Escolar Documentos
Profissional Documentos
Cultura Documentos
ISSUE 0
LIFTING OPERATIONS
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
CONTENTS PAGE
1 AIM 3
2 APPLICATION 3
3 DEFINITIONS 6
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
1 AIM
To eliminate or minimise the risk of fatalities, injuries and incidents arising from the
performance of lifting operations.
This guideline refers to the Group-wide implementation of the Anglo Fatal Risk Standard
“Lifting Operations” and should be read in conjunction with the respective Standard.
The guidelines contained in this document are considered as "highly recommended" and
deviations are to be documented and justified. Full adherence to these guidelines will not
be a factor in determining compliance with the Standards, since alternative methods can
be available if justified on a risk basis.
In case of conflict with requirements of any other Anglo document or guideline, the
following hierarchy will apply:
It is important that when implementing Standards the organisation takes cognizance of,
and comply with the relevant legal requirements in the country of application.
2 APPLICATION
This Standard applies wherever lifting operations are undertaken. It includes lifts
involving Anglo American owned, hired or contracted cranes and lifting machines such as
mobile, crawler, tower, derrick, portal and pedestal-type equipment (e.g. cherry pickers),
vehicle loading cranes, electric overhead travelling cranes, hoisting blocks/tackle and
monorail cranes. The Standard also applies to lifting equipment including slings, chains,
wire ropes, shackles, pad-eyes, containers, baskets, tuggers, winches, man-riding
winches, jacks, work-belts, harnesses and transfer baskets for equipment and personnel.
This Standard applies to all Anglo American Group managed businesses and operations,
including contractors and visitors when involved in controlled activities.
This guideline has been developed to provide more detail and clarification for the
implementation of the requirements of the Standard. This should enable sites to be more
aligned with each other on what the boundaries are with regards to meeting the
requirements.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
This guideline is by no means exhaustive and will be updated periodically and supported
by good practice sharing. It is not intended as a template for achieving compliance.
The Lifting Operations Standard details the requirements for Anglo owned, hired or
contracted cranes and other mechanical lifting equipment to operate on Anglo owned or
managed sites. It includes the planning, resourcing (equipment), training, competency,
operation, monitoring and auditing requirements and responsibilities. Reference is made
to Appendices providing additional information as needed. The standard requires that a
system of work for the use of cranes and lifting equipment is established and maintained.
Ensuring all lifting operations have been adequately assessed with regards to their risk
Ensuring all cranes and lifting equipment utilised on a lift are fit for their intended purposes
Ensuring all personnel involved in the lift have the necessary skills, experience and
competence to safely perform such lifts
Included are cranes such as mobile, crawler, tower, derrick, portal and pedestal-type,
vehicle loading cranes, electric overhead travelling cranes, and monorail cranes or crawl
beams. The Standard also applies to lifting equipment including slings, chains, wire ropes,
shackles, pad-eyes, containers, baskets, tuggers, winches, man-riding winches, chain
blocks, and workbaskets. Shaft slinging of long or heavy material or equipment below
conveyances in vertical mine shafts, and installation or removal of conveyances, are also
included as a lifting operations, requiring the use of winches and performed by a Rigger.
1. Mine shaft lifting operations
Shaft slinging is the term used for transporting long or heavy equipment down or
up mine shafts. Shaft slinging must be treated as a lifting operation and the
requirements of AA_AFRS_8: Lifting Operations shall apply.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
This guideline does not cover manual lifting operations. Injuries do occur when lifting
using the wrong posture, or lifting heavy items, but this is excluded from the scope of
AA_AFRS_8 so the guideline makes no reference to manual lifting.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
3 DEFINITIONS
Competent person : a person who has the right training and experience to be
regarded as competent under relevant legislation and/or
internal regulations.
External rated : refers to clearly-visible green, amber and red lights mounted
capacity lighting externally to the crane: green to indicate safe operating range,
amber when approaching maximum rated capacity and red
when maximum rated capacity has been exceeded.
Lifting operations : any operation using a crane and lifting equipment that involves
the raising and lowering of a load, including the suspension of
a load.
Controlled Activities/ : Those sites where the Group Company has the authority to
sites determine how to manage the operation.
It does not include monitored or uncontrolled activities.
Monitored Activities : Those sites where Anglo American can exercise some influence
but cannot set Policies and/or comprehensive Control Standards
and/or directly supervise and enforce their application (i.e.
contractor and supplier transporting their goods and/or
personnel to or from “controlled sites”).
Uncontrolled Activities : Those sites where Anglo American does not set or influence
Policies or Control Standards and does not supervise safety
performance. These include services provided by public
Companies, activities performed at supplier or manufacturer
shops, etc.
Where there is uncertainty over whether the activity is controlled, monitored or uncontrolled,
the matter should be referred to the Safety function for determination.
Other definitions and abbreviations used in this Standard
Note: There are various different terms used for equipment, competencies, and activities in different countries
in which Anglo operates. The definitions below give the term used in these guidelines, and where
relevant, alternative terms that may be used.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Anti two-block cut out : a cut out to prevent damage or injuries due to two solid blocks –
or components – being pulled or pushed together. The most
commonly applied anti two-block cut out stops the hoist drum on
a crane if the hook block is pulled up too close to the sheave
block. Additional anti two-block cut outs may be applied to cut
hydraulic power on a mobile crane if the boom is retracted too
close to stops, or if the boom is elevated or lowered too close to
its stops.
Note: in South Africa this would generally be described as an interlocked limit
switch or an interlocked trip switch.
Anti two-block
devices
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
External rated : refers to clearly visible green, amber and red lights mounted
capacity lighting externally to the crane: green to indicate safe operating range,
amber when approaching maximum rated capacity and red
when maximum rated capacity has been exceeded.
Lifting crew : are persons working directly with a crane, or other lifting,
operation.
Lifting equipment : any device which is used or designed to be used directly or
indirectly to lift a load or connect a load to a crane or shaft
conveyance, and which does not form part of a load (e.g. wire
rope slings, chain slings, man-made fibre slings, hooks and
fittings, swivels, shackles, eye bolts, rigging screws, wedge
sockets, plate clamps and lifting beams).
Lifting operations : any operation using a crane and lifting equipment that involves
the raising and lowering of a load, including the suspension of a
load.
Lifting plan : a study which reviews a proposed lift with the specific intent of
providing assurance that the lift can be executed in a safe
manner. This will always include at least: a risk assessment;
identification of loads and lifting equipment capacities; ground
condition; and identification of the personnel to be involved
Note: This may also be referred to as a rigging study or a significant lifting
study.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Load chart : means a chart, or set of charts, specifying the crane chart rated
capacity under all possible operating conditions. These charts
should be provided by the crane Manufacturer crane mounted
on a mobile chassis specifically designed for that crane.
Mobile Crane : a crane mounted on a mobile chassis specifically designed for
that crane.
Note: this is sometimes more fully referred to as a mobile truck mounted
crane.
Risk analysis : a formal, rational process of giving consideration to all the risks
potentially associated with a particular job or project, and
determining what actions are necessary in order to reduce any
risks assessed as being too high.
Note: a similar process, frequently done in Australia is a job safety analysis
(JSA).
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
SWL : means the Safe Working Load for a crane or other lifting
equipment
Note: three equivalent terms used in some countries are WLL – working
load limit or MRC – maximum rated capacity or MML – maximum
mass load.
Tag line : means a line attached to a load during lifting for the purpose of
steadying the load against swinging or rotating
Note: this may also be referred to as a guide line.
Wind Vane Mode : means the method of parking a crane to ensure it will have
minimum resistance to weather conditions prevalent during the
period the crane is parked and unattended. This refers
predominantly to tower cranes and port cranes that are able to
slew. When parked, these cranes should not be locked in a fixed
parking position, so that under high wind conditions they can
swing into the position that minimizes the total wind load on the
crane.
Work basket : refers to a personnel carrying device designed to be suspended
from the hook of a crane or other lifting machine.
Note: this may also be referred to as a work box, a man cage, a boatswain’s
chair or a personal transfer basket.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
It is commonly found that mine workers have made up a tripod, “A” frame, or other
makeshift structure for the purpose of lifting some equipment. Often this makeshift lifting
equipment has inadequate strength for the lifting operation being performed.
5 REQUIREMENTS
This section is structured using exactly the same numbering sequence as the Fatal Risk
Standard document. Each requirement is repeated in a box, followed by a statement of
intent. This is followed by discussion and clarification of that particular requirement with
reference to other related requirements, Appendices and other relevant documents.
Appendices are used to reduce the size of this document, and allow more efficient
continuous improvement.
Detail has been added to some, but not all requirements, as some sections were deemed
self explanatory. Links to associated reference material has been given throughout this
document. The main source of reference material and examples of leading practice can
be found on the Anglo Fatal Risk Standard Quickplace.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
All electrical cranes shall have power supply isolation points capable of being
positively locked out and isolated.
Intent
All energy sources for all cranes and other powered lifting equipment (e.g. air hoists)
must have positive isolation capability to prevent inadvertent operation of the crane
or lifting systems or components (inclusive of mobile cranes and vehicle mounted
cranes). The intent is also to comply with Standard 2: Surface Mobile Equipment
and Standard 6: Isolation (where applicable). Other energy sources such as braking
of hoist drums and wheels, air winches, etc. must be considered.
Note: Although this requirement is aimed primarily at electrical cranes, some mobile cranes have
multiple isolation points to enable the isolation of any potential energy such as the power unit,
hydraulics, freefall mechanism levers and compressed air.
Common Hazard
Although there are many examples of lockable isolation points for electrical cranes,
the intent is that power is removed and access is controlled.
Where the removal of power does not guarantee the total immobilisation of the
crane, alternative measures must be implemented to ensure the safety of the
person/s that intend to work on the unit. Movement of the whole crane or
components of the crane may result from gravity, wind, or other causes.
Leading Practice
Ensure that all access to monorail cranes, electric overhead travelling cranes or any
other type of cranes accessible by a ladder system, is locked out and controlled.
Ensure that all access to walkways along overhead crane rail gantries is locked out
and controlled; unless the walkway is separated from the path of the cranes by
adequate guardrails (see Anglo Fatal Risk Standard No 7: Working at Heights for
information on adequate guardrails).
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Cranes shall have their operability assessed against site conditions and workforce
(e.g. language for the controls) and have fall protection systems provided for
people in charge of their operation, maintenance and inspection.
Intent
Common Hazard
When safe access is not fixed and persons are required to make use of other means
of temporary access, the risk is that at night or away from the workshop, persons will
take a shortcut due to unavailability of these temporary means resulting in injury or
fatality exposure.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Leading Practice
Provide safe means of access to Operator’s cabin or platform.
Provide fall protection to all other raised work areas where practical.
Cranes shall not be used without a physical locking system that disables and
isolates their free-fall capability.
Intent
Cranes equipped with freefall devices require the ability for these devices to be
positively isolated to stop inadvertent free fall of the hook blocks. This isolation shall
be in place unless a particular task may require the use of free fall, in which case a
risk assessment is required and appropriate site authorisation obtained prior to
removal of the locking mechanism to enable the device to operate as intended.
Common Hazard
On some cranes these levers are in an exposed position where accidental activation
is possible.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Electric overhead travelling and portal cranes should have overload protection.
Intent
Overload protection is intended to prevent a crane from lifting a load more than the
SWL thus placing a mechanical, electrical or other risk to equipment, load and
personnel. The overload protection should stop the lifting of the load yet allow the
safe removal of the load. Whilst this requirement refers specifically to electrical
overhead cranes and portal cranes, any other types of cranes and lifting devices
where practical, should not be excluded. In the case of manual winches such as
chain blocks, a portable load cell may be required to confirm the load being applied.
5. Temperature control
Intent
The reason for this inclusion is to stem the effects of fatigue in both hot and cold
climates. Be aware of placement of air conditioning units to allow for safe access.
This requirement is also to ensure a positive cabin pressure with filtered air to
prevent ingress of atmospheric contaminants. Air conditioning and heating allows
the cabin to remain closed which will also have positive effect on reducing operator
exposure to unacceptable noise levels.
Note: be aware of potential fogging issues, particular in underground situations, which may affect
operator visibility.
Common Hazard
The exposure time of the operator to heat or cold is an important factor in the risk
assessment to determine the need for air conditioners or heaters. Even non extreme
environmental factors could have a huge effect on the judgment of the operator
when executing lifting operations. Positioning of the air conditioning units must be
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
carefully planned to ensure that a working at heights risk is not present when
servicing this unit.
Air-conditioning
Safe access to air-
unit on cab conditioning unit
All crane cabins shall have signs to warn against interruption or distraction of the
operator.
Intent
The intent is to prevent distractions and loss of concentration of the crane or lifting
equipment Operator.
This requirement shall be applied to all lifting operations, including shaft slinging
operations in mine shafts. The Crane Operator or the Winder Driver shall not be
interrupted nor distracted in any way.
Note: Ensure that the signage is sized and placed correctly as to enable persons from all possible
approach angles to see.
Leading Practice
Where cranes are controlled via a pennant or radio transmitter, it is Leading
Practice to have positive identification of the operator by wearing a high
visibility jacket containing the words “Do not interfere with me or distract me
while I am busy with a lift” This method will also aid easy identification of the
person operating the crane in particularly busy areas.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
When complex lifts, or shaft slinging operations in mine shafts, are being
performed, a Person In Charge (PIC) should be appointed who should be
clearly identifiable via a special jacket or insignia. The PIC should be a
competent Rigger.
7. Sufficient controls to prevent crushing
Vehicle loading cranes shall have sufficient engineering controls to prevent the
operator from being crushed during lifting operations.
Intent
The intent is to prevent the operator from being crushed between the jib and the
operator station. Where these units are equipped with multiple controls, interlocks
should be considered to ensure that the unit is operated from the safe side at all
times if operated manually. Positioning of personnel involved in a lifting operation is
a key issue for all crane operations.
Common Hazard
Do not rely on operators and their experience or on procedures to work safely with
these types of cranes. Fatalities world wide involved highly experienced operators
with access to good procedures.
Leading Practice
It is possible to use remote controls as an alternative to ensure the Operator is
separated from the danger zone. There is a risk however of the Operator
placing himself in other danger situations if not careful due to the possibility of
being in any position when operating with this remote control unit.
A procedure should be in place to train personnel to avoid these hazards as a
remote control is not a guarantee that lifting will be executed safely. Controlling
the crane from a remote position does of itself not guarantee the elimination of
all hazards or ensure that the operation will be executed safely.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
All crane hooks shall be fitted with a positive locking safety catch.
Intent
The safety catch or safety clip is designed and positioned in such a way as to
prevent the unintentional dislodgement of the suspended load from the hook. These
units are exposed to severe punishment in the normal line of duty due to the hooks
being bumped and dragged in normal operations thus sustaining heavy wear and
tear. Maintenance of these units should be scheduled to ensure that they are always
in good working order.
Note: Should the sling attached to the hook be exposed to a rolling or twisting action, it is possible for
detachment (roll out) to occur and particular attention should be given to this danger when lifting using
this type of attachment.
Leading Practice
A large shackle should be used to connect the sling to the hook. This shackle should
be of adequate diameter to physically stop the safety catch from opening and
causing roll out.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
The safe working load (SWL) shall be clearly identified and marked on all cranes
and relevant lifting equipment and shall not be exceeded.
Intent
To ensure all personnel involved in lifting operations are aware of the Safe Working
Load of a particular lifting device. This is to prevent equipment being overloaded and
for use in planning of lifting tasks. The mass of all components suspended from a
hook, when added together, must not exceed the SWL. This includes shackles,
slings, lifting beams, and the item being lifted. The mass of all components must be
known prior to commencing any lift.
Note: The only time when the SWL is exceeded on purpose, is when statutory load testing is
undertaken by an appropriately qualified person/s undertaking such testing.
Note: It is important to note that SWL is known by different terms in different countries, and may be
noted differently on equipment supplied from different countries. The terms WLL (working load limit) and
MRC (maximum rated capacity) are equivalent terms to SWL. The most common term used in various
countries is listed in Table 9.1.
TABLE 9.1: TERMS USED AS EQUIVALENTS TO SWL
Country Short term Long term Standard
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Common Hazard
SWL not known. This is particularly often the case on monorail hoist beams which
have been repainted, and on tripods and “A” frames made up by mine personnel.
Safe working load of equipment and tackle being used must be known and used in
the calculation for a safe lift. These limits may never be exceeded
The SWL of all hoisting equipment and rigging hardware are based on almost ideal
conditions seldom achieved in the field. It is therefore important to recognise the
factors such as wear, improper sling angle, point loading and centre of gravity that
can affect the rated safe working loads of equipment and hardware.
Mobile crane with SWL clearly marked EOT crane with MRC and serial no
4000 kg SWL rope block Crawl beam with SWL 5000 kg clearly marked
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Intent
Table 10.1 below gives the load monitoring and cut-out requirements as shall (i.e.
compulsory), should (i.e. to be applied wherever practicable – see section
“Requirements” above) or not applicable.
Note: the anti two-block cut out referred here is to prevent the hook block being pulled up against the
sheave block, possibly resulting in rope break. Anti two-block cut outs on retraction and luffing of the
boom should be used where relevant and practicable.
EOT Crane equipped with load cells for all hoisting mechanisms
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Cable
drum
Leading Practice
To also have an audible alarm that activates to alert the crane Operator and Crew
when the crane chart rated capacity is exceeded. The audible alarm is activated
when the crane’s moment indicator over-ride switch is activated or disabled but will
not be activated when the crane is put in rigging mode to pack the crane up and
place the boom in its cradle. This should be interlocked, so that the alarm can only
be cancelled by only one responsible person who holds the key.
Note: There is evidence that continuous exposure at close range to flashing or rotating lights can create
unsafe working conditions.
LED digital type lights are favoured for this type of application because they have
proven to be more robust than bulb type lights. This could reduce potential crane
downtime.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
All cranes and lifting equipment shall comply with the requirements of the relevant
approved design standard. The minimum acceptable design standard shall be the
relevant ISO Standard. In countries where the requirements of the relevant national
standard exceed the requirements of the ISO Standard, the national standard shall
apply.
Intent
To ensure that all equipment used in lifting operations is fit for purpose. Due to the
many standards of design and differences in interpretation, it is very important that a
recognised relevant and approved design standard is followed. Where these
standards are not present, the relevant ISO standard shall apply. The most stringent
of AAplc Standards, ISO Standards and local national standards shall apply.
Leading Practice
1. Ensure that procurement and reconditioning of lifting tackle is very clearly
specified and preferred Suppliers and products established via a technical
specification.
2. Ensure that manufacturing and reconditioning of lifting tackle is done under
proper quality control. The more stringent of AA STD 100 or the
manufacturer’s Quality Assurance procedure shall apply.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
All cranes and lifting equipment shall be identifiable with a unique identity code and
its rated capacity should be visibly displayed.
Intent
For all equipment involved in lifting operations to be issued with an identify number
and documented on a register to facilitate the inspection and maintenance program
and monitoring of compliance. To ensure that users know the safe strength of all
equipment, and that it is structurally sound and fit for purpose.
Note: In the past, colour coding has been used on some sites in South Africa and various other
countries to designate the SWL of slings and other lifting tackle. This practice must no longer be used,
and all personnel must be trained accordingly. The actual SWL shall be clearly marked, either by being
painted on or hard-stamped on a tag.
Cranes
Cranes should be clearly marked with their identity number and their SWL.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Mine shaft conveyances shall be clearly and permanently marked with their serial
number and the maximum shaft slinging load permitted.
Slings
All slings (whether wire rope slings, fibre slings or chain slings) shall be marked with
an identification number and their SWL. This marking should be on a flat ferrule or
permanent attached ring.
In some cases the SWL for use of the sling at an angle of 45 degrees is also
marked, but this is not specifically required. However, ensure that everyone using
slings is aware that their capacity is reduced when used at an angle, and knows how
to evaluate this reduced capacity.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Cranes may be operated from a cabin, using a pendant, or using a remote control
unit. The use of remote control units has unique hazards associated with it, because
the remote control units are not physically linked to the crane. Crane remote control
units generally utilize unlicensed frequencies (in the industrial, scientific and medical
(ISM) bands), with frequency hopping and encryption to ensure that there is no
interference from other radio signals. Specific guidance is provided by the British
Colombia Heath and Safety Act, Part 14 Crane and Hoist. This is a requirement in
British Colombia, and elsewhere it should be applied as leading practice. Section
14.28 requirements 6 to 10 read:
1. A remote control panel for a crane or hoist must be designed to safeguard
effectively against the unintended activation of the crane or hoist.
2. A wireless remote control system for a crane or hoist must incorporate
a. error checking to prevent the controlled equipment from responding to
corrupt data, and
b. identification coding methods to prevent a transmitter other than the
designated transmitter for that crane or hoist from operating the
equipment.
3. A remote control system for a crane or hoist must be designed to ensure the
following:
a. if the power to the remote control system is removed for any reason, all
crane or hoist functions stop;
b. if the control signal for any crane or hoist motion becomes ineffective,
the crane or hoist motion stops;
c. the remote control panel has an operator controlled emergency stop
feature that
i. permits the operator to stop all crane or hoist movement
regardless of a malfunction within the remote control system, and
ii. requires resetting of the emergency stop feature before equipment
operation can resume.
4. A remote control panel for a crane or hoist must be marked to identify the
corresponding base control unit to be used with it.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
5. The maximum distance between a remote control panel and the crane or hoist
being operated by the remote control system must
a. not exceed the limit specified by the control system manufacturer, and
b. be communicated to the operator before the operator uses the crane or
hoist.
Each site shall ensure that a procedure is in place covering storage and use of the
remote control units.
Leading practice
Remote control units must be clearly marked with the identification number of the
crane they control, and they must be kept in a locked cabinet, for which only the
designated Operator has a key.
13. Maximum environmental conditions identified by competent person
Intent
To ensure that personnel involved or affected by lifting operations are not placed at
risk from operating cranes in adverse weather conditions such as high winds, rough
seas, lightening, heavy rains, poor ground conditions etc.
Note: The environmental hazards described here are indicative. They should not be regarded as a
comprehensive list. There may be additional environmental conditions specific to a particular site that
must be considered.
Never carry out any hoisting or rigging operations when winds create hazards
for workers, the general public, or property. A swinging load cause additional
hazards, increases the size of the drop zone, and makes accurate placement
very difficult.
Assess load size and shape to determine whether high winds may cause
problems. In particular, avoid handling loads that present large wind resistance
surfaces. Even though the weight of the load is within the normal capacity of
the equipment, height or gusting winds may prevent proper control during the
lift.
Wind loading can be critical to how the load is rigged, lifted and landed with
consequences for the safety of everyone involved.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Centered
crane boom
Load swinging
well downwind of
centered boom
Load pushed off centre in a wind that is beyond the recommended speed. There is a
danger that accurate placing cannot be done, and the drop zone is significantly larger
Note: All cranes, with the exception of those working underground or in enclosed buildings and
thus protected from wind, should be fitted with an anemometer for wind speed detection.
(Australian Standard for maximum wind speed during lifting operations is 10m/s or 36 km/hr).
When the visibility of crane Operators, Riggers and Crew is impaired by snow,
fog, rain, poor light, dust or any other factor, strict supervision must be
enforced and the operations must be stopped if the risk is increased.
3. Temperature
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Cranes, with their tall steel booms or towers are prone to lightning strikes
during electrical storms, which could cause injury or fatalities to personnel
and/or damage to the crane.
Items of lifting equipment that are subject to wear and frequent replacement (e.g.
slings, shackles, pad-eyes, shipping and handling baskets) or are used to transport
equipment to and from sites shall be colour-coded to confirm compliance with
inspection requirements.
Intent
Colour coding allows quick visual identification to confirm that lifting equipment
covered under this requirement has undergone specific periodic inspections as per
the colour code for the present period.
Leading Practice
Include the year of inspection on the colour coding tag to ensure that the potential is
eliminated where equipment might have not been inspected for twelve months.
Pad-eye colour coded as per current Typical colour coding information board and
lifting equipment standard per site tags
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Colour coding on fibre slings shall not be used due to detrimental chemical effect of paint on
fibre strength
Notes:
i. South African Sites
Many sites in South Africa (and some other countries) have in the past used colour coding to
identify the SWL of slings and other lifting tackle. With the introduction of this Standard, this
practice must be discontinued. It is very important that as a matter of urgency, sites in South
Africa (and elsewhere) where colour coding has in the past been used for identifying the SWL of
slings and other lifting tackle, must plan and implement a programme to ensure:
a. Re-training of personnel in accordance with this new practice.
b. Removing the old colour coding, and replacing it with the new maintenance schedule
colour coding. To avoid confusion, and ensure a safe transition, it may be worthwhile to
consider complete removal of all colour coding for a period of a few years, and rely solely
on serial numbers and the logbook for compliance with the necessary maintenance
schedule.
This programme requires careful risk assessment and implementation to ensure a safe, simple,
trouble-free transition to the new system.
ii. The colour coding system does not authorize unlicensed users to use the equipment, nor does it
negate the requirement for an inspection prior to use. It merely confirms that the device is
registered and was fit for purpose at the last periodic inspection.
15. Lifting only from designated lifting point
Lifting by the use of a block and tackle, for example, shall only be done from
designated lifting points or be authorized by a competent person.
Intent
When lifting heavy loads it is imperative that lifting equipment is properly anchored,
to sufficiently strong structural supports. The intent of this requirement is to ensure
that no injuries or fatalities occur as a result of the failure or collapse of structural
supports to which lifting tackle is attached.
Leading Practice
i. All designated lifting points should be marked with the SWL. Alternatively, the
SWL of designated lifting points should be clearly shown on drawings.
ii. Designated lifting points should be provided directly above equipment that may
need to be removed for maintenance, or directly above the lifting position.
iii. Designated lifting points should be maintained in good condition.
Common Errors
i. Lifting tackle is attached to inadequate structural members. Light roof trusses,
bracing members, light posts, walkway grating and guardrails are not
adequate attachment points for lifting tackle.
LIFTING OPERATIONS GUIDELINE
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
ii. Lifting tackle is attached to lifting points that are not above the lifting point. This
leads to the load swinging sideways as soon as it is lifted off its supports. This
can result in injury to personnel, or damage to equipment.
Grating
damaged by
slings
iii. “A” frames are made up on site, without proper design or approval by
registered Professional Engineers. The most common error is that “A” frames
do not have adequate bracing, allowing them to sway sideways resulting in
collapse.
“A” frame made up on site. “A” frame “A” frame properly designed. “A”
has leaned against the wall, but if it frame supports load safely.
had leaned the other way it would
have fallen over.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
iv. SWL is not indicated at the lifting point. This may occur because the lifting
point has not been properly designed for a particular SWL. It may occur
because repainting of the steelwork has obliterated it. It may occur because
there is only one item that may need to be lifted, so that it does not seem
necessary to note it.
Pulley force
Example of shaft slinging cage into mine shaft using winch and pulleys
v. Lifting lugs are welded to structural steelwork on site, without design or
approval by registered Professional Engineer. This is commonly done when no
provision has been made for lifting of equipment such as pipes, electrical
motors, pumps, liner plates, and when the constraints of the location prevent
the use of mobile cranes or forklifts.
vi. Lifting beams have no end stops, allowing hoists or trolleys to fall off the end
during lifting operations.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
vii. Slings or winch cables are not aligned with the lifting point anchor, leading to
bending and potential failure of the anchor.
Lifting underground
Where there are no cranes or crawl beams available for lifting underground, loads
are commonly lifted using permanent or temporary eyebolt clusters set in the
hanging wall. Each underground site shall have its own procedure for installing
eyebolt clusters and using them as lifting points. The procedure shall include at least
the following:
Hanging wall rock to be approved for installation of eyebolts by Rock Engineer
or appropriately qualified Mining Official
Number and configuration of eyebolts to lift different loads
Length and size of eyebolts to be used
Inspection and approval that the eyebolt clusters may be used for the intended
lift
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
lashed together
Centre of lift
using 16 mm wire
rope, lashed 5
times through
each pigtail and
secured with 5 500
500
crosby clamps.
500
5 tonnes to Raiseborers 4/Sets of 5 – 16 500
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
DO:
i. Check that the load to be lifted is within the SWL of the designated lifting point
to be used. If no SWL is shown, find out what the SWL is before proceeding.
ii. Inspect the designated lifting point for signs of deterioration, such as corrosion,
cracks, wear, or damage.
iii. Ensure that the lifting tackle cannot slip off the designated lifting point.
DON’T:
i. Weld, or attach lifting equipment to any structural steelwork just because it
happens to be convenient.
ii. Use any designated lifting point if it has deteriorated or been damaged.
TO BE DONE:
i. All locations at which lifting is required, but cannot be done with cranes, must
be identified.
ii. Where no designated lifting points exist at identified locations, a competent
person must be appointed to specify the work required to install designated
lifting points. The designated lifting points must then be installed.
16. All lifting equipment to be maintained
Intent
To ensure that all lifting equipment, including cranes and other lifting devices, as
well lifting tackle including shackles, slings, etc, remains in good condition, so that it
is at all times adequate to carry the loads it is certified to carry.
Daily
Inspections shall be carried out by the Crane Operator or the user of other
equipment.
Inspections of cranes shall be recorded in an equipment logbook.
Periodically
Inspections shall be carried out by a competent person.
Inspections shall be carried out at intervals as specified by legislation, or by
the equipment Manufacturer. These inspections are usually required at
intervals of 3 months to 6 months, or after a specified number of hours of
machine operation.
Inspections of cranes shall be recorded in an equipment logbook.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Annually
Inspections shall be carried out by a testing and inspection authority.
Load testing of cranes is generally required annually.
Load test certificates shall be kept with the crane records.
Special
Inspections shall be carried out by a competent person.
Structural components of cranes are generally required to be comprehensively
inspected at intervals of about 5 to 10 years, or after 5 000 to 10 000 hours of
operation.
Following any accident, overloading event, or other suspected damage lifting
equipment shall be inspected, and tested if necessary.
More detailed information about the inspection requirements for the various items of
lifting equipment is provided in Appendix 2.
Leading Practice
All air powered equipment should have lubricators, air filters and water traps fitted
prior to the equipment air inlet to ensure integrity and safe operation.
Additional Surveillance
DO:
i. Conduct a daily and pre-use inspection of all lifting equipment that is used
daily, and conduct a pre-use inspection of all lifting equipment that is used
irregularly.
ii. Check that all equipment used has been properly inspected and tested.
iii. Discard damaged equipment until it has been properly repaired and certified
by a competent person to be fit for use.
DON’T:
i. Use damaged equipment.
TO BE DONE:
i. Make an inventory of all lifting equipment, and ensure that the inspection and
testing requirements are clearly indicated in the inventory.
ii. Ensure that all relevant lifting equipment has a logbook, and that all inspection
and testing requirements, repairs and the results of such inspection, test
and/or repair are correctly recorded and entered in the logbook.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Intent
This is to ensure that all new or modified lifting equipment is fit for purpose, meets
the appropriate design standards and that any modifications are approved by the
original equipment manufacturer or equivalent, as well as all the requirements of the
lifting operations Standard.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Manufacturer’s crane and lifting equipment operating instructions and load charts
shall be available to the crane and lifting equipment operator. These should be in
the language of the country in which the lifting equipment is being used.
Intent
This is to ensure that crane and lifting equipment Operators have access to legible
operations manuals and load charts that the Operator can understand, to facilitate
safe operation and use of lifting equipment.
Note: Always only use the load charts provided for the specific crane or other lifting equipment being
used.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Where crane and lifting equipment operators are not conversant with the language
of the country, provisions shall be made to ensure that the operators can
understand the operating manuals and load charts.
Intent
This is to ensure that crane and lifting equipment Operators can understand load
charts and manuals to facilitate safe operation and use of lifting equipment.
Reason: Some Anglo American Group operations are located in countries where
the main language is other than English. In other countries where the Anglo
American Group has operations, although English may be considered to be the main
language of business, it is not the home language of all the people (see the chart
giving the language breakdown of South Africa). This is relevant for permanent
Operators as well as contractor Operators.
Afrikaans
English
IsiNdebele
IsiXhosa
IsiZulu
Sepedi
Sesotho
Setswana
Siswati
Tshivenda
Xitsonga
Other
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
* Detailed lifting plans are required for these procedures and shall be approved by
a competent supervisor. Co-ordination meetings shall be held prior to such lifts to
ensure all personnel understand how they are to be executed.
Note: In the point marked “*” “co-ordination meetings” refers to meetings held with all affected parties
prior to the lift, to ensure that all affected personnel understand how the lift is to be executed and what is
required of them. These meetings are also commonly referred to as “safety meetings”.
Intent
The mass of items to be lifted shall be known and the maximum radius of the
lift shall be known. These can be established by calculation or measurement,
as appropriate.
b. The procedure shall address lifting operations when the arcs of operation of
two or more cranes can overlap*
Intent
The intent is to ensure that procedures are in place and followed where the
potential exist of conflicting arcs of different cranes. Measurements must be
done and controls put in place to ensure that the cranes can safely work within
overlapping work space.
Note: This is also applicable to areas where two or more cranes (typically EOT cranes) have
potential to conflicting with other types of cranes such as service cranes.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Intent
To ensure that a lifting plan is developed that takes into account all the risks
when two or more cranes are involved in a common lift.
Intent
To ensure that the lifting plan does not, at any time allow loads to be carried
by more than one crane. Where attempts are made to carry loads using two or
more cranes, the distribution of loads becomes uncertain and uncontrollable
due to unevenness of the ground, movement of the cranes without outriggers,
etc. This makes any carrying of loads with multiple cranes a dangerous
operation, which must thus not be contemplated.
If loads need to be moved, but cannot be safely moved by a single crane, they
shall be loaded onto a trailer or low-bed transporter to be moved.
Note: “Carry” here means that the cranes are moving in order to move the load to a new
location. This does not prevent “Lifting” and luffing or slewing to move the load while the cranes
are stationary.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
e. The procedure shall address the danger to lifting operations when adverse
weather conditions are present or imminent (e.g. Electrical storm, high winds
and sea state)
Intent
To ensure that the lifting plan includes all facets of weather interference and
the negative effect and risks on lifting operations at that time. The plan should
specifically define the course of action to be taken in the event of adverse or
extreme weather.
Typically the greatest risk will be to supply boat to oilrig transfers due to rough
seas causing uncontrolled movement of the supply boat. The course of action
may be to abort the delivery and return to shore, it may be to wait for improved
sea conditions, or there may be other options.
There are also risks to all crane lifting operations associated with rain, dust or
wind. The course of action may be to lower the load to the ground; it may be to
return the load to its transporter, or some other action.
f. The procedure shall address the safety of personnel when cranes and lifting
equipment are operating in the proximity of live electrical conductors*
Intent
The AA plc minimum working distances from overhead power lines are:
a. The minimum distance to be observed from any part of a crane, VLC,
EWP, hoisting device, load line or load, is given in the Table 20.1 below.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
b. A Spotter shall be used when any part of a crane, VLC, EWP, hoisting
device, load line or load encroaches within these minimum distances for
any angle of inclination and swivel.
c. Due to thermal expansion and contraction, the height of power lines from
the road surface to the overhead conductor can vary substantially from
summer to winter. The clearance for vehicles passing under overhead
power lines shall be determined for the maximum summer temperatures
at the site.
Must have a Spotter because load line will reach power line if crane slews
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Working in the Contact Supply authority Determine Can the work process Safe working
vicinity of to establish voltage and the result in employees, plant procedures to
overhead insulation of overhead danger or materials entering the be
power lines power lines zone danger zone? No established
Yes
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
overhead power lines. For example, when deliveries are made, Drivers may
not be aware of the positions of overhead power lines. When cranes are
moved from one location on a site, to another location, the Operators may
not be aware of overhead power lines to be passed under.
g. The procedure shall address lifting operations when lifting near or over
unprotected plant, equipment or services, including live process or
hydrocarbon processes*
Intent
To ensure that the lifting plan considers the content of the process and any
protective measures to deal with the type of hazard. For example, toxic gas
might need breathing apparatus at hand when the task is in progress. Plant
handling harmful substances may need an Operator on standby to shut off the
flow in case of an accident.
h. The procedure shall address the effective hand-over, from one operator to
another, of cranes with complex boom, jib or tower configurations
Intent
To ensure that the lifting plan considers the implications of a new shift
Operator taking over a crane which is rigged or loaded in a complex or
unusual way. It is imperative that the new Operator is fully aware of the current
state of all components of the crane, and any specific information that might
have a bearing on the safety of the lift. This is particularly important when
visibility is impaired for some reason, such as in poor lighting conditions or
when adjacent buildings obstruct the Operator’s view.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
i. The procedure shall address availability and use of check-lists for pre- and
post-operational inspections
Intent
To ensure that inspection points and procedures are not left out and to ensure
that deficiencies are logged for maintenance and shift handover purposes. To
ensure that any risks associated with lifting operations are identified, assessed
and controls put in place to ensure that safe working conditions are
maintained.
21. Operators to have time for familiarization
Cranes shall not be used for lifting operations until crane operators have been
given sufficient time to familiarize themselves with relevant aspects of the crane.
Intent
Crane operators should not only have the required formal qualification, but they
must also be assessed to be competent by a site authorized assessor to operate the
particular crane being used.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Risks associated with all lifting, crane maintenance, assembly activities and
environmental conditions shall be assessed as part of the planning process.
Barricading, warning signs or other means of ensuring personnel protection shall
be in place during lifting operations and for those cranes left unattended in wind
vane mode.
Intent
Leading practice
Where more than one tower crane operate on a site, their booms should be at
different elevations to minimize the likelihood of booms colliding in wind vane mode.
Some EOT cranes move on outside gantries and are therefore exposed to the
elements. These cranes should have storm lock facilities to prevent
uncontrolled movement by wind pressure. Part of the risk assessment
procedure should consider how the storm lock is applied. There have been
cases where workers have been exposed to additional risks (such as lightning)
in order to apply the storm lock.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
The following procedures shall be implemented for the different types of lifts. The
different lift complexity types are categorized in Table 22.1.
a. Routine Lift
Lifting Crews shall complete a “Routine Lift Checklist”, such as that shown
below. If any questions in this checklist are answered by “no”, the lift should be
treated as a Serious Lift.
Standard site procedures for safe lifts may be used. Where there are no
standard site procedures, a risk assessment shall be conducted, and a
procedure developed.
b. Serious Lift
Lifting Crews shall do a risk assessment and prepare a lift procedure. The
Supervisor shall approve the risk assessment and lift procedure before
proceeding with the lift.
c. Critical Lift
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Note: when performing “critical lifts” on a routine basis as part of a regular production process (i.e.
transporting molten metal ladles in a smelter), the lifting plan should be prepared at the commissioning
phase and then updated whenever substantive changes are made. Substantive changes include
changes such as introduction of modified ladles, extension of the smelter building, the addition of a new
crane, any modification of the smelter building that impacts the ladle crane bay, etc. The lifting plan
should be reviewed every three years, even if no substantive changes have been made to the lifting
procedure.
A guide to likely lifting hazards and possible controls can be found in Appendix 1: “A
Guide to Lifting Hazards and Controls”. This guide may be used for risk analyses
and the preparation of lifting plans.
All parties (i.e. site Supervisor or Rigger, Contractor, Rigging Specialist, Project
Manager and the Design Engineer where appropriate) involved in a lift shall be
represented in the risk assessment and in preparation of the lifting procedure or the
lifting plan as required. All parties shall approve and sign-off the risk assessment
and the lifting procedure or lifting plan.
The lift complexity types can be determined using the information in Table 22.1
below.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Mine Area
Project
The Load
Do you know the weight? Have you included all the items to be lifted i.e. all items on or below the boom
head?
If you are using lifting lugs have they been properly designed (preferably by the Designer of the
equipment or structure to be lifted) and tested? Are the lugs aligned with the slings so they are not bent?
If you are not using lifting lugs is the load attachment simple and clear?
Is the load free of loose unsecured items and is it ready to lift, e.g. restraints removed?
Will the lifting hook be directly over the centre of gravity of the load at pick up and placement?
Is all temporary bracing and support required by the Mechanical or Structural Designer in place?
Have the SWL of the slings, shackles, etc been checked for the load to be applied?
Have the sling angles and rigging method been considered in checking the capacity?
Has all equipment been checked for correct capacity and up to date inspection and test certificates?
Has the lifting equipment been inspected for defects and damage?
Is the lift within the specific limits of the relevant crane load charts for the configuration and radius?
Have the pre and post start operational checks been completed?
If the crane exceeds 10 tonne capacity, is the external rated capacity lighting functioning correctly?
Is the crane set up with outriggers fully deployed and supported on the correct crane mats?
Is there adequate ancillary equipment, e.g. boom lifts, scissor lifts, fork lifts?
The Lift
Is there a routine procedure, or have you done a risk assessment or prepared a lifting plan as
appropriate?
Does the lifting procedure include bringing equipment and loads to site, setting up equipment, lifting,
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Is there adequate guidance in the defined behaviours and rules for your site for this lift?
Is the area of the lift free of operating plant, piping, live electrical lines and underground services? If not,
have the risks associated with these been properly considered?
Has the radius been checked with a tape measure or surveyed using Engineering plans, etc?
Has the area of the lifting operation been protected using barricades, tape and/ or spotters?
If people are working at height, has a risk assessment been done and correct PPE sourced?
Are environmental conditions safe for the lift e.g., not too windy, storms approaching?
If there any chance of the load impacting the boom, or the crane body or boom impacting obstacles has
a rigging study been done?
The crew
Does the Rigger have the appropriate statutory certification and certification by the site as being
competent for a lift of this nature?
If the load is heavier or more complex than the Rigger normally handles does the Rigger have the
Supervisor’s permission to lift?
Do the Operators of ancillary equipment have appropriate statutory certification? Have the Operators
been assessed by the site as being competent to operate the equipment as per the site standards?
Has the Controller of the lift been identified and is he/she wearing an appropriately coloured reflective
vest?
Has the Crane Operator the appropriate statutory certification and been assessed by the site as being
competent to operate this crane/ lifting equipment for this type of lift?
Have all members of the Lifting Crew been assessed as being medically fit for their tasks?
Note: The approval of a Supervisor is required before proceeding with the lift if any question is answered “No”.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Intent
To ensure that cranes are not used outside of their specifications for safe operation
as designated by the OEM. This also includes horizontal pushing or pulling of loads
with the boom. On EOT cranes and hoists load should only be applied in the vertical
plane and no dragging of the load is permitted.
Note:
This must be reinforced as part of the crane operators and dogger/rigger induction to all sites
This also needs to be included as part of the pass out package for crane operators
The consequences of side loading crane booms also need to be explained e.g.
- Tipping the crane over
- Bending of the crane boom
- Breaking or the damaging of head sheaves
- Damaging of hoist ropes
- Load swinging out of control
24. Outriggers to be used
With the exception of pick and carry operations, no lifting shall be carried out
without outriggers being deployed and locked.
Intent
To ensure that outriggers are fully deployed in such a way as to prevent the crane
from overbalancing. This requirement is applicable only to those cranes to which
outriggers are fitted.
Leading practice
Leading practice is to use packers under the outriggers, the dimensions of which
should be determined by the stability of the ground.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Common Hazards
a. Pick and carry operations should only be permitted where it is not practical to
transfer the load to a more suitable means of transport. In most cases pick and
carry operations are only required for a few meters to enable the crane to reach
an area where alternative transport can be safely made available. Pick and
carry operations using two or more cranes are not ever allowed.
All pick and carry operations should only be attempted by competent crane
operators and spotters must be used to ensure no risk is created during these
operations. All persons must be aware that the drop zone is enlarged during
pick and carry operations because the load is moving and swinging.
All pick and carry operations should be in line with the manufacturer’s
recommendations, particularly for tyre pressure and slope of the ground. This is
normally indicated on the machine’s load chart. These recommendations should
be considered as part of the risk assessment process.
Controls shall be in place to prevent the falling of objects from lifting equipment and
suspended loads.
Intent
The chart below shows the consequences resulting from a range of reported events
involving dropped objects. Although this chart should not be taken as definitive
because of the many variables involved, it does give some idea of the possible
consequences when objects of different weights drop from different heights. This
chart thus assists in understanding the risk of loose items dropping from heights
during a lift.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
100
10
0.1
1 10 100 1000 10000 100000
Mass of object (kg)
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
The lifting of personnel with cranes shall be carried out only with the use of
approved workbaskets or cages. Cranes used for this purpose shall be approved
as suitable for man-lifting operations. A recovery plan should be in place before
personnel are lifted.
Intent
These controls should be in place and used to ensure that the risks associated with
the use of man cages are reduced to low as reasonably practicable. Any additional
controls as required after risk assessment per site should be included.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Total under hook load (which should be taken as not less than 750 kg)
multiplied by a factor of 2, should not exceed the crane chart rated capacity.
Note: the use of the work basket shall be limited to those situations where it is necessary to elevate
personnel to carry out work where it is not possible to use any other appropriate method and should
only be allowed where no other method is available for safely elevating personnel.
Common Hazard
In most incidents investigated, recovery plans were not present. Recovery plans
may need to be developed on a task by task basis. Personnel involved in the
formulation and/or carrying out of recovery plans must be competent in the skills
required to safely perform the rescue task.
The elimination of the need to work under or in the drop zone of suspended loads
shall be pursued. Where working under suspended loads is unavoidable, controls
shall be in place to eliminate or minimize the risks to personnel.
Intent
That working under suspended loads is the absolute last resort. In the unlikely
circumstance that working under a suspended load is required a comprehensive risk
assessment is required and shall be authorized by the senior site manager. It is vital
to ensure that all the controls that were identified in the risk assessment are
implemented.
Note: Counterweights are deemed to be suspended loads. Counterweight suspension chains are
deemed to be lifting chains. Leading practice is that counterweights should be suspended within
screened off or barricaded areas. Alternatively, counterweights should be adequately controlled by the
use of support beams placed beneath and above the counterweight.
Common Hazard
In the highly unlikely event where personnel are required to work under a
suspended load they should adopt the work basket rule as follows:
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Double the required capacity i.e. if the load is 10 tonnes then the crane would
have to be capable of lifting 20 tonnes at the given radius and lifting equipment
must be rated at 20 tonnes.
Where people may be in danger of being under a load that swings or rotates
the load should be kept under control by using one or more taglines.
Any modification to cranes and lifting equipment shall be subjected to the original
equipment manufacturer’s approval and to a rigorous change management
process.
Intent
To ensure that any modifications made to lifting equipment do not have a negative
impact on performance specifications. If situations exist where the OEM is no longer
in existence an approved equivalent will assess any modifications.
Note: The relevant site change management procedure must be used in conjunction with approval of
the OEM or approved equivalent.
This process should be followed irrespective of how small the proposed modification
is considered to be. For example, tack welding a small bracket or plate to the boom
of a crane may very quickly lead to fatigue cracking of the boom, and thus an unsafe
situation.
Intent
To ensure that all equipment utilized in any lifting operation is maintained in a safe
operating condition. Preventative maintenance activities need to be in compliance to
local legislation, the manufacturer’s specifications, and to any relevant regional
standards. Monitoring of preventative maintenance activities needs to be completed
to ensure that they are being completed as per the schedule.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Note: The rated safe working loads apply only to equipment and hardware in a good serviceable
condition. Any equipment damaged in service should be taken out of service and repaired or destroyed.
See Appendix 2 for additional information relating to caring for, inspecting and
maintenance of cranes and lifting equipment.
Leading Practice
Common Hazards
Slings – After the hoist rope, the sling is the most commonly used piece of rigging
equipment. Observe the precautions in Table 29.1 when working with slings.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Precaution Sketch
Avoid dragging slings from underneath
loads and avoid crushing slings under
loads
Keep wire rope slings away from flame
cutting and electric arc welding
Never make slings up from discarded
hoist rope
Avoid using single leg wire rope slings
with hand spliced eyes where possible.
The load can spin, causing the rope to
unlay and the splice to pull out. Use
slings with Flemish Spliced Eyes
Never wrap a rope completely around a
hook. The sharp radius will damage the
sling
Avoid bending the eye section of wire
rope slings around corners. The bend
will weaken the splice or swaging.
There must be no bending near any
attached fittings
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Precaution Sketch
Ensure the sling angle is always
greater than 45 degrees. When the
horizontal distance between the
attachment points (S in figure below)
on the load is less than the length of
the shortest sling leg (L in the figure
below), then the angle is greater than
60 degrees and generally safe
Notes:
(a) When using slings in this configuration,
ensure that they cannot pull inwards,
allowing the load to tilt and fall out of the
slings.
(b) When using slings in this configuration,
always calculate the actual load on the
slings (see Section 12 “Identification of
Crane and Lifting Equipment” above)
Do not assume that multi-leg slings will
safely lift a load equal to the SWL of
one leg multiplied by the number of
legs, although the rated SWL of the
multi-leg slings will be based on this
assumption. There is no way of
knowing that each leg is carrying its fair
share of the load. With slings having
more than two legs and connected to a
rigid load, it is possible for some of the
legs to take practically the full load
while the others merely play a
balancing role. It should always be
assumed that any two legs may carry
the entire weight of the lifted load.
All cranes and lifting equipment shall be inspected and tested to ensure all safety
devices are working (including non-destructive testing as required by the relevant
standard) prior to being operated or put into service. After any repair and/or
modification, cranes and lifting equipment shall be inspected (and non-destructively
tested as required by the relevant standard) prior to being returned to service.
Intent
To ensure that all lifting equipment and cranes are fit, and remain fit, for their
intended use.
Leading Practice
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
A system of periodic inspection shall be in place for all cranes and lifting
equipment. Lifting equipment shall be inspected visually and confirmed fit for
purpose prior to being put into service. Visual inspection of lifting equipment by an
approved competent person shall be performed on a regular basis (e.g. six
monthly) unless regulations in the local area require examination more frequently.
Intent
Common Hazards
Defects are sometimes difficult to see if very close detailed inspections are not done.
Defective components – Examine all hardware, equipment, tackle and slings before
use. Destroy and de-register any defective components. Equipment merely
discarded may be picked up and used by someone unaware of its defects.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Cracked EOT crane rail could lead to serious incident if not detected and repaired.
Each site should maintain a register of all lifting equipment owned by them.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
8 PEOPLE REQUIREMENTS
33. Suitably qualified people
Intent
To ensure that all personnel involved in lifting operations have the required
qualifications, certification, authorisation and competencies required to operate and
utilise lifting equipment in a safe manner. These qualifications will be to the relative
national standard.
Note: The single most important precaution in lifting operations is to determine load weight before
attempting any lift.
Competency assessment
This guideline provides minimum competencies for rigger and crane operators as
defined in the Anglo Fatal Risk Standard for Lifting operations. It is acknowledged
that different countries may use different terms to describe the jobs of the persons
defined below.
Note: All of the competencies specified here apply irrespective of whether the Riggers and Crane
Operators are employed by Anglo American through any of its Divisions, or by an external rigging
company.
Rigger
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Knowledge of:
- Effects of angles on slings and lifting accessories.
- Effects of load moments on cranes.
- Estimation of approximate weights of loads composed of different
materials.
- Slinging loads including awkward loads and positioning loads in restricted
areas.
- Selection of crane and set up and crane rated capacity calculations.
- Attachment of hooks to lifting lugs and eye bolts.
- Procedures when working at heights.
- Procedures when thunder is heard or lightning is observed.
- Procedures in windy conditions.
- Procedures for working in the vicinity of, or when the potential exists for
coming into contact with live electrical conductors.
Note: Riggers need to demonstrate additional competencies to the above for activities such as:
Lateral shifting of loads which may involve the use of chain blocks, tirfors, sheaves, winches etc.
sometimes in conjunction with cranes,
Knowledge of crane selection and set up and crane chart rated capacity calculation for multi-
crane lifts,
Competence in steel erection,
Competence in directing lifts involving personnel in work baskets,
Competence in demolition rigging,
Specialist rigging applications.
Crane operator
In addition to the competencies for the Rigger, the Crane Operator must
demonstrate knowledge of:
Interpretation of operator manuals.
Interpretation of load charts.
Interpretation of crane configuration requirements for the crane being
operated.
Daily maintenance requirements as detailed in the Operating Manual for the
crane being operated.
Emergency response strategies for loss of power during lifting operations.
In addition the Crane Operator must operate the crane and demonstrate the ability
to:
Conduct a pre-start check of the crane and document the results.
Set the crane up correctly for operation
Correctly enter the crane configuration into the onboard computer, if
applicable.
Check the operation of crane limit switches and safety devices.
Boom up and down and hold a load 1 meter above the ground.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
With an unloaded chain set on the hook, slew the crane to cause a pendulum
effect and then control (catch) the resulting swing bringing it to a standstill.
With an unloaded chain set on the hook, raise and lower the boom to cause a
pendulum effect and then control (catch) the resulting swing bringing it to a
standstill.
Float a load in a boom down and hoist up scenario and vice versa.
The competent Rigger as referred to above is required with his lifting crew to
undertake the planning and implementation of lifting operations and supervise the
lifting operations as required.
Intent
To ensure that all persons involved in lifting operations clearly understand their roles
and responsibilities.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Individual Responsibilities
The Equipment Operator is generally responsible for the safety of the crane
operation as soon as the load is lifted. Operators must know:
The particular model of crane they operate, its characteristics, functions and
limitations
The information in the crane’s operating manual
The crane’s load chart, including all notes and warnings and how to calculate
or determine the crane’s actual net capacity in every possible configuration
Proper inspection and maintenance procedures to be followed in accordance
with the guidelines of the owner and manufacturer
Any site conditions that may effect crane operation, including the presence of
overhead power lines
Basic load rigging procedures
Refuse to operate the equipment if there are any problems that may affect its safe
use. Inform the owner in writing of these problems with the equipment, preferably in
the machines logbook. Only recommence use of the equipment once repairs have
been completed, appropriate inspections and tests have been completed, and a
competent person has certified the equipment safe for use.
Record in the register all inspections, maintenance and work done on the
crane in the field.
Check that the site is properly prepared for crane operation.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
The Site Supervisor (Site Foreman, Rigger Foreman, Lead of the Trade
involved etc.) has overall responsibility as Person in Charge (PIC) of the lift and
must therefore plan all phases of the operation. Specifically the PIC must:
Supervise all work involving the crane.
Determine the correct load weight and radius and inform the Crane Operator.
Ensure that the lifting crew is experienced and capable of establishing weight,
judging distances, heights and clearances, selecting correct tackle and lifting
equipment suitable for the load, rigging the load safely and securely.
Supervise the lifting crew.
Ensure that the load is properly rigged.
Ensure the Spotters are capable of directing the crane and load, including use
of international hand signals where other forms of communication are not
possible.
Designate Spotters and identify them to the Crane Operator.
Ensure the safety of the rigging crew and other personnel that could be
affected by the crane operations.
Keep the public and non essential personnel clear of the crane during
operations.
Control the movement of all personnel in the area affected by the lift.
Ensure all required precautions are in place when the lift is in the vicinity of
power lines.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Ensure that all personnel involved in the lift understand their respective roles
and responsibilities and their roles in the overall safety of each lift.
Important: The lifting plan must specify all responsibilities. These must not be
assumed. This is particularly important when there are several parties involved. For
example, a construction site may have a steel erection crew on site, which includes
a competent Rigger. For a particular heavy lift, a specialist rigging company may
have been appointed, with their own Rigger. If responsibilities are not clearly
defined, it may be unclear which Rigger is in charge of a particular lift.
Intent
To ensure that all personnel are appropriately qualified and competent to perform
required lifting operation tasks in a safe manner.
Having personnel with the appropriate teaching/training qualifications to the
appropriate regional standard.
Implementing a pass out system so that the operators have a clear
understanding of their role and are comfortable that they, within reason are
able to perform any task that is required.
Documented experience of operators.
Having a clear understanding of the experience and limitation of operators.
Ongoing and refresher training.
Knowledge of the relevant Mines Act and Regulations and other local statutory
requirements.
Knowledge of the relevant regional Standards.
Persons are required to be reassessed for competency on a frequency of 2
years
Intent
To ensure that persons inspecting lifting equipment have the knowledge and skills to
be able to identify items that are not fit for purpose. The examiner should be
appropriately qualified to perform the assessments as per regional standards.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Intent
Where radios are used for communication, these shall be on a unique frequency
channel provided by the local regulatory authority. Citizen Band (CB) or similar shall
not be used. Mobile phones shall not be used, and shall be switched off during lifting
operations.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Intent
To ensure that crane drivers’ operating in a solo capacity, such as Vehicle Mounted
Cranes or pendant control cranes, are able to sling loads in a safe manner. Also to
ensure that Crane Operators are able to identify poor slinging practices applied by
others in the Lifting Crew before the load is lifted.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Leading Practice
It is considered leading practice to use a Rigger for every lift. In some cases more
than one person may be required to safely supervise and control a load. This needs
to be considered when performing the risk assessment.
Not a good technique as the slings are not spread wide enough, no one is controlling the load,
the Operator is in the danger zone and he is not protected from falling from heights.
Intent
To reduce the risk of serious injury or fatality due to lifting accidents caused by
Crane Operators or other persons involved in lifting operations that are not fit for the
task. A selection process for personnel is required which will include medical
certification of fitness to work on lifting operations.
Paragraph 5.1 of the Anglo Occupational Health Way stipulates that “All operations
shall have systems in place to ensure that all personnel and contractors are
medically fit to perform their activities...” and, “...relevant personnel have been
certified medically fit to perform their activities based on fitness criteria that are
inherent to the requirements of the task or job”.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
The Anglo Occupational Health Guidelines have been incorporated into the
Occupational Health Way and the section on risk-based medical surveillance
describes the process for certification of fitness for work.
All employees should be medically examined and certified fit for their own job
based on a man-job specification (which describes the inherent requirements
of the job).
All medical examinations, pre-placement and periodical, will be conducted
against the fitness criteria for operating cranes and the certificate of fitness
issued will cover this.
Since medical examinations and certification of fitness are usually only undertaken
on an annual basis the employees health and fitness may have changed since the
certificate was issued and it is essential that employees are encouraged to come
forward should they feel unwell or know of a condition which may make them unfit to
operate cranes. In a project setting it is prudent to ask employees if there is any
condition that may make them unfit to do the task even if they have a current
certificate of fitness. A positive answer should result in referral to the company
occupational medicine practitioner.
Beyond the fitness to work assessments, the most important thing to remember is
for the supervisor to observe the team at work during the day. Knowing the team,
their ability and their how they perform during the day is critical. All supervisors
should be open to their team members who are working on lifting operations coming
forward to inform him/her if they do not feel comfortable. A decision may have to be
made about the team member continuing on the team but if the reason is a
temporary one then the person should be accommodated on other work for the day.
Illness should be referred as mentioned above.
Intent
The intent is to avoid serious injury/fatality from lifting operations where unsafe
behaviour could result in selection of inappropriate equipment and methods. It is
vital that a ‘no blame no shame’ concept is incorporated during observations.
Common Hazards
The safe working loads of most rigging and hoisting equipment is determined from
the static loads and appropriate safety factors is applied to account for dynamic
motions of the load and equipment. To ensure that safety is not compromised due to
behaviour, allow for other dynamic forces created by the normal operational
movement of the machine and its load. Always avoid the sudden snatching,
swinging and stopping of suspended loads. Rapid acceleration and deceleration can
only increase the stresses on both machine and tackle and thus increase risk of
failure.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
AS 2550-1 : Cranes, Hoists and Winches – Safe Use Part 1: General Requirements
ISO 10972-5 : Cranes - Requirements for mechanisms - Part 5: Bridge and gantry
cranes
ISO 11629 : Cranes – Measurement of the mass of a crane and its components
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
ISO 12488 : Cranes – Tolerances for wheel and travel and traversing tracks
ISO 1835 : Ductile iron pipes, fittings, accessories and their joints, for use in high
and low pressure systems for portable and foul water.
ISO 2262 : General purpose thimbles for use with steel wire ropes - Specification
ISO 2374 : Lifting appliances -- Range of maximum capacities for basic models
ISO 2415 : Forged shackles for general lifting purposes – DEE shackles and Bow
shackles
ISO 25599 : Cranes – Jib cranes – International standards for design, manufacturing,
use and maintenance requirements and recommendations
ISO 3056 : Non-calibrated round steel link lifting chain and chain slings – Use and
maintenance
ISO 4304 : Cranes other than mobile floating cranes – General requirements for
stability
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
ISO 4347 : Leaf-chains, clevises and sheaves – Dimensions, measuring forces and
tensile strengths
ISO 7363 : Cranes and lifting appliances – Technical Characteristics and acceptable
documents
ISO 7531 : Wire rope slings for general purposes – Characteristics and
specifications
ISO 7592 : Calibrated round steel link lifting chains – Guidelines to proper use and
maintenance.
ISO 7593 : Chain slings assembled by methods other than welding – Grade T(8)
ISO 8539 : Forged steel lifting components for use with grade T(8) chain
ISO 9373 : Cranes and related equipment – Accuracy requirements for measuring
parameters during testing
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
The following provides a guide to likely lifting hazards and possible controls. Whilst this is detailed,
it does not cover all aspects and scenarios. Individual lifts need to be assessed within their own
particular context and specific hazards relating to the lift identified.
Note: If in doubt, do a lifting plan.
The following format of “Possible Hazard” and “Possible Controls” can facilitate the preparation of
risk assessments, or the Job Safety Analysis with or without pre- and post-risk scores.
STEP/ITEM POSSIBLE HAZARD POSSIBLE CONTROLS
Isolation Considerations
Electrical Lifting is carried out without properly electrically Necessary Electrical Isolations must be enacted
Isolations isolating the associated equipment as per site procedures e.g.:
Restricted Operation
Out of Service
Danger Tagging
People operating ancillary equipment/ erecting No personnel operating ancillary equipment/
scaffold within the operating area of an EOT crane erecting scaffold etc must work within the
without the EOT crane being de-energised operating area of an EOT crane unless it is
isolated.
Please note that in incidents with EOT cranes
Isolation is a major factor, so give it particular
attention.
Mechanical, Lifting is carried out without properly mechanically Necessary Mechanical Isolations must be
Hydraulic and or hydraulically isolating the associated equipment enacted as per site procedures.
Pneumatic
Isolations
Lifting activities cause an item of mechanical In the case of conveyors, procedures must take
equipment to be moved by an energy source which into account that whilst the electrical energy
is not it’s own and others working on the source is isolated, the belt may still be capable of
equipment are unaware of the lifting activity movement as a result of lifting operations.
Unexpected mechanical movement occurs while A procedure must be in place to protect people
performing maintenance or the like on an working using isolation procedures from
electrically isolated EOT crane, e.g. due to wind, unexpected mechanical belt movements
being bumped resulting from lifting or mechanical operations
(e.g. “bag tag” procedures).
Check that brakes are functioning correctly to
guard against unexpected movement.
People
Inexperienced Person/ persons in Lifting Crew are not competent Ensure personnel have relevant local Statutory
Crew/ Unfamiliar to carry out the lift certification where applicable.
with Lifting Task
Ensure personnel have been assessed by the
site and have been judged to be competent
Use a competent person to guide and advise the
lifting personnel until people are competent.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Resourcing the Insufficient / inadequate resources as listed below Assess the risk, plan the job and select and list
Lift to carry out the task: resources required.
people Check that resources are on site before
conducting the lift/ lifts.
PPE, fall protection equipment etc
support equipment (boom lifts etc)
the correct Crane
certified lifting accessories
water, UV protection and the like
chocks and dunnage
approved outrigger packing
Communication Crane Operator receives signals from more than Nominate the person controlling the lift in the pre
one person lift planning process.
Have person/ persons controlling the lift wear
unique coloured high visibility vests.
Crane Operator is confused about who is Identify when control will be passes from one
controlling the lift when control passes from one person to another and detail in JSA.
Rigger to another
The person controlling the lift during placement is Ensure the person controlling lift can see
unable to see the personnel placing the load personnel placing the load during placement.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Crane Operator is confused by terminology being Rigger and Crane Operator are familiar with
used by Rigger on the radio radio protocols.
Rigger and Crane Operator work together as a
regular crew.
Mobile phone ringing during lift distracts personnel Pre job briefing reminds personnel involved in
from their task the lift that all mobile and other phones will be
switched off until completion of the lifting
sequence.
Responsibility Weight of item being lifted is underestimated Require Rigger and Crane Operator to be jointly
responsible for determining the weight. Seek
Supervisor’s support if unsure.
Radius of lift is underestimated Require Rigger and Crane Operator to measure
the radius with a tape if the lift is over 70% of the
Rated Capacity of the Crane for the configuration
and radius.
Crane inappropriately set up for the lift Make Crane Operator responsible for setting up
the crane, programming the computer with the
correct configuration and operating within the
Rated Capacity of the crane.
People believe they are not empowered to stop the Make clear in job briefing that in case of
lift when they believe it is unsafe to proceed emergency, ANYONE may stop the lift.
Make clear to the signalling Rigger that he/she is
empowered to stop the lift whenever the lift
varies from the plan.
Make clear to the Crane Operator that he/she
can stop the lift whenever he believes it is unsafe
to continue.
Minimising Manual handling of heavy rigging accessories Planning allows for maximum use of Crane
Manual causes injury to Rigger or Assistants auxiliary hoist where applicable or other
Handling mechanical devices to minimise manual
handling.
Load
The Weight Weight of the item to be lifted underestimated Weight to be obtained from Engineering or
Vendor drawings or data sheets. Rigger and
Crane Operator may perform independent
calculation from first principles.
Weight of Container underestimated. Take a trial pick and confirm weight on crane
Load Cell (can’t do on demolition work).
Weight of all items on and below boom head not Take a trial pick and confirm weight on crane
allowed for Load Cell.
Know the weights of rope fall, block etc and keep
in crane cabin.
Require use of “Lift Calculation Sheet” to ensure
rigour
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Use of poor quality lugs Visually check lug welds for proper weld quality.
Confirm with NDT if unsure.
Improperly slinging load in weak direction of the Check drawings and engineering records
lug
Align sling in strong direction of the lug.
Strength of Load collapses during lift (this may be expected on Strength of load to be checked by Designer of
load long or slender loads, such as roof trusses or equipment.
conveyor gantries)
Load only to be lifted at designated lifting points.
Wind can apply significant loadings to the lifted Use certified and competent riggers. Check
load (e.g. shutters) weather forecasts before lifting if load is to be
suspended for an extended period of time.
The load has sharp edges which may damage the Protect slings from damage using packers/
slings protection. Rig correctly to avoid any chance of
slings slipping (use spreader beams?).
Load tilts and slides out of slings Ensure slings are attached above load centre of
gravity
Ensure slings are well spread towards the ends
or corners of the load
Have stability checked by a competent person if
spreader beam or lifting frame is used
Load has Pieces may be loose or loosen during lift Ensure all pieces are properly secured prior to lift
separate pieces commencing
Crane
Crane access to Crane cannot be set up in correct location Prior to lift, check site plan or drawing,
site considering headroom, road width and turning
circle requirements.
Crane is damaged or damages services along Prior to lift, check site plan or drawing,
access road considering headroom, road width and turning
circle requirements. Check bridges and culverts
for load carrying capacity.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Lifting with Side loading to crane booms/ carriages. Plan lifts to avoid producing out of vertical lifting
hoist rope out ropes.
of vertical Load is likely to slide sideways as weight is Plan lifts to avoid producing out of vertical lifting
transferred from ground or floor onto crane ropes.
Welding a Hoist ropes and crane electronics damaged by Planning allows for isolation of crane hook from
suspended earth leakage induced by welding suspended load, e.g. using soft slings or approved isolating
load loads device.
Longer period of time taken to weld suspended Check out weather forecasts before proceeding
load increases risk of lift being effected by wind or with the lift. Ensure item being welded is correctly
bad weather earthed.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Structure Structure unable to bear weight of load Get engineering input to confirm adequacy of
Strength to structure to support load
Support Weight
of Load.
Ground Ground unable to bear weight of load, crane and Inspect ground before lifting. Look for filled or
Capacity to accessories imparted through outriggers or tracks soft ground, evidence of old trenches. If in doubt,
Support Weight e.g. wharf get engineering input. Use packing and/ or mats
transferred under outriggers/ tracks
through Tracks/
Outriggers.
Structure Structure unable to bear weight of load, crane and Get engineering input to confirm adequacy of
Strength to accessories imparted through outriggers or tracks structure to support load
Support Weight e.g. wharf or suspended slab
transferred Use packing under outriggers/ tracks to transfer
through Tracks/ weight correctly to structure
Outriggers.
Uneven Ground Ground is uneven where crane is to be set up Assess whether able to be compensated for by
using safe amount of outrigger packing
Level the crane set up area by installing a crane
pad
Underground Loads imposed by lifting activity damages Check Plans and get Engineering advice
and Aerial underground plant / services
Services
Trenches for underground services, sumps, or Check Plans and get Engineering advice
large storm water pipes, weaken bearing area
Crane contacts overhead power lines Inspect for overhead power lines and other aerial
services. Apply site procedures if aerial
conductors are in the vicinity
Soft ground Filled ground not properly compacted Competent person to approve ground for
outrigger pressure
Site of demolition of old structures may have All old material to be removed, holes filled,
holes, loose blocks of concrete/steel/masonry ground made good and compacted
Trip Hazards Personnel injured by trips and falls Remove significant trip hazards from work
environment
Ensure people are aware of hazard
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Clearances of Crane component strikes adjacent structure during Check clearance of Counterweight, A Frame,
crane and load lift Masts and Gantries to Obstacles.
to objects during
the lift Load impacts boom during lift (“boom bound”) Check clearance of Boom to Obstacles.
Check clearance of load to Boom.
Load being lifted by EOT crane strikes crane Check clearance of load to crane beam and
beams / carriage carriages.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Bundled load shifts against itself and injures Never touch bundled loads with hands, use tag
Rigger’s hand lines.
Feet crushed when taking weight/ placing loads Keep feet out of crush areas.
Placing The Load And Shutting Down
Placing Loads Insufficient personnel and/ or support equipment to Plan adequately and identify personnel and
safely place the load equipment (e.g. boom lifts) required in the risk
assessment or lifting plan
Personnel are in crush areas as load is placed. Body positioning discussed in pre job planning if
confined areas are involved
Releasing Boom impacts structure above as weight is Confirm adequate headroom exists before lifting.
Loads released (due to boom deflection) Do a scaled drawing if necessary
Slightly lower boom to release weight ensuring
there is no contact with the obstruction above
Rigging accessories catch on structure during Rigger directs till rigging gear in sight of Crane
removal Operator
Load is placed in incorrect position on a truck Planning allows for truck driver to be involved in
discussions about orientation and placement of
the load on the truck
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Wheel hits a pot hole or bump causing dynamic Operator engages Axle Locks if applicable and
loading of the sling uses low range.
Load swings and strikes surrounding objects or Use rigger with tag line to control the load or tie
crane the load to the crane using appropriate
accessories.
Load strikes other people in congested area Use a spotter in congested areas.
Clear the area of unnecessary people
Slings swinging on unloaded hook strike others or Stow gear after releasing the load
surrounding objects
Load drops on the Rigger and/or Assistants Rigger uses tag line, Load is carried low and
Rigger and Assistants are never under the load
Travelling Travels crane with boom in raised position Chooses to stow boom before travelling. If it is
necessary to travel with the boom up, ensure
load charts are used for planning the travelling
and that only a very short distance is travelled.
Engage necessary locks
Apply the pick and carry checklist and controls
above.
Interactions With Other Cranes
Interactions with One crane operates while passing its boom over Plan work and separate and mark “Arcs of
other cranes or under the boom of another crane. Operation” for each crane and do a risk
assessment of lifting plan for passing one crane
boom over or under another crane boom.
Two EOT cranes carry out a tandem lift Consider risks involved in disabling anti collision
devices and in loadings on supporting structures.
Do a lifting plan.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Lifting with Lifting is carried out with a floating crane Specialist procedures for the particular type of
floating Crane lifting will be developed and used.
Sub Sea Lifts Lifting is carried out in a sub sea situation Specialist procedures for the particular type of
lifting will be developed and used.
Lifting Lifting personnel when other methods are Consider options and choose method based on
Personnel available to do the work risk.
Lifting personnel with a crane in other than a NOT ALLOWED.
certified man cage/ basket
Lifting personnel in a certified man basket The requirements detailed in the site procedure
for lifting personnel shall be applied.
Emergency Situations
Lightning, Load is to be suspended for an extended period of Check out weather forecasts before proceeding
Storms and time, exposing the lift to changes in the weather with the lift.
High Winds
Ensure Crew knows routine if it storms. If it
storms, Crew is to stop lifting and the boom is to
be retracted/ lowered if practical to do so. The
crew must understand that they are not to touch
rigging accessories while lightning is about.
If using an EOT crane, lower the load to the
ground. If unloaded, lift the hook to maximum
height. Check whether the crane beam needs to
be tied to the main girders.
Power Lines Crane contacts energised power lines Lift maintaining minimum clearances to lines and
structures/use spotter as per local regulations
and site procedures.
Remind Crane Operator and lifting Crew of
practices to be applied in case of contact before
undertaking the lift.
Environmental Considerations
Spills Oil spills from crane impact environment Crane carries oil spill kit.
Oil spill from load (e.g. gearbox) impact Crane carries oil spill kit.
environment
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Applicable Legislation
South Africa: The Occupational Health and Safety Act (Act 85 of 1993) and Regulations.
Regulations, Driven Machinery, Lifting Machines and Lifting Tackle.
All equipment used for lifting operations shall be properly maintained, including relevant inspections
and load tests. The specific requirements, inspection intervals and discard criteria vary in different
countries, and should be obtained from applicable legislation or from the Manufacturers.
a. Cranes
Operator Daily Inspections:
See typical “Daily Crane Operation Log Book”
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
Look for burn holes or damage from welding or other heat sources.
Check that slings and chains have the proper tag showing the necessary
information.
If the slings or chains are damaged or worn, do not use them.
Competent Person Inspections:
A competent person other than the user should inspect all slings and chains
periodically. These inspections shall be done at intervals complying with local
legislation. In the absence of specific applicable legislation, the inspections
should preferably be done every three months, but they shall be done at least
once a year.
Care, Marking and Inventory:
Store slings and chains in a dry, and safe environment; ideally in a locked storage
area.
Maintain a register indicating the date of entry into service, and the nature of the
work performed or other relevant details.
Ensure that tags remain firmly attached to slings and chains.
Periodic Inspections:
All slings and chains shall be load tested at intervals not exceeding one year.
Tag in place,
showing all
necessary
information.
A test certificate shall be obtained from the test authority. All test certificates shall be
kept in the register.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
c. Shackles
User Inspections:
Shackles should be checked on a regular basis and before each use.
If sprung latches are not closing properly, they should be cleaned and lubricated
carefully, and discarded if the problem cannot be resolved. Check for damage,
deformities, or excessive wear.
Damaged shackles shall be tagged and removed from service and the inventory
list.
Care, Marking, Use and Inventory:
Dirty shackles shall be cleaned with kerosene, WD-40, or similar solvent and
immersed in boiling water for 30 seconds to remove cleaning agent
Dry with a soft cloth to ensure that the gate and gatekeeper operate properly.
Shackles shall not be loaded along the gate side.
Discard the shackle:
After it has been damaged.
Discard shackles and all integral components if any discoloration, deformation,
cracks, or abrasions are detected.
If it has sustained any fall.
If the spring brake and latch are bent, or not closing properly even after cleaning.
If the gatekeeper no longer engages the slot cleanly.
If it shows excessive wear, chemical damage, burn damage, and/or ultraviolet
deterioration.
After 5 years of use.
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.
AA_AFRG_000008
ISSUE 0
This flowchart is intended as a quick reference for the use Project Managers or Engineering
Managers who are in control of sites where lifts must be performed.
The flowchart makes reference to other sections of this guideline document, and is intended for
use together with this guideline. It is not intended as a stand-alone document.
L IF T P L A N N IN G G U ID E
Id e n t if y lif t p a r a m e te r s in c lu d in g :
L if t m a s s
A r e a o f lif t – In c lu d in g s ite p la n
G r o u n d c o n d itio n s
E n v ir o n m e n ta l f a c to r s IF A N Y I N F O R M A T IO N IS U N K N O W N – D O N O T L IF T
Id e n t if y L if tin g C r e w in c lu d in g : F o r a h e a v y o r c o m p le x lif t, th is m a y b e d o n e b y a
R ig g e r S p e c ia lis t R ig g in g C o n tr a c t o r , b u t it m u s t b e d o n e .
C r a n e O p e r a to r
O th e r s IF A N Y P E R S O N H A S N O T B E E N F O U N D
C h e c k c o m p e te n c e a n d m e d ic a l f itn e s s C O M P E T E N T – D O N O T L IF T
R o u t in e S e r io u s C r it ic a l
Id e n t if y a p p r o p r ia te s ta n d a r d P e r f o rm r is k a s s e s s m e n t a n d P e r f o rm r is k a s s e s s m e n t.
p ro c e d u re p la n lif t p r o c e d u r e . P r e p a r e c o m p r e h e n s iv e lif tin g
OR p la n .
P e r f o rm r is k a s s e s s m e n t a n d
p la n lif t p r o c e d u r e .
O b ta in S u p e r v is o r a p p r o v a l f o r
lif t. O b ta in In d e p e n d e n t C o m p e te n t
P e r s o n a p p r o v a l f o r lif t.
P e r f o rm p r e - s ta r t in s p e c t io n o f
e q u ip m e n t.
P e r f o rm p r e - s ta r t in s p e c t io n o f
C h e c k th a t e v e r y b o d y
e q u ip m e n t. P e r f o rm p r e - s ta r t in s p e c t io n o f
u n d e r s ta n d s th e ir r e s p o n s ib ilit ie s .
C h e c k th a t e v e r y b o d y e q u ip m e n t.
u n d e r s ta n d s th e ir r e s p o n s ib ilit ie s . C h e c k th a t e v e r y b o d y
C h e c k C o n tr a c to r in d u c t io n s u n d e r s ta n d s th e ir r e s p o n s ib ilit ie s .
S e t u p lif tin g e q u ip m e n t a n d w h e r e a p p r o p r ia t e . C h e c k C o n tr a c to r in d u c t io n s
d e m a r c a te o r b a r r ic a d e w o r k w h e r e a p p r o p r ia t e .
a r e a , in c lu d in g d r o p z o n e .
S e t u p lif tin g e q u ip m e n t a n d
d e m a r c a te o r b a r r ic a d e w o r k S e t u p lif tin g e q u ip m e n t a n d
P E R F O R M L IF T S A F E L Y d e m a r c a te o r b a r r ic a d e w o r k
a r e a , in c lu d in g d r o p z o n e .
a r e a , in c lu d in g d r o p z o n e .
P E R F O R M L IF T S A F E L Y
P E R F O R M L IF T S A F E L Y
This document is intended for Company use only. Reproduction for external use is allowed only under specific authorisation.
Anglo American assumes no responsibility for the content and/or the implications of its use by third parties.