MASONRY

---
1. AREA x 0.633 = NO. OF BAGS OF PORTLAND CEMENT (CHB 6")
2. AREA x 0.0844 = CU.M. OF SCREENED SAND (CHB 6")
3. AREA x 0.328 = NO. OF BAGS OF PORTLAND CEMENT (CHB 4")
4. AREA x 0.0438 = CU.M. OF SCREENED SAND (CHB 4")
==================================
PLASTERING
1. AREA x 0.192 = NO. OF BAGS OF PORTLAND CEMENT
2. AREA x 0.016 = CU.M. OF PURE SAND
3. AREA x 12.50 + 5% (AREA) FOR BREAKAGE = NO. OF CHB
4. NO. OF CEMENT x 1.50 = PAIL OF WATER
---
NOTE:
1 CU.M. OF SAND = 36 SACKS
---
OR:
SAND = 3 SACKS / 1 BAG OF CEMENT
GRAVEL = 4 SACKS / 1 BAG OF CEMENT
CEMENT = VOLUME x 10
==================================
PAINTING
---
1. FLATWALL LATEX (CEMENT) = AREA / (20-25) = NO. OF GALLONS
2. GLOSS LATEX (CEMENT) = FLATWALL LATEX x 2
3. FLATWALL ENAMEL (WOOD)
4. GLOSS ENAMEL (WOOD & STEEL)
5. THINNER = 4 GALLONS OF PAINT = 1 GALLON THINNER
==================================
TINSMITHRY
---
1. UMBRELLA NAIL
8' = 18 PCS / ROOF
10' = 22 PCS
12' = 26 PCS
120 PCS = 1 KILO
2. GUTTER = 2.35 EFFECTIVE LENGTH
3. FLASHING = TOTAL LENGTH / 2.30 EFFECTIVE LENGTH
4. RIDGE ROLL = 2.20 EFFECTIVE LENGTH
==================================
TIE WIRE
1. 1kg = 53m = 212pcs (0.25m)
2. 1roll = 32kg
==================================
COLUMN STIRRUPS
LENGTH - 0.60 � 0.20 + 10 = NO. OF STIRRUPS
==================================
CARPENTRY
---
1. CEILING = LENGTH / 0.60 (FOR HOR & VER STUDS)
2. FASCIA BOARD ( 3/4" MARINE PLYWOOD) = LENGTH / 2.40
---
NOTE:
1 PLYWOOD CAN MAKE 4 FASCIA BOARD
==================================
EXCAVATION
---
0.72 CU.M. PER DAY
P400 - P500 (ITEM UNIT COST)
==================================
GROUTED RIPRAP
---
VOLUME X 2.50 = NO. OF BAGS OF CEMENT
VOLUME = CU.M. OF BOULDERS
NO. OF BAGS OF CEMENT X 4 � 36 = PURE SAND
NO. OF BAGS OF CEMENT X 1.50 = WATER (PAIL)
==================================
ELECTRICAL
---
TW WIRE # 10 = LENGTH X 2
TW WIRE # 14 = 7m PER POST
FLEXIBLE ELBOW = 2pcs PER POST