Você está na página 1de 14

Improved conceptual process design

avoids revamp scope growth


Tony Barletta and Gary R Martin Process Consulting Services
Adrie Visser National Petroleum Refiners of South Africa (PTY)

F
or grassroots design, defining project scope Introduction
is a straightforward exercise. Grassroots CPD is the most important activity in revamp
projects can follow optimum execution design. Often, its significance is overlooked. As a
procedures for engineering and construction. result, minimum engineering effort is expended
Office-based conceptual process design (CPD) on it, with the expectations that the more
works well because there is no existing unit to detailed process design work can be performed
present unique challenges and obstacles. For a during FEED or the beginning of DE.
revamp, however, CPD demands a much more Consequently, many revamps start with superfi-
detailed attack, because most equipment — with cial process work and little money assigned for
all its possibly hidden shortcomings — already CPD. Often looming behind these seemingly
exists. The only foolproof way of carrying out cost-effective CPD packages are scope growth
CPD for a revamp is to first establish a perform- and revamp cost escalation.
ance base line of the existing unit. This entails CPD largely determines revamp costs and
making a comprehensive test run to gather whether or not the results will meet yield, run
actual field data on temperatures, pressures and length and reliability objectives.1,2,3,4 Failure to
flows. Original equipment drawings, P&IDs and meet any one of these processing objectives can
control room data are not sufficient. Once real- turn an otherwise profitable revamp into one
time field data is obtained, it is used for that loses refiners millions of dollars due to poor
calibrating computer simulations in the design performance or an unscheduled outage to correct
office. All major cost bottlenecks are now identi- revamp design flaws. When done properly, CPD
fied and alternative process flow schemes are will identify all significant process and equip-
evaluated to determine the lowest cost. ment modifications, and scope growth will be
Finally, equipment lists and cost estimates are minimal as engineering progresses.
developed. Admittedly, all this takes time By today’s standards, revamps are deemed
and costs money, but unless such work is thor- successful if: throughput, yield and reliability
oughly and carefully carried out at this point, objectives are achieved, and they are on schedule
scope can grow enormously during front-end and under budget. Large overruns can wreck
process design (FEED) and detailed engineering revamp economics. Volumes have been written
(DE). about cost estimating, cost control, project
This article presents data on a revamp under- management and scheduling. All of these are
taken for National Petroleum Refineries of South important activities that must be executed well
Africa (PTY), (NATREF, a joint venture of for a successful revamp. However, if the CPD is
SASOL and Total Fina Elf) in which a study was poor quality or insufficient in detail, then no
begun to determine whether increasing crude amount of cost estimating, cost control, project
capacity at its Sasolburg refinery was a sound management and scheduling activities will
investment. A NATREF multidisciplinary team prevent scope growth. This article presents
coordinated engineering work with several guidelines for revamp CPD. If these guidelines
contractors to carry through a staged process are executed properly, they will minimise revamp
beginning with CPD, continuing through FEED scope growth. While the examples presented are
and ending in DE. specific to crude/vacuum units and the approach

www.digitalrefining.com/article/1000227 March 2002 1


and thorough CPD is needed to
±50-100% satisfy the competing objectives.

Order of magnitude estimate


±20%
±30-40% Why is a different approach

Semi-detailed estimate
needed?

Preliminary estimate
±10%
When a conventional office-based

Definite estimate
approach is applied to revamp
design, it is common today for a
major portion of the process engi-
neering design to take place in the
Feasibility FEED stage. Only a superficial
Conceptual F.E.E.D.
study
design
amount of process design is
Detailed engineering performed during the CPD, resulting
Start End in a cursory review of much of the
equipment. Consequently, the
Figure 1 Stages of engineering revamp scope of work is poorly
defined. Conventional office-based
used by NATREF, the techniques can be applied CPD focuses on scheduling and cost estimating,
to other refinery unit revamps. not on process design. But if scope is poorly
defined, the estimate will not be accurate even if
Revamp conceptual process design it is expertly prepared with much detail.
Project schedules often demand fast-track revamp During CPD, all related revamp modifications
conceptual process design. Overall revamp dura- must be identified so a cost estimate can be
tions can be as short as one year from beginning prepared. If the scope of work is well defined,
to startup for fast-track revamps (typically under costs can be estimated with a reasonable degree
$20 MM) or longer for larger investments. of accuracy. However, if the scope is incomplete,
Whatever the case, CPD must be fast and efficient. the estimate will not capture all revamp costs.
There is no time for re-engineering. Poorly defined scope is the number one cause of
CPD costs must also be controlled. At the revamp cost escalation. It is the conceptual proc-
conceptual design stage, the revamp has not yet ess design, not cost control or project
received full funding (see Figure 1). If engineer- management activities, that defines the flow
ing costs are excessive and the revamp does not scheme and therefore the revamp scope.
get funded, money is wasted. However, there is For grassroots design, defining the scope is a
some minimum amount of engineering that must straightforward exercise. Grassroots projects can
be performed to sensibly direct the capital follow optimum project execution procedures for
expenditure. Otherwise, all major scope-related engineering and construction. The office-based
items may not be identified and the process flow CPD approach works well because there is no
scheme selected may not be minimum cost.5 existing unit with its many challenges and obsta-
Minimum CPD cost and sufficient engineering cles. However, project execution procedures that
are always competing objectives during the work well with grassroots design must be altered
conceptual design stage. The trend has been to for revamp design. Revamp CPD demands a
reduce the cost of CPD by pushing essential proc- more detailed process design because most of
ess engineering evaluations into FEED and DE. In the equipment exists. Revamps present
many revamps, this has resulted in either scope unknowns, constraints and problems that are
growth or scope rationalisation, where many common within an existing operating unit. The
pieces of equipment were removed to control conceptual designer must maximise the use of
costs. At this point, it may be well to ask if equip- existing equipment (or minimise new equip-
ment can be removed to control costs without ment) to implement a cost-effective revamp.
impairing the process scheme, and why the equip- Otherwise, revamp costs can be excessive and
ment was specified in the first place. In corollary, jeopardise the chance for approval. Revamp
if the process scheme will be impaired, how can conceptual designers must therefore understand
removal be justified? A more intelligent, efficient existing unit performance and constraints in

2 March 2002 www.digitalrefining.com/article/1000227


detail and know how to circumvent them with study recommended making minimum modifica-
practical, cost-effective flow scheme modifica- tions to the PFD; equipment sizes were increased
tions. This requirement does not exist in or new parallel equipment such as a new vacuum
grassroots CPD. While the conventional office- column and vacuum heater were to be installed
based approach works well for grassroots to meet processing objectives. One consequence
projects, rarely does it foster an intimate under- of maintaining the existing PFD was that a new
standing of all factors affecting revamp success. parallel crude line from the charge pumps in the
Without this understanding, it is impossible to tank farm to the unit would be needed to meet
make good investment decisions. the higher crude flow rate (see Figure 2).
Refiners must recognise that CPD is where the Increasing crude flow rate increases pressure
process flow diagram (PFD) is set and equipment drop if the existing process flow scheme is to be
modifications are identified. The options for the retained and the desalter operating pressure
engineering effort to influence costs are greater considered fixed. The new parallel charge line
in the CPD stage than at any other time in the would be over 5000 ft long and the cost high.
revamp. If the PFD that is developed during the During CPD, it was essential that alternative
conceptual process design is found to have flaws process flow schemes be explored.
during FEED or DE, scope growth will almost
always result. Once the PFD has been set, there A different cpd approach: understanding unit
is usually very little time available in the sched- performance
ule to re-engineer the PFD. Scope rationalisation, The complexities of revamp design demand a
“value” engineering or other similar exercises stronger emphasis on understanding the existing
that are common today are frequently employed unit performance and constraints; otherwise,
to lower costs resulting from a flawed process scope growth will be likely. Additionally, concep-
flow scheme and/or incomplete scope definition. tual designers must also consider non-idealities
But, “value” engineering participants often have like fouling and s These demands are not usually
little understanding of unit limitations that drive attainable with the office-based approach with-
the process flow scheme selection; hence, the out excessive CPD cost and schedule impacts.
focus becomes the elimination of equipment. The following guidelines, which supplement CPD
This simply is not an effective means of meeting activities, will minimise revamp scope growth:
reliability and operability6,7 requirements. • Perform comprehensive unit performance test
In the revamp under discussion, prior to the run
CPD NATREF had done a crude/vacuum unit • Evaluate unit hydraulics
feasibility study based on a conventional • Evaluate heat integration, fired heaters and
approach using only office calculations. The column internals.

New line

Pressure, kg/cm2 25.5


0.3

Crude
charge

23.5
Desalter

17.0
22.5 21.7 21.2 20.8 20.4 19.9

Figure 2 Crude hydraulics - parallel feed line

www.digitalrefining.com/article/1000227 March 2002 3


• Identify damaged or under-performing
Cold train heat (% design)
equipment
• Generate a calibrated process simulation.
Pumparound Test run duty, % design
The plant performance test run is the only
Top 43
Heavy naphtha 107 method of evaluating the real unit performance
No. 2 oil 112 and bottlenecks. To many people, a performance
Total pumparound duty 68 test is a casual exercise. Samples are drawn for
Diesel from hydrotreater 70
laboratory analysis while the refinery process
Total cold train duty 69
computer retrieves process data. Maybe a few
control valve positions are noted in the field. The
Table 1 information is taken back to the office and a
computer simulation is built. This is not a
Following these guidelines requires that the comprehensive performance test, and the results
conceptual process designers’ experience be are usually misleading, leading to disastrous
matched to the specific unit being revamped. scope growth later in engineering.
A performance test is a comprehensive test run
Performance test runs that establishes a full pressure, temperature and
By definition, a revamp starts with an existing composition profile of the unit. In addition to
operating unit. Maximum reuse of existing obtaining data from the process computer, pres-
equipment minimises new equipment and sures are measured locally for all hydraulic
revamp costs.10 A conceptual design engineer systems to establish baseline hydraulic perform-
must have an intimate understanding of the ance criteria (see Figure 3). Temperatures are
existing unit performance and bottlenecks to measured locally where remote indication does
maximise the use of the existing equipment in not exist. Control valve and battery limits pres-
the revamp flow scheme.11,1. However, the sures are measured. Bypasses that are partially
competing objectives of schedule and cost limit open around control valves are noted. The test
the time and money available to become inti- run does not end with the collection of field-
mately familiar with the existing unit operation measured and computer system data. The data
during the conceptual stage. A performance test are then used to generate a heat and material
run is an effective method for developing an in- balance, which is the basis for a baseline simula-
depth understanding of the unit performance tion. The simulation is calibrated with
and bottlenecks while minimising the expendi- field-measured test run data. The simulation
ture of time and money. The performance test calibration will typically include:
run enables the conceptual design engineer to: • Distillation tower stage efficiencies
• Measure unit performance • Heat exchanger fouling factors
• Quantify unit bottlenecks • Heat exchanger hydraulics allowances
• Quantify hydraulic system limitations • Fired heater radiant flux imbalances.
• Identify and quantify non-idealities such as Comprehensive performance test runs are
heat exchanger fouling rarely performed for refinery revamp CPD

Field measured pressure, kg/cm2


21000 BPD
Battery
limits
FC

151 148 146 145 140 25% 45


48
open Kerosene
Kerosene product
product to treater
138

Figure 3 Baseline kerosene product hydraulic profile

4 March 2002 www.digitalrefining.com/article/1000227


Desalters
Raw
crude

Flashed crude
vapours

Flashed crude

Figure 4 Existing raw crude/desalter crude PFD

because the designers or project management do constraints can be a significant portion of the
not see the value added. The conventional total revamp cost. However, crude hydraulics are
wisdom is that a simulation can be generated rarely reviewed during the CPD at the level of
with information that is extracted from the as- detail necessary to identify all hydraulic-related
built data sheets and drawings, original scope of work changes. But sensible decisions
equipment specifications and limited plant data about the revamp flow scheme cannot be made
(office-based approach) and, therefore, test runs without understanding the impact of crude
are deemed wasteful. This is a terrible hydraulics. An office-based method of evaluating
misconception. hydraulics consists of collecting the equipment
Simulations that are built with the office-based as-built data sheets and piping isometrics and
approach rarely represent actual operating unit rigorously calculating the system pressure drop.
performance. It is ironic that more effort is not While this approach may be very scientific, it is
put into generating an accurate simulation, since not practical because it consumes many man-
the simulation is the main process tool that is hours, is too expensive, takes too long for the
used to evaluate process changes that will ulti- CPD stage, and does not necessarily reflect actual
mately define the revamp scope and installed unit hydraulics that are affected by fouling.
cost. True, conducting a performance test run These rigorous calculations are more appropriate
will be more expensive and time consuming than for the DE stage, where a final check of all
an office-based conceptual process design system design is warranted.
approach that pushes the majority of meaningful A more efficient method of identifying
process engineering into FEED and DE. hydraulic constraints during CPD can be accom-
However, planning and executing a comprehen- plished by using field-measured performance
sive test run is the most cost-effective method of test run data. One of the performance test
performing the minimum amount of conceptual run objectives is to develop a complete hydrau-
process design required to fully define the lic profile of each circuit. Once hydraulic
revamp scope at the CPD stage. profiles are developed from the performance
test run, the conceptual design engineer can
Hydraulics scale the baseline hydraulic profile up or down
When crude/vacuum units are revamped to to quickly and accurately evaluate revamp
increase throughput, crude hydraulics are almost hydraulics.
always a unit constraint. Capital expenditure Heat integration
necessary to overcome crude hydraulic In another completely different crude/vacuum

www.digitalrefining.com/article/1000227 March 2002 5


Revamp cold train heat (MMBtu/hr) pressure. Not only was the operating pressure at
the front end above the design pressure of the
first exchanger, it was also above the pressure
Pumparound Duty
Top 71 that the piping flange rating would permit.
No. 1 oil 40 Flanges and valves would have to be replaced as
Total pumparound duty 111 well. These changes resulted in a significant
Diesel from hydrotreater 50 amount of scope growth.
Total cold train duty 161
In this example, scope growth was incurred
because the crude hydraulics were not properly
Table 2 evaluated in the CPD stage. The engineering
company had chosen to use an office-based
unit revamp, an objective was to increase the approach. When the conceptual designer was
crude unit desalter operating temperature. Raw asked during the CPD if the crude hydraulics
and desalted crude preheat trains are shown in would be a problem when two exchangers were
Figure 4. Revamp modifications resulting from added to the raw crude preheat train, her
an office-based CPD approach are shown in response was “no, but we will look at the hydrau-
Figure 5. Two desalted crude heat exchangers lics in the next stage of engineering”. Had the
were re-piped from downstream of the desalter conceptual designer used the performance test
to upstream of the desalter. The piping costs run data that were available to her, she would
were estimated and included in the overall have quickly seen the flaw in the design (see
revamp cost estimate. Figure 6).
When a detailed hydraulic evaluation was It is especially important to consider crude
performed during DE, it was discovered that unit hydraulics during the CPD stage. Crude
relocating the two desalted heat exchangers units utilise a high level of heat integration
upstream of the desalter would increase the between the crude/vacuum column products and
front-end operating pressure above the design pumparounds in the crude preheat train. This
pressure of the first heat exchanger. At this stage high level of heat integration tightly links the
of the project it was too late for re-engineering; crude and vacuum columns’ heat balance and
the alloy exchangers would have to be replaced crude preheat train hydraulics. For example,
with exchangers designed for higher operating modifications to one or more of the crude/

Relocated
exchangers
Desalters
Raw
crude

Flashed crude
vapours

Flashed crude

Figure 5 Re-piped raw crude/desalter crude PFD

6 March 2002 www.digitalrefining.com/article/1000227


pressure, PSIG

216 185 182 175 169


Desalters
Minimum desalter
Raw pressure to prevent
crude vaporisation is 165 PSIG
Near maximum
262 215 front-end pressure

Flashed crude
vapours
160 130 90
40

120

50

Flashed crude

Figure 6 Field-measured raw crude/desalter crude pressures

vacuum pumparound systems may involve required to evaluate them in enough detail to
adding additional exchangers to satisfy revamp determine equipment scope even though he may
heat balance requirements. Adding additional be proficient at modelling and developing heat
exchangers to the preheat train affects crude and material balances. Yet, in an effort to mini-
hydraulics. mise cost, equipment specialists may not get
involved in CPD. Therefore, heater and column
Fired heaters and distillation column internals internals scope is often poorly defined.
Fired heater and distillation column internals
modifications can be significant revamp cost Average radiant flux rate
items. Major modifications in these areas can Average radiant flux rate is the heat duty
extend turnarounds and require special plan- absorbed in the radiant section of a heater
ning. Fired heater and distillation column divided by the surface area of the radiant section
internals must be evaluated in enough detail tubes (see Figure 7). Average radiant flux rate
during CPD to identify modifications and define rules-of-thumb are used in the refining industry
revamp scope. But sadly, fired heaters and to give only very general guidelines for heater
column internals are often only reviewed with capacity. Sometimes, conceptual designers do
cursory calculations or rules of thumb during use average radiant flux guidelines to determine
CPD. This approach can result in scope growth. heater capacity during CPD. But when heaters
Abbreviated or rule-of-thumb evaluations, such operate with flux imbalances, using average radi-
as use of average radiant heat flux or percentage ant flux rate alone can lead to grossly incorrect
of flood, can be very misleading and result in conclusions about heater capacity. Average radi-
incorrect conclusions about fired heater or distil- ant flux guidelines assume even flux distribution
lation column performance. Good field data and in the radiant section. In reality, many heaters
a detailed review of the specific equipment operate with flux imbalances that result in a
parameters that determine ultimate capacity are difference in pass flow rates as high as 50%
what is really needed to determine maximum between radiant passes.13,14 Flux maldistribution
heater or distillation column capacity. is a function of firebox tube geometry, pass
Fired heaters and distillation column internals layout, burner operation, number of burners and
pose a real challenge to the conceptual design burner location (see Figure 8). The vacuum
engineer. Many times the conceptual design heater in Figure 9 operated with average radiant
engineer does not have the equipment expertise flux rates of 9000 Btu/hr-ft2, within the guide-

www.digitalrefining.com/article/1000227 March 2002 7


passes were coking while the upper passes were
Shield tubes not.
Radiant tubes This demonstrates that average radiant flux
rate is not a good indicator of heater coking
potential or capacity. Peak film temperature and
Convection oil residence time, which determine vacuum
section heater coking and ultimate capacity, are better
indicators of heater capacity. Oil mass velocity
and flux distribution determine peak oil temper-
ature. When heaters operate with large radiant
section flux maldistribution, the difference in
Radiant peak film temperature can be as high as 75ºF
section between passes. This is why average radiant flux
rate should not be used to make decisions
concerning heater capacity. A tube-by-tube
heater simulation calibrated with accurate field-
measured data is the only way peak oil film
Figure 7 Simplified heater sketch temperatures can be calculated when heaters
experience flux maldistribution. Three essential
lines for vacuum heater operation. However, the items must occur to accurately calculate peak
heater flux imbalances resulted in flux rates of film temperature in this situation:
13 000 Btu/hr-ft2 and 5000 Btu/hr-ft2 for the • The conceptual designer must recognise that
lower and upper passes, respectively! The lower the heater has flux maldistribution
• Accurate field data must be collected
• A rigorous heater model (tube-
Steam Steam by-tube) must be calibrated with the
field-measured data to simulate the
Pass Pass Pass Pass flux imbalance.
No. 1 No. 2 No. 4 No. 3 Often, the rigorous nature of the
calculations necessary to properly
Reduced crude Reduced crude
evaluate fired heater capacity are
viewed by project management as
exercises more appropriate for the
FEED and DE stages. This delays
critical scope definition decisions
Pass Pass until later stages of engineering,
No. 1 No. 3 resulting in cost escalation.

Crude column stripping trays


Heater pass Heater pass
outlet outlet
In most refineries, the performance
of crude column stripping trays is
critical. Low stripping tray efficiency
or damaged trays increase the
amount of light material in the crude
Pass Pass
No. 2 No. 4 column bottoms product. Light
crude columns bottom product loads
the vacuum ejectors, raising column
operating pressure, and costs refin-
Coking ers millions of dollars. Replacing
damaged or poorly designed strip-
ping trays with properly designed
Figure 8 heater layout sketch trays almost always has an attractive

7 March 2002 www.digitalrefining.com/article/1000227


payback, but can be a costly
Relative flow rate
revamp item. To hold to
Temperature, ºF Pass No. 1
budget, the need must be
identified during cpd. Pass No. 2
Failure to identify low-effi- Pass No. 3
Atmospheric Vacuum unit
ciency stripping tray operation column
Pass No. 4
fired heater
or damaged trays unfortu-
769
nately is a common oversight Pass
1.0 No. 1
during CPD. Yet, damaged or No. 1 800
dislodged stripping trays can No. 2
1.5
be identified with precise field Pass 768
No. 2 No. 3
measurements using accurate
pressure gauges. An experi- 801
1.1 No. 4
Pass
enced CPD engineer will No. 3
measure stripping tray pres-
sure drop during a 1.4
Pass
performance test (see Figure No. 4
10). Damaged or dislodged
stripping trays have little or Figure 9 Pass heat-flux maldistribution
no pressure drop, while intact
stripping trays have a pressure
Pressure, PSIG
drop of 0.06-0.12 psi per tray.
Stripping trays have inherently
low efficiencies. A well- 7
designed stripping tray will 6
have an efficiency of 40%,
Feed from
while a poorly designed tray crude heater
can have an efficiency of only
dP = 0.5 PSI 20.5
10-25%. Poorly designed strip-
5
ping trays result in low 4
strip-out of light material from 3
2
the crude column bottoms 1
product. Crude column strip- dP = 0.5 PSI 21.0
Stripping
ping trays operate with high steam
liquid loads and low vapour
loads. This combination
demands a special design;
otherwise, the trays will have
low efficiencies. A well-
designed stripping tray is not
an off-the-shelf item.
Poorly designed stripping Reduced
trays operating with low effi- crude
ciencies often go unnoticed
during CPD. Standard calcula- Figure 10 Stripping section pressure survey
tions of percentage flood are
sometimes the only calculations that conceptual able percentage flood. Since the problem with
designers use to determine if a distillation tray is poorly designed stripping trays is weeping, not
fit-for-purpose. But standard calculations of tray flooding, more rigorous calculations are needed
percentage flood will not identify a poorly to identify poorly design stripping trays. If the
designed stripping tray. In fact, stripping trays stripping trays are not evaluated in sufficient
operating with low efficiency will have an accept- detail during CPD, the need for replacement can

www.digitalrefining.com/article/1000227 March 2002 9


Furthermore, conceptual designs that are
generated by designers who do not have
experience with the type of unit being
revamped often result in unstable, inop-
erable or unreliable designs. Most refinery
units have qualities or characteristics that
are specific to each process. Failure to
consider these qualities can result in
unproven or untried revamp solutions.
Refiners should ask, “Where have you
successfully done this before and who can
I talk to about it?”

Stripping tray mechanical design


Distillation column internals are normally
designed for stable steady-state operation.
Failure to consider non-steady state oper-
Figure 11 Damaged stripping trays ation, like startup, during conceptual
process design can lead to scope growth.
go unnoticed until FEED or detailed design Not only must stripping trays be designed prop-
stages — an expensive oversight. erly to achieve good efficiency, but well-designed
stripping trays must also withstand start-up
Conceptual designer experience conditions during which they can be easily
Revamp conceptual process design must be fast dislodged (see Figure 11).16,17 For that reason,
and efficient. The experience of the conceptual stripping trays require a more robust mechanical
designer specific to the unit being revamped can design. Stripping trays should be constructed
make the difference between an efficient concep- with shear clips and through bolts, and should
tual process design package that defines all of typically be designed to withstand an uplift force
the revamp scope, and one that results in signifi- equivalent to 2 psi. The cost of a mechanically
cant scope growth or even worse, does not robust stripping tray is approximately three to
achieve revamp objectives. In revamping a five times the cost of a standard stripping tray. If
crude/vacuum unit, the conceptual designer the conceptual designer is not familiar with
must have extensive experience with crude/ crude unit startup procedures, a standard strip-
vacuum units. In revamping an FCC unit, he ping tray may be specified with unfortunate
must have extensive experience with FCCUs. results.
While this is only common sense, it is often
overlooked. Conventional approaches to CPD NATREF’S crude/vacuum unit and FCCU product
based on project management hierarchy view the recovery CPDs
CPD as simply another activity. People are To return to the South African revamp,
assigned based on availability and the projected NATREF’s objective was to increase crude
CPD completion on the Gantt chart, rather than processing capacity by over 22%; consequently,
necessary expertise. all refinery units required capital investment.
When the conceptual designer has extensive Revamp scope of work and capital investment
experience specific to the unit being revamped, varied for each unit. However, the crude/vacuum
he will know what roads to go down and what and FCC product recovery units combined capi-
roads are dead ends. Knowing which revamp tal investment represented about 50% of overall
options to evaluate and which ones to discard refinery investment. Figure 12 shows the refinery
saves both time and money. A minimum cost block diagram.
solution may require altering the process flow NATREF used a four-staged engineering
scheme to circumvent bottlenecks.15 This can be approach for the refinery expansion. The four
complex. Quickly knowing what alternate flow stages of engineering were:
schemes to consider only comes with experience. • Feasibility study

10 March 2002 www.digitalrefining.com/article/1000227


C3’s
LSR LSR Premium
MEROX Alkylate gasoline

Reformate Blender
FCC gasoline Regular
Sat. gasoline
Reformer
gas

Kerosene Kerosene Kerosene


MEROX
Blender
C4
Alky. Jet fuel
ISOM
Crude
unit Diesel Distillate
hydro-treater
AGO

FCC
Crude
oil Blender Diesel
LVGO
Vacuum MVGO Distillate
unit HVGO
hydro-cracker

Fuel oil /
RCD asphalt

Figure 12 NATREF refinery block diagram

• CPD crude/vacuum unit and FCCU product recovery


• FEED unit. NATREF’s CPD work scope included:
• DE. • Comprehensive performance test run
NATREF funded the refinery expansion and • Identification of all major cost bottlenecks
has already completed construction on several • Evaluation of process flow scheme alternatives
units. The revamped FCCU product recovery unit to find the least-cost flow scheme
has started up, while the crude/vacuum unit • Development of equipment lists and cost
work is being finished in early 2002. Even estimates.
though the crude/vacuum and FCC product First, the performance test run gathered suffi-
recovery unit revamps were more complicated cient plant data to evaluate unit performance
than other refinery unit revamps, they experi- and identify limitations that would prevent addi-
enced significantly less scope growth from the tional crude processing capacity. During and
end of CPD to the definitive estimate. immediately following the test run, it became
NATREF and Process Consulting Services used clear that there were a number of major equip-
the CPD approach discussed in this article for ment limitations that would have to be
the crude/vacuum and FCC product recovery circumvented in order to increase crude process-
units. The CPD for the other refinery units was ing capacity. Maintaining the existing process
done in a traditional manner, with thorough flow scheme (see Figure 13) simply would not
process design work conducted during FEED allow crude rate to be increased without high
and DE, not within the CPD stage. investment and poor energy utilisation.
In December 1998, NATREF kicked off the As test run data gathering must be
CPD with a comprehensive test run on the comprehensive and should not rely solely on the

www.digitalrefining.com/article/1000227 March 2002 11


zone pressure were all meas-
ured with an accurate absolute
pressure manometer.
Increasing vacuum unit feed
rate would have increased
transfer line pressure drop and
Naphtha increased heater outlet pres-
sure, which would reduce the
HVGO product yield or require
Kerosene
higher heater outlet tempera-
ture to maintain cutpoint.
Crude
oil LVGO NATREF’s vacuum heater
Diesel already operated with flame
impingement and rapid tube
‘Cold’ MVGO
AGO coking; therefore, additional
exchanger
train
heater firing was not feasible.
HVGO This emphasises that identify-
ing limitations cannot be done
with computer system data
alone.
Desalter
Once all performance test
‘Hot’ crude run measurements were
exchanger train completed, a calibrated base
VTB
case process flow sheet model
Atmospheric Vacuum column was developed. Unit constraints
column were clearly defined in the
model; otherwise, it would not
Figure 13 Existing NATRF crude/vacuum unit simplified PFD have been possible to effi-
ciently evaluate practical flow
scheme alternatives.
Absolute pressure, mmHG Some of the major crude unit
24
constraints that needed to be
circumvented to meet
113 50
NATREF’s capacity objectives
were:
• Vapourisation at the crude
418 heater pass inlet control valves
• Crude hydraulics and preheat
train design pressure
• Desalter capacity
• Crude heater duty
• Crude column heat removal
Vacuum heater Vacuum column • Crude column shell capacity
• Vacuum heater duty
Figure 14 NATREF tansfer line pressure survey • Vacuum column shell
capacity
easy-to-get information such as process control • Product cooling circuits.
computer data, complete pressure and local A conceptual designer with extensive experi-
temperature surveys were performed throughout ence specific to the unit being revamped can
the unit. Figure 14 shows some of the vacuum narrow down the flow scheme alternatives to a
unit pressure measurements. Vacuum heater few practical options, but rote solutions are
outlet pressure, transfer line pressure and flash common. As in NATREF’s feasibility study,

12 March 2002 www.digitalrefining.com/article/1000227


Naphtha

Naphtha
Crude
oil
Gas

‘Cold’ Kerosene
exchanger
train
LVGO
Light Light
diesel diesel
Heavy MVGO
diesel
Desalter
HVGO
Pre-flash
Desalted crude AGO gas oil
exchanger train

VTB

Pre-flash Atmospheric Pre-flash Vacuum column


column column vacuum column

Figure 15 Revamped NATREF crude/vacuum unit simplified PFD

paralleling or replacing equipment with larger ied, with the selected process flow scheme shown
pieces of equipment is almost never cost effec- in Figure 15. The most cost-effective revamp
tive when there are major unit constraints. used two preflash columns: an atmospheric
Finding the least-cost flow scheme requires preflash and a vacuum preflash. The atmospheric
extensive crude unit revamp experience. This is preflash column would eliminate vapourisation
critical to cost control. at the heater inlet, debottleneck crude hydrau-
Two major bottlenecks were the atmospheric lics, reduce crude column overhead condensing
and crude vacuum column diameters. Both duty, reduce loads in the crude column, allow for
columns had to be paralleled or replaced if the changes to the preheat train that would increase
existing process flow scheme were maintained. heat recovery, and require no new heaters. The
The engineering company that performed the vacuum preflash column would pre-flash atmos-
feasibility study had decided to parallel the pheric residue before the vacuum heater and use
vacuum heater and vacuum column. But revamps the idled RCD vacuum column. This enabled
should maximise the use of existing or spare crude throughput to be increased without
equipment to minimise cost. During the CPD, a exceeding the vacuum heater, transfer line and
survey of all idled equipment was done. NATREF vacuum column ultimate capacity. The vacuum
was modifying the reduced crude desulphuriser heater would need to be revamped; however, no
(RCD) unit, and several pieces of its equipment other heater changes would be needed.
were available for use in the crude/vacuum unit. Identifying the right process flow scheme thus
The most significant was the RCD vacuum minimised revamp costs.
column, which could easily be modified for use Once the least-cost PFD was identified, equip-
in the crude unit. ment lists and cost estimates were completed.
Practical flow scheme alternatives were stud- These were relatively straightforward activities.

www.digitalrefining.com/article/1000227 March 2002 13


However, all significant scope items had to be Capital Approach, Fuel and Technology Management, March/April
identified; otherwise, the most highly skilled cost 1996, 37-45.
estimator in the world could not do the job prop- 3 Barletta T, Smith M, Macfarlane C, Crude Unit Revamp
erly. Total installed equipment costs (TIC) are Increases Diesel Yield, PTQ, Spring 2000, 45-51. See www.
many times equipment purchase price. CPD digitalrefining.com/article/1000251
4 Hanson D W, Lieberman N P, Lieberman E T, De-entrainment
performance tests must therefore identify all
and Washing of Flash Zone Vapors in Heavy Oil Fractionators,
bottlenecks and find the least-cost process flow
Hydrocarbon Processing, July 1999, 55-60.
scheme if estimators and schedulers are to do 5 Golden S W, Minimum Investment Revamps — Achieving
their jobs effectively. Attractive Economics, 1997 NPRA Annual Meeting, San Antonio,
Texas, Paper AM-97-58.
Conclusions 6 Golden S W, Revamping FCCs — Process and Reliability, PTQ,
The complexities of revamp conceptual process Summer 1996, 85-93.
design demand a stronger emphasis on under- 7 Martin G R, Luque E, Rodriguez R, Revamping Crude Unit
standing existing unit performance and Increases Reliability and Operability, Hydrocarbon Processing,
constraints, and more attention to detail than June 2000, 45-56.
grassroots conceptual process design. For this 8 Barletta T, Revamping FCC Units: Debutanizer Reboiler Fouling
— Don’t Treat the Symptoms, World Refining, Jan/Feb 2001, 20-
reason, an office-based CPD approach that works
22.
well for grassroots design does not work well for
9 Barletta T, Revamping Crude Units - Consider Heat Exchanger
revamp design. Since the CPD sets the revamp Fouling When Redesigning Heat Exchanger Networks, Hydrocarbon
scope and will therefore largely determine Processing, Feb 1998, 51-57.
revamp costs, well-executed conceptual process 10 Golden S W, Pushing Plant Limits: Test Runs, Plant
design results in minimum-cost revamps that Expectations, and Performance Confidence, World Refining,
achieve yield and run length objectives, and March/April 1999, 75-91.
minimum scope growth during the revamp 11 Golden S W, Fulton S, Low cost Methods to Improve FCCU Energy
design life cycle. Properly executed revamp Efficiency, PTQ, Summer 2000, 95-103. See www.digitalrefining.
conceptual process design costs more than office- com/article/1000249
based conceptual process design. But, when the 12 Hartman E L, Hanson D W, Weber B, FCCU Main Fractionator
Revamp for CARB Gasoline Production, Hydrocarbon Processing,
conceptual designers’ experience matches the
Feb 1998, 44-49.
unit being revamped, applying the guidelines put
13 Martin G R, Heat-Flux Imbalances in Fired Heaters Cause
forth in this article will reduce the cost of FEED Reliability Problems, Hydrocarbon Processing, May 1998, 103-
and DE. 109.
Scope definition has an enormous impact on 14 Martin G R, Barletta T, Vacuum Unit Fired Heater Coking —
the accuracy of the cost estimate. Total installed Avoid Unscheduled Shutdowns, PTQ, Spring 2001, 119-125.
cost (installed, direct and indirect field costs, 15 Barletta T, Practical Considerations for Crude Unit Revamps,
engineering, taxes, etc) is typically four to eight PTQ, Autumn 1998, 93-103. See www.digitalrefining.com/
times the cost of equipment for refinery revamps. article/1000250
Therefore, failure to identify scope items can 16 Martin G R, Barletta T, Revamping Crude Units — Consider
quickly lead to large scope growth and cost esca- Startups to Improve Unit Reliability, World Refining, Jan/Feb
2000, 30-35.
lation between CPD and detailed design. CPD
17 Nigg J M, Sitton K D, Improve Reliability and Maintenance of
packages that minimise the process design effort
FCC Main Fractionator Internals, AKZO Nobel Australian Seminar,
solely to reduce up-front engineering costs may 13-14 May 1999.
appear to be an appropriate utilisation of engi-
neering funds. However, this almost always leads
to higher overall engineering costs, revamp cost
escalation and/or compromised revamp Links
objectives.
More articles from: Process Consulting Services
References
1 Barletta T, Martin G R, Revamping Conceptual Process Design, More articles from the following categories:
PTQ, Winter 2001, 41-48. Crude Vacuum Units Heavy Crudes
2 Golden S W, Kowalczyk D, FCC Optimization — A Minimum

14 March 2002 www.digitalrefining.com/article/1000227

Você também pode gostar