CRONOGRAMA DE AVANCE FISICO DE OBRA: "CREACION DEL COLISEO CERRADO MUNICIPAL DEL DISTRITO DE PALCAMAYO - TARMA -JUNIN"

ID ITEM NOMBRE DEL PROYECTO M-1 COSTO DURACION M1 M2 M3 M4 M5


14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08
1 ITEM “CREACION DEL COLISEO CERRADO MUNICIPAL DEL DISTRITO S/. 765,065.02 120 days?
DE PALCAMAYO - TARMA - JUNIN”
2 INICIO S/. 0.00 0 days
3 01 OBRAS PROVISIONALES,TRABAJOS PRELIMINARES S/. 35,824.68 10 days?

4 1.01 OBRAS PROVISIONALES S/. 13,416.16 2 days?


5 01.01.01 OFICINA S/. 3,582.88 1 day? 1 day?
6 01.01.02 ALMACEN S/. 5,118.40 1 day? 1 day?
7 01.01.03 CASETA DE GUARDIANIA S/. 1,535.52 1 day? 1 day?
8 01.01.04 CERCOS S/. 2,358.93 1 day? 1 day?
9 01.01.05 CARTEL S/. 820.43 1 day? 1 day?
10 1.02 INSTALACIONES PROVISIONALES S/. 1,249.48 1 day?
11 01.02.01 ENERGIA ELECTRICA PROVISIONAL S/. 1,249.48 1 day? 1 day?
12 1.03 TRABAJOS PRELIMINARES S/. 1,226.62 1 day?
13 01.03.01 LIMPIEZA DE TERRENO S/. 1,226.62 1 day? 1 day?
14 1.04 MOVILIZACION DE CAMPAMENTO, MAQUINARIAS Y S/. 15,000.00 1 day?
HERRAMIENTAS
15 01.04.01 MOVILIZACIONDE CAMPAMENTO MAQUINARIA Y S/. 15,000.00 1 day? 1 day?
HERRAMIENTAS
16 1.05 TRAZO NIVEL Y REPLANTEO S/. 4,932.42 10 days
17 01.05.01 TRAZO Y REPLANTEO PRELIMINAR S/. 3,662.60 2 days 2 days
18 01.05.02 TRAZO Y REPLANTEO DURANTE ELPROCESO S/. 1,269.82 10 days 10 days
19 2 ESTRUCTURAS S/. 409,662.95 120 days?
20 2.01 MOVIMIENTO DE TIERRAS S/. 19,976.51 11 days?
21 02.01.01 CORTES S/. 0.00 1 day? 1 day?
22 02.01.02 EXCAVACION MASIVA CON EQUIPO PESADO S/. 2,337.49 2 days 2 days
23 02.01.03 NIVELACION DE TERRENO S/. 3,317.07 2 days
24 02.01.03.01 NIVELACION Y COMPACTADO S/. 3,317.07 2 days 2 days
25 02.01.04 EXCAVACIONES S/. 5,198.52 7 days
26 02.01.04.01 EXCAVACIONES EN TERRENO NORMAL S/. 5,198.52 7 days 7 days
27 02.01.05 ELIMINACION DEL MATERIAL EXCEDENTE S/. 9,123.43 1 day
28 02.01.05.01 ELIMINACION MASIVA DE MATERIAL CON CARGADOR S/. 9,123.43 1 day 1 day
+ VOLQUETE D = 25 km
29 2.02 OBRAS DE CONCRETO SIMPLE S/. 23,597.01 50 days
30 02.02.01 CIMIENTO CORRIDO S/. 3,681.90 6 days
31 02.02.01.01 CONCRETO CILOPEO PARA CIMIENTACION 1:10 + 30% S/. 3,681.90 6 days 6 days
P.G.
32 02.02.02 SOLADO E=0.10M S/. 215.38 2 days
33 02.02.02.01 CONCRETO SOLADO MEZCLA 1:12 S/. 215.38 2 days 2 days
CEMENTO-HORMIGON e=0.10 m.
34 02.02.03 SOBRECIMIENTO S/. 3,547.58 8 days
35 02.02.03.01 CONCRETO SOBRECIMIENTOS MEZCLA 1:8 + 25% P.M. S/. 1,812.83 2 days 2 days

36 02.02.03.02 ENCOFRADO DE SOBRECIMIENTO S/. 1,734.75 8 days 8 days


37 02.02.04 TRIBUNA S/. 16,152.15 17 days
38 02.02.04.01 RELLENO CON MATERIAL GRANULAR EN CAPAS DE 0.30 m
S/. 7,075.73 5 days 5 days
39 02.02.04.02 ENCOFRADO S/. 1,155.10 10 days 10 days
40 02.02.04.03 CONCRETO LOSAS f'c=175 kg/cm2 S/. 7,921.32 2 days 2 days
41 2.03 OBRAS DE CONCRETO ARMADO S/. 229,327.25 120 days?
42 02.03.01 ZAPATAS S/. 29,664.48 7 days
43 02.03.01.01 CONCRETO ZAPATAS f'c=210 kg/cm2 S/. 17,338.80 2 days 2 days
44 02.03.01.02 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 S/. 12,325.68 5 days 5 days
45 02.03.02 COLUMNAS S/. 79,364.59 68 days
46 02.03.02.01 CONCRETO COLUMNAS f'c=210 kg/cm2 S/. 18,116.65 6 days 6 days
47 02.03.02.02 ENCOFRADO EN COLUMNAS S/. 16,384.73 6 days 6 days
48 02.03.02.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 S/. 44,863.21 10 days 10 days
49 02.03.03 VIGAS S/. 90,265.08 13 days
50 02.03.03.01 CONCRETO VIGAS f'c=210 kg/cm2 S/. 18,213.77 4 days 4 days
51 02.03.03.02 ENCOFRADO DE VIGAS S/. 47,461.15 7 days 7 days
52 02.03.03.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 S/. 24,590.16 7 days 7 days
53 02.03.04 LOSA S/. 22,137.57 19 days
54 02.03.04.01 TRIBUNA S/. 22,137.57 19 days
55 02.03.04.01.01 CONCRETO LOSA f'c= 210 kg/cm2 S/. 6,234.81 2 days 2 days
56 02.03.04.01.02 ENCOFRADO LOSA S/. 2,616.73 7 days 7 days
57 02.03.04.01.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 S/. 13,286.03 10 days 10 days
58 02.03.05 ESCALERAS S/. 3,813.37 22 days
59 02.03.05.01 CONCRETO ESCALERAS f´c=210 kg/cm2 S/. 1,562.88 1 day 1 day
60 02.03.05.02 ENCOFRADO NORMAL EN ESCALERA S/. 954.46 3 days 3 days
61 02.03.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 S/. 1,296.03 5 days 5 days
62 02.03.06 TANQUE CISTERNA S/. 3,140.16 100 days?
63 02.03.06.01 EXCAVACIONES EN TERRENO NORMAL S/. 185.70 1 day? 1 day?
64 02.03.06.02 CONCRETO CISTENA f'c=210 kg/cm2 S/. 939.16 1 day? 1 day?
65 02.03.06.03 ENCOFRADO DE CISTERNA S/. 1,469.09 1 day? 1 day?
66 02.03.06.04 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 S/. 546.21 1 day? 1 day?
67 02.03.07 ROTURA DE PROBETAS S/. 552.00 20 days
68 02.03.07.01 PRUEBA DE ROTURA DE PROBETAS DE CONCRETO S/. 552.00 20 days 20 days
69 02.03.08 BANCAS DE MADERA S/. 390.00 2 days
70 02.03.08.01 BANCAS DE MADERA S/. 390.00 2 days 2 days
71 2.04 ESTRUCTURA METALICA S/. 136,762.18 28 days
72 02.04.01 TIJERAL DE ESTRUCTURA METALICA I S/. 48,546.06 10 days 10 days
73 02.04.02 TIJERAL DE ESTRUCTURA METALICA II S/. 12,525.72 10 days 10 days
74 02.04.03 CORREAS METALICAS S/. 1,536.86 5 days 5 days
75 02.04.04 COBERTURA CON CALAMINON S/. 40,247.41 5 days 5 days
76 02.04.05 SOLDADADURA EN ESTRUCTURA DE ACERO S/. 7,548.00 5 days 5 days
77 02.04.06 HABILITADO Y DOBLADO DE SECCIONES DE ACERO S/. 19,638.13 5 days 5 days
78 02.04.07 ENCUENTRO DE VIGA Y COLUMNA DE CONCRETO S/. 6,720.00 6 days 6 days
79 3 LOSA MULTIDEPORTIVA S/. 80,537.41 41 days?
80 3.01 MOVIMIENTO DE TIERRAS S/. 30,575.72 2 days
81 03.01.01 RELLENOS S/. 30,575.72 2 days
82 03.01.01.01 RELLENO CON MATERIAL GRANULAR EN CAPAS DE 0.30 m
S/. 30,575.72 2 days 2 days
83 3.02 OBRAS DE CONCRETO SIMPLE S/. 33,258.86 13 days
84 03.02.01 CONCRETO SIMPLE S/. 25,672.28 2 days
85 03.02.01.01 CONCRETO LOSAS f'c=175 kg/cm2 e=0.10m pulido S/. 25,672.28 2 days 2 days

86 03.02.02 ENCOFRADO Y DESENCOFRADO S/. 1,894.48 5 days


87 03.02.02.01 ENCOFRADO LOSA S/. 1,894.48 5 days 5 days
88 03.02.03 JUNTAS S/. 5,692.10 6 days
89 03.02.03.01 JUNTAS ASFALTICAS e=1" S/. 815.70 6 days 6 days
90 03.02.03.02 JUNTAS ASFALTICAS e=1/2" S/. 4,876.40 6 days 6 days
91 3.03 PINTURA S/. 9,226.83 3 days
92 03.03.01 PINTURA PERIMETRAL S/. 5,320.59 2 days 2 days
93 03.03.02 PINTURA ÁREA INTERNA S/. 3,906.24 3 days 3 days
94 3.04 ROTURA DE PROBETAS S/. 276.00 1 day?
95 03.04.01 PRUEBA DE ROTURA DE PROBETAS DE CONCRETO S/. 276.00 1 day? 1 day?
96 3.05 CARPINTERIA METALICA S/. 7,200.00 20 days
97 03.05.01 ACCESORIOS METALICOS S/. 7,200.00 20 days
98 03.05.01.01 ARCO METALICO DE FULBITO Y TABLERO DE BASQUET S/. 6,400.00 10 days 10 days
99 03.05.01.02 SUMINISTRO E INSTALACION DE POSTES CON RED PARA VOLEY
S/. 800.00
SEG/DISEÑO 10 days 10 days
100 04 ARQUITECTURA S/. 198,411.30 99 days?
101 4.01 MUROS Y TABIQUES DE ALBAÑILERIA S/. 68,427.56 27 days
102 04.01.01 MURO DE LADRILLO K.K. DE CABEZA 18 HUECOS PRIMERA PLANTA
S/. 39,386.89 15 days 15 days
103 04.01.02 MURO DE LADRILLO K.K. DE CABEZA 18 HUECOS SEGUNDA PLANTA
S/. 23,750.51 7 days 7 days
104 04.01.03 MURO DE LADRILLO K.K. DE SOGA 18 HUECOS PRIMERA PLANTA
S/. 5,290.16 5 days 5 days
105 4.02 REVOQUES Y REVESTIMIENTO S/. 44,100.83 34 days
106 04.02.01 TARRAJEO EN INTERIORES MUROS PRIMER NIVEL S/. 10,582.39 10 days 10 days
107 04.02.02 TARRAJEO EN INTERIORES MUROS SEGUNDO NIVEL S/. 4,657.25 6 days 6 days
108 04.02.03 TARRAJEO EN EXTERIORES MUROS PRIMER NIVEL S/. 3,074.40 6 days 6 days
109 04.02.04 TARRAJEO EN EXTERIORES MUROS SEGUNDO NIVEL S/. 1,860.06 3 days 3 days
110 04.02.05 TARRAJEO COLUMNAS S/. 7,918.59 3 days 3 days
111 04.02.06 TARRAJEO DE VIGAS S/. 13,576.06 3 days 3 days
112 04.02.07 VESTIDURAS DE DERRAME S/. 2,432.08 3 days 3 days

Tarea Hito Resumen Resumen del proyecto Agrupar por síntesis solo el comienzo solo fin Tarea crítica

DURACION DEL PROYECTO: 120 DIAS CALENDARIOS


CRONOGRAMA DE AVANCE FISICO DE OBRA: "CREACION DEL COLISEO CERRADO MUNICIPAL DEL DISTRITO DE PALCAMAYO - TARMA -JUNIN"
ID ITEM NOMBRE DEL PROYECTO M-1 COSTO DURACION M1 M2 M3 M4 M5
14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08
113 4.03 PISOS S/. 42,359.03 10 days?
114 04.03.01 RELLENO CON MATERIAL GRANULAR EN CAPAS DE 0.30 m S/. 15,728.31 1 day 1 day
115 04.03.02 CONTRAPISO DE 4" CONCRETO F'C=145KG/CM2 S/. 14,313.03 1 day? 1 day?
116 04.03.03 PISO DE 2" CONCRETO F'C=175KG/CM2. S/. 8,802.60 2 days 2 days
117 04.03.04 ENCHAPE DE PORCELANATO 30 X 30 cm EN PISO S/. 3,515.09 6 days 6 days
118 4.04 ZOCALOS Y CONTRAZOCALOS S/. 6,578.68 6 days
119 04.04.01 ZOCALO DE PORCELANATO DE 30X30 cm S/. 3,471.17 6 days 6 days
120 04.04.02 CONTRAZOCALO CON PORCELANATO DE 30 X 30 cm S/. 3,107.51 6 days 6 days
121 4.05 CARPINTERIA DE MADERA S/. 737.10 3 days
122 04.05.01 PUERTA DE MELAMINE S/. 737.10 3 days 3 days
123 4.06 CARPINTERIA METALICA S/. 2,100.34 6 days
124 04.06.01 VENTANA DE ALUMINIO S/. 150.34 2 days 2 days
125 04.06.02 PUERTA DE ALUMINIO S/. 1,250.00 2 days 2 days
126 04.06.03 PUERTAS DE PLANCHA METALICA S/. 700.00 2 days 2 days
127 4.07 MANPARAS DE ALUMINIO S/. 165.00 1 day?
128 04.07.01 MANPARAS DE ALUMINIO Y ACCESORIOS S/. 165.00 1 day? 1 day?
129 4.08 CERRAJERIA S/. 887.40 1 day?
130 04.08.01 BISAGRAS CAPUCHINA ALUMINIZADA DE 3 1/2 X 3 1/2" S/. 270.00 1 day? 1 day?
131 04.08.02 CERRADURA PARA PUERTA INGRESO S/. 190.40 1 day? 1 day?
132 04.08.03 CERRADURA PARA PUERTA DE BAÑOS E INTERIORES S/. 427.00 1 day? 1 day?
133 4.09 VIDRIOS CRISTALES Y ALUMINIO S/. 700.00 1 day?
134 04.09.01 ESPEJO CON BISEL S/. 700.00 1 day? 1 day?
135 4.1 PINTURAS S/. 20,978.85 6 days?
136 04.10.01 PINTURA VIGAS S/. 4,937.63 1 day? 1 day?
137 04.10.02 PINTURA COLUMNAS S/. 2,972.73 1 day? 1 day?
138 04.10.03 PINTURA EN MUROS INTERIORES S/. 9,304.94 2 days 2 days
139 04.10.04 PINTURA EN MUROS EXTERIORES S/. 3,122.28 3 days 3 days
140 04.10.05 PINTURA PUERTAS S/. 346.30 1 day? 1 day?
141 04.10.06 PINTURA EN DERRAMES S/. 294.97 1 day? 1 day?
142 4.11 VARIOS S/. 11,376.51 63 days?
143 04.11.01 LIMPIEZA PERMANENTE DE OBRA S/. 4,552.33 30 days 30 days
144 04.11.02 LIMPIEZA FINAL S/. 6,824.18 1 day? 1 day?
145 5 INSTALACIONES ELECTRICAS S/. 22,368.09 38 days?
146 5.01 CONEXIÓN A LA RED EXTERNA DE MEDIDORES S/. 750.00 1 day?

147 05.01.01 PAGO POR DERECHO DE ACOMETIDA A EMP. CONCESIONARIA S/. 750.00 1 day? 1 day?
148 5.02 SALIDA DE PUNTOS DE CONEXIÓN S/. 503.28 2 days
149 05.02.01 SALIDA PARA PUNTOS DE ILUMINACION S/. 207.90 2 days 2 days
150 05.02.02 SALIDA PARA TOMAC.DOBLE A PRUEB DE AGUA- PUESTA A TIERRA
S/. 119.04 2 days 2 days
151 05.02.03 SALIDA DE INTERRRUPTOR SIMPLE S/. 176.34 2 days 2 days
152 5.03 CANALIZACIONES Y TUBERIAS S/. 4,242.36 2 days?
153 05.03.01 TUBERIA PVC ø 40 MM (1 1/2" Ø) SAP (ELECTRICA) S/. 136.95 1 day? 1 day?
154 05.03.02 TUBERIA PVC ø 25 MM (1" Ø) SAP (ELECTRICA) S/. 1,837.29 1 day? 1 day?
155 05.03.03 TUBERIA PVC ø 20 MM (3/4" Ø) SAP (ELECTRICA) S/. 2,268.12 1 day? 1 day?
156 05.04 CONDUCTORES Y CABLES S/. 4,792.15 2 days?
157 05.04.01 CABLE N2XOH 2-1x25 MM2 S/. 319.31 1 day? 1 day?
158 05.04.02 CABLE N2XOH 2-1x10 MM2 S/. 635.93 1 day? 1 day?
159 05.04.03 CABLE NH-80/6 MM2 S/. 1,892.29 1 day? 1 day?
160 05.04.04 CABLE NH-80/4 MM2 S/. 1,944.62 1 day? 1 day?
161 05.05 TABLEROS ELECTRICOS S/. 1,031.28 1 day?
162 05.05.01 TABLERO ELECTRICO METALICO MONOFASICO DE ENGRAMPE S/. 1,031.28
DE 12 POLOS 1 day? 1 day?
163 5.06 DISPOSITIVOS DE MANIOBRA Y PROTECCION S/. 805.91 2 days?
164 05.06.01 INTERRUPTOR TERMOMAGNETICO DE REGULABLE 2X112-160S/.A 86.03 1 day? 1 day?
165 05.06.02 INTERRUPTOR TERMOMAGNETICO DE REGULABLE 2X60 A S/. 185.66 1 day? 1 day?
166 05.06.03 INTERRUPTOR TERMOMAGNETICO DE REGULABLE 2X30 A S/. 173.66 1 day? 1 day?
167 05.06.04 INTERRUPTOR TERMOMAGNETICO 2X20 A S/. 88.92 1 day? 1 day?
168 05.06.05 INTERRUPTOR TERMOMAGNETICO 2X25 A S/. 104.32 1 day? 1 day?
169 05.06.06 INTERRUPTOR DIFERENCIAL 25A 30mA, 220V S/. 167.32 1 day? 1 day?
170 05.07 ARTEFACTOS ELECTRICOS S/. 232.04 2 days
171 05.07.01 SPOT LIGT EQUIPO COMPLETO S/. 232.04 2 days 2 days
172 5.08 POZO A TIERRA S/. 1,763.44 1 day?
173 05.08.01 POZO DE TIERRA S/. 1,763.44 1 day? 1 day?
174 5.09 ARTEFACTOS DE ALUMBRADO S/. 6,424.03 2 days?
175 05.09.01 ARTEFACTO FLUORESCENTE CIRCULAR 1x32w (ADOSADO) S/. 540.45 1 day? 1 day?
176 05.09.02 ARTEFACTO PARA LUZ DE EMERGENCIA CON EQUIPO Y LAMPARA
S/. 2,950.88
DE 2x25 w 2 days 2 days
177 05.09.03 REFLECTORES HALOGENURO DE 400 W S/. 2,932.70 2 days 2 days
178 5.1 ACCESORIOS ELECTRICOS S/. 1,323.60 2 days?
179 05.10.01 CAJA DE PASO DE 100 MM X 100MM S/. 685.00 1 day? 1 day?
180 05.10.02 INTERRUPTOR SIMPLE S/. 75.00 1 day? 1 day?
181 05.10.03 TOMACORRIENTE BIPOLAR DOBLE CON TOMA A TIERRA S/. 462.00 2 days 2 days
182 05.10.04 TOMACORRIENTE BIPOLAR DOBLE A PRUEBA DE AGUA L/T S/. 101.60 2 days 2 days
183 05.11 PRUEBAS ELECTRICAS DE CIRCUITOS Y PUESTA EN SERVICIO S/. 500.00 2 days

184 05.11.01 CERTIFICADOS Y PROTOCOLO DE PRUEBAS: CONTINUIDAD,S/.


AISLAMIENTO,
500.00 RESISTIVIDAD DE PUESTA A TIERRA
2 days 2 days
185 6 INSTALACIONES SANITARIAS S/. 18,260.59 17 days?
186 6.01 SALIDAS DE DESAGUE S/. 1,086.37 3 days?
187 06.01.01 SALIDA DESAGUE DE PVC-SAL 4" S/. 605.92 2 days 2 days
188 06.01.02 SALIDA DESAGUE DE PVC SAL 2" S/. 370.11 2 days 2 days
189 06.01.03 SALIDA VENTILACION DE PVC-SAL 2" S/. 110.34 1 day? 1 day?
190 6.02 REDES DE DISTRIBUCION S/. 1,653.47 2 days
191 06.02.01 TUBERIA DE PVC SAL 4" DE DESAGUE S/. 446.38 2 days 2 days
192 06.02.02 TUBERIA DE PVC SAL 2" DE DESAGUE S/. 1,207.09 2 days 2 days
193 6.03 ACCESORIOS DE REDES DE DESAGUE S/. 479.95 1 day?
194 06.03.01 CODO PVC SAL 2"X45° S/. 96.91 1 day? 1 day?
195 06.03.02 CODO PVC SAL 4"X45° S/. 23.62 1 day? 1 day?
196 06.03.03 YEE PVC SAL 4" X 2" S/. 108.66 1 day? 1 day?
197 06.03.04 YEE PVC SAL 2" S/. 122.21 1 day? 1 day?
198 06.03.05 CODO PVC SAL 2"X90° S/. 68.67 1 day? 1 day?
199 06.03.06 TEE PVC SAL 2" S/. 59.88 1 day? 1 day?
200 06.04 ADITAMENTO VARIOS S/. 312.60 1 day?
201 06.04.01 SUMIDERO DE BRONCE ROSCADO 2" S/. 157.98 1 day? 1 day?
202 06.04.02 REGISTRO DE BRONCE 4" S/. 101.94 1 day? 1 day?
203 06.04.03 SOMBRERO DE VENTILACION 2" S/. 52.68 1 day? 1 day?
204 6.05 CÁMARA DE INSPECION S/. 275.67 1 day?
205 06.05.01 CAJAS DE REGISTRO DE DESAGUE 12" x 24" S/. 275.67 1 day? 1 day?
206 6.06 SISTEMA DE AGUA FRÍA Y CONTRAINCENDIOS S/. 14,452.53 9 days?

207 06.06.01 SALIDAS DE AGUA FRIA S/. 14,452.53 9 days?


208 06.06.01.01 SALIDA DE AGUA FRIA TUBERIA PVC - 1/2" S/. 1,003.51 1 day? 1 day?
209 06.06.01.02 RED DE DISTRIBUCION CON TUBERIA DE PVC DE 1/2" S/. 2,590.67 1 day? 1 day?
210 06.06.01.03 ACCESORIOS DE REDES 1/2" S/. 697.81 2 days?
211 06.06.01.03.01 CODO PVC SAL 1/2"X90° S/. 165.23 1 day? 1 day?
212 06.06.01.03.02 TEE PVC SAL 1/2" S/. 297.92 1 day? 1 day?
213 06.06.01.03.03 BATERIA PVC 15mm (1/2") P/C.D. TIPO SEDAPAL INC. NIPLE
S/. 78.65
P/MED 1 day? 1 day?
214 06.06.01.03.04 UNION PR PVC SAP P/AGUA DE 15mm (1/2") S/. 9.25 1 day? 1 day?
215 06.06.01.03.05 CAJA TERMOPLASTICA P/MEDIDOR DE AGUA C/SOLADO S/. 88.78 1 day? 1 day?
216 06.06.01.03.06 MARCO Y TAPA TERMOPLASTICA P/CAJA DE AGUA S/. 57.98 1 day? 1 day?
217 06.06.01.04 VALVULAS S/. 1,444.60 3 days?
218 06.06.01.04.01 VALVULAS DE COMPUERTA DE BRONCE DE 1/2" S/. 328.60 1 day? 1 day?
219 06.06.01.04.02 GRIFERIA DE BRONCE ø 1/2" S/. 696.00 1 day? 1 day?
220 06.06.01.04.03 GRIFERIA DE BRONCE ø 1/2"-DUCHA S/. 250.00 1 day? 1 day?
221 06.06.01.04.04 REGADERA PARA DUCHA ø 1/2" S/. 170.00 1 day? 1 day?
222 06.06.01.05 APARATOS SANITARIOS S/. 6,125.86 1 day?
223 06.06.01.05.01 INODORO DE LOZA BLANCO TANQUE BAJO (INCLUDO S/.ACCESORIOS
2,558.22 COMPLETOS)
1 day? 1 day?
224 06.06.01.05.02 LAVATORIO DE LOSA SIMPLE DE 20 X 18” CONTROL DES/.MANO
2,772.40
(INCLUIDO ACCESORIOS
1 day? COMPLETOS) 1 day?
225 06.06.01.05.03 URINARIO DE LOSA (INCLUIDO ACCESORIOS COMPLETOS) S/. 795.24 1 day? 1 day?
226 06.06.01.06 TANQUE ELEVADO Y ACCESORIOS S/. 2,590.08 1 day?
227 06.06.01.06.01 TANQUE ELEVADO CAP 2500.TRS S/. 2,590.08 1 day? 1 day?
228 FIN S/. 0.00 0 days

Tarea Hito Resumen Resumen del proyecto Agrupar por síntesis solo el comienzo solo fin Tarea crítica

DURACION DEL PROYECTO: 120 DIAS CALENDARIOS