Você está na página 1de 1

Cadangan Kerja-kerja Menaiktaraf Gazebo, Rumah Pengetua Dan Tempat Pengumpulan Sampah Sediada Kepada ‘Laundry Gazebo, Dormitory’

Dan Rumah Sampah, Di Rumah


Antarabangsa Universiti Malaya, Seksyen 17, Petaling Jaya, Universiti Malaya.

Keterangan Kerja Harga T.Mula T.Siap 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20


1 Projek 427,400.00 17/07/17 03/12/17
2 Prelim 21,820.00
3 Mobilization
4 Demolition-Dormitory
5 a) Wall & Floor 8,200.00 25/07/17 07/08/17
6 b) Ceiling & dll 3,000.00 27/07/17 09/08/17
7 New Work - Dormitory
8 a) Brickwork & Rendering 14,030.00 07/08/17 16/09/17
9 b) Piping work 6,000.00 14/08/17 09/09/17
10 c) W/proofing work 2,240.00 28/08/17 11/09/17
11 d) Tiling Work 44,610.00 03/09/17 14/10/17
12 e) Skin coat & painting 14,800.00 21/08/17 07/10/17
13 f) Door & HPL work 14,400.00 23/09/17 12/10/17
14 g) Bar counter & cabinet 10,000.00 30/09/17 20/10/17
15 h) Artificial Grass 4,500.00 06/10/17 26/10/17
16 i) Sanitary fitting 14,780.00 29/09/17 13/10/17
17 j) Grill & roller blind 4,950.00 13/10/17 27/10/17
18 Demolition - Gazebo
19 a) Struktur binaan & pokok 4,000.00 07/08/17 21/08/17
20 b) Lantai & dll 4,500.00 14/08/17 28/08/17
21 New Work - Gazebo
22 a) Lowest Gid work 7,660.00 28/08/17 16/09/17
23 b) R.C work 40,010.00 10/09/17 01/10/17
24 c) Column RHS 12,000.00 25/09/17 08/10/17
25 d) Roof Structure 36,000.00 09/10/17 30/10/17
26 e) Roof Finishing 24,000.00 01/10/17 21/10/17
27 f) Brick work 22,720.00 22/09/17 21/10/17
28 g) Railing 18,600.00 28/10/17 19/11/17
29 h) Floor Finishing 7,490.00 05/11/17 26/11/17
30 i) Door & glass work 6,600.00 03/10/17 19/11/17
31 j) Counter work & grill 10,000.00 22/10/17 26/11/17
32 k) Furniture & dll 10,100.00 05/11/17 26/11/17
33 Demolition (Rumah Sampah)
34 a) Brickwall 2,000.00 16/09/17 30/09/17
35 b) Lantai Concrete 1,400.00 23/09/17 07/10/17
36 New Work (Rumah Sampah)
37 a) Lowest Gid work 5,400.00 23/09/17 14/10/17
38 b) R.C work 6,000.00 07/10/17 21/10/17
39 c) Roof Structure 9,000.00 14/10/17 28/10/17
40 d) Roof Finishing 7,200.00 14/10/17 14/11/17
41 e) Brick work 8,160.00 21/10/17 14/11/17
42 f) Ceiling work 5,220.00 28/10/17 05/11/17
43 g) Tiling work 4,410.00 28/10/17 12/11/17
44 h) Painting & door 6,200.00 05/11/17 12/11/17
45 i) Apron & pipe work 1,900.00 05/11/17 19/11/17
46 j) M.sgrating & dll 3,500.00 12/11/17 03/12/17
47 k) Testing & cleaning 19/11/17 03/12/17
48 l) Hand Over 26/11/17 03/12/17