Dear Eng.

Rami / Sami

Further to your activities for Pavements and Interlocks etc. at IPM-800 Site,
Kindly complete the following submission as a part of project documents and
Records

01. Prequalification AIMS General Contracting AGC


02. Test Result for approved Material from ARAB Centre for Road base etc. As
Per RCA & ADMs
03. Method of statement & ITP mentioning Pavements works from formation to
paving interlock
04. White sand Material submittal for Fire Hydrants Pipes & ITP with Method of
statement

Furthermore as instructed earlier, kindly adhere to Applicable QA/QC Procedure at


Site and Submit required test Result (Compaction test) in order to proceed further.

Your Prompt action will be appreciated