Escolar Documentos
Profissional Documentos
Cultura Documentos
Scholars' Mine
International Conference on Case Histories in (2013) - Seventh International Conference on Case
Geotechnical Engineering Histories in Geotechnical Engineering
Laxman Rajwani
Royal Haskoning India Pvt. Ltd., India
Dhananjay Shah
M.S. University of Baroda, India
Recommended Citation
Shukla, Jaykumar; Rajwani, Laxman; and Shah, Dhananjay, "Analysis and Design of Breakwater for Sea Water Intake Facility On South
East Coast of India" (2013). International Conference on Case Histories in Geotechnical Engineering. 65.
http://scholarsmine.mst.edu/icchge/7icchge/session03/65
This Article - Conference proceedings is brought to you for free and open access by Scholars' Mine. It has been accepted for inclusion in International
Conference on Case Histories in Geotechnical Engineering by an authorized administrator of Scholars' Mine. This work is protected by U. S. Copyright
Law. Unauthorized use including reproduction for redistribution requires the permission of the copyright holder. For more information, please contact
scholarsmine@mst.edu.
ANALYIS AND DESIGN OF BREAKWATER FOR SEA WATER INTAKE FACILITIY
ON SOUTH EAST COAST OF INDIA
Jaykumar Shukla Laxman Rajwani Dhananjay Shah
L&T- Sargent & Lundy Royal Haskoning India Pvt. Ltd. M.S. University of Baorda
Baroda, India- 390019 Mumbai, India- Baroda, India-390009
Jaykumar.Shukla@Lntsnl.com L.rajwani@haskoningindia.co.in dr_dlshah@yahoo.com
ABSTRACT
The proposed power project site on the South East coast of India required the construction of breakwaters to prevent detrimental
effects owing littoral drift along the coast and also to protect the intake channel lining against sea attack. This paper describes the
geotechnical design and analysis for breakwater facility proposed for the site. The preliminary design of breakwater was carried out
using raw geotechnical data made available in form of the few boreholes investigation and SPT N-values. The general soil profiles
suggest that the stratum consist of 37 metres of soft clay below sea bed resting on medium dense to dense sand formations. Ground
improvement was inevitable for the site and attempts were made to review the techno commercial feasibility of ground improvements
in the staged construction framework for vibroreplacement and band drain installation. Slope stability analysis and time dependent
settlement analysis were implemented for suggested staged construction sequence to ensure the desired stability at each construction
stage. The partial treatment scenario was considered owing to practical limitation for carrying out the ground improvement along the
full clay depth. The study describes the possible strength gain approach as geotechnical solution for such difficult sites to achieve
techno commercial tradeoff. The stability analyses are addressed in the present study for each construction stage along with settlement
analysis. The good quality geotechnical investigation carried out for the site has revealed that sound geotechnical judgmental
engineering from the insufficient preliminary data can lead to converge better in this competitive environment.
.
INTRODUCTION
Recognizing that electricity demand in India was increasing at life. To decide the optimum scheme, technical feasibility of
a rate faster than overall energy supply, in the year 2004, the various offshore and onshore intake structures were explored.
Government of India formulated a major policy to enhance the Keeping in mind important aspects such as maintenance
production of electricity so that overall development is not dredging, shore protection, hot water recirculation, and design
hampered on account of a power shortage. To implement the of protective structures, it was decided to implement offshore
policy, a scheme was initiated for setting up large 4000 MW intake structure with breakwater protection option for cooling
units termed as Ultra Mega Power Projects (UMPP). One of water intake system.
these UMPP is planned to set, along the coastal areas of
villages Ayyavaroppakhandriga and Shambhunithopu, north In this alternative, an open channel of the required dimensions
of the Krishnapatnam Greenfield harbor in Andhra Pradesh, was proposed to be dredged in order to bring make-up water to
India. Fig. 1 describes the geographical location of the an inshore pump house. Since such a channel was proposed to
proposed project. be connected to the required depth of water to ensure that the
supply remained uninterrupted, even at the lowest
The developer, having gone through the various aspects for astronomical tide, the channel would be exposed to wave
the project, identified the need for make up water to meet the action which could transmit to the sump, thereby affecting the
cooling water requirement of turbines. For make up water pump performance. Some protection would therefore have to
requirements building up the sustabable and robust sea water be provided, which would also prevent entry of sediment to
intake facilities was considered to be most important element the exposed part of the intake channel. Schematic layout of the
and lifeline for keeping power plant operation throughout its intake channel is reproduced and shown in Fig. 2.
Fig. 2 General Layout and Alignment of the Intake Channel & The parameters generally considered in the design of the
Breakwaters armour unit are unit weight (of rock, in the instant case), wave
Depth (m)
1 15 Soft Clay 10 kPa 0.365 0.0032 -20
m from -24
G.L. -26
-28
2 10 Medium 15 kPa
-30
(6.5 to 20 Clay
-32
m from /Intermediat
-34
G.L. e Clay
-36
3 20 Deep Clay 40 to 50 Not considered MBH 9
-38
(20.0 to kPa and in settlement MBH 10
-40
50.0 m modeled calculations 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48
from G.L. as Plasticity Index (Ip) %
Cu/Pc = Fig. 5 Distribution of Plasticity Index for the site (MBH 9 &
0.22 MBH 10)
4 As Break Water CU=0 ,
per Fill Phi = 400 The staged construction method was adopted for the
Fig. considere construction of Breakwater. It was proposed to place the
3 d breakwater fill in the three stages. In the first stage 6.11 m
height of the fill will be constructed and then left for the two
0 month for allowance of the consolidation of the treated
Ground. The installation of Geo-Grid at the Elevation 2.75m
-4
Sand; Average N-Value = 12; from the present ground level is considered. The Breakwater
-8
fill should be placed up to height 6.11 after the installation of
MBH10
MBH 09 Geo-grid. In the second stage the fill height will be raised upto
-12 MBH 11 8.3 m fill height (i.e. second stage fill height = 8.3 – 6.11 =
MBH 16
MBH 22 2.19m). After finishing the second stage again 2 month
-16 MBH 1 waiting time will be given to stabilize the pore pressures and
thereby achieving additional consolidation and strength gain.
-20 Soft Marine Clay; Average N-Value = 1;
WL= 53; LL=79%; Ip=53% Finally in the third stage the breakwater will be raised up to
-24 11.5m height (i.e. third stage fill height = 11.5 – 8.3= 3.2 m).
Depth (m)
FOS=1.52
Radius=39.83
Quarry run
Quarry run
Quarry run
Quarry run
Soft Clay 10-30kPa
10-30kPa
stone
10-30kPa
stone
stone clay
10-30kPa
stone
10-30kPa
stone stone
10-30kPa
column
stone clay
10-30kPa
column
stone
10-30kPa
column
stone
10-30kPa
column stone
column
10-30kPa
clay
column
stone
10-30kPa
column
stone
10-30kPa
clay
column
stone
10-30kPa
clay
column column
10-30kPa
clay
stone
10-30kPa
clay
column
stone
10-30kPa
clay
column
stone
10-30kPa
clay
column
10-30kPa
stone
clay
stone
10-30kPa
clay
column
stone
10-30kPa
clay
column
stone
10-30kPa
clay
column
stone
10-30kPa
clay
column
10-30kPa
stone
clay
column
stone
10-30kPa
clay
column
stone
10-30kPa
clay
column
stone
10-30kPa
clay
column
stone
10-30kPa
clay
column
10-30kPa
stone
clay
column
stone
10-30kPa
clay
column
10-30kPa
stone
clay
column
stone
10-30kPa
clay
column
stone
10-30kPa
clay
column
stone
10-30kPa
clay
column
stone
10-30kPa
clay
column
stone
10-30kPa
clay
column
stone
10-30kPa
clay
column
stone
10-30kPa
clay
column
10-30kPa
stone
clay
column
stone
10-30kPa
clay
column
stone
10-30kPa
clay
column
stone
10-30kPa
clay
column
stone
10-30kPa
clay
column
10-30kPa
stone
clay
column
stone
10-30kPa
clay
column
stone
10-30kPa
clay
column
stone
10-30kPa
clay
column
stone
10-30kPa
clay
columnstone
10-30kPa
stone
clay
column
stone
10-30kPa
clay
column
10-30kPa
stone
clay
column
stone
10-30kPa
clay
column
clay
columncolumn
10-30kPa
clay
column
clay
column
clay
column
clay
clay
clay
clay
clay
stone
stone
stone
stone stone
stone
column
stone
column
stone
column
stone
columncolumn
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
stone
column
column
column
column
column
20-30kPa clay
INT clay
Depth (m)
the effective overburden pressure (Fig. 11).Taking the
advantage of the various findings in the fresh geotechnical 25
investigations, the ground improvement scheme was revisited
considering the increased construction time to optimize the 30
cost of the breakwater construction. The revised soil model is
presented in Table 4.
35
0 0
BH11- UU BH11- CU
BH16- UU BH16-CU 40
BH22 -UU BH22-CU
BH23- UU BH23-CU
10 10 45
0 10 20 30 40 50 60 70 80 90 100
Cu (kPa)
20 Fig. 11. Measured coefficient of consolidation (Cc) and initial
Depth (m)
Depth (m)
20
void ratio from fresh geotechnical investigations
with base
25 25
Cu=10
6 Break CU=0 , As per stage under
30 30
Water Phi = 400 consideration
Fill considered
35 35
BH 23 BH 22
BH 22 BH 23 GROUND IMPROVEMENT USING PVDs
40 40
0.5 0.6 0.7 0.8 0.9 1.2 1.3 1.4 1.5 1.6 1.7
Cc Void ratio Since the given construction time is comparatively large, the
ground improvement using Prefebricated Vertical Drains
(PVDs) is explored. However, the stability modeling in given
Fig. 10. Measured coefficient of consolidation (Cc) and initial construction stage was challenging task since the strength gain
void ratio from fresh geotechnical investigations in clay is purely depend upon the degree of consolidation. It is
The possible variation of the undrained cohesion (CU), in the Construction Cum. fill Cum. consolidation
second stage of construction is estimated using the spread Stage height (m) settlement (m)
sheet and recommendations made by Tavenas and Leroueil ( IS:8009 part I)
(1980); Bergado et al. ( 1991); Ladd (1991); Chai et al. (1994) Stage 1 4 1.109
are referred to for the strength gain calculation with an Stage 2 6.5 1.964
assumed maximum Cu value due to loading given by Cu/σ’ = Stage3 8.5 2.633
0.25. A geotextile layer (tensile strength 300 kN/m) is
Stage 4 10 3.046
proposed to laid at the elevation of 4m to counter the stability
Stage 5 11 3.280
issue in the second and subsequent staged construction.
Appendix A describes possible variations of the effective Stage6 11.5 3.389
stresses and strength gain in each construction stage.
Considering the strength variation of the subsoil profile given Table 6. Estimated Time required (in month) to achieve
The strength gain approach can be suitably applied for Tavenas F. and Lroueil S. [1980] “The behavior of
geotechnical solution for such difficult sites implementing embankments on clay foundations”. Can. Geotech. J., Vol. 17,
the stage construction sequence for stability modeling of pp 236-260.
breakwater and similar structures. Post construction
settlement is considered to be most important and sensitive
parameters that need proper evaluations as it can lead to
complete collapse of high embankment type structure in
long term if no assessed properly at design state. Needless to
mention, design adjustment based on monitoring strength
gain and settlement during construction is essential to
validate the final design issued for construction.
Table A-1. Estimated strength variation of the in situ clay layer under each stage of embankment loading.
Elevati At the End of Stage 1 At the End of Stage 2 At the End of Stage 3 At the End of Stage 4 At the End of Stage 5 At the End of Stage 5
on
from
σ’ Total cohesion σ’ Total cohesion σ’ Total cohesion σ’ Total cohesion σ’ Total cohesion σ’ Total cohesion
Sea
(kPa) available Cu(kPa) (kPa) available Cu(kPa) (kPa) available Cu(kPa) (kPa) available Cu(kPa) (kPa) available Cu(kPa) (kPa) available Cu(kPa)
bed
(m)
Under Under Under Under Under Under Under Under Under Under Under Under
triangular central triangular central triangular central triangular central triangular central triangular central
portion portion portion portion portion portion portion portion portion portion portion portion
A B C D E F G H I J K L M N O P Q R S
-2.5 55.13 11.60 12.13 95.32 17.98 23.83 135.3 23.83 33.83 165.28 37.57 41.32 185.24 43.81 46.31 195.21 47.56 48.80
-10 54.77 16.69 18.37 94.59 24.61 30.84 133.72 35.73 40.62 162.48 44.22 47.81 181.08 50.13 52.46 190.08 53.58 54.71
-20 52.86 25.00 25.00 90.81 31.04 37.08 126.35 41.53 45.97 151.05 49.06 52.14 166.07 54.02 55.89 172.99 56.76 57.63
-35 49.64 50.00 50.00 81.03 50.00 50.00 109.68 50.00 50.00 128.4 51.84 53.67 139.23 55.02 56.37 144.08 56.98 57.59
Stage At Start of Stage At Starti of At Start of At Start of Stage At Start of Stage At Start of Stage At end of Stage 6
1 Stage 2 Stage3 4 5 6 (during hand over of
Breakwater)
Clay strength Table 1 Table 6 Column Table 6 Column Table 6 Column Table 6 Column Table 6 Column Table 6 Column (R,S)
used (Ref) (C,D) (F,G) (L,M) (O,P)
(I,J)