Você está na página 1de 12

This article was downloaded by: [Colorado College]

On: 27 October 2014, At: 17:34


Publisher: Taylor & Francis
Informa Ltd Registered in England and Wales Registered Number: 1072954 Registered office: Mortimer House,
37-41 Mortimer Street, London W1T 3JH, UK

Structure and Infrastructure Engineering:


Maintenance, Management, Life-Cycle Design and
Performance
Publication details, including instructions for authors and subscription information:
http://www.tandfonline.com/loi/nsie20

A risk and criticality-based approach to bridge


performance data collection and monitoring
a b b a
Simon Bush , Piotr Omenzetter , Theunis Henning & Peter McCarten
a
Opus Consultants , Auckland , New Zealand
b
Department of Civil and Environmental Engineering , The University of Auckland ,
Auckland , New Zealand
Published online: 07 Dec 2011.

To cite this article: Simon Bush , Piotr Omenzetter , Theunis Henning & Peter McCarten (2013) A risk and criticality-based
approach to bridge performance data collection and monitoring, Structure and Infrastructure Engineering: Maintenance,
Management, Life-Cycle Design and Performance, 9:4, 329-339, DOI: 10.1080/15732479.2011.638143

To link to this article: http://dx.doi.org/10.1080/15732479.2011.638143

PLEASE SCROLL DOWN FOR ARTICLE

Taylor & Francis makes every effort to ensure the accuracy of all the information (the “Content”) contained
in the publications on our platform. However, Taylor & Francis, our agents, and our licensors make no
representations or warranties whatsoever as to the accuracy, completeness, or suitability for any purpose of the
Content. Any opinions and views expressed in this publication are the opinions and views of the authors, and
are not the views of or endorsed by Taylor & Francis. The accuracy of the Content should not be relied upon and
should be independently verified with primary sources of information. Taylor and Francis shall not be liable for
any losses, actions, claims, proceedings, demands, costs, expenses, damages, and other liabilities whatsoever
or howsoever caused arising directly or indirectly in connection with, in relation to or arising out of the use of
the Content.

This article may be used for research, teaching, and private study purposes. Any substantial or systematic
reproduction, redistribution, reselling, loan, sub-licensing, systematic supply, or distribution in any
form to anyone is expressly forbidden. Terms & Conditions of access and use can be found at http://
www.tandfonline.com/page/terms-and-conditions
Structure and Infrastructure Engineering
Vol. 9, No. 4, April 2013, 329–339

A risk and criticality-based approach to bridge performance data collection and monitoring
Simon Busha, Piotr Omenzetterb, Theunis Henningb and Peter McCartena*
a
Opus Consultants, Auckland, New Zealand; bDepartment of Civil and Environmental Engineering, The University of Auckland,
Auckland, New Zealand
(Received 25 March 2011; final version received 19 October 2011; accepted 2 November 2011; published online 7 December 2011)

Bridges constitute a substantial and vital part of any transport infrastructure system. The functionality of the system
is therefore reliant on the asset management strategies adopted for its bridges. To understand and manage bridge
performance, data of appropriate quality has to be collected in a cost-efficient way and closely linked to the decisions
made with it. To ensure a coherent approach, a data collection strategy for asset management of road bridges has
been developed in this study. In the strategy, a combined risk and criticality-based approach is used to prioritise each
bridge and to assign it to one of three data collection levels comprising core, intermediate and advanced. For each
collection level, the strategy provides guidance on the type of data to collect, the accuracy and precision required in
Downloaded by [Colorado College] at 17:34 27 October 2014

the data collection process, the frequency of inspections, and the recommended collection techniques to be used,
including visual inspection, non-destructive evaluation and structural health monitoring. The strategy will help asset
managers to develop a deeper level of knowledge on the bridges that have the greatest impact on the system
functionality and to collect data of the required quality needed for the decisions they make.
Keywords: bridges; asset management; risk; criticality; performance; data collection; monitoring

and mitigation discussed in the context of bridge asset


Introduction management. The commonly adopted definition, also
Bridges are important, often critical, and expensive used in this study, quantifies risk by multiplying the
components of transportation network infrastructure. probability of bridge failure with overall consequence
This fact together with an increasing pressure to satisfy or impact of the failure. ‘Failure’ is here understood
stringent requirements of the benefits from the invest- broadly as any situation when a bridge does not fulfil
ment into these structures creates the need to manage its performance expectations. This may, in extreme and
bridges using formalised processes. It is accepted that rare cases, be the same as structural collapse or
infrastructure, including road bridges, should be damage but also includes non-catastrophic failures
managed using the asset management approach where, e.g. vehicle load or speed are restricted to
(NAMS Group 2006, New Zealand Society of Local manage structural element fatigue or because of bridge
Government Managers 2007). A well-recognised stan- functional deficiency. It is useful to break the overall
dard, PAS 55-1:2008: Specification for the Optimised consequences of failure into the following two
Management of Physical Assets (British Standards categories:
Institution 2008) defines asset management as systema-
tic and coordinated activities and practices through . direct consequences including bridge mainte-
which an organization optimally and sustainably man- nance, repair or replacement costs;
ages its assets and asset systems, their associated . wider, whole network or regional level conse-
performance, risks and expenditures over their life cycles quences including traffic delays, service interrup-
for the purpose of achieving its organizational strategic tion, loss of business, lowered community
plan. This definition clearly emphasises the need to resilience to natural hazards, and even loss of
manage performance and risks in an optimal way heritage or iconic status assigned to the structure.
considering the costs of the mitigation strategy. This is
the key focus of this article and the data collection and From the point of view of risk perception, events of
monitoring strategy proposed herein. low probability and high consequences prove to be a
In order to facilitate and focus the subsequent challenge for risk assessment and risk-based decision
discussions, a number of basic definitions are intro- making, as in such cases risk is a small number
duced first, and aspects of risk perception, assessment multiplied by a large number with a somewhat

*Corresponding author. Email: Peter.McCarten@opus.co.nz

ISSN 1573-2479 print/ISSN 1744-8980 online


Ó 2013 Taylor & Francis
http://dx.doi.org/10.1080/15732479.2011.638143
http://www.tandfonline.com
330 S. Bush et al.

‘arbitrary’ result (Stewart and Melchers 1997). How- applying targeted and planned interventions, such as
ever, events with large consequences or impacts maintenance, repairs, strengthening and replacements,
warrant a special treatment, as the public’s risk to those structures that present the largest risk or are
tolerance decreases as the consequences increase, the most critical. Secondly, the availability of reliable
irrespective of the failure occurrence probabilities data itself leads to immediate gains in terms of risk
involved (Faber and Stewart 2003). Some proposed management and mitigation (Omenzetter et al. 2011).
approaches to risk management of transportation This is because lack of data or its inadequate accuracy
systems are even primarily consequence driven (Trans- or precision has to be compensated by overly
portation Research Board 2009). In the context of conservative assessments of failure probabilities or
transportation networks and bridge asset management, consequences. This compensation may particularly
bridges with large failure consequences will be herein strongly inflate risk assessment outcomes for bridges
referred to as ‘critical’. It is traditionally assumed in that are already considered high risk.
road asset management that criticality assessment Collection of higher quality, more detailed, accu-
takes into account only the wider, network and rate and precise data will, however, incur additional
regional level consequences (Theoharidou et al. 2009) costs. In the current economic climate, it is unlikely
and a similar approach is also adopted in this study. It that significant additional funding will be available for
can be seen that risk and criticality are different factors bridge asset management. Changes and improvements
Downloaded by [Colorado College] at 17:34 27 October 2014

and both are important for bridge asset management to data collection should therefore be cost neutral,
decision making. This article therefore argues that it is such that enhanced data collection approaches are
essential for bridges to be managed in a two dimen- used where they deliver the largest benefits from the
sional, risk and criticality, domain. point of view of risk management.
In order to understand performance, undertake risk The above arguments suggest that a strategic
assessment and analysis, and carry out life-cycle approach is required which would prioritise bridges
planning, an asset manager has to collect data which for data collection based on their criticality and risk
are linked to decisions made with it. For example, their condition poses to the operations of transporta-
Rücker et al. (2006b) discusses several levels of tion networks. This improvement to current practice is
assessment of performance and reliability of existing urgently required, as evidenced, e.g. by a study by Bush
structures. These levels range from simple assessments et al. (2011) that found that although there is significant
based on inspection and engineering judgement data collection taking place on bridges, the value of the
through to full probabilistic analyses, and have data and its usefulness is sometimes questionable. One
increasing data requirements related to material and of the issues that were identified suggested that there
structural properties, loads and responses. Improve- may be too detailed data collected on lower risk
ments to bridge asset management therefore need to structures while more information is needed on more
start with improvements to data collection (Transpor- critical or higher risk bridges on the network.
tation Research Board 2011). The need for developing The purpose of this study is to develop a data
robust performance knowledge and linking data to the collection and monitoring strategy for bridge struc-
decision-making process is evidenced by comments and tures with the following specific aims:
critique from the United States Government Account-
ability Office (USGAO 2008) and the New Zealand . collecting the appropriate data that is closely
Office of the Auditor General (NZOAG). These linked to its end purpose in the asset manage-
documents note that bridge asset managers should ment process, taking into account that there are
identify how the decisions they make help to deliver on different levels of asset management processes
national policy directives (USGAO 2008) and that that require different data volumes, collection
authorities need to create comprehensive performance frequency, accuracy and resolution;
frameworks, thereby allowing communities to under- . prioritising bridges for data collection realising
stand the reason for each service (Brady 2004). that these structures may not have the same
The issues surrounding data collection are there- criticality or may not present the same level of
fore twofold, firstly the data has to be present and risk;
linked to the decision-making framework, and sec- . providing guidelines on data types, detail,
ondly the data have to be of sufficient quality. collection frequency, accuracy, resolution, and
Improved data collection is important as it leads to a collection and monitoring techniques that are
better understanding of asset performance, improved linked to bridge risk and criticality.
knowledge of current risks and criticalities, and
facilitates forecasting and long-term planning. Risks The outline of the article is as follows. Firstly, a
can then be managed within the available budget by strategy that differentiates bridge performance data
Structure and Infrastructure Engineering 331

collection into three levels depending on the bridge have increasing risk and/or criticality as further
risk and criticality is outlined. Secondly, it is illustrated in Figure 1. Each regime differs in terms
demonstrated how this strategy fits into the wider of the type of data collected, level of detail, accuracy,
asset management philosophy and process. Thirdly, precision and frequency of collection, resolution and
the justification for the approaches adopted in the collection and monitoring techniques. The following
strategy is provided and the requirements of each sections describe firstly how the proposed data
data collection level, including data types, level of collection strategy fits into more general asset manage-
detail, accuracy, precision, and collection frequency, ment approaches, and secondly discusses in more
resolution and techniques are described. An example detail the requirements of each regime.
of bridge classification for tiered data collection using
several existing bridges is provided to illustrate the
strategy. Finally, a set of conclusions summarises the Linking data to its purpose in asset management process
discussion. In the proposed data collection strategy, there is an
emphasis on strengthening the link between the
collected data and its purpose in the asset management
Risk and criticality-based bridge performance data
process, and on providing a decision-making frame-
collection and monitoring strategy
work that can be used to justify the specific data
Strategy outline
Downloaded by [Colorado College] at 17:34 27 October 2014

collection approach adopted.


The discussion in the introductory part of the article The asset management process is usually differ-
highlighted the following: entiated into the core asset management and the
advanced asset management (Figure 2). The advanced
. the need to manage bridge risk by simultaneously asset management is characterised by two capabilities:
considering both the risk as such and the (i) the ability to forecast the condition or risk over
criticality of a bridge within its transportation time, and (ii) the ability for long-term investment
network, focusing on bridges which present more optimisation. This philosophy was the basis of devel-
risk or are more critical; oping the proposed data collection framework that is
. the fact that higher quality data can facilitate split into core, intermediate and advanced data
better risk management; collection regimes. An extra layer of sophistication of
. the need to link closely the data collected to the data collection was added in this approach since a need
decisions made using the data in the overall asset for more detailed investigation and analysis of most
management process; critical or at-risk structures was perceived. Linking
. the need to ensure that any improvements to explicitly the asset management approaches to data
data collection are cost neutral. collection regimes will ensure that for high risk and
critical bridges appropriate data are available to
Taking into account these considerations, the implement the required advanced approach to their
proposed bridge data collection strategy, outlined in management. On the other hand, for less at-risk or
Table 1, envisages core, intermediate and advanced critical structures, where core asset management is
data collection levels or regimes. These categories are appropriate, data collection can be simplified. The use
broadly based on a general road network data of three data collection levels also allows bridge asset
collection framework proposed by Paterson and managers more freedom in developing bridge specific
Scullion (1990) and adapted herein for the purpose of approaches that can be used to ensure cost neutrality is
bridge data collection. Bridges falling into each regime maintained.

Table 1. Outline of risk and criticality-based bridge data collection and monitoring strategy.

Data collection Bridge risk and


regime criticality band Risk assessment resolution and reporting Data collection techniques and frequency
Core Low Overall hazard and bridge performance risk Visual inspections every three to six years
and criticality assessment Limited, usually reactive NDE and SHM
Intermediate Intermediate Individual hazard and bridge element Visual inspections every two to three years
performance risk and criticality Some, reactive and proactive NDE
assessment and SHM
Advanced High Individual hazard and bridge component Visual inspections every one to two years
performance risk and criticality Extensive, mostly proactive NDE and SHM
assessment
332 S. Bush et al.
Downloaded by [Colorado College] at 17:34 27 October 2014

Figure 1. Risk and criticality-based bridge classification for data collection.

Figure 2. Core and advanced asset management process.


Structure and Infrastructure Engineering 333

In Table 2, the core and advanced asset manage- of non-destructive tests that do not rely on human
ment levels are juxtaposed with the respective data sensory systems, i.e. use specialist equipment to collect
collection needs and levels. In doing so, it allows bridge data. Some examples of NDE and SHM include the
asset managers to adapt their data collection regimes Schmidt hammer, chloride sampling, cover meter
depending on what the data is ultimately used for in surveys, proof-load testing, forced vibration testing,
the asset management decision-making processes, and and permanent or periodic monitoring using sensors
according to the specific information needs for a attached to the structure. These data can subsequently
particular bridge based on its risk and criticality be used in a range of assessment processes. One
assessment. For the advanced asset management example is structural identification (St-Id) where a
process, appropriate data is sourced from an inter- more accurate understanding of the as-built opera-
mediate or advanced data collection level. However, tional performance of a bridge is developed via
advanced data collection is required when more creating and updating of a bridge structural model
detailed analyses, such as diagnostics at the bridge (Catbas et al. 2011). An emerging paradigm, St-Id will
component level, are to be undertaken. be attractive to the bridge engineering community
because it uses well-established and accepted ap-
proaches and tools such as finite element modelling.
Data requirements and collection methods Furthermore, underlying the St-Id paradigm is the
Downloaded by [Colorado College] at 17:34 27 October 2014

As the bridge risk and criticality increase, higher strong and logical connection between the collected
quality and more detailed data on its performance need data and its ultimate use, aligned with the philosophy
to be collected. Higher quality data is here understood of the strategy proposed in this article that all data
as more accurate and precise data, where accuracy should have a clear purpose.
refers to the truthfulness of data and precision to its VIs have a number of issues related to their
repeatability. In other words, accurate data estimates accuracy and repeatability (Phares et al. 2001). Other
correctly the mean value (albeit perhaps with large limitations include lack of quantitative information on
spread of individual samples), while precise data has loads and their effects, high manpower demands for
small scatter (Taylor 1999). The requirement for more structures that need to be frequently inspected, and
detailed data addresses the need to collect data that difficulty or impossibility to detect problems in hard to
enables better understanding and assessment of in- reach or hidden locations, e.g. corrosion of reinforce-
dividual hazards, vulnerabilities and performance of ment. Bridge asset managers should therefore reflect
bridge elements and components. on the appropriateness of relying solely on VIs in
When collecting performance data, bridge asset bridge data collection, especially for at-risk or critical
managers have a range of techniques available to them, bridges. While VIs will likely remain the main data
including visual inspections (VIs), non-destructive collection approach, NDE and SHM can offer new
evaluation (NDE) and structural health monitoring insights into, and provide different, usually quantita-
(SHM) (Rücker et al. 2006a, b). VI refers to the tive, data on the structural condition and performance.
process of examination and data collection on struc- With proper NDE and SHM application and data
tures and components by the use of the human sensory interpretation, e.g. within the St-Id framework, im-
systems aided only by simple mechanical enhance- proved understanding can be achieved. By combining
ments such as magnifiers, dental picks and the like. VIs, NDE and SHM, a fuller picture can be developed,
NDE and SHM, in this study, encompass a wide range overcoming limitations of the individual techniques.

Table 2. Correspondence of asset management and data collection levels.

Asset management level


Data collection
level Core Advanced
Core Basic functionality of asset management can be Core data may not be sufficient for advanced asset
a c h i e v e d i n c l u d i n g v a l u a t i o ns a n d management processes
Intermediate prioritisation of annual budget expenditure Advanced asset management processes including
network level analysis, forecasting condition/risk
and investment level scenario analysis can be
achieved using intermediate data
Advanced Advanced data is utilised for further analyses at a more
detail level (e.g., project detail level) such as
diagnostics and more accurate intervention needs
and costs
334 S. Bush et al.

The proposed data collection and monitoring strategy and advanced approaches to data collection and
provide recommendations on when each technique maintenance optimisation. For example, Robelin and
should be used and relates this to bridge risk and Madanat (2006) proposed a joint model for planning
criticality. inspection, maintenance and replacement of bridges in
Many bridge issues related to deterioration and a transportation network, where inspection frequency
aging require periodic reassessment. Because bridge was a decision variable. The optimisation aimed at
condition changes with time, the accuracy of old data reducing the total cost of the various actions.
when applied to current risk assessment deteriorates as Durango-Cohen and Madanat (2008) studied the
time passes. Therefore, for more accurate risk assess- problem of optimisation of inspections and mainte-
ment more frequent data collection is required. nance taking into account performance model uncer-
Additionally, when less precise data collection techni- tainty attributed to different technology used. They
ques, such as VI, are used more frequent inspections demonstrated that adopting a variable inspection
may compensate for lower precision too. In the frequency may lead to savings.
proposed strategy, for higher risk and more critical
structures data are collected more frequently.
As the bridge risk or criticality increases, it Core data collection regime
becomes more important to understand which hazards Bridges for which the core data collection level will be
Downloaded by [Colorado College] at 17:34 27 October 2014

and bridge element and component condition and adequate have a lower risk and lower criticality profile.
vulnerabilities contribute the most to the overall risk. They will not be exposed to severe hazards, will be
A broad categorisation of hazards would break them operating well within their performance capabilities,
(Moon et al. 2009) into those affecting geotechnical, will be in good condition, will have sufficient structural
hydraulic and structural safety, serviceability, durabil- redundancy and limited number of critical elements
ity and maintenance, and functionality of a bridge. A and components, and will only have a limited impact
more detailed assessment will consider what contri- on network operations if their service performance is
butes to those broad hazards. For example, hazards to reduced. For these reasons, core bridges can be
structural safety may include high seismicity and local managed using a core asset management approach
soil type combination, large traffic counts, and (Figure 2).
significant proportion of heavy vehicles and associated The core asset management process requires
probability of overloading. Bridge ‘element’ refers in sufficient data to have a basic understanding of the
this discussion to abutments, decks, piers, handrails, asset and to manage, through prioritisation, perfor-
bearings, etc., while individual ‘components’ make up mance related risks. More information about the types
elements, e.g. several girders and a slab make up the of data required at each level of data collection is
deck. There will typically be a range of possible provided in Bush et al. (2011) and herein only general
hazards to be matched with element and component data categories are listed. For core bridges, data will be
vulnerabilities. It is often the case that only a limited collected for key performance criteria and broad
number of hazards to be realistically expected at the hazard and vulnerability categories, including basic
bridge site will meet associated vulnerabilities. A more traffic data, load carrying capability, bridge condition
refined understanding of the resulting risks and and defects, and, if required, scour or seismic suscept-
criticalities will therefore facilitate targeted interven- ibility. Past work history data will also be stored,
tions, such as strengthening or repair, to be applied thereby allowing basic costs estimates to take place.
only to those selected components and elements The outcome of the assessment process will be a
leading to cost-effective risk management. The pro- prioritised list of work actions, which have costs
posed strategy requires risks to be assessed at varying assigned to them.
levels of element and component resolution. An For core bridges, it is considered acceptable that
important aspect of vulnerability is the consideration the data quality can be lower, and as such VIs will be
of bridge components and elements as parts of the the predominant form of data collection, with NDE
whole structural system. This enables focusing atten- and SHM used sparingly and mostly reactively to
tion on those which have low or no redundancy and understand identified performance weaknesses.
whose failure may therefore lead to wide ranging and Further, as the bridges are in good condition, it is
catastrophic consequences. considered that the VI program can be altered to
The following sections describe in more detail the between three and six years compared to the com-
data requirements and approaches to data collection monly adopted biennial cycle. By extending the
and monitoring for the core, intermediate and ad- inspection cycle, it will enable reallocation of funding
vanced data collection regimes. These guidelines may and inspection resources to those assets with increased
be understood as simplified versions of more rigorous risks and criticality ratings.
Structure and Infrastructure Engineering 335

Intermediate data collection regime Advanced data collection regime


Intermediate bridges will have an increased risk or It is envisaged the advanced data collection regime will
criticality profile because they are subjected be applied only to a limited number of structures that
to increased levels of hazards, are in a poorer have the highest risk or criticality profile as they are
condition, operating close to performance cap- central to the operation of the network, can be
abilities, have limited structural redundancy, have subjected to the most severe hazards, are in poor
critical components or elements whose failure condition, lack structural redundancy and have many
may result in the whole system failure, or will have critical elements and components whose failure will
an increased impact on the functionality of the trigger a whole system collapse, or are operating close
network if their performance is lost or reduced. to their performance capabilities. The advanced asset
Intermediate bridges will be managed using an management approach (Figure 2) will be used for those
advanced asset management approach, therefore bridges; however, an enhanced level of data detail and
facilitating long-term planning and optimisation quality will need to be provided for efficient manage-
of expenditures taking into account a whole-of- ment. To that end, the advanced data collection regime
life approach to performance management is extended such that individual hazard and vulner-
(Figure 2). abilities can be assessed, and a component level
Downloaded by [Colorado College] at 17:34 27 October 2014

To effectively carry out advanced asset manage- understanding of the bridge performance and condi-
ment, an improved level of information will be tion is developed. This will allow work optimisation to
required, and therefore a broader range of data take place at a greater level of resolution and therefore
collected. Individual hazards and vulnerabilities will very specific bridge management plans to be put in
need to be assessed based on collected data. Data place for cost-effective interventions.
resolution will also have to be at the bridge element These bridges require very well defined reliability-
level if an adequate risk assessment is to be achieved. based performance assessments. It is considered that
To undertake advanced asset management, data will extensive and proactive use of NDE and SHM is
be collected for the full range of performance criteria required to achieve this level of data quality and is
including load carrying capability, bridge condition therefore highly recommended for the management of
and defects, overhead strikes, overweight manage- advanced bridges. SHM will be used either periodically
ment data, barrier capacities, weigh in motion to regularly update bridge risk status, or even
data, traffic data, scour data, seismic data and safety continuously especially towards the end of the
data, e.g. number of traffic accidents. Cost data structure’s useful life. These bridges will also have
will be stored on the past and future bridge VIs on a one- to two-year cycle to be able to quickly
management requirements. This data will be used identify problems as they develop. The high level of
to understand future performance states and will be accuracy attained using NDE, SHM and the frequent
used to take a long-term view of bridge and network VI programme, linked with data collected at the
management. individual hazard and bridge component level, will
To manage the increased risk and criticality, it is facilitate the development of high resolution long-term
proposed that the VI program follows a two- to three- management plans, and will allow asset managers to
year cycle, and NDE and SHM have a greater level of more accurately understand the performance capabil-
integration into the data collection process. To ities of their high risk and most critical infrastructure.
improve decisions, NDE and SHM will be used to By providing the level of flexibility in data
both carry out testing on bridge specific defects and collection regime and data collection approach, the
undertaken for a number of typical bridges in the bridge asset manager can tailor the strategy to suit
entire stock to improve the understanding of aspects local network requirements, risk tolerance and budget,
such as deterioration models for a wider population of thereby ensuring cost neutrality of strategy
structures. Further, automatic data collection systems implementation.
will also be used to collect network level data such as
ground motion, flooding, traffic, and vehicle loading.
Automatic data collection systems are promoted for Example of risk and criticality-based bridge
this type of data as they are considered the only classification for data collection
feasible tool available to bridge asset managers. By Four bridges taken from the New Zealand highway
collecting this type of data, improved network models network are used in this example, namely a corrugated
can be developed, and the relationship between bridge steel culvert, a single span timber bridge, the
performance, network performance and strategic out- Auckland Harbour Bridge (AHB) and Newmarket
comes developed. Viaduct (Figure 3). It should be noted here that only a
336 S. Bush et al.

detailed evaluation should follow taking into account


individual hazards and vulnerabilities of bridge
elements and components. The specific details relat-
ing to each bridge, its hazards, condition, network
criticality and current asset management and data
collection approaches are covered in Table 3. Even
for such a limited sample, the bridges range from
major, key structures of national significance through
to much smaller and simpler bridges with varying
network importance, and represent a variety of
hazards, vulnerabilities and asset management
approaches.

Risk and criticality assessment and quantification


In this research, the method proposed by Moon et al.
(2009) for risk assessment and relative quantification is
Downloaded by [Colorado College] at 17:34 27 October 2014

used. Risk is calculated as:


R¼HVCU

where H ¼ probability of a hazard, V ¼ vulnerability


to a given hazard, C ¼ consequences resulting from a
failure to perform adequately, and U ¼ uncertainty
premium. For each bridge, risks related to four
broadly defined performance criteria, namely structur-
al safety, hydraulic/geotechnical safety, serviceability,
durability and maintenance, and functionality are
calculated separately. Detailed tables are provided in
Moon et al. (2009) which enable determination of the
factors in the above risk equation. Relative scores
ranging between 1 and 3 for the first three factors, i.e.
H, V and C, are used. For example, the score for
hydraulic/geotechnical hazard probability depends on
design flood return period at the bridge location,
seismic design category, distance from the coast,
possibility of vessel impact, scour potential and history
of hazard occurrence. The uncertainty premium U
takes into account the accuracy of the data available
and approaches used for risk analysis and quality
control measures employed. Five different values are
proposed, ranging from 2.5 for assessments based on
minimum standard VIs and document review to 1.0
when best practice VIs and document review are used
together with best practice NDE and SHM. To obtain
an aggregate bridge level risk, the RMS of the
individual performance criterion risks was calculated.
Doing so ensures that greater emphasis is placed on
Figure 3. Analysed bridges: (a) corrugated steel culvert, (b)
single span timber bridge, (c) Auckland Harbour Bridge, and specific performance issues that contribute more to the
(d) Newmarket Viaduct. aggregated risk. However, for bridges with heightened
overall risk, it is recommended that individual
performance risks are also examined to understand
high-level risk and criticality assessment are under- their relative importance.
taken in the example. For high-risk and/or criticality Bridge criticality is measured by the wider con-
structures, as suggested by Moon et al. (2009), a more sequences to the network functionality and regional
Structure and Infrastructure Engineering 337

Table 3. Risk and criticality considerations for bridges used in the classification example.

Bridge Description
Corrugated A corrugated steel culvert of 4 m diameter supports state highway of national strategic importance
steel culvert Overall good condition; only minor corrosion to the barrel; no scour
Replacement cost low; annual average daily traffic (AADT) 4 50,000 vehicles; heavy commercial vehicle
5%; reasonable level of service could be restored within a few days; temporary measures quickly
available; alternative routes available with only minor reductions to service level
Data collected via regular minimum standard VIs
Single span 12-m span timber bridge carrying a road of local importance over a small river;
timber bridge Designed to outdated load standards; overall moderate condition
Replacement cost moderate between NZ$100K and NZ$1m; AADT is 1000;
Service can be returned after several days with a temporary bridge installed to cross the river
Data collected via regular minimum standard VIs
Auckland Harbour Key link across a harbour supporting state highway of national strategic importance at the heart of the
Bridge (AHB) major economic centre of New Zealand; complex truss bridge with ‘clip-on’ extensions on both sides
Navigable shipping channel; coastal environment
Known fatigue issues in extensions (heavy vehicles prohibited on extensions); extensions recently
strengthened but only limited service life expected
Replacement cost very high 4NZ$750M; AADT for extensions 438,000, centre truss 480,000; major
service would take 41 year to restore; a detour available for long routes, but nothing available locally;
Downloaded by [Colorado College] at 17:34 27 October 2014

failure will cause significant delays in the region and impact heavily on local, regional, and inter-regional
commerce; a national icon
Individual management plan implemented including best practice VIs, NDE and SHM
Newmarket Key link supporting state highway of national strategic importance at the heart of the major economic
Viaduct centre of New Zealand; completed in 2011; twin post-tensioned bridges with 12 spans, *60 m each
Replacement cost very high 4NZ$200M; AADT 4160,000; service would take 41 year to restore;
detours available but failure will cause significant delays in the region and impact heavily on local,
regional, and inter-regional commerce
Data collected via best practice VIs and technical analyses conducted; a University-operated monitoring
system in place that could be integrated into management plan

economy resulting from a failure. By separately It can be seen from Table 4 that the AHB and
reporting on criticality, it ensures that the bridge asset Newmarket Viaduct, while having very different risk
manager takes into account those bridges that have a scores, both have the same criticality rating, which
significant impact on network functionality, but could be anticipated given their importance. The
because of their low failure probability might not proposed strategy indicates that both bridges should
have the same recognition if only a purely risk-based be managed using an advanced asset management
outlook were used. The overall bridge criticality score process, data should be collected on the full range of
was assumed as the maximum criticality score for the performance criteria, and the data should be collected
individual performance criteria. As with the overall using the most accurate techniques. At this point in
risk score, for highly critical bridges it is recommended time, the AHB is being managed using an up-to-date
to examine the individual scores. data collection and asset management processes, with
Using the outlined risk and criticality assessment SHM and a weigh in motion system used to under-
and scoring method, the results for the four bridges are stand structural performance, and the bridge is also
shown in Table 4. Individual risk and criticality scores visually inspected annually. It is also worth noting that
are provided and overall risk and criticality scores using these best practice approaches to data collection
computed. At the bottom, each bridge is assigned to a reduces the overall bridge risk by a factor of 2.5 using
data collection regime and asset management level. the adopted uncertainty premium scores. However,
Those assignments are indicative only as the decision given the comparable criticality of Newmarket Via-
to which regime and level a bridge will be eventually duct, it is recommended that for this bridge a detailed
assigned to will have to take into account budgetary understanding of its reliability be developed. The asset
constraints and risk tolerance. This will require manager may then decide to defer an advanced data
conducting risk and criticality assessment at least for collection regime, but the review needs at least be
the majority of bridges in a particular stock. For undertaken and a proactive management plan put in
example, while it can be argued that the AHB is certain place.
to receive special attention, whether the culvert will be Another important conclusion is that the corru-
a subject of advanced approaches will be up to the gated steel culvert, while being a relatively simple
asset manager to decide. structure in good condition, still has a high criticality
338 S. Bush et al.

Table 4. Risk and criticality assessment of analysed bridges.

Newmarket
Culvert Timber bridge AHB Viaduct
Performance criteria Risk Consequence Risk Consequence Risk Consequence Risk Consequence
Structural safety 10.0 2 7.5 1 27.0 3 11.3 3
Hydraulic/geotech. safety 10.0 5.0 22.5 3.8
Serviceability 5.0 1 5.0 1 12.0 2 7.5 2
Functionality 15.0 2 5.0 1 18.0 2 7.5 2
Aggregate: risk (RMS)/ 10.6 2 5.7 1 20.6 3 8.0 3
criticality (max consequence)
Data collection regime (indicative) Intermediate Core Advanced Advanced
Asset management level (indicative) Advanced Core Advanced Advanced

rating and it is therefore suggested that it should be boundaries between the core, intermediate and ad-
managed using an advanced asset management vanced data collection levels, and which bridges fall
approach. A greater data quality will then have to be into each regime. However, a robust and rational
Downloaded by [Colorado College] at 17:34 27 October 2014

ensured, likely with the help of techniques such as process will underpin the relative assessment of each
NDE and SHM. Based on more traditional bridge bridge risk and criticality in comparison to the whole
management practices, the culvert would not be stock of assets to be managed.
managed using an advanced asset management Collecting the data in the way it is proposed in this
approach, as many asset managers would perceive it framework will help to close the gaps identified by the
to be a low risk and therefore only undertake limited USGAO and NZOAG audits related to linking bridge
investigations. asset decisions to national policy directives and
creating comprehensive bridge performance frame-
works. This will allow bridge asset managers to obtain
Conclusions strategic knowledge of the bridge asset in their care in a
In this article, a risk and criticality-based bridge data cost-effective way. It is considered that the data
collection strategy has been proposed. In the assess- collection and monitoring strategy developed in this
ment of bridge failure risk and consequences, a article provides a new framework for asset manage-
broader, network and regional economy level outlook ment of road bridges, as it brings together the idea of
is taken, and bridges are seen as parts of the wider network management, criticality and risk to provide a
transportation network. Depending on their risk and deeper understanding of a network operational per-
criticality within the network, bridges are considered to formance capability.
fall within one of the three data collection regimes
comprising core, intermediate and advanced. The data Acknowledgements
collection regimes are aligned with the broader asset The authors thank the New Zealand Transport Agency,
management process to ensure that the data collected Auckland City Council and Waitakere City Council for
is sufficient and appropriate for its purpose in the providing financial support and the project steering group for
their guidance.
decision-making process. The two general levels of
asset management, core and advanced, are linked to
core and intermediate/advanced data collection re- References
gimes, respectively. Brady, K.B., 2004. Report of the Controller and Auditor-
The strategy provides guidance on the type and General on local government: Results of the 2002–03
extent of data to collect, its accuracy, precision, audits. Wellington, New Zealand: Office of the Auditor
collection frequency, resolution, and inspection, eva- General, 52–66.
luation and monitoring techniques. The more ad- British Standards Institution, 2008. PAS 55-1:2008: Specifi-
cation for the optimized management of physical assets.
vanced data collection regimes require more detailed London: British Standards Institution.
and higher quality data and this will be achieved by Bush, S., et al., 2011. Data collection and monitoring strategies
wider integration of NDE and SHM, more frequent for asset management of New Zealand road bridges.
data collection and higher resolution up to the Wellington: New Zealand Transport Agency (in press).
individual bridge component level. Catbas, F.N., et al., eds., 2011. Structural identification (St-
Id) of constructed facilities – approaches, methods and
To ensure that the proposed changes are cost technologies for effective practice of St-Id. USA: Amer-
neutral, bridge managers will have a reasonable ican Society of Civil Engineers and Structural Engineer-
amount of freedom to decide where to draw the ing Institute.
Structure and Infrastructure Engineering 339

Durango-Cohen, P.L. and Madanat, S.M., 2008. Optimiza- Robelin, C.A. and Madanat, S.M., 2006. A bottom-up,
tion of inspection and maintenance decisions for infra- reliability-based bridge inspection, maintenance and
structure facilities under performance model uncertainty: replacement optimization model. In: Proceedings of the
a quasi-Bayes approach. Transportation Research Part A, 85th annual meeting of the Transportation Research
42, 1074–1085. Board, Paper no. 06–0381.
Faber, M.H. and Stewart, M.G., 2003. Risk assessment for Rücker, W., Hille, F., and Rohrmann, R., 2006a. Guideline
civil engineering facilities: critical overview and discus- for structural health monitoring. Phoenix, AZ: SAMCO.
sion. Reliability Engineering and System Safety, 80(2), Rücker, W., Hille, F., and Rohrmann, R., 2006b. Guideline
173–184. for the assessment of existing structures. Phoenix, AZ:
Moon, F.L., et al., 2009. A pragmatic, risk-based SAMCO.
approach to prioritizing bridges. In: F. Wu, A. Diaz, P. Stewart, M.G. and Melchers, R.E., 1997. Probabilistic risk
Shull and D. Vogel, eds. Proceedings of SPIE conference assessment of engineering systems. London: Chapman
on nondestructive characterization for composite materials, and Hall.
aerospace engineering, civil infrastructure, and homeland Taylor, J.R., 1999. An introduction to error analysis: The
security 2009, San Diego, USA, 72940M-1-11. study of uncertainties in physical measurements. Sausalito,
NAMS Group, 2006. International infrastructure manage- CA: University Science Books.
ment manual. Wellington: NAMS Group. Theoharidou, M., Kotzanikolaou, P., and Gritzalis, D.,
New Zealand Society of Local Government Managers, 2007. 2009. Risk-based criticality analysis. In: C. Palmer and S.
Dollars and sense: guidance on financial management Shenoi, eds. Critical infrastructure protection III. Berlin:
under the Local Government Act 2002. Wellington: Springer, 35–49.
SOLGM. Transportation Research Board, 2009. Costing asset protec-
Downloaded by [Colorado College] at 17:34 27 October 2014

Omenzetter, P., et al., 2011. Risk based bridge data collection tion: an all hazards guide for transportation agencies
and asset management and the role of structural health (CAPTA). Washington, DC: Transportation Research
monitoring. In: F. Wu, ed. Proceedings of SPIE’s Board. NCHRP Report 525.
conference on smart structures and materials/nondestruc- Transportation Research Board, 2011. How we travel: A
tive evaluation and health monitoring. San Diego, USA, sustainable national program for travel data. Washington,
79830K1-13. DC: Transportation Research Board.
Paterson, W.D.O. and Scullion, T., 1990. Information United States Government Accountability Office (USGAO),
systems for road management: draft guidelines on system 2008. Highway bridge program: clearer goals and
design and data issues. Washington, DC: World Bank. performance measures needed for a more focused and
Phares, B.M., et al., 2001. Reliability of visual bridge sustainable program. Washington, DC: United States
inspection. Public Roads, 64 (5), 22–29. Government Accountability Office.

Você também pode gostar