorized as Lower, through a temporary opening made Blast Furnace Cooling System: In
Middle and Upper tower. The in the shell. The carbon blocks were order to keep the furnace refractory
lower tower structure was erected handled using hoist arrangement in a cooled condition, an elaborate
in 4 lifts. Erection of middle and fixed to the safety deck and were cooling system of soft water and
upper tower was taken up in placed over the leveling grid.
Cast House
Liquid iron and slag from the tap-
hole flow down a deep trench called
a “trough”. Set across and inside
the trough is a block of refractory,
called a “skimmer”, which has a
small opening underneath it. The
hot metal flows through this skimmer
opening, over the “iron dam” and
down through the iron runners.
Since the slag is less denser than
iron, it floats on top while the iron
flows down the trough, hits the View of Granulation system cooling tower & Chimney
skimmer and is diverted into the slag
runners. The liquid slag flows into from the iron notch area, skimmer, Slag Granulation Plant
slag granulation plant and the liquid iron runner, tilting and slag runners
iron flows into refractory lined ladles is collected from various suction The main output of BF process
known as “torpedo cars”. These are hoods and passed through a is hot metal/liquid iron. During
operated by Pusher Car to control duct network, ESP’s (Electro Static tapping operation, the liquid
the movement within the cast house. Precipitators), ID (Induced Draft) metal is collected in torpedo
fans and will be finally discharged ladle through runner system and
Cast House Details to atmosphere by means of a stack. then sent to steel melt shop for
No. of cast houses : 2 The ESP’s are designed to handle production of steel.
an inlet dust load of 1 g/Nm3 of
No. of tap holes : 4 During the process, two by-
flow rate 13,00,000 m3/hr at
products are formed, BF Slag &
Cast house columns are of structural operating temperature of 800C to
BF Gas. The liquid slag coming
steel with a floor of heat resistance discharge a maximum outlet dust
out of the BF is quenched by a jet
concrete. The dusty air coming out load of 50mg/Nm3.
of high velocity of water thereby
producing granulated slag. This
is mainly used as a raw material in
cement industry, and as an additive
for concrete.
Injection (PCI) plant. PCI comprises the same will be injected inside The raw coal and fine coal silos,
of two numbers of vertical rollers the furnace along with the Hot grinding equipment and injection
mill. Non coking coal will be Blast. equipment are housed in a steel
grinded in the mills and will be structured building of height 60m.
Max. Coal Injection:200 kg/tHM
conveyed pneumatically through
pipe line to Tuyeres from where Avg. Coal Injection:150 kg/tHM Electrical &
Instrumentation
A state-of-the-art electrical system
has been installed at VSP, which
comprises of HT and LT panels
apart from indoor and outdoor
transformers. All the substations are
automated by means of intelligent
control system. The SAS (Sub-station
Automation System) co-ordinates
with the remaining electrical system
in the plant and optimizes the power
consumption.
The level 1 of automation system
consists of Distributed Control
System which centralizes the
entire blast furnace operation.
This reduces the number of
Illuminated view of Hot stoves
Variable Voltage Variable installed at critical locations buildings for stock house, TRT,
Frequency (VVVF) systems for continuous monitoring. SGP, PCI and Pump Houses
are installed to reduce the
power consumption and All the installation works related Service rooms, Hydraulic and
provide a maintenance free with electrical and instrumentation lubrication rooms in different
operation. have been completed and locations
Intelligent addressable Fire Alarm presently testing and charging Chilled water plant, Cooling
System integrated with HVAC activities are underway. towers, Air Conditioning &
(Heating, Ventilation and Air Ventilation systems
Auxiliaries
Conditioning) and Clean Agent Emergency overhead (80m)
System has been implemented The plant is also provided with the
water tank, Filter press
for enhanced plant safety. following facilities
Fire Fighting System, Fire Alarm
Blast Furnace office cum main
CCTV cameras with Latest System, High Velocity Water
control room
technology day/night CCTV Spray (HVWS) system and Clean
system (IP based) are Different electrical control room Gas Agent system
Corporate Social
Responsibility
L&T’s VSP team has also devoted
their time for CSR initiatives by
spending time with the under
privileged children of a nearby
orphanage in Vizag. The team
has distributed basic amenities
like hygiene kits, sports material,
food items, etc., to the children
there.
Visit of Hon’ble Minister of Steel at VSP project on 10th May’10
(From Left to Right - Mr. P K Bishnoi – CMD RINL, Mr. Virbhadra Singh - Hon’ble Union Minister of Execution work at VSP project
Steel, Mr. A SaiPrathap - Hon’ble union minister of state for Steel, Smt. Daggubati Purandeswari - is completed and testing and
Minister of State for Human Resource Development (Higher Education)
commissioning of various plant
and equipment are underway.
Maintenance equipment camp that has been constructed
The plant is scheduled to undergo
including EOT cranes, Electrical outside the plant boundary to
production within a couple of
and mechanical hoists accommodate about 6,000
months thereby fulfilling VSP’s
Plant road, Railways, Sewerage workmen during peak periods.
mission of achieving 6.5 mtpa
and Drainage system within the Proper care is being taken for
of liquid steel production.
battery limit sanitation and cleanliness at
labour camp. For L&T, commissioning of Blast
Spare Stores, Canteen and
Furnace # 3 at VSP has added yet
wash-room blocks The VSP project site achieved 38.2
another feather to its cap. This
Car park, Cycle & Scooter Million Accident Free Man hours
project will further reinforce the
stand as on Sept, 2010 and has won the
belief that “Steel is L&T’s strength
following awards
and it will continue to play a more
Environmental, Health, ROSPA Gold in 2010 significant role in this sector, in the
Safety and Quality ROSPA Silver in 2009 years to come”
T
he IT industry in India has grown the topography to transform the The Project
amidst global competition like place into ‘Cyberabad’ that is home
no other industry has. From a to almost all leading names in the IT Godrej Waterside, as the name
mere US $ 150 million in the early industry. In all major cities L&T has rightly suggests, is a breathtakingly
90’s the IT industry has touched a built sprawling IT parks that offer imposing structure along a water
staggering US $ 60 billion by 2010. best-in-class amenities to leading body on one side and access to a
A reasonable amount of this growth IT brands from the world over. One busy road on the other. With a total
spurt can be attributed to the creation such significant and recent addition built-up area of 2.2 million square
of world-class IT infrastructure in to the city of Kolkata is the ‘Godrej feet Godrej Waterside comprises
rapid speed and scale. L&T, in line Waterside’ an IT park located at two independent towers (G+11 &
with its role of being a nation builder Salt Lake in Kolkata. This project G+18) over one single podium. This
has helped the country realize is located within the busy IT hub of includes two car parking basements
this dream and ride the IT wave to Salt Lake in Kolkata. The proximity with a capacity to park 1300 cars.
become one of the world’s leading of Salt Lake to the hub of the Once completed, Godrej Waterside
exporter of IT and ITES. city and the airport has made it is poised to become one of largest
a very promising IT destination. building in the precincts of Salt Lake,
L&T was a pioneer in providing IT Kolkata. The scope of work for L&T
Today Godrej Waterside is
infrastructure with unimaginable consists of construction of warm-shell
surrounded by elite IT companies
scale and speed. The firsts of its with common area finishing and NSC
that adorn the skyline of Salt
projects include Hi-tech city at co-ordination on MEP works. This
Lake area of Kolkata.
Hyderabad which has revolutionized
The two tower blocks of Godrej Waterside with the lake on one side
being L&T’s first business association The Godrej Waterside project too was the same season adding further to
with GODREJ, the project team not without its share of challenges the difficulty. In order to alleviate this
was in a higher state of excitement during execution. Hurdles such as challenge, about 510 lakh liters of
to create a landmark structure that heavy rain, space constraints, delays, water was dewatered in a period of
is complete with all amenities and price escalation of resources were all seven days.
services to suit the requirements of mitigated in the most professional
the ever emerging IT industry. manner to complete the project as Another critical challenge faced,
designed. was the scarcity of skilled manpower
in West Bengal. The boom in
Challenges faced infrastructure development and real
Major scope of work estate added to this scarcity. The
Excavation : 184808 cu.m The Godrej Waterside project began Godrej Waterside project required
Earth disposal : 163800 cu.m as an item-rate contract, but by virtue approximately 2000 workmen;
of the impressive performance of L&T mobilizing and retaining skilled
Reinforcement
steel : 10710 t and strong rapport and confidence workmen was therefore a tough
building with client, the contract was proposition.
Concrete : 101602 cu.m
baptized and converted to Lump
Formwork : 344867 sq.m Sum Contract with increased scope. Since the project was located in an IT
Masonry : 13961 cu.m Among the various challenges zone, establishing a batching plant
faced, the major one could be stated was not possible due to locational
Plastering : 173069 sq.m
as the flash floods during basement restrictions. Therefore, the need
Flooring, skirting, for concrete was met by procuring
dado : 98732 sq.m construction which caused the entire
site to get submerged with 2 m deep ready-mix concrete to the required
Waterproofing : 58272 sq.m specification from external RMC
water due to heavy downpour. This
Painting : 216872 sq.m kind of flooding occurred twice in agencies. Procuring standardized
was delaying the post-tensioning and three tower cranes were installed the Towers are the same. Also,
subsequent de-shuttering activities. for the construction of Tower-II. after giving due importance to
Initially the target for using table This addition of resource greatly Safety & Productivity, many new
form was from the typical floor level improved productivity by reducing and innovative machinery such
which is 3rd floor onwards, but due slab-to-slab cycle time from 10 as‘ Builder Hoist’ with a height
to the acute space constraints at site days to 8 days even though the of upto 90m was erected with an
location for material stacking and plate area of floor slab in both ingeniously fabricated support.
for table form fabrication yard, L&T
had fabricated the table form units MEP Highlights
at the site itself and thereby started
utilizing the same ahead of schedule The power consumption of 14 MVA is the highest among all buildings
from the 1st floor level itself. in the vicinity with 100% power backup facility by nine – 2000KVA DG
sets under Electrical HT/LT system
Resources 1.7 million sq.ft. of saleable floor area is air-conditioned by 6 Chillers
of 850 TR capacity
Any project of this scale warrants
The basement parking facility is installed with automatic ventilation
the requirement of tower cranes
system without ducts under HVAC system
which is one of the major equipment
used for this type of high-rise and 28high-speed lifts are installed for effective transportation of end-
large structure. Initially for the users in both the towers
construction of Tower-I two cranes Hydro pneumatic systems
were installed. One floor mounted Sanitary & plumbing system with STP & WTP facilities
and another floor climbing. With
Fire protection & detection system
the rich experience gathered
from the progress of Tower-I, IBMS & PA system
NSC Coordination
In addition to the main contract,
L&T has also been awarded with the
NSC (Nominated Sub-Contractor)
coordination work on MEP jobs for
Godrej Waterside project where
GODREJ has adopted world-class
technologies with the implementation
of Green Building concepts aimed at
GOLD rating. The client entrusted
various packages to reputed agencies
Entrance lobby
like Voltas, Godrej & Boyce, SPFAB
and Otis. CCTV Surveillance & Public OTIS – Lifts: 28 nos.
Address System
Voltas The coordination job of single-point
Sanitary & Plumbing and STP /
HVAC, Intelligent Building responsibility was however with L&T
WTP System
Management Systems, Electrical for overall completion of the project
& Diesel Generators SPFAB – External Façade including Value Engineering, Project
Fire Protection & Fire Fighting Time Scheduling, Quality and Safety
GODREJ & BOYCE – Bus bar as well as final handing over to
System
HSE
To meet the tight construction
schedule under a safe working
environment, the project team had
taken the various safety measures
such as:
100% use of PPEs by all
Induction (through e-learning)
and screening of workmen
working at site
‘Safe for use’ certificate to all
construction equipment upon
verification
Two tier safety nets for all height
the customer. Therefore, it was a achievable. The main success factor
works at slab casting level and
challenging task to interface all the was the confluence of continuous
two floors below
activities that were to be carried out efforts of all project engineers
by different organizations under engaged by different agencies, Besides this, the project being vast in
one roof with in the tight completion customer, consultants and L&T. nature and being located in a high-
schedule. Close monitoring and This close coordination and project profile area, L&T had innovated
team efforts has made this target management has helped the team and implemented various measures
like full-height door with lockable statutory and political agencies is has also faced crises, but is
arrangement in lift shaft opening, another key activity. Major hindrances undergoing fast recovery. From
floor edge protection (1.2m high) have been tackled with initiatives to L&T, all possible support in the
with hard barricading, installation develop and maintain good rapport form of value engineering in
of debris chute, sound-proof Diesel with the local community, political Tower-2 has been implemented
Generator sets, third party periodic and other governmental bodies. to save on resources and costs.
pollution control check, etc. Thus, with their co-operation, L&T Through such impressive and
could manage space constraints by proactive customer support L&T
Safety performance at Godrej creating and arranging space for has secured further orders from
Waterside was excellent right from labour hutment (to contain 2500 Godrej that includes Godrej
the beginning stages. Through this, persons), temporary office, material Genesis (IT Park) & Godrej Prakriti
the site has achieved 8.02 million storage and other temporary (Housing Complex) in Kolkata
accident-free safe man-hours from construction support yards. and other projects at Chandigarh,
January’2007 to May’2010, which Hyderabad and Ahmedabad are
speaks testimony for the safe work Current status in the pipeline.
methods and the impeccable safety
culture established at the site. The Presently, Tower – 1 is almost D. Mukhopadhyay
site has also received appreciation completed except some last-mile- Project Manager
for “7 million safe man-hours” from connection sand commissioning while
Godrej. Tower-2 is structurally completed.
MEP and other finishing works are in
Administration - A vital role progress in Tower – II.
Salient features
Elevated world-class station buildings at
approximately every kilometer.
Connecting major offices, retail and residential
areas- The two tracks (up and down lines) pass
through the arterial roads of the city
Mr.V.B.Gadgil Managing Director - L&T Hyderabad Metro Rail Private
Limited (left) shaking hands with Mr.T.S.Appa Rao - Principal Secretary Connects major bus stations at Miyapur,
Urban Development (right) in the presence of the Chief Minister of
Andhra Pradesh Dr.K.Rosaiah (Centre – back row)
MGBS, Koti, Dilsukhnagar, Charminar and
Jubilee Bus Station
L&T signed the Concession Agreement with the
Government of Andhra Pradesh on 4 th September, Integration with existing rail terminals at
2010 at Hyderabad for the development of Hyderabad Secunderabad, Begumpet and Nampally
Metro Rail project in public private partnership (PPP) Link to MMTS services at Bharatnagar,
mode. This project will be implemented by L&T Begumpet, Khairatabad, Malakpet &
Hyderabad Metro Rail Private Limited - a special Falaknuma
purpose vehicle (SPV) of L&T. To be completed in
Feeder bus services to stations from different
a span of five years from the appointed date, this
areas of the city by GoAP
project will be executed on a design, build, finance,
operateand transfer (DBFOT) basis. The concession Green & Eco friendly mode of travel- reduces
period for the project is 35 years which is extendable carbon emission, reduces fuel consumption,
further by 25 years. city becomes cleaner and greener
The Agreement was signed by Mr.V.B.Gadgil Faster, safer and comfortable air-conditioned
Managing Director - L&T Hyderabad Metro Rail travel with reduced travel time
Private Limited and Mr.T.S.Appa Rao -Principal
Ultra-modern coaches
Secretary Urban Development in the presence of the
Chief Minister Dr. K.Rosaiah, Mr.Y.M.Deosthalee- High frequency of trains- reducing waiting time
Chief Financial Officer L&T, Municipal Administration (train every 3 to 5 minutes in peak hours)
Minister Mr. Anam Rama Narayana Reddy, Ministers User-friendly stations with lifts, staircases and
from the city Mr. D.Nagender, Mr. Mukesh Goud & facilities for the disabled
Mrs. SabitaIndra Reddy along with the Chief Secretary
Mr. S.V.Prasad. Also present during this occasion Parking facility at 25 different locations along
was Mr. K.Venkatesh, Senior Vice President & Head - the route
Developmental Projects, L&T along with senior officials Automatic ticket vending machines-reducing
from L&T. waiting time in queues and counters
Consisting of three high density corridors, Automatic Fare Collection system-hassle free
Hyderabad Metro network will cover a total entry and exit from the stations
distance of 71.16 km involving 66 ultra-modern
Essential Facilities at Stations- toilets, public
station buildings with state-of-the-art depots and
address and information system, telephones
complete infrastructure.
and refreshment facilities.
Corridor - I Miyapur - LB Nagar (28.87 km - 27 stations)
Mr. S. Rajavel, Executive Vice President (Electrical & Gulf Projects OC), L&T excchanging the agreement with Mr. Ravi Desai – Director, Befula
Investments (PTY) Ltd. in the presence of Mr. K.V. Rangaswami, President (Construction) and Member of the Board, L&T.
Larsen & Toubro (L&T), India’s leading engineering, technology located in Durban having core strengths in general
& construction company and Befula Investments (PTY) Ltd., engineering with structural and plate fabrication, tank
South Africa have signed a Share Holders Agreement to manufacture including cranes and material handling
incorporate a Joint venture company ‘LARSEN & TOUBRO equipment Befula Investments with its associate partners
T&D SA (PTY) LTD’ in South Africa to capitalize on the Power have a wide network access to resource pools for labour
Transmission and Distribution opportunities in South Africa. and services across multiple sectors including Labour
sourcing, site location of labour, logistics and supply
With an installed capacity close to 44000 MW South Africa chain management support.
is facing a severe peaking demand shortage in electricity.
The current peak demand shortage is approximately 3,000 The agreement was signed by Mr. S. Rajavel, Executive Vice
MW and this is expected to grow 6% every year. Thus there is President (Electrical & Gulf Projects OC), L&T with Mr. Ravi
a long felt necessity of huge generation capacity additions. Desai – Director, Befula Investments (PTY) Ltd at Chennai in
Sizeable investments are lined up by the Government to cater the presence of Mr. K.V. Rangaswami, President (Construction)
to major generation capacity addition and augmentation of and Member of the Board, L&T Through the agreement
Transmission & Distribution Network in the next five years. the two companies have agreed to collaborate on areas
The Transmission Lines are expected to be in 400 / 765 including turnkey execution of Power Transmission Lines,
kV class to service the major load centers and strengthen Sub-Stations, Rural Electrifications, Power Distribution, and
the National Grid for balancing of power and to minimize Industrial Electrification in South Africa. Mr. K.V.Rangaswami,
instances of shut downs. President Construction and Member of the Board, L&T said:
“The agreement brings together L&T’s vast experience in
Recognising this opportunity and to exploit the business power transmission and distribution and Befula’s country
potential existing in the country, L&T has signed the Share knowledge and local networking capabilities. The JV will
Holders Agreement with Befula Investments (PTY) Ltd – effectively leverage the strengths of both the companies to
a leading general engineering and investment company tap rapidly emerging opportunities in South Africa.”
K.S.R.K. Verma, Joint General Manager receiving the memento from Hon’ble Chief Minister of Kerala, Shri. V.S. Achuthanandhan
The Kuttiyadi Additional Extension Scheme is a Hydro- Erection of Penstock ferrules, each weighing around 8-10
electric Power Project located at Kakkayam, in, Kozhikode tons were successfully lifted and erected over the steep
District of Kerala. With an installed capacity of 100MW, terrain by laying temporary rail tracks with smooth turnings
this project contributes a firm share of 223 million units at different locations using winches and wire ropes.
of energy/annum, which is considered as a blessing for Head Race Tunnel was driven from both Intake and
the entire State ofKerala, especially for the Malabar area. Surge Shaft eliminating the Adit Tunnel.
The project was successfully executed by L&T and this was
A Concrete pump was employed for pumping of
dedicated to the Nation on June 19, 2010 by Hon’ble
concrete to about 80 m head.
Chief Minister of Kerala, Shri. V.S. Achuthanandhan in the
presence of Union & State Ministers, Members of KSE Board, Self-Compacting concreting (SCC) technique was
Panchayat President/Members including the common public adopted in Power House, Approach Channel Bell
numbering around 5000 from various locations. mouth, Head Race Tunnel and Surge Shaft which
yielded good productivity and Quality.
Project Highlights
Speaking on the occasion of inauguration of the project,
The order for Kuttiyadi HEP was awarded to BHEL- Mr. V.S. Achuthanandan, Hon’ble Chief Minister of
L&T Consortium against stiff Global International Kerala appreciated the efforts taken by KSE Board for
competitive bidding. As per this contract all Hydro- implementing this National project of importance. He
Mechanical works and Main Civil structures were also extended his appreciation to L&T for execution of
executed by L&T and all Electro-Mechanical works this project and making this a glittering reality Shri. A.K.
were carried out by BHEL. Balan, Hon’ble Power Minister of Kerala, also recognised
The work involved manual Rock Excavation of around the contributions made by L&T and publicly lauded the
40,000 m3 and concreting of around 3400 cu.m, high quality of work including successful completion of
executed in a steep terrain of about 60 ° slope.
L&T’s regional office at Ahmedabad has played a orphanage in Kancheepuram, yesterday. The event
remarkable role in further uplifting the social face of the was presided over by the Tehsildar of Kancheepuram
organization by developing a play area for the differently Mr. T. Varadharajan. Present during the occasion was
abled children of Samarpan Muk-badhir Sishu Vidya Mr. Ramesh Aravamudhan, Regional Manager, L&T
Mandir, Ahmedabad. – ECC Chennai Region, Mr. V. S. Ramana, General
Mr. A.M. Naik accepting the award from the Chief Minister. Dr. R. A.Mashelkar, Chairman of Priyadarshini Academy’s Global Awards Advisory
Committee and Mr.NanikRupani, Chairman, Priyadarshini Academy, are at left, and fourth from left, respectively.
Mr. K.V Rangaswami, Member of Board and at Panipat, Ocean Engineering Lab at IIT – Chennai,
President (Construction) was honoured with the Jawaharlal Nehru Stadium - Chennai, Sree Kanteerava
ICI (TNCC) - Ultratech Award for “Outstanding Indoor Stadium - Bangalore, Super Speciality Hospital
Concrete Engineer of Tamil Nadu - 2010” at an – Puttaparthi etc…’ (Contd.... on page 55)
awards function held at Hotel Green Park, Chennai
on 7th September 2010 to commemorate ‘Concrete
Day ’.
Mr. A.M. Naik accepting the NDTV Profit Special Award from Mr.Pranab
Mukherjee.
Printed by RR Donnelley Publishing India Pvt. Ltd., Sriperumbudur. Edited by Mr. V.S. Ramana for Larsen & Toubro
Limited – ECC Division, from ECC-HQ, Manapakkam, Chennai 600089. The views expressed in this magazine are not
necessarily those of the management of Larsen & Toubro. The contents of this magazine should not be reproduced without
the written consent of the editor. Not for sale - only for free circulation to employees of L&T group and subscribers.