Você está na página 1de 4

47 to 74: bringing a Victorian terrace house up to

an energy efficient standard

© March 2007 Pett Projects Case Study 01/2007

Summary
In terms of improving a building's energy efficiency, most Victo-
Key points rian houses can be described as ‘hard to heat’ (or hard to
treat). Hard to heat homes either have solid wall construction
• Victorian terrace
or are not connected to the gas network. This means that the
house
most cost-effective measures for saving energy and fuel bills
• Full loft insula- like cavity wall insulation can’t be applied to them. The alter-
tion (top-up) natives are more expensive to fit, and meanwhile the homes
cost more to run because they use more fuel. Hard to heat
• Gas condensing should really be ‘expensive to heat and expensive to solve’ but
boiler fitted Terraced house at Epping, Essex
the snappy phrase is easier on the tongue! The basic problem
(pictured in June)
is that the easiest ways to improve a house’s energy efficiency
• Solar pv array
cannot be applied to them.
• Location: Essex, This case study describes how a Victorian terrace house with
(Epping) gas central heating (typical SAP rating 47 for an unimproved
property) was brought up to a respectable SAP 74.

The main improvements were, in addition to double glazing:

• Full loft insulation

• Gas condensing combi boiler

• Solar photovoltaic panels

As the house faced south-west at the back, with the typical


arranged of two roofs at right angles, and the owner could
commit to a large outlay, a larger than standard pv array was Solar pv roof fitted on both main
fitted. The resulting electricity produced would exceed all the roof and back addition (April)
Contents
owner’s electricity needs over the year—but not at the time
Energy conserva- 2 needed, so export to the grid is included.
tion work

Renewable energy 2
options
Background
Solar panels - 2
details The house is a mid-terrace room somewhat earlier. The loft insulation installed n the
house built in 1889. In com- kitchen and bathroom form a mid-70s.
Energy perform- 3 mon with most of its single storey back addition
neighbours, various internal (the term used for the bit The owner, a single profes-
ance
sional person, bought the
improvements had taken sticking out, and NOT an ex-
house in 1985 and had gradu-
Difficulties over- 4 place such as gas central tension but an original part of
heating installed in about the building). ally replaced the wooden win-
come
dows with double glazed units.
1975, at about the same time
The roof had been renovated (mainly metal with wood sur-
Comfort and ease 5 that the interior walls were
removed to make a through with recycled slates in 1990. rounds).
of use
At that stage the loft insula-
lounge-diner. The toilet was The owner was keen on both
tion was stated as ‘around
Key contacts 6 moved from outdoor to indoor energy conservation and pro-
within the downstairs bath- 50mm’ which is typical of the
moting new technology.
47 to 74: bringing a Victorian terrace house up to an energy efficient standard Page 2

Energy conservation work


The first issues were to con- rafters were built up by putting engineers as to whether there
sider heat disappearing out of another batten above the ex- was technically sufficient ven-
the roof and cold coming in isting rafters. On top of these tilation available to this back
from the ground. A damp the boards were put across for boiler.
proofing ‘skim’ had been ap- three metres across the centre
In two stages of work over
plied in 1988, and considera- of the loft area, leaving room
for air circulation at the side. three years, the gas boiler was
tion could have been given to
changed to a condensing
floor insulation, however car-
The gas boiler had previously combi situated in the lobby
peting throughout with a thick
been a back boiler in the chim- between the kitchen and bath-
underfelt was considered a
ney space, heating a water room, vented direct to the
reasonable option. The walls
tank situated on the landing, outside. This gave almost
Internal work included had a metre of plaster re-
damp proofing, rewiring which supplied water to the instant response in terms of
moved, a membrane inserted
and loft top-up insula- back addition through a long hot water, reduced pipe
and were replastered to inhibit
tion run of pipes. Not only did it lengths and repositioned pipes
damp.
take at least two minutes for to reduce risk of freezing.
The loft was insulated to a the water to run hot, there had
been problems in the past of After consideration it was de-
total of 350 mm with standard
cided that internal or external
mineral fibre insulation. In freezing pipes overnight in
wall insulation on the front or
order to maintain use of the winter. There had previously
been some concern by the gas back wall would lead to insig-
roof space for storage, the
nificant energy savings.

Renewable Energy options


The owner had
The options considered were stage of deployment, and the cooker). The fridge was A
already
solar water heating, solar lifestyle of the owner did not rated, freezer A*, washing
minimised photovoltaic and microCHP. qualify for any of the testing machine A*. Computers and
electricity programmes. other electrical devices were
For a single person who uses
turned off at the wall when not
consumption a shower daily and very little Solar pv to provide electricity in use except the video re-
before fitting hot water otherwise, solar HW was attractive to the owner as corder (on 1 watt setting) and
did not present an attractive it provided a demonstration of
the solar the clock-radio. No other
option. This led to the deci- distributed generation. stand-by modes were used.
panels sion to switch to a gas con-
densing combi boiler for effi- The owner had already mini- Because the back roofs faced
cient production of hot water mised household electricity SE and SW, both could be
on demand. use with a total of 12 energy used for panels. These were
efficient light bulbs (including fitted in April 2006.
MicroCHP was still in its early candles for wall lights and

1.64kWp using 8 x high efficiency modules 1.025kWp using 5 x high efficiency modules
Morning shade from house
4500

Solar panels — details


The contractor selected were wall into the roof to a DC-AC
4000

6000

Chelsfield Solar, of Kent. convertor, the cables from the


main roof into a second con-
The panels selected were verter, from whence the elec- 2200

Sony high efficiency panels


tricity was fed into a Landis & 45°
S

rated 0.205 kWp each. The


Gyr meter in the front corner
arrangement was for 5 on the of the living room adjacent to
back addition, facing SE, and kWh generated.
the main fuse box.
The solar pv 8 on the main roof, facing SW.
The installation was made
panels arrive This gives an installed rating The electricity then exited the
under the DTI Major Photo-
of 2.665 kWp. property onto the grid. The
voltaic Demonstration Pro-
owner signed up to the Good
The cables from the back addi- gramme—Stream 1, which
Energy Home Generation
tion were run on the exterior gave a grant of 50% of the
scheme, obtaining 4.5p per
eligible costs.
Case Study 01/2007 Page 3

Energy Performance
A hand held monitor gave a The SAP rating of the house year, so the amount generated
spot reading for the amount of was calculated using Builder™ is around twice the annual
energy generated at any one software. The estimated rat- usage, but of course, not at
time, a running total (less dis- ing before the loft top up, with the times needed. Fixing the panels on
tribution losses—the meter the older gas boiler and with the back addition roof
The amount of gas used went
was the final arbiter of this) double glazing was 54. Before
the solar panels were fitted, up 5% from 2004 to 2005, but
and total CO2 saved to date.
dropped to 12% below 2004
the house rated 63, and after-
The maximum spot generation in 2006.
wards 74.
noticed in the period April to
September was 2576 Wp Because of the small wall area Solar panel performance

(impressively close to the total involved, external or internal


3000

rated performance). wall insulation would have only 2500

added c 1 SAP point.


A number of attempts to moni- 2000

tor generation over a day were The total energy generated in

watt
1500

made, the results shown in the the 47 weeks to 01/03/2007


graph, where the black line was 2492 kWh, saving approx 1000

shows the line of best fit for 1500 kg CO2.


500

11th June (the most complete


The pattern of electricity use
set, a sunny day with some 0

of the owner was 1250kWh a 05:00 07:24 09:48 12:12 14:36 17:00 19:24

light cloud at times). time

Difficulties encountered & Lessons learned The total


There were some delays to the later without the need for the the start of the installation. energy
start of the project as the owner to be present. generated in
available contractors in the Issues relating to registration
The main difficulty is that the of generation were handled by the 47 weeks
area had waiting lists, and the
grant programme experienced meter into the house from the Chelsfield Solar, who guided to 1st March
a rush of applications as it was grid started to run backwards the owner through any paper-
and had to be replaced. It was work necessary and the owner 2007 was
nearing the end of its life. The
some time before the owner or felt confident with them. 2492 kWh,
new programme is now in
place. the supplier recognised this, saving approx
Lesson to be applied in future
which caused a problem in
There were no problems with installations; check incoming 1500 kg CO2.
billing. The paperwork for the
the installation, the scaffolding Home Generation scheme meter regularly as well as out-
was put in place the day be- going meter to ensure both are
went astray but the company
fore and removed two days working properly and make
backdated the application to
sense!

Comfort and ease of use

The home definitely felt The panels were a talking The grant money came
warmer with the newly insu- point and gave no trouble at through without any problems,
lated loft and the new boiler, all—self cleaning as the manu- and the whole arrangement
but the distribution of heat facturers said; no glare or for the solar panels was excel-
changed. The suggested rea- reflections, no noise, and func- lent.
son is that the hot water pipes tioned well.
Some residual problems re-
that had been under the up-
Billing caused a few problems mained with the damp preven-
stairs floor, and the hot water Completing the installation
cylinder ,had previously mak- as a result of the meter prob- tion, but consistent with the
of the panels
lems and because the owner age of the house. There were
ing a substantial (and expen-
had a prolonged period of no problems with storage in
sive) contribution to the up-
stairs warmth. absence , so use was over- the well-insulated loft.
estimated.
Pett Projects carries out research projects and related services to
promote and remove the barriers to implementation of sustainable
Pett Projects energy and sustainable building in the community.

Sustainable energy implies:


Mill House
Lenwade Mill • Use low and zero carbon sources of power
Lenwade
Norfolk NR9 5QA
• Use less fuel for the services needed

Phone: 01603 879890 • Use efficiently generated power in the most efficient man-
Mobile: 07963 189314 ner possible.
E-mail: pett.projects@btinternet.com
Sustainable building implies developing new buildings and refur-
www.pett-projects.org.uk
bishing old ones that:

sustainable energy and • Reduce their impact on the environment,


buildings research • Minimise resource use and waste,
• Make places that promote sustainable lifestyles.

www.pett-projects.org.uk

Key contacts
Chelsfield Solar Energy Saving Trust
66 The Highway 21 Dartmouth Street
Chelsfield, Kent BR6 9DJ London, SW1H 9BP
Tel: 01442 211766 Tel: 020 7222 0101

info@chelsfieldsolar.co.uk
www.est.org.uk
www.chelsfieldsolar.co.uk www.saveenergy.co.uk

Good Energy
Monkton Park Offices,
Chippenham, Wiltshire
SN15 1ER Before and after: the
Tel: 0845 456 1640 completed solar pv
generation@good- panels on the back
energy.co.uk roofs

www.good-energy.co.uk/
renewable_generation.asp

Você também pode gostar