VALORIZACION DE OBRA N° 01

MES DE SETIEMBRE DEL 2017

OBRA: CREACION LOSA DEPORTIVA MULTIPLE EN EL ANEXO DE CORAZON DE JESUS, DISTRITO DE LUYA, PROVINCIA DE LUYA, AMAZONAS.

RESIDENTE DE OBRA: ING. OSCAR ZEGARRA VASQUEZ.


SUPERVISOR DE OBRA: ARQ. MANUEL WILZO AYALA CABRERA.
INICIO DE OBRA: 04 DE SETIEMBRE DEL 2017.
FECHA TERMINO DE OBRA: 03 DE OCTUBRE DEL 2017
AVANCE
SALDO
ANTERIOR ACTUAL ACUMULADO
ORDEN NOMBRE DE LAS PARTIDAS UNIDAD METRADO COSTO UNITARIO S/ COSTO PARCIAL S/
METRADO PARCIAL S/ METRADO PARCIAL S/ METRADO PARCIAL S/ % METRADO PARCIAL S/ %

1.00 OBRAS PRELIMINARES


1.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 4.80MX4.00M UND 1.00 1,350.00 1,350.00 0.00 0.00 1.00 1,350.00 1.00 1,350.00 100% 0.00 0.00 0.00%
2.00 OBRAS PROVISIONALES -
2.01 TRAZO Y REPLANTEO M2 720.00 2.29 1,648.80 0.00 0.00 720.00 1,648.80 720.00 1,648.80 100% 0.00 0.00 0.00%
2.02 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS GLB 1.00 1,800.00 1,800.00 0.00 0.00 0.50 900.00 0.50 900.00 50% 0.50 900.00 50.00%
3.00 MOVIMIENTO DE TIERRAS -
3.01 CORTE DE MATERIAL SUELTO CON EQUIPO M3 180.00 5.25 945.00 0.00 0.00 180.00 945.00 180.00 945.00 100% 0.00 0.00 0.00%
3.02 EXCAVACION DE ZANJAS PARA MURO DE CONTENCION M3 14.69 40.67 597.44 0.00 0.00 14.69 597.44 14.69 597.44 100% 0.00 0.00 0.00%
3.03 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO, HASTA 1.50KM.
M3 194.69 6.97 1,356.99 0.00 0.00 150.69 1,050.31 150.69 1,050.31 77% 44.00 306.68 22.60%
3.04 NIVELACION INTERIOR Y APISONADO MANUAL. M2 738.00 2.03 1,498.14 0.00 0.00 738.00 1,498.14 738.00 1,498.14 100% 0.00 0.00 0.00%
3.05 AFIRMADO DE 4" COMPACTADO. M2 738.00 11.56 8,531.28 0.00 0.00 738.00 8,531.28 738.00 8,531.28 100% 0.00 0.00 0.00%
4.00 CONCRETO SIMPLE -
4.01 ENCOFRADO Y DESENCOFRADO LOSA DEPORTIVA. M2 75.40 48.74 3,675.00 0.00 0.00 37.00 1,803.38 37.00 1,803.38 49% 38.40 1,871.62 50.93%
4.02 CONCRETO SIMPLE F'C= 140KG/CM2 SARDINEL. M3 12.96 395.13 5,120.88 0.00 0.00 6.96 2,750.10 6.96 2,750.10 54% 6.00 2,370.78 46.30%
4.03 CONCRETO SIMPLE F´C= 140 KG/CM2 LOSA 4" (ACABADO). M3 74.02 484.62 35,871.57 0.00 0.00 37.02 17,940.63 37.02 17,940.63 50% 37.00 17,930.94 49.99%
4.04 ENCOFRADO Y DESENCOFRADO MURO DE CONTENCION M2 81.60 48.74 3,977.18 0.00 0.00 81.60 3,977.18 81.60 3,977.18 100% 0.00 0.00 0.00%
4.05 CONCRETO SIMPLE F´C= 140KG/CM2 MURO DE CONTENCION. M3 36.86 432.77 15,951.90 0.00 0.00 36.86 15,951.90 36.86 15,951.90 100% 0.00 0.00 0.00%
5.00 PINTURA. -
5.01 PINTADO PARA DEMARCACION DE LOSA DEPORTIVA M2 441.02 4.43 1,953.72 0.00 0.00 0.00 0.00 0.00 0.00 0% 441.02 1,953.72 100.00%
6.00 CARPINTERIA METALICA -
6.01 ARCO DE FULTBITO Y TABLERO DE BASQUET (02). GLB 1.00 3,600.00 3,600.00 0.00 0.00 0.00 0.00 0.00 0.00 0% 1.00 3,600.00 100.00%
6.02 PARANTES DE NED DE VOLEY/INST. ACC.(02). GLB 1.00 2,000.00 2,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0% 1.00 2,000.00 100.00%
7.00 PISOS Y PAVIMENTOS. -
7.01 JUNTAS ASFALTICAS. M 248.00 6.52 1,616.96 0.00 0.00 0.00 0.00 0.00 0.00 0% 248.00 1,616.96 100.00%
8.00 FLETE. -
8.01 FLETE TERRRESTRE GLB 1.00 2,500.00 2,500.00 0.00 0.00 0.50 1,250.00 0.50 1,250.00 50% 0.50 1,250.00 50.00%
COSTO DIRECTO 93,994.86 0.00 64.00% 60,194.16 60,194.16 64.00% 33,800.70 36.00%

RESUMEN AVANCE MENSUAL 01 __________________________


AVANCE ANTERIOR 0.00% 0.00 OSCAR ZEGARRA VASQUEZ
AVANCE ACTUAL 64.00% 60,194.16 INGENIERO CIVIL
AVANCE ACUMULADO 64.00% 60,194.16 CIP N° 70914
SALDO POR EJECUTAR 36.00% 33,800.70 RESIDENTE DE OBRA