Project Daily Report

PMC-FM-CON-1507 Local Roads & Drainage Programme Revision: 0 Date: Oct 2016
Document Owner:: Anwar Maharmeh Authorised by: Mike Iverson Date: Oct 2016

Roads & Infrastructure in Government Residential


Project Name: Date : 10-June-2018
Division in North of Al Wukair (DS131)

Project No: (DS131)

GEC: Parsons International Limited (PIL)

Contractor: Boom-Lotus Joint Venture (JV)

Week No. 147 Report No.

Details of Project/Contract
Roads & Infrastructure in Government Residential
Project Title: Area :
Division in North of Al Wukair (DS131)
Project ID: IA 14/15C057ST

Owner: Public Works Authority (PWA)

PMC: Parsons Brinckerhoff (PB)

GEC: Parsons International Limited (PIL)

Contractor: Boom-Lotus JV

Contract Start Date: 07-Jun-2015 Duration of Contract (Days): 510

Contract Completion Date(Original): 28 Oct. 2016

Contract Completion Date(With Extension): 14-Jul-2018 Duration of Extension (Days): 231

Weather Details

a) Sunny- Maximum Temp.=45º C ; Minimum Temp.= 40º C

b)

Details of Project Progress Week No.

a)

b)

c)

d)

Details of Current Activities on Site

A) Bitumen primer for S1-1/26, S1-1/26/1, S1-1/26/2.

b) Casting concrete for MH S1-1 3rd lift wall.

c) Shaft excavation on hold MH, S1-1/8, S1-1/9, S1-1/10, S1-1/22, S1-1/19, S1-1/18 and S1-1/20. (depth 8m reached)

d) Shuttering for blinding S1-1B & SH8/25/1A/4.

e) Excavation for flow meter & surge vessel chamber.

f) Diving of micro-tunnelling boring machine from S1-1/23 to S1-1/24 (progress length 39m)

g) Casting concrete blinding for S1-1/26/5 & S1-1/26/6.

THIS DOCUMENT IS UNCONTROLLED ONCE PRINTED - Last printed 0/0/0000 0:00:00 AM


Page 1 of 3
Project Daily Report
PMC-FM-CON-1507 Local Roads & Drainage Programme Revision: 0 Date: Oct 2016
Document Owner:: Anwar Maharmeh Authorised by: Mike Iverson Date: Oct 2016

h) Shaft excavation on going S1-1/6 completed.

I) Shaft excavation on going S1-1/7 (up to 12.8m depth).

j) Rocker pipe connections for S1-1

k) Preparation for GRP liner In wet well.

l) Excavation for house connection (pumping station).

Details of Submittals/Approvals

a)

b)

c)

Details of Noteworthy Issues on Site

Utilities

a)

b)

c)

Safety

No of Safety Incidents 0

No of Environmental Incidents 0

No of Observations (Positive / Negative) 11

Safety Meetings / Training 0

Other

a)

b)

c)

Traffic Management

a)

b)

c)

Quality/Testing

a) No issues

b)

c)

THIS DOCUMENT IS UNCONTROLLED ONCE PRINTED - Last printed 0/0/0000 0:00:00 AM


Page 2 of 3
Project Daily Report
PMC-FM-CON-1507 Local Roads & Drainage Programme Revision: 0 Date: Oct 2016
Document Owner:: Anwar Maharmeh Authorised by: Mike Iverson Date: Oct 2016

Stakeholder

a)

b)

c)

Commercial/Contractual

a)

b)

c)

d)

Communication with Client

a)

b)

c)

Communication with ADM

a)

b)

c)

Name: Name:

Designation: Designation:

Date: Date:

Key Persons of the Project & Contact Details

Organization Name Contact Number

PWA

PB
(Area Delivery Manager)
GEC
(Senior Resident Engineer)
Contractor
(Project Manager)

THIS DOCUMENT IS UNCONTROLLED ONCE PRINTED - Last printed 0/0/0000 0:00:00 AM


Page 3 of 3