April 2018
Mode 05 08 11 14 17 20
0 Software 95.75 days Fri Fri
Development 13/04/18 24/08/18
1 Scope 3.5 days Fri 13/04/18 Wed 18/04/18
2 Determine 4 hrs Fri 13/04/18 Fri 13/04/18 Management Management
project scope
3 Secure project 1 day Fri 13/04/18 Mon 2 Management Management
sponsorship 16/04/18
4 Define 1 day Mon Tue 3 Project Manager Project Manag
preliminary 16/04/18 17/04/18
5 resources
Secure core 1 day Tue Wed 4 Project Manager Project Man
resources 17/04/18 18/04/18
6 Scope complete 0 days Wed 18/04/18Wed 18/04/185 18/04
7 Analysis/Software 14 days Wed Tue
Requirements 18/04/18 08/05/18
8 Conduct needs 5 days Wed Wed 6 Analyst
analysis 18/04/18 25/04/18
9 Draft 3 days Wed Mon 8 Analyst
preliminary 25/04/18 30/04/18
software
10 specifications 2 days
Develop Mon Wed 9 Project Manager
preliminary 30/04/18 02/05/18
11 budget
Review 4 hrs Wed Wed 10 Project
software 02/05/18 02/05/18 Manager,Analyst
specifications/budget
with team
Page 1
ID Task Task Name Duration Start Finish Predecessors Resource Names
April 2018
Mode 05 08 11 14 17 20
12 Incorporate 1 day Thu Thu 11 Analyst
feedback on 03/05/18 03/05/18
software
specifications
13 Develop 1 day Fri 04/05/18 Fri 04/05/18 12 Project Manager
delivery
14 timeline
Obtain 4 hrs Mon Mon 13 Management,Project
approvals to 07/05/18 07/05/18 Manager
proceed
(concept,
15 timeline,
Secure required 1 day Mon Tue 14 Project Manager
resources 07/05/18 08/05/18
16 Analysis complete0 days Tue 08/05/18Tue 08/05/1815
17 Design 14.5 days Tue 08/05/18Mon 28/05/18
18 Review 2 days Tue Thu 16 Analyst
preliminary 08/05/18 10/05/18
software
specifications
19 Develop 5 days Thu Thu 18 Analyst
functional 10/05/18 17/05/18
20 specifications 4 days
Develop Thu Wed 19 Analyst
prototype 17/05/18 23/05/18
based on
functional
21 specifications 2 days
Review Wed Fri 25/05/18 20 Management
functional 23/05/18
specifications
Task Inactive Summary External Tasks
Page 2
ID Task Task Name Duration Start Finish Predecessors Resource Names
April 2018
Mode 05 08 11 14 17 20
22 Incorporate 1 day Fri 25/05/18 Mon 21 Management
feedback into 28/05/18
functional
specifications
23 Obtain approval 4 hrs Mon Mon 22 Management,Project
to proceed 28/05/18 28/05/18 Manager
24 Design complete0 days Mon 28/05/18Mon 28/05/1823
25 Development 21.75 days Tue 29/05/18Wed 27/06/18
26 Review 1 day Tue Tue 24 Developer
functional 29/05/18 29/05/18
27 specifications 1 day
Identify Wed Wed 26 Developer
modular/tiered 30/05/18 30/05/18
design
28 parameters
Assign 1 day Thu Thu 27 Developer
development 31/05/18 31/05/18
29 staff
Develop code 15 days Fri 01/06/18 Thu 21/06/1828 Developer
30 Developer 15 days Wed Wed 29FS-75% Developer
testing (primary 06/06/18 27/06/18
debugging)
31 Development 0 days Wed Wed 30
complete 27/06/18 27/06/18
32 Testing 48.75 days Tue 29/05/18Fri 03/08/18
33 Develop unit 4 days Tue Fri 01/06/18 24 Testers
test plans using 29/05/18
product
specifications
Page 3
ID Task Task Name Duration Start Finish Predecessors Resource Names
April 2018
Mode 05 08 11 14 17 20
34 Develop 4 days Tue Fri 01/06/18 24 Testers
integration test 29/05/18
plans using
product
35 specifications
Unit Testing 15 days Wed 27/06/18
Wed 18/07/18
36 Review 5 days Wed Wed 33,31 Testers
modular 27/06/18 04/07/18
37 code
Test 2 days Wed Fri 06/07/18 31,36 Testers
component 04/07/18
modules to
product
38 specifications
Identify 3 days Fri 06/07/18 Wed 37 Testers
anomalies to 11/07/18
product
specifications
39 Modify code 3 days Wed 11/07/18Mon 16/07/1838 Testers
40 Re-test 2 days Mon Wed 39 Testers
modified 16/07/18 18/07/18
41 codetesting 0 days
Unit Wed Wed 40
complete 18/07/18 18/07/18
42 Integration Testing
12 days Wed 18/07/18Fri 03/08/18
43 Test module 5 days Wed Wed 41 Testers
integration 18/07/18 25/07/18
44 Identify 2 days Wed Fri 27/07/18 43 Testers
anomalies to 25/07/18
specifications
Page 4
ID Task Task Name Duration Start Finish Predecessors Resource Names
April 2018
Mode 05 08 11 14 17 20
45 Modify code 3 days Fri 27/07/18 Wed 01/08/1844 Testers
46 Re-test 2 days Wed Fri 03/08/18 45 Testers
modified 01/08/18
47 code
Integration 0 days Fri 03/08/18 Fri 03/08/18 46
testing
complete
48 Training 45.75 days Tue 29/05/18Tue 31/07/18
57 Documentation 30.5 days Tue 29/05/18Tue 10/07/18
58 Develop Help 1 day Tue Tue 24 Technical
specification 29/05/18 29/05/18 Communicators
59 Develop Help 3 wks Tue Tue 58,29FS-50% Technical
system 12/06/18 03/07/18 Communicators
60 Review Help 3 days Tue Fri 06/07/18 59 Technical
documentation 03/07/18 Communicators
61 Incorporate 2 days Fri 06/07/18 Tue 60 Technical
Help 10/07/18 Communicators
documentation
62 feedbackuser
Develop 2 days Tue Wed 24 Technical
manuals 29/05/18 30/05/18 Communicators
specifications
63 Develop user 3 wks Tue Tue 62,29FS-50% Technical
manuals 12/06/18 03/07/18 Communicators
64 Review all user 2 days Tue Thu 63 Technical
documentation 03/07/18 05/07/18 Communicators
Page 5
ID Task Task Name Duration Start Finish Predecessors Resource Names
April 2018
Mode 05 08 11 14 17 20
65 Incorporate 2 days Thu Mon 64 Technical
user 05/07/18 09/07/18 Communicators
documentation
66 feedback
Documentation 0 days Tue Tue 65,61
complete 10/07/18 10/07/18
67 Pilot 70.25 days Tue 08/05/18Tue 14/08/18
74 Deployment 5 days Tue 14/08/18Tue 21/08/18
81 Post 3 days Tue Fri 24/08/18
Implementation 21/08/18
86 Review
Software 0 days Fri 24/08/18 Fri 24/08/18 85
development
template
complete
Page 6
May 2018 June 2018
20 23 26 29 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28
gement
Management
Project Manager
Project Manager
18/04
Analyst
Analyst
Project Manager
Project Manager,Analyst
Page 7
May 2018 June 2018
20 23 26 29 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28
Analyst
Project Manager
Management,Project Manager
Project Manager
08/05
Analyst
Analyst
Analyst
Management
Page 8
May 2018 June 2018
20 23 26 29 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28
Management
Management,Project Manager
28/05
Developer
Developer
Developer
Developer
Deve
27/0
Testers
Page 9
May 2018 June 2018
20 23 26 29 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28
Testers
Page 10
May 2018 June 2018
20 23 26 29 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28
Technical Communicators
Technical Communicators
Page 11
May 2018 June 2018
20 23 26 29 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28
Page 12
July 2018 August 2018 September 2018
28 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 30 02 05
Page 13
July 2018 August 2018 September 2018
28 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 30 02 05
Page 14
July 2018 August 2018 September 2018
28 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 30 02 05
oper
Developer
27/06
Page 15
July 2018 August 2018 September 2018
28 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 30 02 05
Testers
Testers
Testers
Testers
Testers
18/07
Testers
Testers
Page 16
July 2018 August 2018 September 2018
28 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 30 02 05
Testers
Testers
03/08
Technical Communicators
Technical Communicators
Technical Communicators
Technical Communicators
Technical Communicators
Page 17
July 2018 August 2018 September 2018
28 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 30 02 05
Technical Communicators
10/07
24/08
Page 18