Escolar Documentos
Profissional Documentos
Cultura Documentos
: PTBP-090-CA
CONTENTS
1. PURPOSE/GENERAL
2. SCOPE OR COVERAGE
3. APPLICABLE CODE & SPECIFICATION
4. WORK ORGANIZATION
5. EQUIPMENT, TOOLS & MANPOWER
6. WORK METHOD
7. INSPECTION AND TEST REPORT
ATTACHMENTS
A. FORM REPORT
PT Sutindo Project Ind PT Bangadua Petroleum Job No. : PTBP-090-CA
1. PURPOSE/GENERAL
The purpose of this procedure is to ensure that construction of onshore pipelines through
creek and river crossing is carried out correctly and in accordance with recognized
practices, codes and standards.
2. SCOPES OR COVERAGE
This procedure would be applied in conjunction with trunk line and flow line construction in
Cimanuk River.
4. WORK ORGANIZATION
River crossing work crew shall follow the procedure and would be supervised by foreman.
The fore man is responsible to Construction Manager and Construction Superintendent to
meet the project specification.
The following items of major equipment are planned to be available for us6 at crossings.
Any additional equipment requirements will be provided from the mainline section.
Dragline As Needed
Excavator 20T Long Arm 0.75 m3 One (1) Units
Fuel Truck 5.000 liters One (1) Units
Grader - As Needed
Front End Loader - As Needed
Low Boy / Truck Crane - As Needed
Man hauls 20 Seat One (1) Units
Lifting Equipment / Excavator 0.75 m3 One (1) Units
Welding Machine 400 AMP Four (4) Units
Tip Truck - As Needed
Diesel Pump & Hoses - As Needed
Suction Dredge - As Needed
Survey Equipment Theodolite or Equivalent One (1) Set
6.2 Tools
The following-items of major tools will be used :
Item Model / Capacity Quantity
Lifting bells & Head irons 5 Tons Four (4) EA
Crest meter Survey Equivalent One (1) Units
Holiday Detector 0.75 m3 One (1) Units
5.3 Manpower
PT Sutindo Project Ind PT Bangadua Petroleum Job No. : PTBP-090-CA
6. WORK METHOD
6.1 General.
6.1.1 The pipeline shall be laid under the riverbed and shall be secure from currents, floods, and
channel changes and scouring.
6.1.2 Depending on method of crossing approved, care must be taken to avoid blocking rivers from
use for normal traffic.
6.1.3 Cover to pipe shall be measured from top of pipe to lowest point of watercourse bed.
6.2 Pipeline Fabrication
The pipeline section for each creek or river crossing is fabricated to the required length to
span the crossing. In some situations sag and over bends may be included in the fabricated
pipe string .
Fabrication of the pipeline section is scheduled ahead of the trenching operation to ensure
that the trench remains open for a minimum period of time, so that the pipe is ready for
installation on completion of trenching.
PT Sutindo Project Ind PT Bangadua Petroleum Job No. : PTBP-090-CA
6.3 Buoyancy
Buoyancy devices such as sealed drums or wood blocks may be required to assist with the
pulling of the pipe string across the creek or river.
The buoyancy will be securely fastened to the pulling head and lead joint of the pipe to
ensure the pipe does not bury itself when being bottom pulled.
Additional buoyancy may be secured along tile length of tile pipe string if required to reduce.
This will depend of the length of tile crossing and pipe diameter.
The alignment and gap set-up of the ends is considerably more difficult to achieve than for
production welds, because the overlapped pipes require accurate cutting to form a one weld
tie-in or an additional pipe length has to be cut where there is a gap between strings to form
a two weld tie-in.
Localized enlargement of the trench (bell hole) will be provided to allow adequate welder
access. Shoring will be installed where necessary to ensure safe working conditions in the
bell hole.
An externally applied line-Up clamp is used to hold the ends for welding after cutting to size.
6.6 Trenching
6.6.1 General
Trenching for wet crossings are be divided into three components:
(a) Ordinary Pipeline Trench - The trench on both sides -of the crossing, up to the flotation
trench, is excavated using normal methods with long arm excavator or any other
suitable method.
(b) Flotation Trench - The trench or slot on both sides of the crossing is excavated to
provide a smooth profile for the pipeline and sag bends.
(c) Crossing Bed Trench - The trench across the creek or riverbed is excavated using
dragline, long reach excavator or Suction dredge.
Trenching shall be configured in accordance with the minimum allowable roping radius of
the pipe, and the cold or induction bends to be installed.
The trench shall be surveyed before the pipe pull to ensure correct depth and profile with
the use of a boat where required.
PT Sutindo Project Ind PT Bangadua Petroleum Job No. : PTBP-090-CA
Where rock is encountered every attempt shall be made to excavate the trench using the
normal excavation methods and equipment. Should this not be successful in removing the
rock, and then the Construction Superintendent will determine the most appropriate method
of removal. Blasting shall only be considered as a last resort when all other methods have
failed and approvals shall be obtained as required by the relevant authorities.
Suitable bedding material shall be provided where rock is encountered and where required
rock shield shall be fitted to the pipe to provide additional protection to the pipe coating.
The head of the pipe string is placed in the flotation slot with the string held Lip by the lifting
equipment.
When the cables are attached the crossing Foreman carries out a final check to ensure that
every item of equipment is correctly secured to the pipe and that all is in procedure for the
pull.
On a signal from the foreman the lifting equipment will walk slowly forward with the pipe.
Each item of plant adjusts its speed to ensure all are moving at the same speed. The dozer
winds in its winch to maintain tension on the pipe and ensure it remains straight.
As each item of lifting plant approaches the flotation slot the procession stops while that
item is disconnected from the pipe and the pipe is allowed to "float" into the slot
The minimum buoyancy on the pipe ensures that it remains in the trench bottom throughout
the pull until the pipe is correctly positioned in the crossing.
On completion of the pulling the pipeline, any buoyancy devices are removed and the
location f the pipe is surveyed. When access is required by boat, this will be done be
attaching a survey staff to the back of a boat and dropping a weighted probe over the side
directly underneath the staff. The boat is moved until the probe rests on top of the pipe, the
land-based surveyor then records the depth and alignment from the staff or alternatively
depth Sounding equipment will be used to survey the position of the pipe.
The Lowering-in Checklist will be completed by the Foreman and used to record the
checking and completion of work.
6.8 Backfill
6.8.1 General
The trench shall be backfilled with the excavated material free of rock, debris and all
foreign matter which can damaged the pipe.
The minimum depth of cover shall not be less than 150 mm over the pipeline and shall
be thoroughly compacted
If the stockpiled spoil is insufficient, borrow soil shall be supplied and placed so that the
finished backfill profile is level with the original profile of the waterbed.
Banks must be restored as nearly as possible to their original condition. Backfill shall be
compacted.
PT Sutindo Project Ind PT Bangadua Petroleum Job No. : PTBP-090-CA
6.9 REINSTATEMENT
6.9.1 General
The Foreman ensures that all necesary permits are maintained on the R.O.W at all times.
Following the reinstatement work a crew will install marker posts and catholic protection
(C.P.) test points along the pipeline alignment,
(a) The disposal of material is organized by the Foreman who ensures that
All temporary facilities and debris is removed off the R.O.W. and disposed of in a
proper manner.
Disable materials are picked up and reformed to store.
Surplus suitable material is spread over the R.O.W or removed.
The Foreman liaises with the Construction Superintendent to Obtain approved
locations for disposal of any surplus materials in specified location.
Ensure the pipe dimension (include wall thickness, diameter, gradient) would be used in
appropriale location.
PT Sutindo Project Ind PT Bangadua Petroleum Job No. : PTBP-090-CA
The Construction Superintendent completes a Daily Progress Report for each day’s
operation at the end of the day’s work.
Checklist completed by the foreman for the various activities provide the details required
completing the Daily Progress Report. The report is to be forwarded to the Construction
Engineer.
PT Sutindo Project Ind PT Bangadua Petroleum Job No. : PTBP-090-CA
ATTACHMENT
A