Você está na página 1de 16

LABORATORIUM HIDROLIKA

Fakultas Teknik
Jurusan Teknik Sipil
Universitas Muhammadiyah Sumatera Utara
Jl. Muchtar Basri, No. 3 Medan

PENGALIRAN DI ATAS RECTANGULAR NOTCH

Volume Waktu H Q
No
(L) (detik) (mm) (mm3/det)
H3/2 Cd Q2/3 Log Q Log H

1 6 229.10 8 26189.436927106 22.627 0.413 881.896 4.418 0.903

2 6 179.81 11 33368.555697681 36.483 0.326 1036.474 4.523 1.041

3 6 65.82 14 91157.702825889 52.383 0.621 2025.484 4.960 1.146

4 6 50.16 17 119617.22488038 70.093 0.609 2427.704 5.078 1.230

5 6 35.66 20 168255.74873808 89.443 0.672 3047.754 5.226 1.301

Lebar weir = 30 mm Medan, 19 Desember 2017


Pengambilan Data Oleh :
Group : 6
Diketahui Oleh: 1. Retno Friana Dewi
Asisten Laboratorium 2. Nizar Fuadi
3. Rahmad Hariyadi
4. Puji Ramazana
5. Fahmi Idris
6. Jefri Rahmad Fadhil
7. Sapto Prabowo
(Dila Syafira zay, ST )
LABORATORIUM HIDROLIKA
Fakultas Teknik
Jurusan Teknik Sipil
Universitas Muhammadiyah Sumatera Utara
Jl. Muchtar Basri, No. 3 Medan

PENGALIRAN DI ATAS VEE NOTCH

Volume Waktu H Q
No H5/2 Cd Q2/5 Log Q Log H
(L) (detik) (mm) (mm3/det)

1 4 98.38 10 40658.670 316.228 1.721 69.769 4.609 1.000

2 4 48.31 14 82798.592 733.365 1.511 92.728 4.918 1.146

3 4 46.69 18 85671.450 1374.616 0.834 94.001 4.933 1.255

4 4 31.24 22 128040.973 2270.161 0.755 110.393 5.107 1.342

5 4 25.45 26 157170.923 3446.937 0.610 119.825 5.196 1.415

Lebar weir = 30 mm

Diketahui Oleh:
Asisten Laboratorium Medan, 19 Desember 2017
Pengambilan Data Oleh :
Group : 6
1. Retno Friana Dewi
2. Nizar Fuadi
(Dila Syafira Zay, ST ) 3. Rahmad Hariyadi
4. Puji Ramazana
5. Fahmi Idris
6. Jefri Rahmad Fadhil
7. Sapto Prabowo
LABORATORIUM HIDROLIKA
Fakultas Teknik
Jurusan Teknik Sipil
Universitas Muhammadiyah Sumatera Utara
Jl. Muchtar Basri, No. 3 Medan

PENGALIRAN DI ATAS TRAPEZOIDAL NOTCH

Volume Waktu H Q
No H5/2 H3/2 Cd Q2/5 Log Q Log H
(L) (detik) (mm) (mm3/det)

1 6 83.49 7 71864.894 129.642 18.520 0.474 87.621 4.857 0.845


2 6 72.40 10 82872.928 316.228 31.623 0.312 92.761 4.918 1.000
3 6 48.14 13 124636.477 609.338 46.872 0.308 109.209 5.096 1.114
4 6 31.67 16 189453.742 1024.000 64.000 0.334 129.122 5.278 1.204
5 6 20.18 19 297324.083 1573.563 82.819 0.396 154.629 5.473 1.279

Lebar weir = 30 mm

Medan, 19 Desember 2017


Pengambilan Data Oleh :
Asisten Group : 6
1. Retno Friana Dewi
2. Nizar Fuadi
3. Rahmad Hariyadi
4. Puji Ramazana
(Dini Sarah Zaivina, ST) 5. Fahmi Idris
6. Jefri Rahmad Fadhil
7. Sapto Prabowo
LABORATORIUM HIDROLIKA
Fakultas Teknik
Jurusan Teknik Sipil
Universitas Muhammadiyah Sumatera Utara
Jl. Muchtar Basri, No. 3 Medan

PENGALIRAN DI ATAS PENAMPANG SEMI CIRCLE

Volume Waktu H Q
No (L) (detik) (mm) (mm3/det) H5/2 H3/2 Cd Q2/5 Log Q Log H r

1 5 114.10 6 43821.209 88.182 14.697 0.8634 1242.957 4.642 0.778 31.5


2 5 108.10 8 46253.469 181.019 22.627 0.5213 1288.535 4.665 0.903 31.5
3 5 48.70 10 102669.405 316.228 31.623 0.7560 2192.606 5.011 1.000 31.5
4 5 43.30 12 115473.441 498.831 41.569 0.6015 2371.309 5.062 1.079 31.5
5 5 33.00 14 151515.152 733.365 52.383 0.5917 2842.087 5.180 1.146 31.5

Lebar weir = 30 mm

Medan, 29 Nopember 2015


Pengambilan Data Oleh :
Asisten Group : 22
1. Azmi Arief
2. Ilman Adly
3. Anggi Syaputra
4. Indra Mulia Matondang
( Latifah Hanum, ST ) 5. Singgih Purnomo
6. M. Iqbal Febriandi
LABORATORIUM HIDROLIKA
Fakultas Teknik
Jurusan Teknik Sipil
Universitas Muhammadiyah Sumatera Utara
Jl. Muchtar Basri, No. 3 Medan
PENGALIRAN DI ATAS GRAVEL BED

RUMPUT
Q Q V A Y R I
No n
(L/hr) (cm3/det) (cm/det) (bxY) (mm) (cm) (%)
1 3300 916.667 130.208 7.040 1.1 0.819 0.4000 0.0485
2 3300 916.667 143.229 6.400 1 0.762 0.6400 0.0558
3 3300 916.667 159.144 5.760 0.9 0.702 0.8800 0.0588

PASIR
Q Q V A Y R I
No n
(L/hr) (cm3/det) (cm/det) (bxY) (mm) (cm) (%)

KERIKIL
Q Q V A Y R I
No n
(L/hr) (cm3/det) (cm/det) (bxY) (mm) (cm) (%)
1 3300 916.667 143.229 6.400 1.0 0.762 0.4000 0.0441
2 3300 916.667 159.144 5.760 0.9 0.702 0.6400 0.0501
3 3300 916.667 179.036 5.120 0.8 0.640 0.8800 0.0521

Lebar weir = 64 mm

Medan, 19 Desember 2017


Asisten Pengambilan Data Oleh :
Group : 6
1. Retno Friana Dewi
2. Nizar Fuadi
(KHAIDIR AFFANDI BATUBARA, S.T) 3. Rahmad Hariyadi
4. Puji Ramazana
5. Fahmi Idris
6. Jefri Rahmad Fadhil
7. Sapto Prabowo
LABORATORIUM HIDROLIKA
Fakultas Teknik
Jurusan Teknik Sipil
Universitas Muhammadiyah Sumatera Utara
Jl. Muchtar Basri, No. 3 Medan

HYDROSTATIC PREASURE

( IMMERGED PLANE SURFACE ) / TERBENAM PENUH

Pengisian Tangki Pengosongan Tangki Rata-Rata


NO Berat Air Tinggi Air Berat Air Tinggi Air Berat Air Tinggi Air Xca Xcr
(m) (y) (m) (y) (m) (y)
1 250 117 250 115 250 116 1512.87 194.23
2 265 121 265 120 265 120.5 1486.10 194.20
3 280 124 280 123 280 123.5 1494.86 194.18
4 295 129 295 128 295 128.5 1454.76 194.14
5 310 132 310 131 310 131.5 1459.78 194.12
6 325 135 325 136 325 135.5 1441.39 194.10
7 340 140 340 140 340 140 1412.54 194.07

Medan, 19 Desember 2017


Pengambilan Data Oleh :
Asisten Group : 6
1. Retno Friana Dewi
2. Nizar Fuadi
3. Rahmad Hariyadi
4. Puji Ramazana
(Brenda Ira Clara, ST) 5. Fahmi Idris
6. Jefri Rahmad Fadhil
7. Sapto Prabowo
LABORATORIUM HIDROLIKA
Fakultas Teknik
Jurusan Teknik Sipil
Universitas Muhammadiyah Sumatera Utara
Jl. Muchtar Basri, No. 3 Medan
HYDROSTATIC PREASURE

( PARTIALLY SUBMERGED PLANE SURFACE )

Pengisian Tangki Pengosongan Tangki Rata-Rata


NO Berat Air Tinggi Berat Air Tinggi Berat Air Tinggi Y2 m/Y2 Xca Xct M/Y
(m) Air (y) (m) Air (y) (m) Air (y)

1 65 44 65 45 65 44.5 1980.25 0.0328 0.267 194.852 1.461


2 80 52 80 53 80 52.5 2756.25 0.0290 0.236 194.825 1.524
3 95 59 95 59 95 59 3481.00 0.0273 0.222 194.803 1.610
4 110 65 110 65 110 65 4225.00 0.0260 0.212 194.783 1.692
5 125 70 125 70 125 70 4900.00 0.0255 0.208 194.767 1.786
6 140 76 140 76 140 76 5776.00 0.0242 0.197 194.747 1.842
7 155 80 155 80 155 80 6400 0.0242 0.197 194.733 1.938

Lebar Weir = 30 mm

Medan, 29 Nopember 2015


Pengambilan Data Oleh :
Asisten Group : 22
1. Azmi Arief
2. Ilman Adly
3. Anggi Syaputra
4. Indra Mulia Matondang
(Alvisyahri Amanda) 5. Singgih Purnomo
6. M. Iqbal Febriandi
LABORATORIUM HIDROLIKA
Fakultas Teknik
Jurusan Teknik Sipil
Universitas Muhammadiyah Sumatera Utara
Jl. Muchtar Basri, No. 3 Medan

SPESIFIK ENERGI - KEDALAMAN KRITIS

A1
Yg Yo Y1 Q Q Ao Vo V1
NO. Eo E1 Yc Emin Vc Fr NF
(mm) (mm) (mm) (L/hr) (mm3/s) (bxYo) (Q/Ao) (Q/A1)
(bxY1)
1 5 45 5 2100 583333 2880 320 202.546 1822.917 47.091 174.369 20.383 30.575 447.166 8.231 1.00
2 7 45 8 2500 694444 2880 512 241.127 1356.337 47.963 101.764 22.895 34.343 473.924 4.842 1.00
3 9 45 9 2800 777778 2880 576 270.062 1350.309 48.717 101.932 24.692 37.038 492.170 4.544 1.00
4 11 45 10 3100 861111 2880 640 298.997 1345.486 49.557 102.270 26.426 39.639 509.154 4.296 1.00
5 13 45 11 3400 944444 2880 704 327.932 1341.540 50.481 102.729 28.104 42.157 525.076 4.084 1.00

Lebar weir = 64 mm

Medan, 19 Desember 2017


Pengambilan Data Oleh :
Asisten Group : 6
1. Retno Friana Dewi
2. Nizar Fuadi
3. Rahmad Hariyadi
4. Puji Ramazana
(AZMI ARIEF, S.T) 5. Fahmi Idris
6. Jefri Rahmad Fadhil
7. Sapto Prabowo
LABORATORIUM HIDROLIKA
Fakultas Teknik
Jurusan Teknik Sipil
Universitas Muhammadiyah Sumatera Utara
Jl. Muchtar Basri, No. 3 Medan
BROAD CRESTED WEIR

No. dc du H Q Q Q H 3/2 h
log H log Q Cd
(mm) (mm) (mm) (L/hr) (L/s) (mm3/s) (mm) (mm)
1 5 95 9 1600 0.444 444444.444 27.000 0.954 3.204 90 0.543
2 7 98 12 1800 0.500 500000.000 41.569 1.079 3.255 90 0.397
3 8 101 15 2000 0.556 555555.556 58.095 1.176 3.301 90 0.315
4 10 104 18 2300 0.639 638888.889 76.368 1.255 3.362 90 0.276
5 11 107 21 2600 0.722 722222.222 96.234 1.322 3.415 90 0.248

Lebar Weir = 64 mm
Medan, 19 Desember 2017
Pengambilan Data Oleh :
Group : 6
Asisten 1. Retno Friana Dewi
2. Nizar Fuadi
3. Rahmad Hariyadi
4. Puji Ramazana
(KHAIDIR AFFANDI BATUBARA, S.T) 5. Fahmi Idris
6. Jefri Rahmad Fadhil
7. Sapto Prabowo
LABORATORIUM HIDROLIKA
Fakultas Teknik
Jurusan Teknik Sipil
Universitas Muhammadiyah Sumatera Utara
Jl. Muchtar Basri, No. 3 Medan

DEBIT DI BAWAH SLUICE GATE

Yg Yo Y1 Yg/Yo Q Q Ao A1 Vo V1
NO. Eo E1 Cd
(mm) (mm) (mm) (mm) (L/hr) (mm3/s) (bxYo) (bxY1) (Q/Ao) (Q/A1)
1 5 45 5 0.111 2100 583333.3 2880 320 202.546 1822.917 47.091 174.369 1.940
2 7 45 8 0.156 2500 694444.4 2880 512 241.127 1356.337 47.963 101.764 1.650
3 9 45 9 0.200 2800 777777.8 2880 576 270.062 1350.309 48.717 101.932 1.437
4 11 45 10 0.244 3100 861111.1 2880 640 298.997 1345.486 49.557 102.270 1.302
5 13 45 11 0.289 3400 944444.4 2880 704 327.932 1341.540 50.481 102.729 1.208

Lebar weir (mm) = 64


Medan, 19 Desember 2017
Pengambilan Data Oleh :
Group : 6
Asisten 1. Retno Friana Dewi
2. Nizar Fuadi
3. Rahmad Hariyadi
4. Puji Ramazana
5. Fahmi Idris
6. Jefri Rahmad Fadhil
(AZMI ARIEF, S.T) 7. Sapto Prabowo
LABORATORIUM HIDROLIKA
Fakultas Teknik
Jurusan Teknik Sipil
Universitas Muhammadiyah Sumatera Utara
Jl. Muchtar Basri, No. 3 Medan

HYDRAULIC JUMP DI ATAS MERCU

NO. Yg(mm) Yo Y1 Y3 Q Q A1 A3 V1 V3 V12/g.Y1


E1 E3 Yc AH/y1 y3/y1
(mm) (mm) (mm) (L/hr) (mm3/s) (bxY1) (bxY3) (Q/A1) (Q/A3)
1 9 192 6 21 2000 555555.556 384 1344 1446.75926 413.360 112.683 29.709 35.561 19.731 1.1161 3.5
2 10.5 194 7 22.5 2200 611111.1 448 1440 1,364.087 424.383 101.839 31.679 27.097 21.025 0.8444 3.214
3 12 195 8 24.5 2400 666666.7 512 1568 1,302.083 425.170 94.413 33.714 21.603 22.281 0.7162 3.063
4 13.5 197 9 25.5 2600 722222.2 576 1632 1,253.858 442.538 89.130 35.482 17.807 23.502 0.5437 2.833
5 15 199 10 28.5 2800 777777.8 640 1824 1,215.278 426.413 85.275 37.767 15.055 24.692 0.5554 2.85
6

Lebar weir = 64 mm

ASISTEN Medan, 19 Desember 2017


Pengambilan Data Oleh :
Group : 6
1. Retno Friana Dewi
2. Nizar Fuadi
(Azmi Arief, ST) 3. Rahmad Hariyadi
4. Puji Ramazana
5. Fahmi Idris
6. Jefri Rahmad Fadhil
7. Sapto Prabowo
LABORATORIUM HIDROLIKA
Fakultas Teknik

Jurusan Teknik Sipil

Universitas Muhammadiyah Sumatera Utara


Jl. Muchtar Basri, No. 3 Medan

HIDRAULIC JUMP DI BAWAH PINTU

NO. Yg(mm) Yo Y1 Y3 Q Q A1 A3 V1 V3 V12/g.Y1


E1 E3 y3/y1 AH/y1 Yc
(mm) (mm) (mm) (L/hr) (mm3/s) (bxY1) (bxY3) (Q/A1) (Q/A3)
1 5 45 5 20.5 2100 583333.3 320 1312 1822.917 444.614 174.369 30.576 67.748 4.100 1.817 20.383
2 7 45 8 24.5 2500 694444.4 512 1568 1356.337 442.885 101.764 34.497 23.441 3.063 0.716 22.895
3 9 45 9 27.5 2800 777777.8 576 1760 1350.309 441.919 101.932 37.454 20.652 3.056 0.711 24.692
4 11 45 10 31 3100 861111.1 640 1984 1345.486 434.028 102.270 40.601 18.454 3.100 0.747 26.426
5 13 45 11 32 3400 944444.4 704 2048 1341.540 461.155 102.729 42.839 16.678 2.909 0.598 28.104
Lebar weir = 64 mm

Medan, 19 Desember 2017


Pengambilan Data Oleh :
Group : 6
Asisten 1. Retno Friana Dewi
2. Nizar Fuadi
3. Rahmad Hariyadi
4. Puji Ramazana
5. Fahmi Idris
6. Jefri Rahmad Fadhil
(AZMI ARIEF, S.T) 7. Sapto Prabowo
LABORATORIUM HIDROLIKA
Fakultas Teknik
Jurusan Teknik Sipil
Universitas Muhammadiyah Sumatera Utara
Jl. Muchtar Basri, No. 3 Medan

HIDRAULIC JUMP DI ATAS MERCU

NO. Yg Yo Y1 Y3 Q Q A1 A3 V1 V3 E1 E3 V12/g.Y1 Y3/Y1 ∆H/Y1 Yc


(mm) (mm) (mm) (mm) (L/hr) (mm3/s) (bxY1) (bxY3) (Q/A1) (Q/A3)

1 3 184 2 12 600 166666.7 128 768 1302.083 217.014 88.413 14.400 86.413 6.000 5.208 8.842
2 7 187 4 14 700 194444.4 256 896 759.5486 217.014 33.404 16.400 14.702 3.500 1.116 9.799
3 11 192 5 17 1000 277777.8 320 1088 868.0556 255.310 43.406 20.322 15.362 3.400 1.016 12.430
4 15 198 8 24 1700 472222.2 512 1536 922.309 307.436 51.356 28.817 10.839 3.000 0.667 17.705
5 19 205 10 32 2200 611111.1 640 2048 954.8611 298.394 56.471 36.538 9.294 3.200 0.832 21.025
6 23 209 12 34 3000 833333.3 768 2176 1085.069 382.966 72.009 41.475 10.001 2.833 0.544 25.855

Lebar weir = 64 mm

ASISTEN Medan, 29 Nopember 2015


Pengambilan Data Oleh :
Group : 22
1. Azmi Arief
2. Ilman Adly
(Dedi Wahyu Purwanto) 3. Anggi Syaputra
4. Indra Mulia Matondang
5. Singgih Purnomo
6. M. Iqbal Febriandi
LABORATORIUM HIDROLIKA
Fakultas Teknik
Jurusan Teknik Sipil
Universitas Muhammadiyah Sumatera Utara
Jl. Muchtar Basri, No. 3 Medan

HIDRAULIC JUMP DI BAWAH PINTU

NO. Yg Yo Y1 Y3 Q Q A1 A3 V1 V3 E1 E3 V12/g.Y1 Y3/Y1 ∆H/Y1 Yc


(mm) (mm) (mm) (mm) (L/hr) (mm3/s) (bxY1) (bxY3) (Q/A1) (Q/A3)

1 5 60 4 21 1300 361111.1 256 1344 1410.59 268.684 105.415 24.679 50.708 5.250 3.656 14.805
2 10 60 8 30 2350 652777.8 512 1920 1274.957 339.988 90.850 35.892 20.712 3.750 1.386 21.970
3 15 60 13 34 3000 833333.3 832 2176 1001.603 382.966 64.132 41.475 7.866 2.615 0.403 25.855
4 20 60 15 40 3950 1097222.2 960 2560 1142.94 428.602 81.581 49.363 8.877 2.667 0.434 31.059
5 25 60 19 44 4500 1250000.0 1216 2816 1027.961 443.892 72.858 54.043 5.669 2.316 0.246 33.879
6 30 60 22 49 5200 1444444.4 1408 3136 1025.884 460.601 75.641 59.813 4.876 2.227 0.207 37.307

Lebar weir = 64 mm

ASISTEN Medan, 29 Nopember 2015


Pengambilan Data Oleh :
Group : 22
1. Azmi Arief
2. Ilman Adly
(M. Iqbal) 3. Anggi Syaputra
4. Indra Mulia Matondang
5. Singgih Purnomo
6. M. Iqbal Febriandi

Você também pode gostar