CALENDARIO VALORIZADO DE AVANCE DE OBRA

DEDUCTIVO DEL SERVICIO DE “MANTENIMIENTO PERIÓDICO DE LA CARRETERA DEPARTAMENTAL, TRAMO: RUTA HU-102,
TRAMO: EMP. PE-3N (PACHAS)-LIBERTAD-LLATA, EMP. HU-102 (LA LIBERTAD)-HUERGOSAYOG (L=55.282 KM)"

PLAZO DE EJECUCIÓN : 10 DIAS

ITEM DESCRIPCIÓN UND. METRADO PRECIO S/. PARCIAL S/. 10 DIAS

01 OBRAS PRELIMINARES 3,219.84


1.01 TOPOGRAFIA Y GEOREFERENCIACION GLB 0.044 53,258.24 2,343.36 S/. 2,343.36
1.02 MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL GLB 0.044 19,920.00 876.48 S/. 876.48
02 CONSERVACIÓN DE CALZADA EN AFIRMADO 53,819.93
02.01 REPOSICION DE AFIRMADO M3 1,430.240 37.63 53,819.93 S/. 53,819.93
03 TRANSPORTE 45,407.22
03.01 TRANSPORTE DE MATERIAL PARA AFIRMADO HASTA 1 KM M3K 818.240 4.38 3,583.89 S/. 3,583.89
03.02 TRANSPORTE DE MATERIAL PARA AFIRMADO > 1 KM M3K 24,894.840 1.68 41,823.33 S/. 41,823.33
04 CONSERVACIÓN DE DRENAJE SUPERFICIAL 1,535.31
04.01 RECONFORMACION DE CUNETAS NO REVESTIDAS ML 2,437.000 0.63 1,535.31 S/. 1,535.31
05 CONSERVACIÓN DE SEÑALIZACIÓN Y SEGURIDAD VIAL 3,227.82
05.01 REPOSICION DE SEÑALES PREVENTIVA UND. 5.000 459.50 2,297.50 S/. 2,297.50
05.02 REPOSICION DE POSTES KILOMETRICOS UND. 2.000 465.16 930.32 S/. 930.32
COSTO DIRECTO S/. 107,210.12 S/. 107,210.12
GASTOS GENERALES 11.95% S/. 12,811.61 S/. 12,811.61
UTILIDAD 10.00% 10.00% S/. 10,721.01 S/. 10,721.01

SUB TOTAL GENERAL S/. 130,742.74 S/. 130,742.74


FACTOR DE RELACIÓN 0.839759055 S/. 109,792.40 S/. 109,792.40
IMPUESTO GENERAL A LAS VENTAS (18.00%) 18.00% S/. 19,762.63 S/. 19,762.63

TOTAL GENERAL S/. 129,555.03 S/. 129,555.03


TOTAL ACUMULADO S/. 129,555.03
PORCENTAJE PARCIAL 100.00%
PORCENTAJE ACUMULADO 100.00%
CALENDARIO DE DESEMBOLSOS

DEDUCTIVO DEL SERVICIO DE “MANTENIMIENTO PERIÓDICO DE LA CARRETERA DEPARTAMENTAL,


TRAMO: RUTA HU-102, TRAMO: EMP. PE-3N (PACHAS)-LIBERTAD-LLATA, EMP. HU-102 (LA LIBERTAD)-
HUERGOSAYOG (L=55.282 KM)"
PRESUPUESTO TOTAL S/. 129,555.03
MONTO DEL ADELANTO DIRECTO S/. 25,911.01

% AVANCE % AVANCE MONTO DESEMB.


MES DESCRIPCION
PARCIAL ACUMUL. DESEMB. PARC. ACUMUL.

Adelanto Directo 25,911.01 25,911.01

N° 01 Valorización N° 01 100.00% 100.00% 0.00 25,911.01

TOTALES 100.00% 25,911.01

NOTA : Los montos incluyen IGV, Gastos Generales y Utilidad .


CALENDARIO DE UTILIZACION DE EQUIPOS
DEDUCTIVO DEL SERVICIO DE “MANTENIMIENTO PERIÓDICO DE LA CARRETERA DEPARTAMENTAL, TRAMO: RUTA HU-102, TRAMO: EMP.
PE-3N (PACHAS)-LIBERTAD-LLATA, EMP. HU-102 (LA LIBERTAD)-HUERGOSAYOG (L=55.282 KM)"
PLAZO DE EJECUCION : 10 DIAS CALENDARIOS

GESTIÓN DE COSTOS - USO DE PRINCIPALES EQUIPOS


ESTRUCTURA DETALLADA
DE USO DE EQUIPOS

TIEMPO DE EJECUCIÓN
DETALLE DE LA GESTIÓN DE USO DE COSTOS EQUIPOS ENTREGABLE - 10 (DÍAS)

Item Descripción Und. Cantidad Precio S/. Presupuestado S/. 1.00

1.00 CORDEL pza 0.8800 11.77 10.36 10.36


2.00 MIRA PLEGABLE PARA NIVEL TOPOGRÁFICO hm 24.6400 4.30 105.95 105.95
3.00 PALETA DE SEGURIDAD VIAL und 1.0560 120.00 126.72 126.72
4.00 CAMION VOLQUETE 6x4 385 HP 15 M3. hm 314.7756 135.00 42,494.71 42,494.71
5.00 SOLDADORA ELECT. MONOF. ALTERNA 225 AMP. hm 0.4000 80.25 32.10 32.10
6.00 MOTOBOMBA 10 HP 4" hm 25.1722 13.50 339.82 339.82
7.00 CAMION CISTERNA 4X2 (AGUA) 2,000 GAL. hm 83.9551 100.00 8,395.51 8,395.51
8.00 RODILLO LISO VIBR AUTOP 70-100 HP 7-9 T. hm 22.8838 165.00 3,775.83 3,775.83
9.00 TRACTOR DE ORUGAS DE 190-240 HP hm 29.7490 240.00 7,139.76 7,139.76
10.00 CARGADOR FRONTAL 200 HP hm 37.2130 220.00 8,186.86 8,186.86
11.00 ZARANDA METALICA hm 31.8944 19.50 621.94 621.94
12.00 MOTONIVELADORA DE 125 HP hm 89.9621 180.00 16,193.18 16,193.18
13.00 GPS hm 24.6400 4.20 103.49 103.49
14.00 ESTACION TOTAL TOPOGRAFICO hm 24.6400 13.50 332.64 332.64
15.00 NIVEL TOPOGRAFICO hm 24.6400 10.50 258.72 258.72
SUB TOTAL N.S. S/. 88,117.59 88,117.59
TOTAL N.S. S/. 100.00% 88,117.59 88,117.59
AVANCE MENSUAL (%) 100.00
AVANCE ACUMULADO (%) 100.00
CALENDARIO DE UTILIZACION DE MATERIALES
DEDUCTIVO DEL SERVICIO DE “MANTENIMIENTO PERIÓDICO DE LA CARRETERA DEPARTAMENTAL, TRAMO: RUTA HU-102, TRAMO:
EMP. PE-3N (PACHAS)-LIBERTAD-LLATA, EMP. HU-102 (LA LIBERTAD)-HUERGOSAYOG (L=55.282 KM)"
PLAZO DE EJECUCION : 10 DIAS CALENDARIOS

GESTIÓN DE COSTOS - EMPLEO DE MATERIALES


ESTRUCTURA
DETALLADA DE USO DE
EQUIPOS

TIEMPO DE EJECUCIÓN
DETALLE DE LA GESTIÓN DE USO DE MATERIALES ENTREGABLE - 10
(DÍAS)

Item Descripción Und. Cantidad PRECIO Presupuestado S/. 1.00

1.00 ALAMBRE NEGRO # 8 kg 3.6160 4.50 16.272 16.27


2.00 CLAVOS PARA MADERA kg 2.6400 4.50 11.880 11.88
3.00 ACERO DE REFUERZO FY=4200 GRADO 60 kg 4.2336 3.20 13.548 13.55
4.00 LAMINA REFLECTIVA ALTA INTENS. p2 19.5000 35.45 691.275 691.28
5.00 PIEDRA MEDIANA m3 0.3530 65.00 22.945 22.95
6.00 MATERIAL DE AFIRMADO (PAGO POR DERECHO DE CANTERA) m3 1,430.2400 0.70 1,001.168 1,001.17
7.00 HITOS KILOMETRICOS ESTANDAR und 2.0000 332.00 664.000 664.00
8.00 CEMENTO PORTLAND TIPO I (42.5KG) BOL 6.8490 19.80 135.610 135.61
9.00 YESO DE 15 Kg BOL 5.2800 10.50 55.440 55.44
10.00 FIBRA DE VIDRIO DE 4 MM. ACABADO m2 1.8000 45.65 82.170 82.17
11.00 SOLDADURA CELLOCORD P 1/4" kg 0.4000 12.35 4.940 4.94
12.00 WINCHA 50 MTRS pza 0.1320 56.47 7.454 7.45
13.00 TINTA CELOGRAFICA NEGRA DE ALTA INTENSIDAD gln 0.1300 135.45 17.609 17.61
14.00 HORMIGON m3 1.2600 80.00 100.800 100.80
15.00 AGUA m3 0.1459 8.00 1.167 1.17
16.00 MADERA PARA ENCOFRADO p2 6.3524 2.90 18.422 18.42
17.00 ESTACAS DE MADERA und 6.6000 3.50 23.100 23.10
18.00 PLATINA DE FIERRO 1/ 8" X 2" ML 8.5000 4.50 38.250 38.25
19.00 THINER gln 0.1500 16.25 2.438 2.44
20.00 PINTURA ESMALTE SINTETICO gln 0.4550 33.25 15.129 15.13
21.00 TUBO Fo.GALV. DE 3" m 15.0000 60.50 907.500 907.50
SUB TOTAL N.S. S/. 3,831.13 3,831.13
TOTAL N.S. S/. 3,831.13 3,831.13
AVANCE MENSUAL (%) 100.00
AVANCE ACUMULADO (%) 100.00