HINDALCO MAHAN, 6X150 MW

STANDARD OPERATING PROCEDURE


TITLE: Doc. No. OPN/SOP/037
Standard Operating Procedure for Turbine Issue No. /
protection and interlock 01/ 01- 08-2012
Date
Rev. No /
DEPARTMENT : OPERATION 00/ 01- 08-2012
Date

Purpose : This procedure is used as work instruction for TG operator , Desk Engineer , Shift
Incharge.

Scope : This instruction sheet explains the interlock and protections for Turbine.

Responsibility: TG operator , Desk Engineer , Shift Incharge.

Procedure:

Details of Alarm and Trip Setting as below

Sl Description Alarm Trip Remark


No
1 Turbine Over speed Trip -1 (RPM) 3300
2 Turbine Over speed Trip -2 (RPM) 3300
3 Main Steam temp. low (Degree C) 450
4 HP Exhaust temp. high (Degree C) > 485 > 500
5 LP Exhaust hood temp. high (Degree C) > 90 > 110
6 Condenser Vacuum low > - 0.8 > - 0.7 &
540 RPM
7 Lube oil press. Very low ( Kg / Sq cm) < 4.5 < 1.2 01 out of 02

8 Main Oil Tank Level Very Very Low 390


9 Axial Shift in mm +/- 0.5 + / - 1.0 01 out of 02
10 Bearing Temp (1 – 3) Deg C > 110 > 130

Page 1 of 2
Desk Engineer Deptt.Head Head – Operation & Maintenance
Prepared By Reviewed by Approved By
HINDALCO MAHAN, 6X150 MW

STANDARD OPERATING PROCEDURE


TITLE: Doc. No. OPN/SOP/037
Standard Operating Procedure for Turbine Issue No. /
protection and interlock 01/ 01- 08-2012
Date
Rev. No /
DEPARTMENT : OPERATION 00/ 01- 08-2012
Date

Sl Description Alarm Trip Remark


No
14 Manual Trip Device TRIP
15 Fire Protection 1 or 2 Operated TRIP
16 Generator Electrical Protection TRIP 01 out of 02
17 Generator Protection (Mechanical) Class B TRIP 01 out of 02
18 Turbine Trip from DCS Console TRIP
19 Turbine Trip from ATRS TRIP
20 Emergency Trip from HMI TRIP
21 Master Fuel Trip 01 out of 02

Cross Reference : CCR/TG/Turbine/O&M manual

RECORDS : Nil

Page 2 of 2
Desk Engineer Deptt.Head Head – Operation & Maintenance
Prepared By Reviewed by Approved By