Interim Arrangements for Restoration of Barh Motihari Ckt-1 and Motihari-Gorakhpur Ckt-1

Sl No Activities Details Action plan Duration


Gorakhpur-Motihari Ckt -1 will 1. Opening of Jumpers at 2 locations
be transferred to Motihri Gkp- (35/0 and 26/0) of Motihari-Gkp Line -2.
Ckt-2 and again will be 2.Opening of 2 Jumpers at Locations
1 transferred back to Motihari- (26/0 and 35/0) of Motihari -Gkp Line -1. Team-1 and Team-2 from 10:00hrs to 14: 00hrs
Gkp Ckt-1 before and afater 3.Transferring Ckt-1 to Ckt-2 at location -
river belt respectively. 26/0 and again tranferring it to CKt-1 at
Location No- 34/1.
Motihari – Barh Ckt-1 will be
charged by transferring it to
Gorakhpur –Motihari Ckt -1 1. Opening of Jumpers at 2 locations
before river belt and again (27/0 and 26/0) of Motihari-Barh Line -1.
2 Team -3 and Team-4 from 10:00hrs to 14:00hrs.
transferring it to Motihari-Barh 2.Transferring Motihari-barh Ckt-1 to
Ckt-1 after river belt by which Motihari GKP- Ckt-1 at location -26/0 and
we will be able to avoid the ERS again tranferring it to Motihari Barh ckt-1
towers. at Location No- 27/0.