Escolar Documentos
Profissional Documentos
Cultura Documentos
Page 1 Page 2
10. CHEMICAL SYSTEMS 93 14.2.1 General Design Criteria 117
12.1 Screenings 105 16.1.3 Pipe size and pump capacity for 400 MLD 137
12.2 Pre-Treatment Waste Water 105 16.1.4 Pipe size and pump capacity for 150 MLD 140
Page 3 Page 4
20. COMMISSIONING STRATEGY 161 24.2.2 Procedures 184
20.1 RO Plant Overall Commissioning Strategy 161 24.2.3 Continuous Supervision and Tracking 184
20.2 Seawater Lift Pump Station 163 24.3 Supervision with SCADA System 185
20.3 Pre-Treatment 163 24.3.1 Reports 186
Page 5 Page 6
27.5 Consumables 201
31. INCIDENT MANAGEMENT PLAN 209 – TSS measured in July/August 2013 on the seabed offshore from Perur was, on
31.1 Identification of an Emergency Situation 209 average, 73.3 mg/L, and 48.7 mg/L at the surface.
31.2 Alert and Information Transmission 210
31.3 Final Incident Assessment Report 210
– The specification for the Nemmeli desalination plant nominates a design range for
32. SAFETY, HEALTH, WORKING CONDITIONS AND ENVIRONMENT 211 TSS of 50 mg/L to 200 mg/L. By comparison, the desalination plant for Sydney is
32.1 Safety, Health and Working Conditions Considered in the Plant’s Design 211 designed for TSS of 7 mg/L.
32.2 General Principles of Health and Safety for Plant Operation 211
32.3 Health and Safety 212
– Intake water quality data from Nemmeli plant was provided for the period from and
33. THE QUALITY APPROACH 214 including May 2013 to early December 2013. The data shows poor water quality
33.1 Quality Objectives and Approach 214 on a number of occasions as evidenced by frequent spikes in turbidity.
33.2 Certification 214
34. PROJECT FINANCIALS 216 – There is strong evidence that jelly fish are frequently in abundance along the
34.1 Capital Cost 216 Chennai coast and have caused considerable nuisance in power station intakes.
34.2 Operational Cost 220
– In literature, algal blooms have been documented along both the west and east
coasts of India. It can be expected that algal blooms will impact upon a
desalination plant at Perur from time to time.
Page 7 Page 8
is significant and the annual net drift takes place in a northerly direction.
– Fine screens will be provided before the sea water pumps to capture the jelly fish
3. Seabed offshore from Perur and minimise the chance of breaking up the jelly fish, which would make it harder
– The nearshore seabed, up to 1,500 m offshore, is comprised of ‘sandy clay’ and to remove jelly fish particles.
‘clayey sand’. At a distance of 500 m offshore the sediment cover to the
acoustic basement is around 6 m, and at 1,200 m offshore the cover is around 7 – The fine screens will be provided with 3 mm apertures, targeting jelly fish.
m. These conditions should be suitable for the construction of intake and .
outfall pipelines by pipe jacking. Twin intakes extending 1,200 m offshore at a – DAF process may be capable of handling 10-20 mg/L of TSS, but would not be
depth of 11 m below chart datum are under consideration. An outfall extending capable of handling greater than 75 mg/L of TSS. For this reason Lamella
700 m offshore at a depth of 7.5 m below chart datum is under consideration. settlers, preceded by coagulation-flocculation and polymer dosing have been
suggested. It is expected that the Lamella settlers will significantly reduce the
– The survey identifies exposed rock some 1,200 m offshore from the southern TSS, but will be only partially successful in removing the larvae, algae and jelly
end of the Perur site. This rock outcrop should be suitable for the construction fish particles off neutral buoyancy; this material should be removed effectively by
of an intake tunnel by tunnel boring machine, and then the construction of drill the following DAF and filtration processes.
down intakes from the rock outcrop. The rock outcrop at 1,200 m offshore is
around 10.5 m below chart datum. – A DAF loading rate of 8 m/hr has been nominated, when operating with 20%
recycle. The nominated recycle rate is high, cf 10 to 12 m/hr at other plants, so
– The candidate intakes for Perur are located about approximately 1,000 m to as to be able to handle the anticipated high solids loading rate. Lower recycle
1,200 m northeast of the Nemmeli outfall. Modelling is required to quantify any rates will be available to the operator when the water quality is good.
impact of the Nemmeli and Perur outfalls on the Perur intake, prior to the
finalisation of the design of the intakes and outfall. – The DAF will be followed by dual media filters. The filter loading rate is the same
as for the DAF: 8 m/hr. The filters are to operate as ‘in depth’ filters, with the
material being removed being held in the pores of the filter media. For this
Pre-treatment Processes reason the filter media is deep to store the material and have reasonable periods
– Notwithstanding the paucity of water quality data offshore from Perur, high levels between backwashing. Dual media filters have been nominated. The sand will
of TSS, algae and jelly fish are expected to be drawn in at the intake to the be 900 mm deep, ES 0.6 mm. The anthracite will be 900 mm deep, ES 1.43 mm
plant, either constantly or cyclically, and the pre-treatment plant must be
designed to maintain a high quality feed to the desalination plant, over the long RO Plant Redundancy
term.
Each train will be subject to planned and unplanned shutdown. For the said module,
planned shutdown will be primarily for cleaning-in-place (CIP): 1 CIP per train per
– Because of the jelly fish, at the intake offshore a vertical screen with 100 mm c/c
three months, resulting in 36 cleans per year, or once every ten days, for a duration of
have been proposed to have an approach velocity not exceeding 0.1 m/s at peak
1 to 2 days. A number of short term shutdowns can also be anticipated and
flows. A fish net is proposed to be placed outside the vertical mesh screens to
infrequent long term shutdowns. Short term unplanned shutdowns can be expected
reduce the intake of jelly fish.
to be 6 hours or less. Long term shutdowns will be a function of design, construction
Page 9 Page 10
and supervision, and materials supplied. Provision can be made for long term Membrane Flux and Overall Recovery
shutdown, but cannot be programed. Sydney desalination plant is designed to deliver
250 MLD for 94% of the time. The RO plant is a single stage/single pass design with an overall recovery of 46%
specified.
From time to time production at Perur may fall below 400 MLD, and it will be desirable SWRO membrane elements of 8-inch diameter have been selected. Each pressure
to ‘catch-up’ on production; redundancy is required to allow ‘catch-up’. ‘Catch-up’ vessel will house eight membrane elements. The design treated water TDS for the
could be achieved by simply increasing the pumping rate through the membranes; RO plant is 300 mg/L. In sizing the RO plant, an average membrane flux of
this is not desirable as it may result in flows exceeding the guarantees for the approximately 13.5 L/m2/hour (LMH) has been selected. The provision of 8% spare
membranes. The alternative is to increase the size of all trains, or to provide a space for more membranes provides the flexibility to reduce the flux if warranted, to
standby train. The number of pressure vessels is similar in both cases; however, the reduce cleaning frequency or reduce power consumption.
provision of a standby train requires the installation of another set of high pressure
Pumping System Design and Pressure Control
and booster pumps. Provision of a standby train is proposed: Sixteen duty trains and
1 standby train for 400 MLD module. ‘Catch-up’ can then be achieved by running all Based on preliminary membrane projections for DOW and Hydranautics membranes,
the duty trains plus the standby train for relatively short periods. it is anticipated that the required membrane pressure will range between 51.6 bar and
65.3 bar, depending on feed water and membrane conditions, and depending on the
To allow this to happen, pipework and pumps have been designed for flows assuming membrane selected. In order to provide the above pressure range, and based on the
all duty trains are in operation, plus the standby train. However, increasing the design temperature and salinity ranges set out depicted in the report, a combination
capacity of upstream processes such as DAF and filtration would be costly, and of VSD driven booster pumps and fixed speed RO HP pumps has been selected to
cannot be justified for these relatively short term operations. Upstream processes provide operational flexibility and minimise electrical energy costs.
have been designed for flows associated with 16 trains operating, and process design With this design the RO Booster pumps will provide feed pressure adjustments
parameters have been selected to be sufficiently robust to operate on overload for suitable to cover the required membrane pressures for average to maximum salinity
short periods. Potabilisation and chlorination have been designed for peak flows. events. For feed waters with below average salinities further controls will be required
in the form of a HP throttling valve, essentially ‘burning-off’ excess energy created by
Space has been provided in the RO racks for additional pressure vessels, which may the pumping system upstream.
be installed to respond to operational and environmental changes, as well as
compensate for deviations in equipment performances. It is not intended that the Potabilisation
additional pressure vessels be installed to increase the capacity of the trains above This design nominates a target alkalinity of 40 to 60 mg/L as oppose to the ISO
the design value, but rather to make sure that the design capacity of the plant is standard of 200 mg/L (‘Desirable’). This is because at this alkalinity, a positive
achieved. Langelier Index is achieved, which is the minimum requirement for addressing the risk
The cycling of the standby train will need to be relatively frequent as standby duration of corrosive water. Higher target alkalinity, while desirable (as it would further reduce
without preservation is approximately 48 hours. The provision of a standby train the risk of corrosive water by minimising pH change in the final water) would require
should ensure the consistent delivery of 400 MLD, from each module; that is, a design additional stabilisation chemicals, and therefore additional cost. The nominated target
target of 100% of design capacity delivered over the short, medium and long term. alkalinity thus represents a balanced approach between water quality and cost.
Page 11 Page 12
Product Water Main 1. INTRODUCTION
All pipes above 1.1 m dia have been proposed as Carbon Steel with internal CC lining
as per IS 3589 and external coating/lining, whereas all pipes below 1.1m are stated to 1.1 Background
be Ductile Iron with internal CC lining. The product water main is designed for 550
Chennai Metropolitan Area (CMA) is spread over an area of 1189 sq. km and
MLD, to cater to the 150 MLD flow from the proposed 150 MLD SWRO next to the
comprised of Chennai Corporation, 16 Municipalities, 20 Town Panchayats and
said facility.
214 Village Panchayats comprised in 10 Panchayat unions and one cantonment
namely St. Thomas Mount with the total population of about 8.0 million. Rapid
urbanization is taking place not only in the city but also in the surrounding urban
local bodies (ULBs), Municipal areas, and Town Panchayats. Due to this rapid
urbanization, it warrants for providing essential municipal infrastructures.
Pipe borne water supply system was first provided in Chennai about 100 years
back and has been expanded over time to satisfy the increasing demands for
water since its inception. However during the last 20 to 30 years, water demand
has increased drastically due to the natural growth of the Chennai City and
substantial inward migration of people from rural areas. But, the supply of water
has virtually remained constant and has increased at a very slow rate.
The population of Chennai as per 2011 census was 6.726 Million with projection of
7.4 Million for 2016. The water Demand in 2011 was 1042 MD and in 2016 with
155 LPCD shall be 1133 MLD. In addition to 1133 MLD in 2016 another 37 MLD
shall be required for industries, 28 MLD for bulk water supply to establishments,
17.7 MLD to Sriperumpudur and 14 MLD to SIPCOT Industrial estate. Also
Another 329 MLD shall be required for additional areas of CMA such as Avadi,
Pallavaram, Pammal, Tambaram etc. thus summing the total water demand for
2016 shall be 1526 MLD with supply of approx 831 MLD including 200 MLD from
existing two SWRO one in north and the other in south of the city.
Page 13 Page 14
The main sources of water supply to the Chennai city is from surface water 2. FIELD INVESTIGATIONS
sources such as Poondi, Cholavaram and Redhills reservoirs and also from
ground water sources from Araniar and Korataliar basin. The water supply
source has been augmented with distant sources such as Krishna Water A major component of the seawater quality assessment study is to carry out a
Supply scheme with supply from the State of Andhra Pradesh and by Chennai seawater quality monitoring program to characterise seawater at the proposed
Water Supply Augmentation Project with supply from Veeranam Tank. A seawater intake sites for engineering and process design of the plant.
desalination plant of capacity 100 MLD has been commissioned in July
To fulfil the assignment it was required to complete a range of surveys (Terrestrial
2010 near Kattupalli village, Minjur in North Chennai and is in successful
topographical & geotechnical), oceanographic and marine studies (hydro graphic
operation. Another 100 MLD capacity Desalination plant with Central
survey).
Government funds is operational at Nemmeli at the southern outskirts of
Chennai. The demand has been calculated with 2017, since most of the The studies are to collect data on sea water quality, temperature, salinity, seasonal
associated water supply projects are due for completion in 2017. water quality and tidal variation along with other data.
The intention of the studies was to characterise the aspects of the site with the
Water demand for 2017
area of study including; benthic communities and habitat; bathymetry;
Chennai City 760 MLD
oceanographic conditions (such as wind waves, tides, and currents); water quality
42 ULB’s merged with Chennai City 393 MLD and coastal processes.
Tambaram, Pallavaram, Sriperumbudur etc.) for carrying out the relevant oceanographic investigations for the proposed plant.
services to conduct prefeasibility studies, including Financial Viability evaluation, Reference station: The DGPS Beacon Transmitter
into the construction of a 400 MLD Sea Water Reverse Osmosis (SWRO) Plant at installed at Pondicherry Light House by Department of
Perur village along the East Coast Road (ECR). With commissioning of the said Lighthouse and Navigation, Pondicherry was taken as
facility the demand supply gap shall drastically reduce to 363 MLD. Also further reference station. The transmitting frequency of this
there is proposal of another 150 MLD SWRO within the premises of Existing 100 reference station DGPS Beacon transmitter was 315
MLD SWRO at Nemmeli, thus further mitigating the supply demand gap. kHz.
Page 15 Page 16
Mobile station: The horizontal positioning of the mobile unit was carried out using The survey vessel MFV SRINIVASA was used for data collection. The
Hemisphere R100 Series DGPS Beacon Receiver. It combines high-performance echosounder transducer was mounted on the star board side of the vessel by
GPS reception with a DGPS-capable receiver in a lightweight, durable housing and positioning it at 1.0 m below the sea surface. The DGPS receiver antenna was
comes with a separate antenna. It gives the horizontal position to an accuracy of mounted on the mast vertically in line with the transducer, so that it represents the
close to 1 m. exact coordinates of the location where the depth is simultaneously measured by
1.2.1.3 Bathymetry survey the transducer. The Heave Sensor was attached in line with transducer stem on
the boat deck in order to measure the residual vertical displacement of the boat
Area of survey: Bathymetry survey was carried out covering an area of 2.5 km
induced by external disturbances and to carry out the correction. The DIGIBAR-
along the coast and 3 km into the sea at 25 m lines pacing. The survey at less than
PRO sound velocity meter was used to measure the sound velocity across the
5 m water depth where there was a limitation due to boat draught was carried out
vertical and entered as input for calibrating the transmitting frequency of the
using a shallow fiber boat with portable echo sounder which can be connected to
instrument. The bar check was also carried out by lowering the rigid plate at
PC through serial port.
different depths and comparing with the displayed depth. The necessary inputs
Sequence of Survey: ODOM Echotrac CVM Digital Dual Frequency Echo sounder
were given in HYPACK data collection software before the commencement of the
manufactured by ODOM Hydrographic Systems, USA was used for the deeper
survey. The planned track lines were displayed on the monitor at wheel for
water survey where the water depth was more than 5 m. The configuration of
navigation. Watch guards were positioned at bow, transducer/antenna, heave
various arrangements for conducting the bathymetry survey is shown below.
sensor and at rear end. The data were continuously collected at onboard PC along
each transect. After a day of data collection was completed, entire data were down
loaded to external hard disc and stored. The recorded data included: date, time,
latitude, longitude, X coordinate, Y coordinate, heave and depth. The depth data
were recorded at 0.5 sec interval. A tide recorder was erected at site and the water
level variation was recorded separately in the internal memory. The recorded
depth data were processed in the laboratory by applying corrections for tidal
variation and transducer draught.
Page 17 Page 18
NEAR SHORE BATHYMETRY SURVEY transreceiver. The connection between transreceiver and PC was established by
RJ 45 link cable. The DGPS antenna was mounted on the mast vertically in line
with the tow fish and necessary inputs were given in HYPACK software before the
commencement of the survey. The planned track lines were displayed on the
monitor at wheel for navigation. Watch guards were positioned at bow, tow vehicle
/antenna and at rear end. SONAR WIZ.MAP software was adopted for seismic
data collection. The data in the form of *.SEG-Y format (Society of Exploration
Geophysicist) were logged continuously in the hard disc and the anomalous
Echosounder Installation Data display DGPS antenna
geological features were noted. The entire data were copied in the external hard
1.2.1.4 Shallow seismic survey disk and DVD.
Area of survey: Shallow seismic survey was carried out covering an area of 2.5 km
The system uses advanced Chirp technology to produce high resolution sub-
along the coast and 3 km into the sea at 25 m line pacing.
bottom profiles of both the shallow and deep sub bottom layers. The system is
modular in design as it can be configured with a variety of tow vehicles, as well as
Sequence of survey: Benthos CAP 6600 Chirp III Acoustic Sub-Bottom Profiler hull mounted transducer arrays. The system comprises the CAP 6600 Chirp III
CAP 6600 Chirp III dual frequency acoustic Sub-Bottom Profiler manufactured by Workstation and a Tow vehicle TTV-170.
TELEDYNE BENTHOS, Inc., USA was used for carrying out the shallow seismic
survey. SHALLOW SEISMIC SURVEY
Chirp sonar technology used uses digitally produced linear FM transmitted signals
along with digital signal processing for matched-filter processing of reflected
energy to produce high resolution images. In Chirp technology, a greater dynamic
range is attained as long FM pulses provide an additional 20 dB to 30 dB of
dynamic range over conventional sub-bottom sonar systems. Enhanced resolution
is achieved with matched filter processing and the transmitted wave forms are
repeatable. The pulse characteristics are programmable, as the pulse length, span
The tow fish was mounted 2.0 m below the sea surface at star board side of the of frequency sweep and phase/amplitude calibration of the transmitted waveform
survey vessel MFV SRINIVASA. The tow-fish cable was connected to the can be varied without hardware changes. The sonar data can be stored for off-line
Page 19 Page 20
processing in SEG-Y format.
Together with the processor, the software and the transceiver serve to process, to
display and to store both channels of sub-bottom sonar data. The CAP-6600 Chirp
III work station also integrates and stores navigation data from the ship’s
navigation system and can generate output through a variety of user-configurable
formats. In addition, the processor provides remote programmable receiver gain C3D side scan sonar Installation of C3D Onboard data display
control of the remote controlled transmit/ receive module. side scan
The Chirp waveforms are input to the transceiver from the processor and are
amplified by the power amplifiers which drive the transducers. Received signals The side scans sonar tow fish was mounted 2 m below the sea surface on the star
are input to the transceiver, filtered and then output to the processor. The board side of the survey vessel MFV SRINIVASA. It was connected to the trans-
transceiver also includes a pre-amplifier with adjustable gain for amplifying the receiver unit through the LAN cable. The DGPS antenna was mounted on the mast
output of non-Chirp systems. vertically in line with the tow fish so that it records the exact coordinates of the
1.2.1.5 Side scan sonar survey locations where the tow fish collects the seabed reflection characteristics. The
necessary inputs were given in HYPACK data collection software before the
Area of survey: Side scan sonar survey was carried out covering an area of 2.5
commencement of the survey. The planned track lines were displayed on the
km along the coast and 3 km into the sea at 25 m line spacing.
monitor at wheel for navigation. Watch guards were positioned at bow, tow vehicle
Sequence of survey: C3D-LPM SIDE SCAN SONAR BATHYMETRY SYSTEM
/antenna and at rear end. The data were continuously recorded at onboard PC
manufactured by TELEDYNE BENTHOS, Inc., USA was used for carrying out the
along each transect. After that day data collection was made, entire data were
side scan sonar survey. The configuration of various arrangements for conducting
down loaded to external hard disc and stored. Using the SONARWIZ.MAP survey
the side scan sonar survey is shown below.
software we interfaced the coordinates of the DGPS and the sea bed reflection
characteristics. The real time data also included time, date, latitude and longitude.
The collected data were stored in ".XTF” format with the help of CODA
GEOSURVEY software.
1.2.1.6 Tides
Tide measurement was carried at Fishing harbor using Aanderaa Water Level
Recorder (WLR 7) for a period of 20 days from 27.07.2013 to 15.08.2013. The tide
data were recorded at 15 min interval.
Page 21 Page 22
quartz crystal oscillator. The pressure is measured every 0.5 seconds and 1024 The various tide levels with respect to Chart Datum for Chennai as presented in
samples are taken (512 seconds) and stored in internal RAM. The instrument is Indian Tide Table 2013 are shown below:
housed in a pressure case and has the arrangement for shallow and deep water
Mean High water Spring 1.15 m
moorings. A mode switch with a test and serial communication setting, a depth-
setting switch and a recording interval switch is built into this board. The quartz Mean High Water Neap 0.84 m
pressure sensor is also attached to the board by a shock-absorbing bracket. A
Mean Sea Level 0.65 m
specially designed bottom mounting frame was used for installing the instrument
on the seabed. The sensor is of quartz pressure type based on a pressure- Mean Low Water Neap 0.43 m
controlled oscillator having frequency of 30 – 45 kHz. It has a range of 0-690 kPa,
Mean Low Water Spring 0.14 m
with an accuracy of 210 Pa and a resolution of 7 Pa.
It has been noticed that the depths near the existing outfall and intake locations
have become deeper due to the existence of construction debris, dredging
activities, burying of pipelines etc. The offshore beyond 11 m water depth is found
to be slightly shallower on the southern side compared to the northern side.
The variation of water depth with distance from the shore is as shown below.
2.1.2 Results
1.2.2.1 Tides
Page 23 Page 24
clayey sand, coarse sand with scattered rocky outcrops.
Depth w.r.t. CD (m) Distance from shore (m) Spread of submerged rocks
2 150
3 200 The higher amplitude acoustic signals on the sonogram shows the presence of
4 225 about 20 rocky outcrops on the seabed. The rock-outcrops are scattered on the
seafloor at various random locations with different elevations above the seafloor.
5 340
Al places, the rock-heads are carpeted by the seashells and coarse sand.
6 140
7 520 Southern side: Four submerged rocky patches of various spatial extents are seen
on the nearshore region till the distance of about 1300 m from the shore. Beyond
8 660
that, the rocks are not visible from side scan records till 2000 m from the shore.
9 835
Further, six patches of submerged rocks are demarcated till the end of the survey
10 1040
limit.
11 1360
Northern side: The nearshore is observed by the absence of rock-outcrops till 1.5
12 1890
km from the shore. Beyond that, the seabed shows the patches of linear rocky
13 2160
outcrops in NE-SW direction. It has been noticed that the stretch of linearrock is
14 2480
about 1 km long in NE-SW direction. It exists at 2 km offshore.
15 2720
Existence of pipelines
16 2950
The intake and outfall pipelines of existing 100 MLD Neemeli SWRO which are
partially buried have been observed on the seafloor. The construction debris and
1.2.2.3 Side scan sonar survey
trenches are also noticed in the side scan records along the pipeline corridor.
The side scan sonar data acquired in the field were processed using CODA
Seabed covered by sediments
GEOKIT software in the laboratory. Several geophysical signal processing
techniques such as low pass, high pass and band pass filters were adopted to
The rest of the seabed apart from rock-heads is carpeted by mainly sandy clay and
eradicate the noise on side scan sonar records. The processed data were
clayey sand. The patches of coarse sand with different grain sizes are noticed to
interpreted using various image interpretation techniques like tone, texture,
be distributed on the seafloor. The presence of seashells is also illuminating the
pattern, alignment, etc. The inferred results were used to prepare the seabed
side scans sonogram at few locations.
surface sediment distribution map.
The analyzed records reveal that the seabed is generally covered by sandy clay, 1.2.2.4 Shallow seismic survey
Page 25 Page 26
The shallow seismic data acquired in the field were processed using CODA shore. At the northern side, rocks are not seen till 1500 m from the shore. Beyond
GEOKIT software in the laboratory. Several geophysical signal processing that, patches of linear rocks are located randomly.
techniques such as low pass, high pass and band pass filters were adopted to filter Buried Rocks
noise level on the seismic records. The processed data were interpreted using
The gradual increase on the sediment thickness close to the rocky-outcrop
various image interpretation techniques like tone, texture, pattern, alignment, etc.
indicates the extension of buried rock beneath the seabed. The buried rocks are
The inferred results were used to prepare isopach maps and construct vertical
extending beneath near the submerged rocky patches at various directions. As the
sections of sub-seabed.
limitation of acoustic basement depends on the mask of seismic multiples, the
dipping angles and depth of extension of buried rocks are not described further
The isopach map thus prepared explains the configuration of minimum sediment
deep.
thickness i.e. the sediment thickness between seabed and acoustic basement. For
example, the isopach contour of 9 m implies that the sediment column is present
for atleast 9 m thickness without presence of any hard strata in between. Sedimentation
Generally, the sediment thickness (till acoustic basement) within the survey
Acoustic basement: In the seismic records, the maximum penetration limit of the
boundary varies up to 9 m.
acoustic wave is defined by the acoustic basement. The penetration of the
acoustic wave is controlled by the compactness of the sediments/rock formations Southern side: The sediment thickness appears slightly lesser than the northern
occurred below the seabed. It does not penetrate more consolidated side and varies up to 5 m at the nearshore. The sediment thickness increases
sediments/bedrocks. So the recorded data signifies the nature of the sedimentary towards offshore till the distance of about 2 km from the shore. Further, the
formations occurred between the seabed and acoustic basement. isopach values decrease due to the presence of submerged and buried rocks. The
sediment thickness of 9 m appears on the southern side at a distance of about 1
Characteristics of sub-seabed
km from the shore.
The shallow seismic study reveals that the sub-seabed consists of sedimentary
layer such as sand and clay up to few meters below seabed. The submerged and
Northern side: At the northern side, the sediment thickness is varying between 3
buried rocks are also noticed within the study region.
m and 7 m till the distance of about 1.5 km from the shore. Beyond that, it
Submerged Rocks decreases due to the existence of linear NE-SW rocky patches. The offshore sub-
seabed is found to be composed by sand and clay varying the thickness between
The seismic records are showing higher amplitude signals at few places which are 7 m to 9 m.
indicating the rocks submerged above the seabed. The isopach contours less than The detailed report is annexed as Annexure-I to the Said Report.
1 m are showing the rocky out crops that are located randomly at different
elevations.
Page 27 Page 28
3. SITE CONDITIONS
The proposed site for 400 MLD desalination Plant is located at Perur (Nemmeli
Village) quite adjacent to the existing 100 MLD Sea Water Desalination Plant at
Nemmeli along East Coast Road, Kancheepuram District, Tamilnadu, India. The
site is located at eastern side of East Coast Road (ECR) at 12° 42' 44" North, 80°
14' 26" East and is approximately 40 km of south of Chennai city.
The climatic conditions are characterised by warm dry winters (270C average daily
max) and hot wetter summers (390C average daily max) with an annual average
rainfall of 1200mm. Cyclones are common in the area and the site is expected to
be effected by approximately 3 per year.
Fig 2:Site Location with respect to existing 100 MLD Nemmeli Desalination
Plant
The front face of the site towards the sea face is fully planted with Causirina
Plantations well grown and maintained by Department of Forest, Government of
Tamil Nadu. Some of palm trees also existed at the boundary of site, which is quite
evident from the site Photographs on next page.
Page 29 Page 30
3.2 Tides, Storm Surge and Wave Runup
Chart Datum RL
Site View from Sea Face Mean Low Water Neaps 0.43 RL - 0.22
Onshore survey levels are recorded as metres above Mean Sea Level. Thus
Mean High Water Springs is 1.15 – 0.65 = RL 0.5, and Mean Low Water Springs is
0.14 – 0.65 = RL - 0.51, on shore.
3.3 Waves
Site View from EC Road The data compiled based on the ship observed deep-water waves over the region
between the latitude 10°N - 15°N, and longitude 80°E - 85°E is considered for the
present project. It is observed that the significant wave heights varied between
There are several heritage sites in close proximity to site mainly being
0.5 and 1 m during February to April, 1 and 3.0 m during May to September and,
Mahabalipuram sea-shore temple which is about 11 km and Tiger Cave which is
between 1 and 2 m during rest of the year. The zero crossing period of the waves
about 7 km respectively from the proposed site and are recognised as World
varied between 5 and 8 s. The project area is located in the region which is
Heritage sites.
significantly influenced during the northeast monsoon. The wave climate remains
Further as cited above an existing 100 MLD Nemmeli Sea Water desal plant is rough from May to November. The occurrence of storms and depressions during
next to the site and a prominent atomic power generation unit named “Indira northeast monsoon often increase the wave activity in this region.
Gandhi Centre of Atomic Research” is about 18km from the proposed site.
3.4 Storm Surge
Page 31 Page 32
3.5 Tsunami
The occurrence of a Tsunami along the Indian coast is an extremely rare event
with a very low frequency of less than once in 500 years. One such tsunami event
was witnessed on 26th December 2004 along the Tamil Nadu coast. From
records of tide gauge data during the 2004 tsunami event, the run up due to
tsunami at different stretches along the coast was observed to vary between 1 m
and 3.5 m. The water level rise due to this Tsunami near the project region was
around 2.0 m and the run-up crossed over the highway (ECR). Eye -witness
accounts say that each high tsunami wave that approached the coast was like a
solitary surging / tidal bore wave, and the rise in water level near the coast due to
such surging wave existed for a short duration of nearly 30 minutes.
To mitigate the above effect, the finished floor level of existing Neemeli 100 MLD
SWRO plant is 6.5 m, which had been kept 0.9 m above the last Tsunami level,
therefore the Finished Surface Level (FSL) of RL 7.0 is being proposed for the said
plant. Finished Floor levels shall be set at not lower than RL 7.3, and equipment
plinth levels not lower than RL 7.5 for ease in operations.
3.7 Climate
Chennai, Tamil Nadu has a tropical wet and dry/ savanna climate (Köppen-Geiger
classification: Aw) with a pronounced dry season in the low-sun months, no cold
season, wet season is in the high-sun months. According to the Holdridge life
zones system of bioclimatic classification Chennai, Tamil Nadu is close to
the tropical dry forest biome. Figure 4 Rainfall (monthly averages)
Page 33 Page 34
3.8 Typical Oceanographic Conditions
The proposed site for 400 MLD desalination Plant is located at Perur (Nemmeli
Village) quite adjacent to the existing 100 MLD Sea Water Desalination Plant at
Nemmeli along East Coast Road, nearer to the sea in Kancheepuram District,
Tamilnadu, India
Page 35 Page 36
4. WATER QUALITY
3.10 Coastal Regulation Zone
The Central Government has declared the following areas as Coastal Regulation
4.1 Seawater Quality
Zones (CRZ),
i. The land between the High Tide Line (HTL) to 500 metres on the 4.1.1 Importance of Sea Water Quality
landward side along the sea front; Knowledge of seawater quality and variability (diurnal and seasonal) at the
ii. Land associated with tidal influenced water bodies such as tidal proposed intake (and outlet) locations is important for the engineering of SWRO
Page 37 Page 38
suspended solids, oil and grease, organics (TOC and DOC) and silt density index the various analytes are tabulated below, in Table 1
(not often available), nutrients, particle size etc. In addition, it is critical to have an
Table 1 Field Investigations - Seawater Quality
understanding of what factors impact on seawater quality e.g. marine
hydrodynamics, point and diffuse pollution sources, riverine inputs during monsoon Parameter Unit Average at Surface Average at
Bottom
seasons, marine activities such as shipping, dredging and the occurrence of algal 1 Temp. (°C) 28.4 27.9
blooms that may impact on water quality in the vicinity of the sites.
2 TDS (mg/l) 35,100 35,200
September (33% of the rainfall). During and following the monsoon periods, a 8 Colour, Hazen Units 17.7 18.7
significant volume of fresh water is flushed into the Bay of Bengal which may 9 Odour Odourless Odourless
impact on salinity and temperature of seawater at Perur.
10 Taste Salty Salty
Page 39 Page 40
26 Sulphate as SO4 (mg/l) 2758 2878
43 Zinc as Zn (mg/l) 0.092 0.088 as set out above, and upon the experience of the designers.
Nemmeli – 2013: – Intake water quality data from Nemmeli plant was taken for the
period from and including May 2013 to early December 2013,. The data shows
poor water quality on a number of occasions as evidenced by frequent spikes in
turbidity.
Page 41 Page 42
Normal – based Sodium Na mg/L 10,789
on field Minimum - Maximum -
Criteria Description Unit measurements adopted adopted
Nitrate NO3 mg/L 4
Water Temperatures
Ammonium mg/L 0.2
- surface °C 28.4 26.0 30.0
- bottom °C 27.9* 25.0 32.0*
4.2 Water Quality Targets
Turbidity NTU <10 10 125 CMWSSB has specified that the water quality targets shall be as per IS 10 500:
Total Suspended Solids mg/L 75 50 200 1991 (reaffirmed in 1993). The quality parameters as per IS 10 500 – 1991 are
pH 8.2 7.7 8.5 indicated in Table 4. It is to be noted that the water quality requirements fall into
two groups, ‘Essential Characteristics’ and ‘Desirable Characteristics’.
Total Dissolved Solids mg/L 35,200 32,000 38,000
(as mg CaCO3/L) CaCO3/L 110 100 120 Sl. No Substance or characteristic Requirement
Note: * The design of the RO Plant will make provision for a rise in seawater temperature of 1oC Essential Characteristics
resulting from the energy input at the pumps.
i. Color, Hazen units, Max. 5
ii. Odour Unobjectiona
In Table 3, the design values for the proposed plant are stated herwith. iii. Taste Agreeable
iv. Turbidity, NTU, Max. 5
Table 3 Seawater Quality – Design Criteria – Dissolved Solids
v. pH value 6.5 to 8.5
Criteria Description Unit Normal – based on vi. Total Hardness (as CaCO3) mg/l, Max. 300
average field
measurements vii. Iron (as Fe) mg/l, Max. 0.3
Temperature °C 27.9
viii. Chlorides (as Cl) mg/l, Max. 250
Total Dissolved Solids mg/L 35,200 ix. Residual, free chlorine ,mg/l, min. 0.2
Bicarbonate (HCO3) mg/L 126.3 x. Fluoride (as F) mg/l, max. 1.5
Magnesium as Mg mg/L 1258 Desirable Characteristics
Barium as Ba mg/L 0 xviii. Phenolic compounds (as C6H5OH) mg/l, Max 0.001
xix. Mercury (as Hg) mg/l, Max 0.001
Boron as B mg/L 3.17
Page 43 Page 44
xx. Cadmium (as Cd) mg/l, Max 0.01 confidence, and higher allowable concentrations, from studies over the last 10
xxi. Selenium (as Se) mg/l, Max 0.01 years. This is reflected by increases in guideline standards, whereby WHO have
xxii. Arsenic (as As) mg/l, Max 0.01 changed their guidelines over the last ten years from 0.3, to 0.5 (2008) and now to
xxiii. Cyanide (as CN) mg/l, Max 0.05 2.4 mg boron/L in the most recent (fourth) edition of the guidelines. A summary
xxiv. Lead (as Pb) mg/l, Max 0.05 statement on the World Health Organisation’s (WHO) recommended boron
xxv. Zinc (as Zn) mg/l, Max 5 guideline value has been posted on the WHO Water Sanitation and Health website
xxvi. Anionic detergents (as MBAS) mg/l, max 0.2 at: www.who.int/water_sanitation_health/dwq/chemicals/boron/en/. The new
guideline value of 2.4 mg/L was based on a human health point of view. The level
xxvii. Polynuclear aromatic hydrocarbons Chromium (as 0.05
was derived based on an assumption that 40 per cent of a 60 kg adult’s total daily
Cr6+) mg/l, Max
intake of boron is a result of drinking 2 litre of water having a boron concentration
xxviii. (as PAH) g/l, Max
of 2.4 mg/L and a ‘safety factor’ of 60x.
xxix. Mineral oil mg/l, Max 0.01
While sodium and chloride ions are well rejected by RO membranes, boron is not
xxx. Pesticides mg/l, Max Absent
well rejected because a high portion of the boron species is uncharged. The
Substance or characteristic
rejection of boron is strongly dependent on feedwater pH. Under optimal neutral to
xxxi Radioactive materials *
alkaline conditions, boron rejection is 70 to 80%, reducing to as low as 50 to 60%
a) Alpha emitters Bq/l, Max 0.1*
under more acidic feed conditions.
b) Beta emitters pci/l, Max 1*
xxxi. Alkalinity mg/l, Max 200 IS 10 500 states that one of the ‘desirable’ characteristics of drinking water is that
the maximum concentration of boron be not greater than 1 mg/L. Modelling
xxxii. Aluminium (as Al) mg/l, Max 0.03
indicates that single pass RO can reduce the concentration of boron to between
xxxiii. Boron mg/l, Max 1
0.4 and 1.0 mg/L, assuming a maximum feedwater concentration in the source
xxxiv Langlier Saturation Index positive
water of 3.4 mg/L, depending on the age and type/brand of the membranes.
For the purposes of this report the design target for boron has been set at 0.75
4.2.1 Total Dissolved Solids
mg/L at commissioning, ie with new membranes. The concentration of boron in
IS 10 500 states that one of the desirable characteristics of drinking water is that the permeate is expected to rise as the membranes approach their AMLT, and it is
the maximum dissolved solids be limited, and not greater than 500 mg/L. For the expected that minor variations to the process operation, primarily adjustment of the
purposes of this report the design target has been set at 300 mg/L for permeate, pH and the addition of anti-scalant, will allow the concentration of boron to be
such that the dissolved solids in drinking water, after potabilisation, will not exceed maintained below the long term goal of < 1.0 mg/L.
500 mg/L.
4.2.2 Boron
4.2.3 Jelly Fish Blooms
Boron emerged as a water quality issue with the increasing use of desalinated
Jelly Fish
seawater for both municipal drinking water supply purposes and for irrigation. The
Jelly fish ingress in a power station cooling system is reported on by S. Rajagopal
human health effects of boron have been debated for some time with increasing
Page 45 Page 46
et al, Home 1989. The power station is located at Kalpakkam on the east cost of 50 years for civil works, buildings & buried pipeline components;
India. Three peaks in the occurrence of jelly fish were noticed in May, July and 50 years for concrete tanks.
October 1988, which accounted for 286, 204 and 129 tonnes respectively. The 25 years for mechanical and electrical equipment;
authors recommend that jelly fish ingress be controlled by preventing their inflow,
20 years for flexible membrane liners and covers to storages;
or by letting them pass freely. ‘To prevent jelly fish from flowing in with water
20 years for steel panel tanks;
current, fish netting is proposed to be installed in front of the water intake where
15 years instruments;
inlet velocity is low. This method is adopted at many power stations including
10 years for polyethylene tanks;
Tarapur Atomic Power Station including existing SWRO plants’.
8 years seawater reverse osmosis (SWRO) membrane life.
The size of the RO train impacts on the number of trains, all equipment’s as well
as the pipework required, along with pump set efficiencies. To have the most
optimal of above, the RO racks have been selected within each train having the
following characteristic:
Table 5 : RO Racks
Page 47 Page 48
One standby train has been provided for the complete capacity of the plant, of the trains above the design value, but rather to ensure maintenance of the
primarily to provide for the shutdown of individual trains. Each train will be subject design capacity of the trains. RO building will be designed to house Seventeen
to planned and unplanned shutdown. Planned shutdown will be primarily for trains, with one row of eight trains and other row for nine trains.
cleaning-in-place (CIP). There may also be a scenario, when demand for potable water is low, or major
In general there shall be one (1) CIP per train per three months, resulting in 36 scheduled maintenance is occurring, then the plant may be required to operate at
cleans per year, or once every ten days, for duration of 1 to 2 days. However a reduced capacity.
unplanned short term shutdowns can also be anticipated as well as infrequent long
term shutdown. Short term unplanned shutdowns can be expected to be 6 hours 5.3 Primary Flows
or less, whereas Long term shutdowns will be a function of design, construction Based on the proposed operation and availability of the plant as described above,
and supervision, and materials supply. However, provision can be made for long primary flows have been calculated and are tabulated below in Table 8. It is to be
term shutdown, but cannot be programed. Hence a Standby train has been noted that these flows are not the final design flows and can be expected to vary
provided to take care of the said eventualities to meet the plant availability criteria slightly as the designs are developed.
as per design.
The cycling of the standby train will need to be relatively frequent as standby
Table 6 Primary Flows – 400 MLD Plant
duration without preservation is approximately 48 hours.
Section Normal Flow Peak Flow
The provision of a standby train should ensure the consistent delivery of 400 MLD
of the product water from the facility. However, from time to time production may Product Water Tank 400 MLD 425 MLD
fall below 400 MLD, and it will be desirable to ‘catch-up’ on production which could
be achieved by increasing the pumping rate through the membranes. However, Utilities and Losses 8 MLD 8.5 MLD
this is not desirable as it may result in flows exceeding the guarantees for the Permeate Production 408 MLD (16 trains) 433.5 MLD (17 Trains)
membranes. Therefore alternative is to provide for running of standby train on
Permeate per Train 25.5 MLD 25.5
occasions for relatively short periods. However, to allow this to happen, pipework
Peak Filtered Seawater Required 948.85 MLD 1008.20 MLD
and pumps must be designed to pass the additional flows and this can be
to RO (based on 43% recovery *)
achieved at a relatively low cost, and pipework and pumps have been designed for
flows associated with 17 trains operating. However, increasing the capacity of Filtered Sea Water to Screens for 2.6 MLD 2.6 MLD
upstream processes such as DAF and filtration is not justified for these short term spray
operations. Hence, upstream processes have been designed for flows associated Sludge and Float losses 22.5 MLD 24.0 MLD
with 16 trains operating; however process design parameters are have been
Filter Backwash Losses 38 MLD 40.0 MLD
selected to be sufficiently robust to operate on overload for short periods to take
Filter to waste losses** 33 MLD 35.2 MLD
care for additional flows.
To Pre-treatment 1044.95 1110 MLD
As shown in Table 5 space has been provided in the RO racks for additional PVs,
say 1045 MLD
which may be installed to respond to operational and environmental changes, as
well as compensate for deviations from the design of the plant or equipment Intake Flow
performances. The additional PVs would not be installed to increase the capacity
Page 49 Page 50
Normal 1043 MLD of screen.
Peak 1108 MLD Two intake conduits and a single outlet conduit each of 2400 mm ID has been
proposed for the plant to produce 400 MLD permeate capacity. The velocity in the
Screened Sea Water to Pre-
conduit at peak flow will be 1.47 m/s. Friction losses at this velocity would be of
treatment
the order of 1.5-1.7 metre in a pipeline 1,200 metres long.
Normal 1045
One outfall will be provided with an internal diameter of 2400 mm. For a flow peak
Peak 1110 flow of 700 MLD, the velocity will be 1.79 m/s. Friction losses at this velocity would
be of the order of 1.6-1.8 metre in a pipeline 700-800 metres long; exit losses
Peak Outfall Rate 700 MLD through multiple ports at 7 m/s would be of the order of 2.5 metres, giving a total
head loss in the outfall of around 4.7 metres say 5 meters at peak flows. For a
* 43% selected to provide a conservative estimate of flow for hydraulic design.
nominal outfall the velocity shall be 1.5 m/sec.
Process design is based on 46% recovery.
6.2 Intake structure with Screen offshore
** Filter is brought back into service following backwashing, the water quality can be
poor and it is good practice to discharge the first product water from the filters to
A 100 mm screen in GRP construction will be provided at the intake to exclude
waste. If this water is not discharged to waste there is the potential for higher loads
larger marine life. One intake chamber and screen will be provided on each
on the cartridge filters and ultimately membrane fouling.
conduit. There shall be two intake heads with screen offshore separated by a
minimum distance of 1500 mm. The screens will be 8.5 m diameter, 1.5 m high,
starting 2 m above the sea floor, in 10 metre depth of water. The approach
velocity will be <0.1 m/s to minimise the entrapment of marine species.
A fish net with will be provided to minimise the ingress of jelly fish to the intake.
The fish net will be required to be inspected and replaced from time to time, as the
same is likely to be damaged by marine lives. The head loss through the intake
system will also be monitored, and in any increase in system losses indicating
fouling at the intake, or the growth of biomass within the intake conduit, the same
shall be cleaned through divers.
Page 51 Page 52
preserving the same and returning them to the sea in order to have a sustainable
Stand by 2
ecosystem.
Sea Water Flow Per screen MLD 277.5
Stainless Steel mesh mm 3
Travelling Band Screens Approach Channel Width m 4.5
A typical band screen installation is shown in Figure 8 below. Width Back opening m 3.0
Channel Approach Velocity m/s 0.85-0.90
Upstream water depth m 2.2
Downstream water depth m 1.8
Wash Water per screen L/s 15-20
Vertical shaft pumps in a wet well are particularly suitable for sites with a low tidal
range, such as is experienced at Chennai. Vertical shaft pumps in a wet well have
been selected.
The tides at Perur are as follows, in metres above Chart Datum, and relative to the
Band screens have been in service for screening sea water for many years. They site datum:
provide efficient removal with relatively low maintenance costs and also have
Construction costs that are relatively low as compared to the total plant cost.
Chart Datum RL
Through-flow band screens have been proposed herewith. Typically mesh sizes
Mean High Water Spring 1.15 RL 0.5
vary from 2 mm to 10 mm, and, in view of the marine biomass problems at
Nemmeli, a mesh size of 3 mm has been selected. Mean High Water Neaps 0.84 RL 0.19
Table 7 : Band Screen Design Parameters Mean Sea Level 0.65 RL 0.0
Page 53 Page 54
Design parameters are set out in Table 8
Onshore survey levels are recorded as metres above Mean Sea Level. Thus Table 8 :Sea Water Intake Pumps
Mean High Water Springs is 1.15 – 0.65 = RL 0.5, and Mean Low Water Springs is
Parameter Units Value
0.14 – 0.65 = RL – 0.51.
Pumping Station Capacity MLD 1110
The low no flow level in the pump well has been taken as RL – 0.50. At a flow of
Wet Wells - 1
580 MLD per conduit (10% additional to take care for biofouling), the hydraulic
Duty Pumps in wet well - 6
grade line entering the proposed pumping station will be approximately 1.7 m
Standby Pumps in wet well - 3
lower, at RL – 2.2. A head loss of 0.8 is provided/allowed for loss through screens
Mean High Water Springs RL 0.5
resulting in low-low water levels in sump cum pump station as RL-3.0.
Mean Low Water Springs RL - 0.51
Three (3) metres has been provided to the bottom of the pumps, which has been Intake Conduit loses at peak flow m 1.8
assumed to be 0.5 m above the bottom of the pumping station at RL – 6.5 to
Pipe diameter - Pump to manifold m 1.30
ensure sufficient submergence for the pumps, and to allow for surging in the intake
Rising mains to each module - 2
line. Subject to the detailed design of the intake conduits, it is anticipated that the
Rising main diameter m 1.8
intake conduit will enter the pumping station at between RL – 6.5 and RL – 4.5.
Pump house Plinth Level RL 7.5
Therefore, the static lift at Mean Low Water Springs will be from RL -3.0 to around
RL 14.5, ie around 17.5 metres; the static lift at Mean High Water Springs will be
Generic type of pump: vertical shaft mounted in pump well,
from RL -2.0 to around RL 14.5, i.e. around 16.5 metres.
Materials: super duplex stainless steel, PERN No > 43
Pump Configuration Equipment per pump unit: isolation valves, non-return valve and magnetic flow
There shall be 6 W + 3 S pumps sets in each wet well delivering to a 400 MLD meter,
There shall be 6 pumps in operation each pump must be capable of delivering Pump station control: by plant PLC based upon target flow rate,
185 MLD (2141 L/s), at a head of around 30 metres. Pump/equipment removal: by EOT,
Each pump will have a delivery line 1.30 metres in diameter (V = 1.61 m/s),
connected to the manifold 1.8 metres in diameter. 6.5 Shock chlorination system
Pair of three pumps shall form one manifold to a module of 12 Settlers. The A shock chlorination system is proposed to minimise marine growth in the inlet
diameter of each manifold 2,600 mm (2.6 m), with a velocity of 1.20 m/sec. pump station and pressure main. Criteria adopted for the shock chlorination
These pumps are Vertical Turbine pumps with large clear passages. The intake system are summarised below;
screen and net at the intake will prevent the ingress of material like to cause a Type of chemical: chlorine gas through Vacuum Chlorinate
blockage. Run times between major maintenance are expected to be long, Max chlorine solution residual in inlet main: 10 mg/l,
therefore for these reasons a 50% standby configuration has been proposed.
Min chlorine solution residual in inlet main: 1 mg/l,
Page 55 Page 56
Dosing time: 1-2 hour per day, controlled support pressure to the tunnel face and allowing for the use of bentonite
Dosing point: Off shore inlet well, Slurry where required. The complete system shall be purpose designed for the
project and shall include TBM, slurry, circuit, main jacking station, interjack stations
For shock chlorination Hypo has been proposed and sizing is calculated in
and automatic bentonite injection system for lubrication of the pipe annulus.
Chapter 10.
The jacking pipes for this project shall be 2400mm I/D. They shall be using steel
6.6 Intake / Outfall Pipes (Super Duplex : PERN>43) banded joints with full section contact between
adjacent pipes. The design of the pipes shall be sufficient to withstand the jacking
Jacking pipes shall be of precast concrete, designed and manufactured to meet
and overburden pressures assuming that inter jack stations are installed at 100m
the requirements of:
spacing. The design should also allow for driving the tunnel at a 100-150m radius.
BS5911 Specification for reinforced concrete jacking pipes with flexible joints.
6.6.2 Main Jacking Station
BS EN ISO 9002 Manufacturing.
The main jacking station shall be of robust construction, and comprise a thrust ring
Or equivalent standards as appropriate.
and cylinders fixed firmly to a back wall and slide rails.
All jacking pipes, including special designs, shall be sufficiently reinforced with
steel to withstand all stresses induced by handling, jacking, earth and water The thrust ring only shall be used for advancing pipes. A local control shall be
pressures and all working loads at the depths at which they are to be used without provided at the pit bottom for use by the shaft bottom crew during pipe extensions
cracking, spalling or distortion. A load factor of not less than 1.5 shall be used in only. During normal advance the main jacking station is controlled from the TBM
the calculations to determine the strength of the pipes required. The clear cover to operators console, however Cylinder pressures should be available to the operator
any steel reinforcement shall not be less than 50mm. at all times.
The strength of the pipes shall be tested by a three edge bearing test. When An interlock arrangement shall exist to transfer control between the operator’s
subjected to the design load in such a test, the maximum crack developed on the console and the shaft, whereby only the operator in ownership of the control can
pipe shall not exceed 0.25mm. make the transfer at the time.
Pipes shall be fully cured and have reached the designed concrete strength prior spacing of 300 m. The seal shall be adjustable to exclude the ingress of ground
to delivery. water and bentonite and shall be capable of withstanding working pressures in
excess of 4bar.
6.6.1 Pipe jacking Hydraulic power to operate the inter jack stations shall be provided by power packs
situated in both the TBM and in the launch shaft. In order to minimise hose lengths
The tunnel shall be constructed by pipe jacking techniques using a purpose made
and subsequent power losses, the forward inter jacks shall be fed from the TBM
TBM for excavation. The TBM shall be designed as a slurry machine offering
Page 57 Page 58
power pack and the rear inter jacks, from the shaft power pack.
On completion of tunnelling operations all interjack cylinders and seal assemblies 7. PRETREATMENT SYSTEM
shall be removed. The exposed steelwork shall be properly cleaned and treated
7.1 Pretreatment Process
with epoxy paint suitable for sea water conditions and the pipes shall be closed to
eliminate the gap. The adjustable interjack sealing systems shall be manufactured The pre-treatment process has been sized assuming that there are 16 membrane
to facilitate easy removal by hand within the tunnel. trains in operation to produce 400 MLD of Permeate water.
Feed pipes shall be 250mm nominal internal diameter and slurry discharge 200mm Turbidity
internal diameter. Automatic valves shall be included at the shaft top to allow for Marine Biomass, jelly fish, larvae and algae
immediate closure by the operator in the event of burst system hoses. The
Other relevant factors are:
separation plant shall be sized to be 25% over capacity to account for any possible
flow surges within the slurry circuit. Capex
All controls and indicators for running the slurry system shall be available at TBM Opex
operator’s console. A telephone system shall be installed to allow direct Ease of operation
communication between the TBM and the separation plant.
Robustness
Field Investigations
The results of Field Investigations into sea water quality are tabulated in Table 1.
The key water quality parameters in respect of the design of pre-treatment facilities
are discussed below.
Turbidity
The average of the turbidity measurements at the surface and at depth, offshore
from Perur, were 1.10 and 1.88 NTU respectively. These readings are ‘normal’ for
sea water. Notwithstanding, turbidity must be reduced to less than 0.5 NTU to
protect the RO membranes.
Page 59 Page 60
Total Suspended Solids 7.3 The Pre-Treatment Processes- Scheme
The average of the TSS measurements at the surface and at depth, offshore from pH correction – coagulation – flocculation – Lamella Settlers-Dissolved Air
Perur, was 48.7 and 73.3 mg/L respectively. These readings are ‘very high’. For Flotation (DAF) – Gravity Dual Media Filters
example, for Sydney desalination plant (250 MLD) the design maximum TSS is 7
mg/L, which is only one-tenth the measurement at Perur.
7.4 pH Correction
The higher concentration of suspended solids at the bottom compared to the
The seawater will be dosed with acid to achieve the optimum pH for coagulation.
surface indicates that the suspended solids have a density slightly higher than sea
The dosing system will consist of duty and standby dosing lances into each pre-
water. Since the seawater intake is located near the seabed, the bottom
treatment train. The pH correction design parameters are summarised in
suspended solids readings are quite relevant to the design of the pre-treatment
Table 9 below.
system.
Seawater turbidity is usually low at 0.5 to 1.0 NTU, however at Perur is high.
Turbidity normally indicates the presence of mineral particles which can cause
colloidal-particle fouling of RO membranes, thus reducing the flux rate of the
membranes. For this reason it is important to reduce the turbidity to an acceptable
level, ie to less than 0.5 NTU, perhaps as low as 0.1 NTU.
Page 61 Page 62
A widely used test is the Silt Density Index (SDI). The test is a laboratory filtration 7.5.2 Flocculation
test detailed in an ASTM standard. The aim of the pre-treatment system is to Flocculation will be provided at the head of each Lamella. Flocculation will be
produce filtered seawater with a Silt Density Index (15 minute test as per ASTM achieved in two flocculation tanks in series with each tank consisting of one or two
D4189 – 95-2002) of less than 4.5 for 100% of the time, under all operating vertical mixers so as to have the mixing energy tapered. Flocculent (flocculation
conditions. aid) will be dosed at the entry to each flocculation tank.
Coagulant will be dosed at the head of each Lamella block. Rapid mixing will be Parameter Units Value
implemented within a concrete structure with at least 30 seconds of detention time.
Design maximum seawater flow, MLD 1110
The coagulation and rapid mixing design parameters are summarised in Table 10
below. Type of flocculation aid polyelectrolyte
Table 10: Coagulation and Rapid Mixing Design Parameters Dose rate – average mg/L 0.1
Design maximum seawater flow MLD 1110 Number of flocculation tanks per cell No. 2
Mixer type Flash mixer Mixing energy (G) – stage 1 s-1 70 – 100
Mixing energy (G) s-1 600 minimum Mixing energy (G) – stage 2 s-1 30 - 50
Mixing time s 30
Page 63 Page 64
7.6 Lamella Settlers Chain and flight scrapers or
Bottom Sludge Removal
Lamella settlers consist of a series of hydraulic vacuum; material of
inclined parallel plates or tubes through construction to be suitable for
which the water passes. The plates are seawater
close together and the suspended solids Clarified water collection Concrete troughs with
travel only a short distance to the plate triangular FRP weir plates
below and then gravitate down the Size provide 18m x7.5 m
inclined plate and are removed from
the flow. For this reason the
7.7 Dissolved Air Flotation (DAF)
footprint of a Lamella settler is
Dissolved air floatation (DAF) is a high rate process using micro-bubbles to float
relatively small. Lamella settlers
coagulated and flocculated particles to the surface of a clarification basin. A
can quickly remove large amount of
portion of the clarified water is drawn off and passed through a pressure vessel
relatively coarse material. However, the turbidity of the water exiting a Lamella
where the water is saturated with air at high pressure. The pressurized water,
settler may be higher than for plain sedimentation. Notwithstanding, low turbidities
supersaturated with air, is released into the water as it enters the bottom of the
may be achieved by providing filters following the Lamella plate settlers.
basin. The sudden release of pressure causes the formation of micro-bubbles
Coagulation and flocculation are provided prior to the Lamella settlers. The capex
which attach to the preformed floc and carry it to the surface where it forms a thick
and opex of Lamella plate settlers are reasonably low, and they are simple to
floating layer. The float is skimmed off, and the clarified water passes to filtration.
operate.
DAF in general adequately removes TSS of 75 mg/L, but above 100 mg/L there is
Table 12 Lamella Settlers Design Parameters likely to be a higher carryover of solids to the filters, resulting in shorter run times.
The potential for short filter runs can be offset to some extent by the provision of
Parameter Units Value
deep dual media filters. Therefore to mitigate the said situation; two stage filtration
Design seawater flow (average) MLD 1045 with deep filter/media beds have been proposed which shall be capable to take
high load of TSS, while producing the required SDI.
Design seawater flow (peak) MLD 1110
No. of settlers Nos. 24 DAF would be effective in the removal of algae, and should be reasonably effective
in the removal of other marine biomass, such as larvae and jelly fish particulate
Lamella Type and Material Plates/Tubes made from FRP
matter. DAF would be effective in the removal of oils and greases.
with 550-600 inclination with
horizontal Ideally, loading rates for DAF would be set after pilot plant testing, and if time
permits, pilot plant testing at Perur should be carried out to provide data on the
Lamella Surface loading rate m/hr <15
most suitable loading rate.
(vertically projected surface area)
DAF a form of physical treatment of water that involves coagulating impurities then
Lamella Supports Concrete
removing these solids by using dissolved air to float them to the surface of the
water. Residual fine particles that are not floated off are removed by the filters
Page 65 Page 66
downstream.
Parameter Units Value
The flotation cell also requires occasional sludge removal to remove settled solids.
DAF Air Dose Rate mg/L 10
The DAF process is proven across the globe for a range of water treatment
applications including as a pre-treatment process in sea water desalination plants Air Saturator Efficiency % 90
for removal of fine solids and organics. It also copes well with algae because it is
Air Saturator Pressure (Gauge) kPa 800 (nominal)
removed in the flotation step, eliminating the possibility of filter blinding. A
simplified cross sectional schematic is as shown below. Number of air saturator No. 60
Filtration
DAF recycle water will be drawn from the small tank just downstream of gravity
filters to minimize pipework distances and variation in hydraulics.
Filtered water
Air Sludge
saturated water
7.8 Dual Media Gravity Sand Filters
.
Clarified water from the DAF outlet shall feed to the inlet channel of the gravity
Table 13 Dissolved Air Flotation and Filtration Design Parameters filters. Each filter inlet shall include an isolation valve/Gate and in filtering mode,
the feed water shall be fed into the filter, above the filter media, in such a manner
Parameter Units Value so as the filter media is not disturbed. The water shall flow through the filter media,
Design seawater flow MLD 1030 without recycle through filter floor nozzles, and into a chamber underneath the filter floor. Filtered
water shall flow from the filtrate collection chamber, through a flow control or into
MLD 1236 with recycle the tank beneath the filter house or placed separately.
Peak seawater flow MLD 1094 without recycle The inlet distribution channel and the outlet filtered water collector channel shall be
equipped with motorized penstock to isolate and bypass the DMF in case
MLD 1313 with recycle operation and maintenance requirements or as the case may be.
Number of DAF Cells No. 60 When in backwash mode, water from the backwash tank shall be pumped by
dedicated duty/ standby backwash pumps, through control and isolation valves into
DAF surface loading All units online m/hr 8 (with recycle)
a single filter filtrate chamber. The backwash water shall flow up through the filter
rate
media support, up through the filter media, removing filtered solids from the filter
One unit offline m/hr 8.5 (with recycle) bed, and into the backwash water troughs, running the length of each filter. The
backwash water troughs shall be designed to ensure that dirty backwash water is
DAF area per cell m2 90
removed evenly from the whole length of the filter. Backwash effluent shall pass
DAF cell dimensions (internal) m 15 x 6 from the backwash troughs, through the effluent isolation valve, and to the
backwash effluent tank. The system shall ensure that no more than 5% of the top
DAF Recycle Rate % 20
media is lost over a one year period, and this shall be tested during the
Page 67 Page 68
performance test. Backwash Air–water
The type, uniformity, size, and depth of filter media are of key importance for the Average filter cell run duration 24hr
performance of pre-treatment filters. Dual-media filters shall have two layers of Flow distribution to individual cells Tapered concrete to keep velocity in the
filtration media distribution channel above 2 m/s at all times
Filtration Velocity 8m/hr ; N-1: 8.5 m/hr
No of Filter Beds (Twin Section) 40 nos.
Size of each 15.5 x 8.5 m
Table No 14: Media Gravity Filters
Filter cell length-to-width ratio 2:1 approx.
Maximum water depth above filter 2.5 m (should be equal to or slightly higher than
An upper layer of coarse material with low density - typical is
bed filter bed head loss, which usually is 1.8 to 2.4m)
anthracite of 0.5 m -1.0 m depth.
Filter Media Sand
A bottom layer of fine material with higher density for refinement, ES mm 0.6
which typically is sand of depth of 0.8-1.5 m. UC - 1.4
The above filtration medium shall be typically supported by a Depth mm 900
layer of gravel bed. The gravel bed is graded in three to six Anthracite
layers and is located on the top of a filter under drain system ES mm 1.43
UC - 1.3
Depth mm 900
A small water storage tank will be located immediately downstream of each bank of
filters; each tank will provided with an overflow weir to maintain the water level in the
filters, and to store water for recirculation to the DAF process. Two such tanks will be
provided, for equalized flow. Water that overflows these weirs will flow to the Filtered
Water Storages; filter backwash water will be drawn from the Filtered Water Storages
Table 15: Dual Media Gravity Filters A maturation tank is proposed to collect the effluent/wash water of GDMF maturation
Filter type Dual media, down flow process. This tank shall collect also the overflows of filters backwash water tank and
Page 69 Page 70
overflows from dirty water tanks. The effluent from the tank shall be discharged to sea The RO plant will be a single stage/single pass design with an overall recovery of
via outfall. 46%.
The 400 MLD modules will be configured as Seventeen individual trains. Each of
7.9 Gravity Filtered Water Storage the Seventeen (17) RO trains will consist of one RO rack each, with dedicated
Filtered water storage will be located immediately downstream of the Gravity Dual pumping system and Energy Recover Devices (ERDs). The plant is to be
Media filtration system. This will serve as control storage between the filtration designed such that full production can be achieved through Sixteen (16) trains.
system and the RO plant. It will ensure that the flow to the RO trains will be The trains will be configured to allow for each individual train to be isolated for
constant while the production from the pre-treatment system fluctuates due to cleaning, maintenance, or membrane replacement.
backwashing. The tanks have been sized to provide twenty minutes storage at a SWRO membrane elements of 8-inch diameter have been selected. Each
seawater flow of 1110 MLD. pressure vessel will house eight membrane elements. The design treated water
The design parameters for the Filtered Seawater Storage Tanks are summarised TDS for the RO plant is 300 mg/L. No allowance has been made in the RO plant
in Table 16. layout for a second pass RO system.
Table 16 Filtered Seawater Storage Design Parameters In sizing the RO plant an average membrane flux of approximately 13.5 L/m2/hour
(LMH) has been selected. The provision of 8% spare space for more membranes
Parameter Units Value
provides the flexibility to reduce the flux if advantageous for reducing cleaning
Design seawater flow MLD 1110 frequency or reducing power consumption.
Parameter Units Value In order to provide the above pressure range, and based on the design
temperature and salinity ranges as depicted in Section 3, a combination of VSD
Design seawater flow MLD 584
driven booster pumps and fixed speed RO HP pumps has been selected. A
MOC - Concrete with inside schematic of the proposed pumping system design is shown Figure below.
protective coating
Page 71 Page 72
Preference to have majority of pumping capacity driven by a fixed speed
drive and operating at the best efficiency point (BEP)
maximum salinity events. For feed waters with below average salinities further The provision of sodium bisulphite (SBS) dosing is included in the design to
controls would be required in form of a HP throttling valve, essentially reducing neutralize residual oxidants present in the feedwater due to intake shock dosing.
(burning-off) excess energy created by the pumping system upstream. It should This will be controlled by measurement of oxidation reduction potential of the
be noted that correct sizing of the RO pumping system is critical, as under-sizing SWRO feedwater. The details of the bisulphite dosing system are sated in
will not achieve the required permeate flows and over-sizing may require excess approaching sections.
pressure to be burnt-off at the throttling valve.
8.5 Scale Control
An alternate option would be equipping the HP pumps with a VSD, while the
booster pumping system would be equipped with a fixed speed drive, only Provision for scale control by means of antiscalant dosing is included in the design.
providing sufficient pressure to overcome friction and head-losses within the The sulphuric acid addition as part of the pre-treatment system will also assist with
cartridge system, as well as ensuring adequate NPSH is available. Reasoning prevention of scaling. Refer to chapter 9 for details of the antiscalant and acid
behind not further pursuing this alternate option was informed by the following dosing systems.
matters:
The cost of large high voltage variable speed drives for high wattage HP 8.6 Reverse Osmosis Pumping and Energy Recovery System
pumps is significant
The energy recovery devices will be an isobaric design. Either the Energy
Inclusion of a variable speed drive would (permanently) reduce the energy Recovery International (ERI) or Calder DWEER technology could be used. The
efficiency of the associated drive by 2% to 3% design is based on the Calder DWEER technology but both suppliers are
considered acceptable.
Page 73 Page 74
Details of the booster pumps are shown in Table 18. Table 19 High Pressure Pumps Design Parameters
Design parameters for the high pressure RO pumps are shown in Table 19. Since
the High Pressure RO pump is a fixed speed pump it is important that the pressure
capability is not too high as that could lead to significant power wastage with new
membranes and warm/low salinity feed water.
Page 75 Page 76
Table 20 Energy Recovery System Design Parameters
Parameter Unit Value
L/s 69
Page 77 Page 78
The membrane design parameters are shown in Table 22. Normal production will
Total number of membranes per train No. 1920
be using 16 racks to produce 400 MLD of product water at a flux of approximately
13.5 LMH. Total number of pressure vessels No. 4080
Number of RO racks No. 17 To allow trialling and testing of individual elements to determine performance, a single
one-element vessel will be installed and operated in parallel to one of the RO racks.
RO Plant Recovery % 46
Projections are attached as Annexure III to the report.
Material of membranes Polyamide
The piping material for the RO system is as shown in Table 23
Type of membrane/module 8 inch spiral wound
Table 23 Piping materials
Membrane manufacturer Hydranautics, Dow
Piping Material
Active area per membrane element m2 41 (440 ft2)
High pressure feed piping Stainless steel, super
RO membrane flux rate Normal LMH 13.5
duplex, PREN > 43
Maximum LMH 15.5
High pressure feed and concentrate piping and Stainless steel, super
Salt rejection Nominal % > 99.8 headers duplex, PREN > 43
Boron retention Nominal % > 93 Connecting pipework feed/concentrate headers to Stainless steel, super
pressure vessels duplex, PREN > 43
Salt Passage Increase %/a 10
Product headers Stainless steel
Flux Decline %/a 7
Product piping Stainless steel
Average Membrane Life a 3.5
(AMLT) Piping for cleaning GRP
Number of pressure vessels per rack No. 240 Piping for shut-down flushing GRP
Page 79 Page 80
8.8 RO Clean In Place System 24.
After chemical cleaning and prior shutdown of membrane trains, the brine and
spent cleaning solution will be flushed out of the RO and ERD racks using RO
permeate. Flushing prior train shutdown will reduce potential for scale build up
and corrosion, and will also reduce fouling and the amount of high TDS water
produced on start up. The flushing system would consist of flushing pumps and
pipework allowing each RO train to be flushed individually.
Design parameters of the chemical cleaning preparation tank are shown in Table Design parameters for the flushing pumps are shown in Table 26.
Page 81 Page 82
Table 26 Flushing Pumps Design Parameters
Number of pumps No. 2+2 Post treatment of permeate is required to meet the statutory product water quality
requirements. Post treatment will consist of remineralisation/stabilisation and
Flow capacity of each pump L/s 295
disinfection of the water.
Water produced by a reverse osmosis process has very low residual hardness and
8.9 Permeate Storage alkalinity, which renders it very aggressive to most materials including steel and
Two permeate storage tanks will be located immediately downstream of the RO concrete thus causing corrosion and premature aging of assets. The lack of
plant. Each tank has been sized for at least 0.5 hours storage at the maximum carbonate alkalinity as well as the low content of calcium and magnesium (i.e.,
permeate flow. The design parameters for the Permeate Storage Tank are very low hardness) causes desalinated water to be unstable and prone to
summarised in Table 27. wide variations in pH due to its low buffering capacity and its inability to form
protective calcium carbonate films on pipe walls, which makes it corrosive.
Table 27 Permeate Storage Design Parameters Therefore, before the permeate from reverse osmosis be supplied to customers, it
needs stabilisation also known as remineralisation or conditioning to prevent this
Parameter Units Value
from happening.
Number of tanks No. 2
Product water remineralisation for corrosion protection has two aspects:
Nominal volume per tank ML/tank 4.6 (1) protection of water distribution systems and household piping and fixtures from
damage caused by corrosion, and
Minimum residence time hr 0.5 (all tanks, at full plant
capacity) (2) maintaining the desalinated water quality in terms of aesthetic appearance
(color and taste).
Item Requirement
Page 83 Page 84
0.74 mg/L of hydrated lime (0.56 mg/L of quicklime) and 0.88 mg/L of carbon
dioxide would need to be added in order to increase desalinated water hardness
9.1.2 Hydrated Lime & Carbon Dioxide and alkalinity by 1.0 mg/L (as CaCO3) each. Therefore, for a target
Water shall be stabilised by the addition of carbon dioxide and lime (calcium recommended dosage of alkalinity and hardness in the product water of 100 mg/L,
hydroxide). The calcium is dosed via limewater, which is produced by mixing the water produced by the desalination system will need to be treated with 74 mg/L
powdered hydrated lime with reverse osmosis permeate using a clarifier. As the of lime and 88 mg/L of carbon dioxide.
lime available in the country contains impurities a considerable volume of waste is The lime product used for remineralisation is usually delivered and stored at the
generated by the limewater clarifier. This waste is relatively inert and could be desalination plant site in silos as either powdered hydrated lime or as
readily dried onsite. pebble-lime (CaO), which is than slaked to generate hydrated lime [Ca(OH)2].
This lime slurry is blended with the fresh water produced by the desalination
process and is thoroughly mixed in lime saturator tanks to create saturated
limewater, which is then injected into the unconditioned desalinated water.
The majority of desalination plants are designed to produce finished water of total
(calcium and magnesium) hardness of 80 to 120 mg/L as CaCO3. Since
desalinated water usually contains less than 2 mg/L of magnesium, over 90
Left to Right: Lime Silo, Limewater Clarifier, Carbon Dioxide Storage Vessels
precent of the total hardness of drinking water conditioned with lime is calcium
Carbon dioxide gas is added to the water. It reacts with the dosed lime to form
hardness.
calcium bicarbonate, which buffers the water and increases the resistance to
changes in pH and thus reduces the corrosivity of the water. Carbon dioxide and
9.1.3 Key design Criteria
lime are currently in common use all parts of the world for treatment of drinking
Lime Silo and Slurry System
water supplies for the said purpose. The Perth Seawater Desalination Plant (130
MLD) uses the said process for portabalization. Lime is delivered to the desalination plant site as bulk powdered hydrated lime,
which is stored on site in cylindrical metal silos with a 60° cone bottom (lime bins).
Equipment typically required for dosing of lime would consist of: lime storage silos, These silos are often the tallest structures on the desalination plant site and
mixing vats, limewater clarifier, lime-water storage tank and dosing pumps. Carbon usually have a diameter between 2.0 and 6.0 m with a height of 5.0 to 15.0 m.
dioxide would be stored and dosed using a proprietary package plant consisting of They are equipped with air vent filters and with bin vibrators to promote flow of lime
storage vessels, evaporators and dosing venturis. from the silo into a transition bin hopper. The feed of lime is controlled by a rotary
The remineralization using lime and carbon dioxide follows the chemical reaction discharge (airlock) valve, which is motorized and closed or opened automatically
presented below: based on the level of lime in the hopper. Lime silos are typically welded/bolted
stainless-steel structures equipped with level sensors, a fill line with long-radius
2CO2 + Ca (OH)2 → Ca (HCO3)2
elbows, and a truck hose loading fitting with dust cap.
Page 85 Page 86
Carbon dioxide is delivered to and stored at the desalination plant in compressed Component/Parameter Specifications/Design Criteria
liquid form [20 bars] of pressure at 20°C. A typical carbon dioxide feed system Type Electric
consists of liquid carbon dioxide storage tanks equipped with refrigeration units, Capacity, horsepower/kg 0.01–0.02
vaporizers, vapor heaters, carbon dioxide dosing system with pressurized gas CO2.day
solubility panel, and an in-line gas feed diffuser.
Key design Criteria Carbon Dioxide and Feed System
Liquid CO2 storage tank cost not used commonly. UV disinfection is a relatively new disinfection method
(refrigerated) even though it was also discovered approximately at the same time as the other
Page 87 Page 88
formation of residuals which remain in the water for longer periods of time
protecting the system from bacterial contamination. Rearranging the formula to determine the time required for the adequate disinfection is
expressed as:
Necessity for Disinfection of RO Process Water
t = (1/k) log(No/ Nt)
The need for continuous disinfection of the process water has been questioned,
since reverse osmosis permeate will have a relatively low/nil level of
Since the number of micro-organisms can never be zero no matter how much
microbiological contamination. The reverse osmosis treatment process will remove
disinfected the water is, the percentage of removing micro-organisms can never be 100%.
the majority of organic matter present. This results in a limited amount of short
However, majority of the water treatment plants must be able to remove or inactivate
chain carbon compounds available as a food source for micro-organism growth.
99.9% (3-log) of Giardia cysts and 99.99% (4-log) of viruses (Critttenden et al., 2005).
However to have a residual chlorine in the distribution network chlorination is
Some micro-organisms are more vulnerable and have less resistance to certain
envisaged for the treated water out of the proposed plant.
disinfectants therefore only 90% (1-log) reduction is required.
Theory of disinfection and Chlorination For effective disinfection there are numerous parameters that are required for killing
or inactivating micro-organisms. This includes the residual concentration, the time at
The rate of change in the number of viable organisms is the product of the reaction which the water is in contact with the disinfectant, the water temperature, the pH balance,
rate constant for particular disinfectants and the number of viable organisms and the type of disinfection used.
(Tebbutt, 1992). It is expressed as:
If the concentration of disinfectant, C, measured in milligrams per litre (mg/l), and
dN/dT = - kN the contact time, T, measured in minutes, are multiplied together it will produce a
value known as the CT value. This value is required to produce adequate parameters in
order to achieve the required log requirements. Different micro-organisms will require
Where k = rate constant for particular disinfectants different CT values therefore, in general, the contact time and the concentration of the
N = the number of viable organisms. disinfectant must be able to remove the most resistant of the micro-organisms. It is
important for the water system to have an adequate CT value so that the water is treated
This expression is also defined as Chicks Law and is the first-order reaction of a
properly before being distributed.
uni-molecular reaction (Crittenden et al., 2005). Integrating the formula and
changing to base 10 gives the formula: In alkaline conditions, chlorine is more
effective and in acid conditions, the
Log (Nt/No) = - kT
hypochlorous acid is more effective.
Therefore it is recommended that the
Where;
typical pH for disinfection should be
Nt = Number of micro-organisms at time t
lessmthan 8 and if chlorine is used,
No = Number of micro-organisms initially
then a lower pH is better.
k = 0.4343 K
Chloramine, which can be formed
during a chlorine and ammonia
Page 89
Page 89
chemical reaction, is a combined residual chlorine and is also an useful disinfectant. Government of India, it is necessary to obtain a storage license when five or more
Break point occurs once all the ammonia is reacted and the combined residual containers are to be stored. For obtaining the storage license safety equipments are
chlorine is converted back to free chlorine (Refer figure above). Increasing the chlorine essential along with scrubber system. Also the building has to be constructed as per
concentration also increases the free-chlorine residual, however increasing it beyond the norms suitable for storing toxic gas cylinders with adequate ventilation systems and
break point is counterproductive due to the production of nitrogen and nitrogen tri- handling accessories. Further as per Manufacture, Storage and Import of Hazardous
chloride, chemicals that have a strong unpleasant odour. Chemicals Rules, 1989 maximum of 10 tonnes can be stored at site
The break point is a good indicator when to supply sufficient amounts of chlorine to remove Chlorine Dosing Rates
any excess ammonia without the risk of producing less welcoming products including di- The recommended chlorine dosing rates for Potable water are;
chloramine and nitrogen trichloride. Continuous disinfection of potable water using gaseous chlorine at a concentration
ranging between 2.0 – 3.0 mg/L, to achieve a residual chlorine of 0.2 mg/l as per IS
10500.
Chlorine Dosing Considerations
Disinfection of the produced water will be carried out using a standard chlorine gas system.
It is important that personnel, engaged in chlorine plant or in any activity involving handling Both the process and potable quality product waters will be dosed. To achieve is
of chlorine, should understand the hazardous properties of chlorine and should have a minimum Residual chlorine in distribution system, 5 mg/l of chlorine shall be dosed
good grasp of the basis of preventive measures. This will make them more conscious using 30 kg/hr. (3 W + 2 S).
about safety which would not be achieved if they are trained to follow certain instructions
mechanically. In India, Chlorine is deemed to be· an explosive, when contained in any Table 29: Liquid Chlorine Characteristics
metal container in a compressed or liquefied state, within the meaning of the Indian Properties
Explosives Act, 1884. The filling, possession, transport and importation is governed by the
Appearance Greenish Yellow
Gas Cylinder Rules, 1940.
Physical state Liquefied compressed Gas
Cylinders should be stored in an upright position. They should be
secured to prevent from falling over. Vapour pressure @ 35oC 27.48 mm Hg at 20oC
Full and empty cylinders should not Boiling point /Range -34 °C (at 1 Atmospheric Pressure)
be stored together. Then containers
Melting point/Freezing Point -101°C
should be stored on their .sides.
Vapour Density (Air Density= 1) 2.49
They should not be stacked or
racked more than one high. All Liquid Density(Water density = 1) 1.47 at 20oC
safety measures shall be as per IS Solubility in water 0.7 % at 20oC
4263 latest edition Code of Safety
Odour Irritating, Bleach like Choking Odour
for Chlorine and IS 10553 (Part I)
1983 Requirements of Chlorination Others Soluble in alkali’s
equipment for its safe operations. Also according to the “Compressed Gas Cylinder Act” Specifications
Page 90 Page 91
Chlorine Content Min.V/V 99.8% 10. CHEMICAL SYSTEMS
Moisture 150 ppm Max. The following chemicals will be required as part of the pre- treatment process:
Residue on Evaporation Shall leave no residue when Table 30 Desalination Plant Chemicals List
evaporated on clean white tile
Chemical Name Chemical Use
Specification of Chlorine Tonner
Antiscalant RO scale prevention
Water Capacity (approx.) Kg. 780
Carbon Dioxide Post treatment for water stabilisation
Chlorine Capacity (approx.) Kg. 930
Chlorine Gas Post treatment for disinfection
Design Pressure, Kg/cm2 19.9 (process & potable product waters)
Inside Diameter (approx.) mm 760 P i
Coagulant f di h hl i
Ferric Chloride
Shell Thickness, mm 10
Hydrated Lime Post treatment for water stabilisation
Dished Ends Thickness, mm 9.6 (Min.)
Flotation Aid - Polyelectrolyte DAF flocculation aid
Overall Length (approx.) mm 2085 Limewater clarification aid
Clarification/Filtration Aid -
Tare Weight (approx.) Kg. 620 Polyelectrolyte
Sodium Hydroxide RO CIP
Valve Outlet 5/8”
Preparation of sodium hypochlorite
Thread 14 tpi bsp (Caustic Soda)
solution
Sodium Hypochlorite Shock dosing for intake biofilm control
(prepared from
Sodium Metabisulphite Protection of RO from oxidants
RO CIP
Sulphuric Acid pH adjustment and scale control
RO CIP only
Miscellaneous Chemicals
(eg: Biocide, Detergent, Ammonia, Acids: Hydrochloric, Phosphoric, etc)
Page 92 Page 93
10.1 Antiscalant mixing will be achieved by other means. At this stage the type of antiscalant to be
Antiscalant is required to be dosed into the reverse osmosis system to manage the used has not been determined. This will be assessed at the next design stage.
Design RO system feed ML/d 1008 Table 32 Carbon Dioxide Dosing Design Parameters
flow rate
Carbon Dioxide Dosing Units Value
Antiscalant concentration % 100
Carbon Dioxide Dose Rate
Form of supply 1000 L IBC
Maximum mg/L 90
Dose rate mg/L 0.7
Average mg/L 60
Dosing point RO High Pressure
Carbon Dioxide Dose Average kg/hr 1085
Pump suction main
Carbon Dioxide Vessels Number Of No. 10
Antiscalant consumption kg/day 706
Capacity tonnes 25
Specific gravity of dosing 1.2
solution Carbon Dioxide Storage At peak flow days 6
Standby No. 5
10.3 Chlorine Gas
Dosing pump capacity L/hr 2.5 Chlorine is required for disinfection of the product water and for shock chlorination
Number of antiscalant storage tanks No. None – direct feed Chlorine will be supplied as liquefied gas in 900 kg drums. The unloading of
from IBC chlorine drums from transport trucks will occur within the chlorine building, thereby
reducing the risk of a chlorine leak occurring outside the building. The system will
It is not proposed to dilute the antiscalant as the flow rates involved can be easily be configured as a vacuum gas draw system with vacuum valves connected
dosed accurately and dilution can lead to degradation of the antiscalant. Adequate directly to the chlorine drums.
Page 94 Page 95
10.4 Ferric Chloride
Design parameters for the proposed chlorination system are summarised in 33. Ferric Chloride is to be dosed to coagulate particles prior to Lamella Settler. The
design parameters are summarised in Table 34.
Table 33 Chlorination Design Parameters
Table 34 Ferric Chloride System Design Parameters
Parameter Units Value
Parameter Units Value
Chlorine for Disinfection of Potable Water
Design seawater flow ML/d 1110
Dose Rate Minimum mg/L 2
Ferric chloride concentration % w/w 42.6
Maximum mg/L 5
Specific gravity of dosing
Treated Water Flow Rate Nominal ML/d 408 1.45
Solution
Maximum ML/d 433.50
Dose rate Typical mg/L 16
Chlorine gas flow range Nominal kg/hr 37
Maximum Mg/l 25
Maximum kg/hr 91
Consumption at maximum
t/day 65.20
Chlorine Consumption Maximum kg/day 2170 flow
Chlorine Storage Dosing flow rate of chemical Typical L/hr 1900 L/hr.
Page 96 Page 97
Table 35 Lime Dosing Design Parameters Table 36 Flotation Aid Polyelectrolyte Dosing Design Parameters
Page 98 Page 99
may also be used for the RO CIP process. The sulphuric acid will be used to provide pH correction for optimum seawater
The redox potential (ORP) will be measured downstream of the dosing point to coagulation. In addition sulphuric acid is required for chemical enhanced
ensure that the dosing is effective. The sodium bisulphite design parameters are backwashing and cleaning of the UF membranes. The design parameters are
Ventilation shall be provided to manage any fumes that may be evolved in the Table 39 Sulphuric Acid System Design Parameters
chemical area.
Parameter Units Value
Table 38 : Sodium (Meta)bisulphite System Design Parameters
Sulphuric acid concentration % w/w 98
Parameter Units Value
Specific gravity of dosing 1.84
Sodium bisulphite concentration % w/v 40 solution
Dose rate (as sodium metabisulphite) Maximum mg/L 30 Dosing flow rate of chemical Typical L/hr 500 L/hr.
Biocide;
Detergent;
Ammonia solution; and
Acids (such as Hydrochloric, Phosphoric, etc)
General storage space only has been included for these chemicals because:
10.9 Sulphuric Acid
The chemicals are used infrequently (say once per year); and Bisulphite);
The facility will be designed to meet the requirements of all of the chemicals that
Cartridge filter (typically 5 micron);
may be used. Between uses, the facility will need to be drained and flushed.
Pipework allowing each RO train to be cleaned individually; and
Design details are provided in the following table.
If required, holding tank to neutralise spent cleaning solution and enable
Table 40 Miscellaneous CIP Chemical Dosing System Design Parameters discharge to environment.
Dosing point RO CIP Tank After chemical cleaning and prior shutdown of membrane trains the brine and
Specific gravity of dosing solution varies spent cleaning solution should be flushed out of the RO and ERD racks using RO
permeate. Flushing prior train shutdown will reduce potential for scale build up and
Number of dosing pumps Duty No. 1
corrosion.
Standby No. 1
The flushing system would consist of flushing pumps and pipework allowing each
Dosing pump capacity kL/hr 2
RO train to be flushed individually.
Number of tanks No. 2
11.1 Process water storage Screenings will be flushed from the screens into wire baskets and the wash water
from the screens will be returned upstream of the screens, and the screenings will
Treated process water will be stored on site prior to being transferred to the city for
be disposed of to a municipal landfill.
consumption. The criteria for the storage tank are summarised below;
Number of units : 35 ML (2 hours storage for average flow), Waste Water will be generated in the pre-treatment system by the following
Tank geometry : to suit site hydraulics and cost optimisation, Lamella settlers – settled sludge.
DAF float
Covered
Filter backwash from gravity dual media filters.
11.2 Process water transfer pump station
The design criteria adopted for design of the pump station is therefore as follows; All the discharges will be directed to the ocean via the outfall.
Nominal pump station duty : 2800 m3/hr with no peaking, 12.3.1 Membrane CIP Wastewater
The waste from the limewater clarifier will be dewatered and trucked from the site
as a solid. The total provision for the same has been made in the potablization
area.
The desalination plant will discharge rejected seawater concentrate and other
12.3.4 Spent Membranes
Spent membranes will be disposed of to a credited inert landfill. These will need to waste streams into the ocean via an outlet pipeline.
be rinsed with fresh water (or permeate) prior to disposal. The criteria adopted for Section 1 of the outlet pipeline are as follows;
Coastal currents flow from south to north from August to October and from north to
south from November to March each year. The currents from the south to the north
are stronger than the currents from the north to the south. For this reason the outfall
will be located to the north of the intake, as at Nemmeli. Consideration was given to
locating the outfall at about 700 m offshore, generally along profile 25 ( of Sea Bed
Sesmic), albeit at an angle to the profile. At 700 m offshore the seabed is about 7.5 m
below chart datum, and the sediment cover over the acoustic basement is about 6 m.
This site is considered an acceptable candidate site for a pipe jacked outfall
Note *
The head required to discharge seawater concentrate is provided by the residual seawater
concentrate pressure after the reverse osmosis process. This pressure would otherwise be fully
recovered and therefore has to be supplemented to make up for the loss of head to the outlet
pipeline. The outfall pipeline can therefore be considered as consuming energy (as with a pump
station) with an associated operating cost.
13.2 Diffusers
The outlet pipeline will discharge seawater concentrate and other waste flows into
the ocean via a system of diffusers. These comprise a large number of small
diameter nozzles discharging jets of seawater concentrate from the seabed into the
water body to entrain dilution flows. Wider dispersion of the saline plume is
achieved through the action of wind, waves and currents. Both the seawater
concentrate jets and the dispersion will be modelled using appropriate computer
models. The adopted criteria for the diffuser design is summarised as follows;
It is anticipated that the concept design and cost estimate of the HV infrastructure
and electrical plant will include and take into consideration the following:
System security;
System reliability;
Determination of appropriate voltages and load currents for the main pump
motors and other large motors as appropriate;
Redundancy requirements;
Environmental impacts; Breakers and other hardware etc. as required. Each outgoing bay shall be
provided with 110kV/11.5kV, 40/50MVA transformers. The 11kV output of these
Lifecycle costs.
Transformers shall be terminated on 11kV Indoor Switch-Board (4-Incoming
A level of security and redundancy will be determined for the reference design. Feeders, 3-Bus Couplers and approx. 20-24 Outgoing Feeders) located in the Main
The appropriate Indian Standards will form the basis for the design of electrical Receiving Sub Station (MRSS) building to further distribute the power to various
works including standards for: loads / load centers / sub stations at 11 kV / 0.433 kV through underground cables.
Earthing The MRSS building shall be located adjacent to the proposed 110kV switchyard.
Protection All protection and metering equipment of 110kV system outdoor switch yard shall
be installed in Relay and Control panel located in control room on the first floor of
Switchgear, etc.
MRSS Building. Remote Tap Changer Control panels (RTCC) of 40/50 MVA
IEC Rules requirements will also be considered in the design.
transformers shall automatically regulate the Transformer input voltage. The RTCC
14.1.3 110 kV / 11 kV Substation within the Plant premises and 11kV (MV) Switchgear (receiving input supply from Transformer output) shall
be installed in the MRSS substation.
A 110 kV / 11 kV transformer shall be provided for the electrical supply to the
seawater intake pumps, the reverse osmosis high pressure pumps and the process Medium Voltage (MV) shall be 11 kV, 3-phase, 50Hz and Low Voltage (LV) shall
water transfer pumps. The L.T supply shall be from HT Panels. This substation will be 433V, 3-phase & Neutral, 50Hz.
be a double bus bar Air/Gas Insulated System type built with the latest
14.1.4 Power Distribution
technologies, maximum operational safety and environmental friendliness
a. Medium Voltage (11 kV) Distribution System
according to IEC 61850 and TNEB. Two incoming lines, coupler and four feeders
will be considered in the substation as minimum. The secondary of each power transformer shall be connected to 11kV, 3000A MV
Two transformers 110/11 kV, ONAN / ONAF, will be installed and it is necessary to switchgear in Main MV Switch Board through 11kV, 2500A MV bus duct.
consider civil works space for other two equal transformer (similar than Microprocessor based multifunction meters with RS 485 connectivity will be
considered). The capacity of one transformer will be enough to feed the total provided for metering system. Numerical protection relay with communication
demand. Besides, it will contain all common equipment, no-load compensation and capability will be provided for protective functions of various feeders. The energy
necessary maneuvers considering three feeders in 11kV from spare transformer as data of the various 11kV feeders and the input energy data will be passed on to
The estimated power requirement of the plant is 85MWe. Tamil Nadu Electricity The power from Main MV Switch Board in MRSS Building to plant loads shall be
Board (TNEB) has proposed to set up a 230/110kV Over Head Line Outdoor distributed via 11kV Switchboards located close to the electrical loads in different
Switch Yard Sub-Station at a distance of approx. 750mtrs away from the 400 MLD process departments through 11kV (UE) cables. The MV loads are basically 11kV
SWROD plant site. motors / pumps etc. and 11kV/433V Distribution Transformers.
The planned SWRO 110kV switch yard shall be equipped with two incoming line
bays, one bus coupler bay and four outgoing bays. The various bays of the switch
Each feeder module of the MCC shall incorporate a mini-processor for serial bus ii. Illumination
connectivity, and shall be connected to the CPU through daisy-chain serial data An energy efficient illumination scheme for the process buildings shall be provided.
link. Further, the MCCs shall comprise of all equipment for a safe remote control of The illumination in process buildings shall be arranged by use of energy efficient
the different plant sections and consist of process power feeders only. luminaries suitable for High Bay / Low Bay mounting depending upon the structure of
the building. Adequate lux level shall be maintained for safety and ease of plant
operation.
14.1.5 Power Factor Correction
Sufficient number of lighting distribution boards shall be considered for automatic
For maintaining a high overall power factor, static / automatic power factor control
control of lighting fixtures at the various locations of the plant.
capacitor banks of suitable kVAR rating and voltage grades shall be considered, as
required. Street Lighting shall be preferably on solar energy.
across the stator switch terminals of respective 11 kV MV motors, wherever iii. Cabling
required.
Overhead ACSR Panther Conductors have been envisaged from TNEB 230/110 kV
For compensation of LV loads, multi-step Automatically Controlled Capacitor sub station to 400MLD SWROD Plant’s 110kV, 85 MW Switch Yard.
Banks shall be installed for connection on the respective departmental PCCs and
11kV Bus Ducts have been envisaged from the output of 31.5/40MVA Transformers
MCCs to improve the power factor to 0.95 or above.
to Main MV Switch Board located in MRSS Building.
14.1.6 Electrical System Component The cables from MV Switch Board in 11kV MRSS to various departments and further
to process building shall be through underground cables.
i. Drives
The type of drives considered shall be based on following requirements: Following type of cables shall be used in the plant:
Speed / torque characteristics of the driven equipment Power (MV) : 11 kV (UE) PVC sheathed XLPE insulated Aluminium cables
Power (LV) : 1.1 kV PVC sheathed XLPE insulated copper/Aluminium cables
Enclosure protection depending upon the work environment Control : 1.1 kV PVC sheathed PVC insulated Cu cables 1.5 and 2.5 mm2
Instrumentation : 0.6 kV screened PVC insulated copper cables, 0.5 and 1.0 mm2
Performance characteristics, i.e. high power factor and efficiency at
operating points iv. Earthing/ Lighting Protection
Accuracy and range of speed control required for specific application. System earthing and earthing of MV and LV equipment’s shall be considered for
safety of operating personnel as well as for proper operation as per the requirements.
All motors, generally above 250kW (>250kW) shall be connected at 11kV and Copper rod earth electrodes connected together with strip shall form the main earth
motors up to 250kW (<=250kW) at 433V. mat, which shall be interconnected together.
Power saving equipment like Medium Voltage AC Variable Frequency / Speed Earth continuity conductor shall be run along with major cable routes to provide
grounding to the equipment. Tall structures shall be protected against lightning by
(MVAC) Drives (with converter transformers, wherever required) and Low Voltage
The control system for the desalination plant will be compatible with the overall
14.1.7 Pumping station electrical works, controls and electrical systems control system and the design will take into account the following requirements:
Voltages and load currents for the RO high pressure pumps and process water The Process Control System (PCS) architecture covering the connection of field
pump motors (and any other large motors) will be 11 kV. Soft start or VSD’s will be instruments, controllers and associated input/output (I/O), Human Machine
provided for large motors (>400 kW). Interfaces (HMI), communication networks and network equipment will be
designed for a process plant availability of at least 98%. This implies that that
the control system itself will have a system availability of at least 99.9%;
14.1.8 Emergency power generation
Use of equipment with a proven track record;
Battery backed UPS systems will be provided for instrumentation, telemetry,
Provision of redundancy for critical items;
emergency lighting and communication systems.
Redundant controllers, networks, power supplies in all locations;
The DC and UPS system shall be redundant (2 x 100% batteries, 2 x 100%
220VDC rectifiers, 2 x 100% 24VDC converters, 2 x 100% 230A inverters), DC Ensuring maintainability of selected equipment and standardisation of equipment
system shall be sized for a minimum period of 2 hour of standby operation. and spares;
One emergency diesel generator (EDG) set shall be provided. The EDG shall be Fibre optic will be provided as the primary bearer to link all units.
mounted in an outdoor soundproof metallic canopy with anti-vibration supports and Process controls and equipment designed to fail to the safest condition;
a high grade exhaust silencer. It will be designed for 24 hours continuous operation
I/O & instrument voltages selected to suit equipment and provided with battery
and maximum 250 hours operation per year.
backup.
14.1.9 Electrical Equipment All on site power, control and communication cables to be run in accordance
Electrical equipment design will be in compliance with IEC Standards. with current industry practices, codes, standards and regulations;
Lightning protection will be provided for all facilities. Surge protection is to be The HMI interface system on site will be suitable for the application, control
considered for all facilities to provide protection to communications and other system requirements in terms of functionality, speed, durability, local support;
electronic based equipment. All HMI systems will display alarms, alarm histories and trends. All data must be
stored for more than twelve months;
14.2.2 Plant Operation Methods
All PCS and communication systems will have at least 20% spare memory, I/O
The following aspects of the plant operation will be taken into account in the design
and communication capacity;
of the control system, alarm system, supervisory system and system
Each controllable drive will have a local control station comprising an emergency
communications.
stop (hard wired in the emergency stop circuitry for the drive which is not
All plant operations will be designed for automatic operation and minimal
disabled in auto mode), a local stop button and a local start button (for starting
requirement for manual intervention;
the motor under maintenance /manual mode of operation). This local control
The desalination plant and process water pump station will be monitored 24 station will include a jog button when appropriate for some mechanical
hours per day; equipment;
Outside of the manned hours of the desalination plant and pump station, The PCS will incorporate monitoring of key alarms for other plant auxiliaries such
operations or maintenance will only be in response to automated alarm as the main low voltage electrical reticulation, building services and fire
notification to nominated personnel on call; suppression system.
For backup to the automated alarm notification outside of manned hours, the site
will also have 24 hour monitoring of all operating parameters and alarms;
Operating protocols will be established such that only the desalination plant will 14.2.4 Off Site Communication
have control “ownership” of the complete water supply system. The minimum design requirements of the control system for off-site communication
The following are the minimum requirements of the control system: The control system will communicate the water transfer system parameters and
The desalination plant will be controlled by its own stand alone control system. alarms to the mine control system to enable the mine operators to monitor the
This will include all equipment, cabling, buildings and services necessary for a transfer system parameters & alarms;
complete system; The water transfer parameters will also be viewable though the PCS at the mine
The Process Control System (PCS) will be of the same manufacturer, make, processing site. The transfer pumps can only be controlled from one location at
model, firmware as that used for the magnetite process plant and will follow the any time.
Chlorine Building;
Workshop;
Buildings will generally be of concrete foundation slabs, sheet metal clad, insulated
and suitable for cyclonic conditions with a design life of 30 years. Buildings shall
comply with the relevant Indian Building Code.
The Finished Floor Level (FFL) shall be a minimum of 300 mm above the external
finished ground level. External parking, laydown and walkway areas shall be
landscaped and illuminated.
15.1.2 Platforms, Access Ways and Stairways All Internal roads shall have a minimum carriage width of 6.0 m. Roads will be
wider in areas adjacent to chemical storage facilities to allow a chemical truck to be
Platforms, access ways and stairways will be included in the design to allow
unloading without restricting through traffic. Road widening will also be required at
sufficient access for operations and maintenance. Ladders will be avoided
bends to provide sufficient room for turning of a trailer. Road cross fall shall
wherever possible.
generally be designed at 2% for sealed pavements and 5% for unsealed with
vertical and horizontal alignment to be designed in accordance with MORTH
15.1.3 Lifting Devices
publications.
Lifting devices will be included in the design where necessary. These will include
electrically operated Cranes (EOT’s) for removal of pumps and air blowers etc.
Gantry cranes will be provided RO buildings and the Chlorine building. Mobile
15.3 Site Services
cranes will be required to move pumping and other equipment to a suitable truck
All electrical and communication services will be located in suitable underground.
loading area.
Site pipework will be buried where feasible.
15.2 Road works
15.4 Storm water Drainage
The desalination plant area will be designed as a large, evenly graded area with
provision for adequate access to the plant such that vehicles will not need to cross Local drainage design around buildings will be based on a 1 in 5 year average
open drains. Grading around the plant will be arranged to ensure drainage away recurrence interval. Collector drains will be based on a 1 in 20 year return period
from the plant at an appropriate grade to minimise the potential for ponding or and over-all site drains will be designed for 1 in 100 year rainfall intensity. Drainage
flooding. flows will generally be handled by drains mostly covered. The drainage design will
be checked for a 1 in 100 year average recurrence interval rainfall event to ensure
Working areas around the desalination plant will be surfaced in a road base or
that no facilities (including electrical equipment) suffer any permanent damage
appropriate capping layer to provide all-weather hard standing areas for
from such a storm.
maintenance traffic. Areas of significant traffic, such as around workshops and
offices and roads between facilities plus roads surrounding and internal to the Storm water drainage from all facilities shall be contained and directed into run-off
process plant shall be bitumen sealed. Any areas that are sensitive to vehicle channels. Drainage from process overflows will be returned back to the process.
impact, in particular building edges, workshop door openings etc, exposed items
such as fire hydrants and other vulnerable infrastructure, shall be protected by 150 15.5 Fire Systems
mm diameter steel bollards painted or marked (in reflective material) and, filled Fire services will be compatible with the requirements of Health, Safety and
with concrete or by roadside type guardrail. Environment and relevant standards.
16. PRODUCT WATER MAIN is maintained in the pipe. Hence, for closed conduits the hydraulic grade line
slopes according to the head loss.
Sound planning dictates the standard design criteria in the planning and design of
Therefore, pipe sizing is based upon taking consideration of following factors:-
pumping/ transmission mains. Pipelines are designed in accordance with the
Quantum of flow ( Q in m³/s)
maximum anticipated flow conditions; hence pipelines need to be sized to carry
Fluid velocity (V in m/s)
water during these events without excessive pressure losses.
Pressure (m in terms of water column)
Head loss (m in terms of water column)Pipe material
A water transmission system is the physical works that deliver water from the water
C-factor (Hazen-Williams coefficient of friction dependent on pipe material)
source to the intended end point or user. It is designed to deliver sufficient water
quantity and quality to meet the requirements of the customer. Typically, this is The governing equation is given by,
achieved by way of pumps and motors, water mains, service pipes, storage tanks D= [4*Q/(π*V)] 1/2
or reservoirs, and related equipment, Where,
in a closed system under pressure. D= Internal Dia. Of pipe (m)
The transmission main is normally Q= flow (m³/s)
designed for the carrying capacity V= velocity of fluid (m/s)
needed to supply water demand on
the maximum consumption day at a Transmission by pumping is applied in cases when the water has to be transported
constant rate. All hourly variations in over large distances and/or to higher elevations. The pumping head is the total
the water demand during the day of head, and comprises the static head plus the friction head loss for the design flow
maximum consumption are then rate. The pump to be selected must be able to provide this head at rated flow.
assumed to be evened out by the
service reservoir. The head loss corresponding to the design flow rate can be computed for several
pipe diameters using Modified Hazen William Equation.
A water system has two primary requirements: First, it needs to deliver adequate h = [L (Q / CR) 1.81]/ (994.62*D4.81]
amounts of water to meet consumer consumption requirements plus needed fire CR = pipe roughness coefficient
flow requirements. Second, the water system needs to be reliable; the required D = internal diameter of pipe in m;
amount of water needs to be available 24 hours a day, 365 days a year. h = friction head loss in m;
L = length of pipe in m; and
In a pipe unlike the free-flow, the hydraulic gradient and not the slope of the
Q = flow in pipe in m3 / s
conduit will govern the flow. The hydraulic laws of closed conduit flows, also
Each combination of the pumping head and corresponding pipe diameter should
commonly called pressurized flows, apply in the design of the same. Pressurized
be capable of supplying the required flow rate over the required distance, and up to
pipelines can be laid up- and downhill as needed, as long as they remain at
the service reservoir. Smaller pipe diameters will require a higher pumping head to
However, Cast iron, Ductile iron and Carbon steel are generally only used for
large-diameter mains and also in cases where very high pressures necessitate
their use in small- or mid-range diameter pipes. Due to heavy weight and lower
flexibility, CI pipes are becoming less advantageous than DI, despite lower prices.
Moreover CI pipes are brittle as compared to DI pipes. Stringent measures that
have to be introduced while handling these pipes involve the prevention of the
production and inhalation of fibre dust (use of special saws cutting under wet
conditions, protection masks for the workers, etc).
Since DI pipe above 1.1m dia are not available commercially, hence all pipes
above 1.1m dia shall be Carbon Steel as per IS 3589 with internal Cement
Concrete Lining (CC) lining in accordance with Is11906 or ISO 4179 and outside
fusion bonded epoxy coating for prevention for corrosion and all pipes below or
16.1.1 Pipe sizing and pump capacity for 550 MLD A Pipe sizing based on internal design pressure
A.1 Selected pipe ID ID mm 2900 2800 2600 2500 2500 2400 2300 2200 2200 2100 2100 2000 2000 1900 1900
A.2 Pipe OD OD mm 2940 2840 2634.4 2534.4 2534.4 2434.4 2332 2232 2232 2132 2132 2032 2032 1928.4 1928.4
Capacity 550.00 MLD
6.37 M³/S A.3 Design Pressure Dp kg/sqcm 2.346 2.754 3.57 4.182 4.182 4.998 5.916 7.14 7.14 8.772 8.772 10.914 10.914 13.872 13.872
Design
LENGTH 60000 M A.4 Td deg.C 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50
Temperature
C 0.8 -
kg/sqcm
TOTAL STATIC HEAD (ΔH) 6 M A.5 Allowable stress Sa 1311.43 1311.43 1311.43 1311.43 1311.43 1311.43 1311.43 1311.43 1311.43 1311.43 1311.43 1311.43 1311.43 1311.43 1311.43
(g)
PIPE MATERIAL (MS) IS 2062
Corrosion
A.6 allowance for C cm 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16
carbon steel
Weld joint
A.7 efficiency for J 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85
REQUIRED PUMP ERW pipes
ACTUAL STATIC
CALCULATED DIA SELECTED HEAD INCLUDING SELECTED
DESIGN VELOCITY UNIT VELOCITY (Q/C)^1.81 994.62 D^4.81 HEAD
(ø M) DIA (ø M) MINOR LOSS (10 %) PUMP HEAD (M) y factor (as per
(M/S) (ΔH) HEAD IN
IN 'M' A.8 ASME B31.1 table y 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4
Kg/Cm² 104.1.2(A))
1 M/S 2.846947987 2.9 0.96 42.69 994.62 167.5461 6 15.37 22.91 23.00 2.346
1.1 M/S 2.714458399 2.8 1.03 42.69 994.62 141.524 6 18.20 26.02 27.00 2.754 Minimum Tc = ((Dp x OD x
1.2 M/S 2.598896054 2.6 1.20 42.69 994.62 99.08817 6 25.99 34.59 35.00 3.57 A.9 calculated pipe 0.1)/(2 x (y x Dp + mm 8.19 7.96 7.50 7.28 7.28 7.05 6.82 6.59 6.59 6.37 6.37 6.14 6.14 5.90 5.90
thickness Sa x J)) + C) x 10
1.3 M/S 2.496938563 2.5 1.30 42.69 994.62 82.05243 6 31.39 40.53 41.00 4.182
1.4 M/S 2.406110204 2.5 1.30 42.69 994.62 82.05243 6 31.39 40.53 41.00 4.182 Mill negative
1.5 M/S 2.324523298 2.4 1.41 42.69 994.62 67.42424 6 38.20 48.02 49.00 4.998 A.10 tolerance for pipe M % 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5
thickness
1.6 M/S 2.250710005 2.3 1.53 42.69 994.62 54.94281 6 46.88 57.56 58.00 5.916
1.7 M/S 2.183509431 2.2 1.67 42.69 994.62 44.36629 6 58.05 69.86 70.00 7.14 Minimum required
1.8 M/S 2.121989743 2.2 1.67 42.69 994.62 44.36629 6 58.05 69.86 70.00 7.14 wall thickness T* = Tc / ( 1 -
A.11 mm 9.36 9.10 8.57 8.31 8.31 8.06 7.79 7.53 7.53 7.28 7.28 7.02 7.02 6.75 6.75
(after considering (M/100))
1.9 M/S 2.06539315 2.1 1.84 42.69 994.62 35.47111 6 72.61 85.87 86.00 8.772 mill tolerance)
2 M/S 2.013096227 2.1 1.84 42.69 994.62 35.47111 6 72.61 85.87 86.00 8.772
2.1 M/S 1.964580755 2 2.03 42.69 994.62 28.05138 6 91.81 107.00 107.00 10.914 Selected
thickness of pipe
2.2 M/S 1.919411941 2 2.03 42.69 994.62 28.05138 6 91.81 107.00 107.00 10.914 A.12 (based on internal Ts mm 20 20 17.2 17.2 17.2 17.2 16 16 16 16 16 16 16 14.2 14.2
2.3 M/S 1.877221912 1.9 2.25 42.69 994.62 21.9182 6 117.51 135.26 136.00 13.872 load thickness
2.4 M/S 1.837697024 1.9 2.25 42.69 994.62 21.9182 6 117.51 135.26 136.00 13.872 calculation)
REQUIRED PUMP
ACTUAL SELECTED HEAD
CALCULATED SELECTED STATIC HEAD INCLUDING
DESIGN VELOCITY UNIT VELOCITY (Q/C)^1.81 994.62 D^4.81 PUMP IN
DIA (ø M) DIA (ø M) HEAD (ΔH) MINOR LOSS (10 %)
(M/S) HEAD (M) Kg/Cm²
IN 'M'
1 M/S 2.013096227 2.1 0.92 12.18 994.62 35.47111 6 20.71 28.78 29.00 2.958
1.1 M/S 1.919411941 2 1.01 12.18 994.62 28.05138 6 26.18 34.80 35.00 3.57
1.2 M/S 1.837697024 1.9 1.12 12.18 994.62 21.9182 6 33.51 42.86 43.00 4.386
1.3 M/S 1.76560219 1.8 1.25 12.18 994.62 16.89899 6 43.47 53.81 54.00 5.508
1.4 M/S 1.701376842 1.8 1.25 12.18 994.62 16.89899 6 43.47 53.81 54.00 5.508
1.5 M/S 1.643686187 1.7 1.40 12.18 994.62 12.83687 6 57.22 68.94 69.00 7.038
1.6 M/S 1.591492307 1.6 1.58 12.18 994.62 9.589967 6 76.59 90.25 91.00 9.282
1.7 M/S 1.543974326 1.6 1.58 12.18 994.62 9.589967 6 76.59 90.25 91.00 9.282
1.8 M/S 1.500473337 1.6 1.58 12.18 994.62 9.589967 6 76.59 90.25 91.00 9.282
1.9 M/S 1.460453502 1.5 1.80 12.18 994.62 7.030706 6 104.47 120.92 121.00 12.342
2 M/S 1.423473994 1.5 1.80 12.18 994.62 7.030706 6 104.47 120.92 121.00 12.342
2.1 M/S 1.389168374 1.4 2.07 12.18 994.62 5.045171 6 145.59 166.15 167.00 17.034
2.2 M/S 1.3572292 1.4 2.07 12.18 994.62 5.045171 6 145.59 166.15 167.00 17.034
2.3 M/S 1.327396343 1.4 2.07 12.18 994.62 5.045171 6 145.59 166.15 167.00 17.034
2.4 M/S 1.299448027 1.3 2.40 12.18 994.62 3.532381 6 207.94 234.73 235.00 23.97
A.2 Pipe OD OD mm 2140 2040 1934.4 1834.4 1834.4 1734.4 1632 1632 1632 1532 1532 1432 1432 1428.4 1328.4
A.3 Design Pressure Dp kg/sqcm 2.958 3.57 4.386 5.508 5.508 7.038 9.282 9.282 9.282 12.342 12.342 17.034 17.034 17.034 23.97
Design
A.4 Td deg.C 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50
Temperature
kg/sqcm
A.5 Allowable stress Sa 1311.43 1311.43 1311.43 1311.43 1311.43 1311.43 1311.43 1311.43 1311.43 1311.43 1311.43 1311.43 1311.43 1311.43 1311.43
(g)
Corrosion
A.6 allowance for C cm 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16
carbon steel
Weld joint
A.7 efficiency for J 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85
ERW pipes
y factor (as per
A.8 ASME B31.1 y 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4
table 104.1.2(A))
Tc = ((Dp x OD x
Minimum
0.1)/(2 x (y x Dp
A.9 calculated pipe mm 6.39 6.17 5.93 5.71 5.71 5.48 5.25 5.25 5.25 5.02 5.02 4.79 4.79 4.78 4.55
thickness + Sa x J)) + C) x
10
Mill negative
A.10 tolerance for M % 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5
pipe thickness
Minimum
required wall
T* = Tc / ( 1 -
A.11 thickness (after mm 7.31 7.05 6.78 6.52 6.52 6.26 6.00 6.00 6.00 5.74 5.74 5.48 5.48 5.47 5.20
considering mill (M/100))
tolerance)
Selected
thickness of
pipe (based on
A.12 internal load
Ts mm 20 20 17.2 17.2 17.2 17.2 16 16 16 16 16 16 16 14.2 14.2
thickness
calculation)
REQUIRED
ACTUAL STATIC PUMP HEAD SELECTED
CALCULATED SELECTED DIA
DESIGN VELOCITY UNIT VELOCITY (Q/C)^1.81 994.62 D^4.81 HEAD INCLUDING PUMP
DIA (ø M) (ø M)
(M/S) (ΔH) MINOR LOSS HEAD (M)
(10 %) IN 'M' HEAD IN
Kg/Cm²
1 M/S 1.486770097 1.5 0.98 4.06 994.62 7.030706299 6 34.88 44.36 45.00 4.59
1.1 M/S 1.417579666 1.5 0.98 4.06 994.62 7.030706299 6 34.88 44.36 45.00 4.59
1.2 M/S 1.3572292 1.4 1.13 4.06 994.62 5.045170546 6 48.60 59.46 60.00 6.12
1.3 M/S 1.303983636 1.4 1.13 4.06 994.62 5.045170546 6 48.60 59.46 60.00 6.12
1.4 M/S 1.256550073 1.3 1.31 4.06 994.62 3.532380874 6 69.42 82.36 83.00 8.466
1.5 M/S 1.213942701 1.3 1.31 4.06 994.62 3.532380874 6 69.42 82.36 83.00 8.466
1.6 M/S 1.175394966 1.2 1.54 4.06 994.62 2.403597776 6 102.02 118.22 119.00 12.138
1.7 M/S 1.140300611 1.2 1.54 4.06 994.62 2.403597776 6 102.02 118.22 119.00 12.138
1.8 M/S 1.108173001 1.2 1.54 4.06 994.62 2.403597776 6 102.02 118.22 119.00 12.138
1.9 M/S 1.078616395 1.1 1.83 4.06 994.62 1.581607864 6 155.04 176.54 177.00 18.054
2 M/S 1.051305217 1.1 1.83 4.06 994.62 1.581607864 6 155.04 176.54 177.00 18.054
2.1 M/S 1.025968838 1.1 1.83 4.06 994.62 1.581607864 6 155.04 176.54 177.00 18.054
2.2 M/S 1.002380195 1.1 1.83 4.06 994.62 1.581607864 6 155.04 176.54 177.00 18.054
2.3 M/S 0.98034717 1 2.21 4.06 994.62 1 6 245.21 275.73 276.00 28.152
2.4 M/S 0.959705971 1 2.21 4.06 994.62 1 6 245.21 275.73 276.00 28.152
Minimum Tc = ((Dp x OD x
A.9 calculated pipe 0.1)/(2 x (y x Dp + mm 5.05 5.05 4.81 4.81 4.58 4.58 4.35 4.35 4.35 4.12 4.12 4.12 4.12 3.88 3.88
thickness Sa x J)) + C) x 10
Mill negative
A.10 tolerance for pipe M % 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5
thickness
Minimum required
wall thickness T* = Tc / ( 1 -
A.11 mm 5.77 5.77 5.50 5.50 5.24 5.24 4.97 4.97 4.97 4.71 4.71 4.71 4.71 4.44 4.44
(after considering (M/100))
mill tolerance)
Selected
thickness of pipe
A.12 (based on internal Ts mm 20 20 17.2 17.2 17.2 17.2 16 16 16 16 16 16 16 14.2 14.2
load thickness
calculation)
18.1 Purpose of the Plan Shows how Occupational Health & Safety issues are addressed explicitly within the
Commissioning Work Packs, procedures and work method statements; and
The Overall Commissioning describes the methods and processes to be used by the
contractor during the commissioning phase of the project. The associated activities 18.3 GLOSSARY OF TERMS
include preparation of documentation such as ITPs (Inspection and Test Plan),
Component Smallest element of the plant identified for
procedures, work method statements and ITRs (Inspection and Test records),
commissioning (e.g.: pump, blower)
construction verification, pre-commissioning, commissioning, hand-over and training. CP Commissioning Program
CPU Control Processing Unit
This document covers the whole Desalinated Water Supply System and its constituent
ESS Electrical SCADA System
parts.
FAT Factory Acceptance Test
FD Functional Description
18.2 Objectives
DCMP Design & Construction Management Plan
The objectives of this plan are to ensure that: DRMP Document Records Management Plan
There are no safety incidents or environmental non-conformances; ITP Inspection and Test Plan
All aspects of commissioning are planned and prepared in advance; ITR Inspection and Test Record
The commissioning proceeds in an integrated, planned and organised manner; JSEA Job Safety & Environmental Analysis
The plant provides water as fast and as efficiently as possible; and MSDS Material Safety Data Sheet
The Commissioning Test requirements of the Commercial Milestones are PCS Plant Control System
achieved. PMS Plant Management System
SSMS Security Site wide Management System
The Overall Commissioning Plan: Sub-System A collection of Components which act together to effect a
process (eg: a single DMPF including valves, instrumentation
Defines the organisational structure, roles and responsibilities for the & control, a single RO rack including pumps, valves,
Commissioning team; instrumentation & control)
Lays out the process for planning, controlling and reporting all commissioning System A collection of Sub-Systems which act together to effect a
process (eg, Pre-treatment Stream 1 consisting of backwash
tasks; system, backwash effluent system, 24 DMPFs, etc)
Sets out the Work Breakdown Structure to be used for commissioning; V&V Verifications and Validations
Describes how Quality Assurance documentation (Check Lists, Inspection and Test WBS Work Breakdown Structure
Plans, Non Conformance Reports) will be developed, reviewed, approved,
monitored in progress and completed;
Gives the format for the various commissioning documents that must be produced
and describes the tasks to be performed: procedures, and ITRs;
This is certainly possible within the process streams themselves (Pre-treatment and
Reverse Osmosis: Streams 1& 2);
The HV power supply is treated as a separate asset for commissioning due to its scale
and its non-redundant nature;
A preparation phase where dedicated teams develop the Commissioning Work Packs
(all documentation required for the activities to be done after, mainly Commissioning
Procedures, Test.) by process areas (Pre-Treatment, RO, and Potabilization) with
other concurrent preparation tasks handled separately.
Before any commissioning task can commence, relevant key activities of Construction
must be completed in the areas relevant to the concerned Components, Sub-Systems or
Systems. Hand-overs between different stages will be the occasion to carry-out thorough
defects inspection, the concept being to have major defects rectified before the next
involved party starts work.
All temporary construction material and equipment will be removed to allow the
Commissioning Team to take over the designated areas/facilities.
commissioning phase: System testing System is described as a number of sub-systems being combined.
From the example above, a system would be the integration of the
two sub-systems to become the ferric sulphate pre treatment
Commissioning stage/
Definition chemical system.
activity
Process commissioning Process commissioning is defined as the integration of the systems
Factory Acceptance Testing of equipment off site at the point of manufacture prior to
contained within a facility or plant area. Using the above example the
Testing delivery to site. The items to be FAT will be nominated in the Scope
ferric sulphate system would be integrated with the other pre
of Work document in the Procurement Package.
treatment chemical dosing systems
Construction Verification Construction verification stage is defined as a series of checks and
Plant integration Plant integration is defined as the integration of all facilities or plant
inspections of all civil structures, mechanical equipment, pipework
areas that make up the desalination plant.
and fittings, electrical equipment, instrumentation and control
equipment to ensure construction and installation is in accordance
with contractual specifications. Testing will include: point to point
tests, pressure and leakage testing of pipework, leak testing 18.7 Commissioning Process & Interfaces Management
vessels/structures. Testing will use temporary hydraulic/electrical
power and temporary seawater and freshwater supply except for
In order to adequately plan the commissioning activities, the Commissioning Manager will
concrete structures that will be tested with potable water. (This work
is performed by the construction team with commissioning monitoring liaise closely with the relevant area / discipline manager during the Construction,
the work) Energisation and Pre-Commissioning stages. Some of the issues to be co-ordinated are
Pre-Commissioning–Dry Pre-Commissioning–Dry stage is defined as activities undertaken to as follows:
test the functionality of all components making up the asset system;
for example, testing motors, pumps, checking valves open and close.
Testing will use installed hydraulic/electrical power Status of installation, inspection and equipment documentation;
Pre-Commissioning– Wet Pre-Commissioning–Wet stage is defined as operating an asset
Anticipated components and sub-system work completion dates;
without chemicals in accordance with approved commissioning
sessions to verify the design criteria as detailed in the Engineering Priorities from commissioning perspective;
Design Report
Process of acceptance and hand-over of component and area to the Commissioning
Component testing Component testing will be undertaken as part of pre-commissioning Team;
and commissioning and will include supplier factory works testing and
onsite testing and checks. For each component, the commissioning ‘Permit to Work’ system and requirements;
team will verify that all required checks have been carried out, with
Defects to be rectified before and after hand-over.
acceptable results. These checks will be carried out prior to system
commissioning. The Commissioning process is an integrated approach between process equipment and
Sub-system testing Sub-system is described as a number of components which interact systems as well as related Control Systems. Those different phases are part of the same
and are connected; mechanically, hydraulically or electrically. An process and cannot be separated. The main phases of the commissioning will correspond
example of this would be the loading system for the ferric sulphate
pre treatment chemical, or the dosing system of the ferric sulphate. A in the Commissioning Lifecycle to the following 4 main steps:
sub-system test demonstrates the interaction of the components.
The panel mounted PCS PLC hardware is subject to FAT prior to issue to site ‐ All field accessories (OLM, I/O racks ...);
construction for installation. This test covers: ‐ All field wiring network cables, FO;
‐ All interconnecting cables including Power.
Visual inspection of cabinet for finish, labelling, colour;
2) Energisation performs all pre-energisation tests (220 VAC, 24VDC) (continuity, cables
Power up of the cabinet. Check of power and earthing, and apply power;
isolation/earthing...) to allow the release of the Notice of Energisation.
I/O testing for each point. Test each hard point by signal injection and monitor it;
Within each energisation ITP, a Commissioning and/or Control System witness point will
Redundancy testing for each paired device. Run a test program and withdraw the duty
module to confirm fail over to the standby module. be defined.
The Reports of the steps 1 and 2 above should be combined in the Hand-over certificates
PLC/SCADA Software FAT
issued to Commissioning for each item of equipment installed on site. The final state of
The device FAT is a functional test for each I/O point, to confirm the link from the hard I/O any devices, network, Systems.etc should be that all above have been completely
through to the software library block. performed prior to start the Pre-Commissioning activities.
One ITR will be issued per component, tagged with a bar code and inserted in the
The individual PLC/SCADA software is subject to FAT against the Functional Descriptions
Commissioning Management System.
documents. This test is from the I/O software block, through all functions of the logic
described in the Functional Description. (iii) Pre-Commissioning Testing (Site)
The Pre-Commissioning-Dry corresponds to the final Energisation of components
Following successful individual PLC/SCADA software FAT for each PLC on the system, including Bump Tests, some additional “no Load Run Test” of components and the SAT
the PLC/SCADA system is pre-tested as a complete system down to CPU level prior to activities of the control system such as:
commenced. commissioning.
(iv) Commissioning Testing Initially, new plant operators will work under the authority of the Commissioning Manager
The Commissioning Testing only occurs once all components are tested; the control and attend commissioning activities. As system commissioning progresses, the O&M
system is operational and mainly consists of putting the plant in operation under normal team will progressively take over the operation and maintenance of the plant under the
process conditions and is called Process Commissioning in the Lifecycle. All tests and direction of the Commissioning Manager.
verification to validate the Process Commissioning are described in each System / Sub-
System ITP. The Commissioning Manager and the O&M Plant Manager will determine and agree on
O&M personnel mobilisation and a training program to ensure the continuity of the ramp-
The following schematic explains the above: up phase between commissioning and pre-operations.
During Acceptance tests, the Commissioning Team will direct the plant operators on
process issues and be responsible for adequate performance of the tests.
By being involved from the start to the completion of the commissioning and interim-
operation phases, the O&M personnel will receive extensive experience in the range of
activities related to sub-systems and overall systems operation. The O&M team will take a
major role in running the overall plant during the commissioning and interim-operation
periods and until Final Acceptance Test.
Commissioning Work Flows outline the sequence of all activities showing all inputs, outputs, interfaces and
responsibilities.
either by being automatically updated when an ITR is signed-off and registered in the Belt tensioning;
will start to produce sludge, the sludge building is necessary in order to treat the waste Dimensional verification
from the filters.
After construction is finished at least some dimensional checks need to be carry on,
Until Seawater availability, RO Commissioning will progress mainly by simulation tests of
mainly related with the correct levelling of the weirs, the right position of the plates and the
the rack automations.
chain sprocket etc.
C.F. has to be draining water by the vents for at least 1 hour before opening the water High pressure pumps performance monitoring;
outlet valve.
Uncoupled motor sequence testing (Tune PID regulation loops);
Identify PV internal leaks, by checking the Conductivity of each individual pressure
vessel and remedy (Conductivity mapping);
Chemical dosing systems will be commissioned using potable water. Since these use Potable water.
common storage and feed systems, all dosing equipment must be commissioned before Shall be commissioned as standalone units, the energisation of the networks through the
the system is drained, cleaned, dried in some cases, and charged with chemical. Control plant will be developed in conjunction with Construction/ Energisation teams in line with
loops, sequences and regulation will be tested and proved. the readiness of the Plant Systems.
In the specific case of Sulphuric Acid, the calibration cylinder only will be filled with water 20.8 POWER
to commission the system without sending water through the lines. The complete system
20.9 Main Power Supply
will be dried before acid is allowed to be introduced.
General
Chemical dosing pumps will all be commissioned. Dosing delivery pipes will be Commissioning activities shall commence after the completion of the construction
disconnected after the pumps skid and water pumped return to the storage tank. activities including completed QA documentation required for the satisfactory hand-over to
After establishment of appropriate licenses and operating permits and installation of the commissioning team.
suitable barriers to safely segregate the chemical storage and handling facilities, the One of the most import elements is the earthing, earth grid installation and testing to
chemicals tanks will be filled. ensure that the installation is in accordance with the design documents and provides the
appropriate level of safety to the personnel and the public when the system is energised
First, the chemical dosing system of the Pre-treatment will be commissioned. The and in service.
chemical dosing system for the Sludge treatment system will also be commissioned in
order to be ready for the process commissioning of the DMF.
with the design documents. All resistance values per test will be recorded and entered onto a cable check sheet,
signed off by the relevant Installation Supervisor/Project Engineer and entered into the
This testing ensures that a trip from one location operates the appropriate circuit breaker/s Systems/Area work pack.
in other locations. This testing will also prove the circuit breaker fail to trip protection.
All Earth Loop Impedance tests to be carried out in the afore mentioned method..
Lightning Protection testing will be carried out as a point to point test with the
measurement being between the top of the Dynasphere to the down conductor’s
relevant earth stake/ground connection.
Plan and implement hazard identification and risk assessment to ensure all OH&S
risks are identified and assessed;
Develop and implement control measures that will control or eliminate hazard/risk.
To ensure the safety of all personnel, access to commissioning activities and nearby
areas shall be tightly controlled. Ownership of an area containing components to be
energised or commissioned will transfer to the Energisation or Commissioning Manager
(respectively) upon acceptance of handover from the Area Construction Manager.
This handover will be evidenced by placement of demarcation (clearly labelled fencing,
bunting, tape, etc as deemed appropriate and as agreed by the Construction Area
Manager and Energisation/Commissioning Manager) around the perimeter of the area
handed over.
Post demarcation, a Commissioning Access Permit will be required each day (from either
the Energisation or Commissioning Manager) to enable access within the demarcated
area for that day.
Upon completion of Commissioning, the demarcated area shall be handed over to control
of the O&M Manager.
Specific OH&S procedures will be developed for all high-risk commissioning activities,
including electrical energisation.
22.1 General
Vendor Equipment Manuals Factory Instruction
FAT’s
Training for Commissioning team members, including the O&M team is fundamental to Off
Vendor Training Documents Special Equipment Operators
Site
achieving quality test results. Training management and co-ordination is the responsibility Training
Special Training Equipment Maintenance Personnel
of the Commissioning Manager. The documenting and recording of the training is the
Commissioning Commissioning Records
responsibility of the Commissioning Completions Manager. Documentation
A Training Plan shall be developed for the training of Commissioning (as required on
Vendor Equipment Manuals Vendor Training Major Classroom & Field
equipment, control systems, etc) and O&M personnel in the operation and maintenance of Equipment Instruction
Vendor Training Documents
the plant. This plan will cover the technical and operator training provided by the D&C Operators
Pre-Commissioning-Dry /
Pre-Commissioning-Wet
Special Training Equipment
contractor for the commencement of operations. Maintenance Personnel
Operation Manuals
The level and extent of training will be dependent on a number of factors and will include: ‘Operational Readiness’ Classroom & Field
Operation Training Training Instruction
Documents
Level of competency of operators and maintenance personnel. Operators
Commissioning Training
The maintenance philosophy for the plant (i.e. extent of maintenance to be done by Maintenance Personnel
O&M personnel and that outsourced to external providers/vendors). Plant Operating Philosophy
Plant Integration
Training Capacity
enable familiarity with the plant through participation with the commissioning team in the
Sampling
commissioning and plant start-up phases. This ‘hands on’ training becomes the informal
training whilst the ‘formal’ training will be addressed by the Training Plan and will consist
of both class room and field training. The early mobilisation will also permit the necessary
vendor training to be conducted at the time of commissioning specific equipment.
The development of the Training Plan will require the strategy for the operation and
maintenance of the plant to be understood. This strategy will be developed using the
equipment list and /or the procurement package list and will be recorded in a simple
spreadsheet. This strategy will also be used in the development of the O&M Manual.
23.1 MOBILIZATION PLAN & START-UP OF THE OPERATION AND MAINTENANCE 23.1.4 Analytical parameters monitoring
The Mobilization Plan will be set in order to ensure that the staff and organization are fully Analytical parameters shall be monitored continuously with online analytical instrument,
ready to take control of the RO Treatment Plant at the Commencement Date. To fulfill the and also over Spot samples. This continuous monitoring will ensure that all performance
objectives the following steps will be achieved. requirements are met and that the RO Plant operation is optimized.
In order to fulfill the analytical monitoring and to perform a suitable operation, the following
23.1.1 Follow-up of the works and plant start-up analysis parameter should be considered (either online either through manual sampling):
Participation in co-ordination meetings, HAZOP (if any), on-site tests and controls;
Experience sharing and technical advice to the constructor; Seawater inlet
Raw water quality characterization by the laboratory accordingly to a monitoring - Temperature, pH value
control plan; - Conductivity
Active support in plant commissioning; - Turbidity
Recruitment of the Operation and maintenance staff; - Hydrocarbons
Assets inventory and identification; - Residual chlorine
Collection and classification of the technical documentation including drawings and Pretreatment
supplier or manufacturer technical documentations. - Turbidity
Coordination with EPC Contractor for the licenses and permits. - Residual chlorine
Implementation of the commercial relations with the partners for the supply of - SDI
consumables, by-product evacuation and subcontracted services; Reverse osmosis inlet
Definition and organization of the supply chain management with suppliers and clients. - Redox potential
- pH
23.1.2 Process monitoring and follow-up sheets implementation.
A process monitoring schedule shall be implemented and follow-up sheets will allow the - Conductivity
operation staff to follow the variations of every parameter for fast and immediate - Turbidity
interventions and also to insure the effectiveness of the process and the equipments on a - SDI
continuous basis.
- Conductivity implemented by a dedicated maintenance team in order to reduce the risk of RO Plant
- Residual chlorine outage, RO Plant shut down, RO Plant failure and RO Plant dysfunction.
This analyzing capacity will be completed with all routine analysis necessary for the good The implementation of the maintenance program will be achieved by the completion of the
operation of the plant. following steps:
23.2.1 Chemicals Consumptions Monitoring Determination of the frequency and the nature of preventive maintenance and editing
The consumptions of the various chemicals on the plant shall be recorded and totalized of the operating procedures for every equipment
on a daily and monthly basis.
Implementation of a Computerized Maintenance Management System (CMMS) for
23.2.2 Other Monitoring and O&M Log. scheduling, optimization and tracking of Maintenance activities of the equipments. The
CMMS shall generate automatically the maintenance task requests in accordance with
As mentioned above, the monitoring program shall be completed with follow-up sheets on the maintenance plan previously elaborated.
which will be recorded the variations of the most important parameters of the plant. Those
Preparation of the procedures for cleaning, maintenance intervention, painting on
follow-up sheets are going to be configured in order to eliminate the risks regarding
equipment, buildings and works.
process efficiency degradation and also in order to help the operation team to identify the
causes and remedies of any problematic situations. 23.3.3 Suppliers Chain Assessment and Management Plan
In order to insure the quality and the continuity in supplies, a Suppliers Assessment and
A daily O&M log shall also be implemented. This log purpose will be to record the most
Management Plan shall be implemented before the start of the Operation and
important parameters and events over a specific day.
Maintenance period. Although this plan will be applied to all goods and services
23.3 Industrial start-up and routine operation purchased, special attention will be given on sensitive purchases like laboratory reagents
23.3.1 Operation and Production and products, materials quality and oil and grease to name a few. This plan shall cover
Determination of the optimum adjustments to achieve the performance levels; two main aspects:
Treatment of the wastewater in strict compliance with the discharge local standards; Pre-assessment through a questionnaire of every supplier on the basis of their ability to
Treatment of by-products in compliance with environmental regulations; meet the requirements in providing quality products or services,
Control and analysis of the treated water Continuous monitoring through an annual monitoring based on the supplier or client ability
Updating documents and tracking the events and information; to guarantee the required level in product quality or services.
Staff on duty 24 hours a day, 365-days-a-year on site;
Remote monitoring and round-the-clock (365-days-a-year) emergency on-call service.
24. OPERATION: TREATED WATER PRODUCTION MANAGEMENT Coordinate actions with the maintenance management. These are essential to
ensure constant plant operation in order to achieve the contractual results,
24.1 General principles
The Operation Manager (as process engineer) monitors closely the performances of
Good production management is strategic for: the various treatment stages and decides new settings or parameters adjustment to
Ensuring constant treatment quality, improve the global result.
Managing energy consumption and reagents,
Shift teams for round-the-clock operation. These teams managed by a team leader
Resuming service in the event of a failure,
are in charge of monitoring all treatment areas parameters and operate the facility
Identifying discrepancies and restoring normal parameters,
Optimizing the overall operating cost. outside office hours;
Several day teams organized by treatment areas and responsible for the production
of their area, by performing day-to-day tasks, such as reagents handling and
removal of by-products, plant preparation for maintenance, routine maintenance and
occasional operations, such as structure drainage. They provide cover to replace
shift absentees, etc.
Within this perspective, the basic principles to be applied are the following:
The Operation Manager gives the teams, operation instructions. These instructions
are either permanent or updated daily. They are issued as tables for numeric data,
or in the form of messages on the “instructions book”;
The sampling activities, the results of all analyses from the laboratory.
24.2 Application
The operating hours of the main equipment like the HP pumps
24.2.1 Work to be carried out
The daily consumptions of chemicals.
The list of all production-related tasks to be carried out shall be prepared by the plant Measurement of all gauges and recorders performed.
manager and is known as the Job Plan. All reports generated by the SCADA system.
Description of all maintenance and repair works performed during the day.
Plan operation tasks, Description of all malfunctions, incidents and breakdowns.
Quantities of all materials, products, and substances stored at and removed from the
The Job Plan defines: RO plant.
The tasks to be performed and their frequency;
The volume of treated water produced daily.
Duration of the tasks and the required qualifications of the staff involved.
Staff working hours on site.
The readings and reports are noted on sheets. These sheets are then archived either in
A methodical and structured examination of the Job Plan ensures a professional approach
paper format or in computer format in the monitoring system. In this case, important data
to the resources needed to achieve the service required.
will be saved, if necessary, in duplicate, to ensure a permanent record. The data is then
24.2.2 Procedures collated manually or by computer to prepare the monthly and annual reports.
During industrial start-up, the plant manager institutes an operating procedure manual.
24.3 Supervision with SCADA System
This manual describes for each piece of equipment:
Supervision is used to:
The operation, the inspection procedures,
The potential incidents, Provide an overall view of all parameters affecting or having affected process in
order to understand the present situation and so optimize operation;
The measures to be taken in handling these incidents,
Generate statistics reports.
The communication route between the different persons involved.
Navigation in this program is via a user-friendly graphic interface. The program will be
installed on the report PCs and will be parameterized according to the operator’s
The operator’s needs are: requirements. Parameterization consists in defining with the operator:
To control the process and take action from a control room The data acquired by the program,
To collect permanently and automatically store a great amount of data and then be The data entered and the organization of data entry sheets,
able to edit it accordingly to a redefined frame. The calculated data,
The site is equipped with a system control and data acquisition (SCADA) for the Coherence checks to be carried out,
monitoring and the control of the plant. This SCADA system will provide: Data reporting models,
Animated mimic charts, Report models.
Controls and adjustments,
24.4 Consumables Management
Events and alarms management (save and acknowledge),
24.4.1 Electricity
Real time and trends data curves,
Network communication. Power consumption in a big size Desalination Plant is a major concern in the operating
expenses and therefore requires particular attentions from the operators.
24.3.1 Reports
We will carry out measurements for all electro-mechanical units installed at the plant. The
correct operation of the plant and the achievement of performance in compliance with the
It is contemplated to supply and implement our report edition program, a Long Term Data
required guarantees are subject to a permanent and reliable availability of electricity
Base tool.
supply.
This fully configurable program can compile technical reports for the operators and the
Client.
Oil and grease for equipment and generators, locally available. To organize maintenance management, it is essential to:
Products and equipment for cleaning premises,
Define the nature and frequency of the Maintenance Service’s operations,
Small tools (workshop consumables, bolts, screws, fixtures, hand tools, etc.),
Define maintenance procedures and then improve them using plant feedback,
Safety-related consumables (individual and portable safety equipment, such as gloves,
Ensure continuous supervision and maintain an up-to-date log.
goggles, boots, shoes, earplugs...),
Small electrical supplies,
Cleaning and degreasing fluids for electro-mechanical equipment,
Office consumables.
Equipment disassembly,
Parts replacement,
Equipment renewal,
Replacement of complete assemblies.
These operations can be scheduled for the short or medium term as a function of tests
carried out during preventive maintenance, a set number of service hours for an
apparatus or in response to an alarm (abnormal noise, repeated cut-outs, weakened
insulation...) or in response to an unforeseen failure.
The Plant Manager will also have indicators enabling him to assess the efficiency of his
maintenance policy. The ratio of the number of Preventive/Corrective operations is
monitored particularly closely to detect any deterioration.
The laboratory is an essential service for production that provides ongoing monitoring of to optimize structure operation and take action as quickly as possible if needed;
water quality at different stages in the treatment process. After analysis of these results, 27.2.2 Equipment and Methods
the process manager determines the parameters adjustment settings and makes sure that The knowledge of the seawater quality, key date for analytical monitoring requires:
the works are operating properly.
- Continuous flow rate measurement,
The analyses are carried out at the most appropriate frequency, and always in compliance - Determination of the treated water quality, either from continuous readings or analyses
of samples.
with the operation requirements. The results are then examined, taking into account the
change in process parameters over time, and result reproducibility. - The application of a quality analytical monitoring system involves the implementation of
appropriate material and equipment to:
The laboratory must above all:
- Measure flow rates under the best possible conditions,
Prepare its sampling and analysis program,
- Take representative samples, and ensure the correct conservation of samples taken,
Provide reliable results that are directly useable,
- Analyze the various pollution parameters necessary to ensure the appropriate
Monitor stocks of reagents and small equipment required for the analyses to ensure it
treatment.
is in a position to meet any specific demand from the process manager at any point in
The representativeness of the results depends on the judicious installation of
time.
measurement equipment up and downstream from treatment structures.
Effective laboratory management makes it possible, through careful examination of the The equipment and methods used are generally covered by international standards.
results obtained (critical thresholds, drifts, trends …) to anticipate actions and adjustments A Water Quality Analyses Plan shall be prepared during the commissioning phase
that will thus avoid malfunctions. showing a precise framework of what shall be performed.
For operation monitoring purpose, analyses are performed at different stages of the
27.2.3 Analytical Monitoring of final water
treatment process according to a program defined by the Process Manager.
The analysis shall be conducted in accordance with standard methods for the examination Samples and Measurement Apparatus
systematic analyses will be extended to include additional analyses as required in requests. He must compile the list of all consumables needed for the proper running of the
response to incidents, such as, storms or sudden changes in seawater pollution. laboratory and manage the necessary stock of reagents and consumables bearing in
mind the following:
27.2.4 Analytical Monitoring of Environmental Impact Assessment
Delivery lead times for each reagent and each type of equipment,
Analyses shall be performed on the outfall to verify the compliance with the limit values Reagent storage conditions and notably use-by dates.
according the Local Legislation.
Operators shall be provided with portable analyzers (pH sensors, analysis kits, etc.) to
carry out routine checks but will rely on the plant laboratory to carry out precise analyses.
The analytical monitoring is carried out in the plant laboratory, equipped in such a way
that it is able to carry out all contractual analyses which have a high frequency of
sampling. Lower frequency analyses for other parameters, will be performed through an
external accredited laboratory.
Analysis results are logged on result sheets. These sheets are saved in paper format or in
softcopy format in the monitoring system. In this case, important data is saved or even
duplicated to ensure a permanent record.
Analysis results are then used manually or automatically by the computer system to
prepare analysis monitoring reports, and the monthly and annual reports.
they concern both the process and the plant’s safety/reliability. goods and reagents” and “Inspection of sub-contracted services” procedures.
It is essential to: All procurements are subject to inspection by the buyer or authorized person.
Inspected goods are used immediately or stored in the designated areas. In the event of
Rigorously monitor their stock so as never to run out, or simply to ensure orders are
placed with sufficient lead-time, the non-compliance with the order, a “supplier anomaly” sheet is opened and is subject to
Make sure of the irreproachable quality of these products upstream from the appropriate processing. The anomaly sheets are part of the supplier continuous
procurements procedure itself.
assessment system.
The key personnel (management team) of the organization are the Plant Manager, the The tasks required for monitoring plant operation and maintenance have been defined as:
Operation Manager, the Maintenance Manager and the OHS officer. The key personnel - Management / Training / Health & Safety / Quality Assurance
selection shall be made in order to ensure a professional and highly efficient management The plant is placed under the authority of a Plant Manager who is responsible for all
by experienced, dedicated and knowledgeable persons. contractual commitments in terms of plant operation and staff management. This item
also involves staff training, awareness of health and safety and Quality Assurance issues
29.3 Management of Human Resources
that are delegated to Quality and OHS officers. The quality officer will be especially in
The effective management of a plant basically, relies on the organization of human
charge of the coordination of the whole training sessions (safety, technical, financial,
resources, which must take into account the following parameters to reach an optimum
environmental…).
result:
Rigorous analysis of the workload, tasks to be carried out, and the level of reliability
- Production / Control - Monitoring
required of the installations,
Ongoing concern, through training, for improving the knowledge of each employee, This item includes all action required to operate the equipment and various processes. It
Definition of common objectives, is, to a large extent, based on analysis of situations and operation parameters to ensure
Realistic attitude to working conditions which leads to Occupational Health and Safety immediate action.
measures,
Ongoing profession levels for all tasks to be carried out,
The gravity of any incident is determined based on the significance of its consequences. A
serious incident is likely to generate significant consequences on employees or other
individuals like Client, subcontractors and visitors, on the environment, on the property or
the RO Plant and even on the quality of services. The following events, to name a few, will
be considered as an emergency situation:
Serious injuries,
Any witness of an emergency situation will be requested to immediately call and forward It is Operator’s policy to take into account all standards relating to occupational health,
the information to a main Standby Safety Coordinator available around the clock at any safety and working conditions right from the very early stages in plant design. This is the
time to receive all alerts. In order to insure that the witness is able to get immediate principle of Integrated Prevention that aims to avoid the occurrence of risks (mechanical,
assistance all the time, an alternate Standby Safety Coordinator will also be available. electrical, drowning or falling, chemical, explosion or fire, and all nuisances caused by
The phone number of the two coordinators will be programmed in every phone set. In noise and excessively high or low temperatures), by eliminating them at the source.
addition the phone numbers will also be posted in numerous locations on a standard
Further, the operator must, when taking over operation of the plant, implement a work
formats the example shown here after.
organization program in compliance with Quality Assurance procedures, make staff aware
The witness will then be requested by the coordinator to provide all the preliminary
of health and safety issues, and make sure that safety rules and work procedures in risk
information available, including:
areas or on dangerous machinery are scrupulously adhered to.
The name, position and telephone number of caller,
Involvement of third parties like Client, neighbors and emergency services, Health and safety considerations for operating water treatment plants are very important
issues because of the diversity of potential risks: rotating machines, automatic machines,
Evolution of the criticity in time (stabilized or not),
electricity, use of chemicals, work in tanks, in confined spaces, dangerous atmospheres
Additional assistance required or not,
(asphyxia, explosion, etc.), near heat units, risk of infection and bacteriological risks, etc.
The impact on the RO Plant.
After gathering the witness information, the Safety Coordinator will be requested to The main divisions in the Operator‘s share holders Safety Action Plan are as follows:
establish a preliminary assessment of the gravity of the incident in order to evaluate the A safety manager based at head office and available to assist sites,
needs or requirements for immediate assistance. In any case the Safety Coordinator will A central Health, Safety Working Conditions Committee,
have to advise the Operator‘s share holders Senior Management as well as Operator‘s
An in-house safety brochure (3rd edition) distributed and discussed with each staff
share holders Safety Department.
member,
Appointment of the plant occupational Health & Safety officer, The following action plans and rules will also be implemented and commented to the
staff:
Creation of a Safety, Health and Working Conditions Surveillance Committee,
- “Crisis situation” action plans, relevant procedures and means to be applied in the
Risk mapping study,
event of a crisis (explosion, pollution, emanation of toxic gas, serious accidents, etc.),
Notices and signs in risk areas,
compiled in liaison with the local Emirati services involved in crisis management,
Noise pollution awareness and mitigation measures,
- “Fire protection and fighting” rules, and relevant checks and procedures,
Environmental awareness and CDR Health & Safety regulations application,
- “Anti-intrusion and anti-vandalism” rules, and relevant checks and procedures.
Availability of essential standard safety equipment,
Supply staff with uniforms and Personal Protective Equipment (work clothes, safety
shoes, ear muffs, gloves, goggles, gas sensors if necessary, etc.),
Work clothes are cleaned and maintained by the company. This task is outsourced to
a specialized company. In this way, perfect health and safety conditions are respected
both at work and at home.
Each staff member is given his or her own copy of the safety booklet specific to our
profession. They also receive training in health and safety from the site Health &
Safety Responsible.
Analysis of any accidents that occur and measures taken to avoid their recurrence,
=> Meeting the customer’s needs, focusing on the transparency of our acts,
=> Improving staff confidence by providing them with training and promoting
initiative and innovation,
The application of this Quality Policy results, in terms of operation, in precise procedures,
in the areas of production organization, maintenance organization and laboratory
organization.
33.2 Certification
Based on a general documentary structure issue from sites experience, a set of
procedures and instructions specific for the RO Plant will be authored. These
organizational procedures will cover the following topics:
- Laboratory
- Production
Further, specifically sea water desalination projects create long-lived assets, with cash
flows that grow slowly, financing requires debt structures with long maturities. The limited
ability and willingness of consumers to pay also requires that debt be amortized over long
periods (15to 25 years) to help minimize annual debt repayments and reduce the
necessity to increase tariffs.
A life-cycle view helps to get better ‘buy in’ from all parties involved. It also provides a
framework for evaluating whether the solution is the most appropriate for the public over
Dual Media Gravity Filters 1,02,02,60,880 Total of Civil and E&M 19,67,96,78,919 17,54,99,261
Reverse Osmosis (RO) 9,61,55,680
Testing,Erection, Commissioning, etc. @ 10% 1,02,27,26,502 1,75,49,926
Potabalization 32,88,88,800 6,02,857
Product water pumps and Disinfection Total E&M and Civil 20,70,24,05,421 19,30,49,187
system 8,55,95,526
Product Water Main inc. all crossing, Contractor Profit and OH 2,07,02,40,542 1,93,04,919
pedestal , intermedite Pumping Station and
6,12,44,95,909
civil works Total of Works 22,77,26,45,963 21,23,54,106
All mixing equipment's and dosing
equipment's including Valves for dosing etc. 40,11,01,875 27,00,000 Freight and Packing, Insurance @ 3% 31,68,13,544.21 52,64,978
1% of Civil and
Total- Grand Inc EB Substation 39,77,87,36,642 3.0% of Project
Value Every Year
Inc. Product Water
US$:INR @ 62.55 8 Maintenance, Insurance etc. main 22,46,575.34 11.47% 5.62
Including Product
9 Depreciation water main 44,15,525.11 22.54% 11.04
O&M costs represent the ongoing costs required to operate the plant, including expenses
associated with replacement membranes, chemicals for pre- and post-treatment, energy
to run the plant, environmental monitoring, and labor for plant operators. Some O&M
costs, such as labor, are fixed, e.g., they do not vary with respect to the amount of water
produced. Other O&M costs, such as for energy and chemicals, are variable and thus
change in response to the amount of water produced. Capital costs are reported as one
time, fixed costs. O&M costs, by contrast, are typically reported as annual costs.