Você está na página 1de 16

************************************************************

Acero de refuerzo fy = 4200 Kg/cm2


160 KG
MO 1 HH OFICIAL
MO 1 HH OPERARIO
MO 0.5 HH PEON
MA 1.07 KG ACERO DE REFUERZO FY=4200 GRADO 60
MA 0.06 KG ALAMBRE NEGRO RECOCIDO # 16
HE 3 %MO HERRAMIENTAS MANUALES
************************************************************
Cama de apoyo con material propio zarandeado e = 0.10 m
120 M
MO 4 HH PEON
MA 0.06 M3 MATERIAL PROPIO ZARANDEADO
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Concreto f'c = 175 Kg/cm2
10 M3
MO 1 HH OFICIAL
MO 2 HH OPERARIO
MO 8 HH PEON
MA 1.2 M3 HORMIGON
MA 8.43 BOL CEMENTO PORTLAND TIPO I (42.5KG)
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM MEZCLADORA DE CONCRETO T. TROMPO 8HP 9P3
EQ 0.5 HM VIBRADOR DE CONCRETO
************************************************************
Encofrado y desencofrado en obras de arte
8 M2
MO 1 HH OFICIAL
MO 1 HH OPERARIO
MO 1 HH PEON
MA 0.2 KG CLAVOS 2, 2-1/2", 3 Y 4"
MA 3.2 P2 MADERA PARA ENCOFRADO
MA 0.02 GL PETROLEO
MA 0.15 KG ALAMBRE NEGRO RECOCIDO # 8
HE 3 %MO HERRAMIENTAS MANUALES
************************************************************
Flete terrestre
1 GLB
MA 1 GBL FLETE TERRESTRE
************************************************************
Relleno y compactaci�n zanja (manual) T- Semi rocoso, hasta H=0.80m de prof.

40 M
MO 4 HH PEON
MA 0.18 M3 MATERIAL DE PRESTAMO SELECCIONADO
MA 0.01 M3 AGUA
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM COMPACTADORA VIB. TIPO PLANCHA 4.0HP
************************************************************
Trazo nivelaci�n y replanteo inicial
600 M
MO 1 HH OFICIAL
MO 2 HH PEON
MO 1 HH TOPOGRAFO
MA 0.001 GL PINTURA ESMALTE SINTETICO
MA 0.01 BL YESO (BOLSA 20 KG)
MA 0.015 KG ACERO DE REFUERZO FY=4200 GRADO 60
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM MIRA TOPOGRAFICA
EQ 0.5 HM NIVEL TOPOGRAFICO
EQ 0.5 HM TEODOLITO
************************************************************
Trazo nivelaci�n y replanteo en obras de arte
150 M2
MO 1 HH OFICIAL
MO 1 HH OPERARIO
MO 4 HH PEON
MO 1 HH TOPOGRAFO
MA 0.001 GL PINTURA ESMALTE SINTETICO
MA 0.026 BL YESO (BOLSA 20 KG)
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM MIRA TOPOGRAFICA
EQ 1 HM NIVEL TOPOGRAFICO
EQ 1 HM TEODOLITO
************************************************************
Tarrajeo interior con mortero arena cemento + impermeabilizante
6 M2
MO 1 HH OPERARIO
MO 1 HH PEON
MA 0.114 GL IMPERMEABILIZANTE PARA CONCRETO
MA 0.025 P2 REGLA DE MADERA
MA 0.025 M3 ARENA FINA
MA 0.2 BOL CEMENTO PORTLAND TIPO I (42.5KG)
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Concreto f'c = 140 Kg/cm2
12 M3
MO 1 HH OFICIAL
MO 2 HH OPERARIO
MO 8 HH PEON
MA 1.2 M3 HORMIGON
MA 7.21 BOL CEMENTO PORTLAND TIPO I (42.5KG)
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM MEZCLADORA DE CONCRETO T. TROMPO 8HP 9P3
EQ 0.5 HM VIBRADOR DE CONCRETO
************************************************************
Junta asf�ltica e=1"
40 M
MO 1 HH OFICIAL
MO 0.2 HH OPERARIO
MO 2 HH PEON
MA 0.002 M3 ARENA GRUESA
MA 0.1 GLN ASFALTO RC-250
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Campamento provisional de obra
7 M2
MO 0.5 HH OFICIAL
MO 0.5 HH OPERARIO
MO 0.5 HH PEON
MA 0.24 KG CLAVOS 2, 2-1/2", 3 Y 4"
MA 0.06 KG CLAVOS PARA CALAMINA
MA 4.995 P2 MADERA PARA ENCOFRADO
MA 0.08 GL PINTURA ESMALTE SINTETICO
MA 0.41 PZA CALAMINA 1.80X0.83,E=0.2 MM
MA 0.04 UND CANDADO MEDIANO INC. ALDABA
MA 0.5832 PLN TRIPLAY DE 4�x8�x4mm
HE 3 %MO HERRAMIENTAS MANUALES
************************************************************
Cartel de identificaci�n de obra 2.40x4.80m
2 UND
MO 1 HH OFICIAL
MO 1 HH OPERARIO
MO 1 HH PEON
MA 1 KG CLAVOS 2, 2-1/2", 3 Y 4"
MA 0.3 M3 HORMIGON
MA 3 UND MADERA ROLLIZO DE EUCALIPTO 4" X 5m
MA 75 P2 MADERA PARA ENCOFRADO
MA 1 GL PINTURA ESMALTE SINTETICO
MA 1 BOL CEMENTO PORTLAND TIPO I (42.5KG)
MA 4 PLN TRIPLAY DE 4�x8�x4mm
MA 9 UND PERNOS HEXAGONALES DE 3/4"x6" INC. TUERCA
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Movilizaci�n y desmovilizaci�n de equipos, maquinarias y herramientas para la obra

0.5 UND
MO 1 HH OPERARIO
MO 10 HH PEON
EQ 3 HM CAMION BARANDA 3 TON
************************************************************
Seguridad en obra
1 GLB
MA 6 PZA LETREROS 0.60x0.60M SOBRE POSTE PARA DESVIO DE TRANSITO
MA 3 UND PUENTES DE MADERA PARA PASE PEATONAL
MA 5 UND TRANQUERA TIPO CABALLETE DE 2.40x1.20M
MA 1000 M CINTA PLASTICA SE�ALIZADORA P/LIMITE DE SEGURIDAD DE OBRA
MA 40 UND BARBIQUEJO
MA 40 UND CASCO DE PROTECCION
MA 40 UND LENTES DE SEGURIDAD
MA 20 UND PROTECTOR DE OIDOS TIPO TAPON
MA 20 PAR GUANTES DE CUERO AMARILLO C/REFUERZO EN LA PALMA
MA 15 UND BOTINES DE CUERO CON PUNTA DE ACERO
MA 15 UND BOTAS DE JEBE CON PUNTA DE ACERO
MA 1 UND ARNES CON TRES ANILLOS
MA 30 M SOGA NYLON DE 3/4"
MA 20 PAR GUANTES DE BADANA
MA 20 UND GUANTES DE NITRON
MA 40 UND CHALECO CON CINTA REFLECTIVA
************************************************************
Capacitaci�n en operaci�n y mantenimientos del sistema de agua potable
1 EVENTO
MA 1 EVENTO CAPACITACION EN OPERACION Y MANTENIMIENTO DE SISTEMA DE
AGUA POTABLE
************************************************************
Instalaci�n de v�lvulas y accesorios
1 GLB
MO 1 HH OFICIAL
MO 1 HH OPERARIO
MO 1 HH PEON
MA 2 UND VALVULA COMPUERTA HD BRIDADA DE 6"
MA 6 UND BRIDAS CON BUGGE PVC SAP C-10 DE 6"-INC. PERNOS Y TUERCAS
MA 1 UND REDUCCION PVC DE 6" x 4"
MA 10 M TUBO PVC SAP C-7.5 � 6"
MA 1 UND VALVULA COMPUERTA HD BRIDADA DE 4"
MA 3 UND BRIDAS CON BUGGE PVC SAP C-10 DE 4"-INC. PERNOS Y TUERCAS
MA 4 M TUBO PVC SAP C-7.5 � 4"
HE 3 %MO HERRAMIENTAS MANUALES
EQ 2 HM LLAVE STYLSON N�24
************************************************************
Limpieza, lavado y desinfecci�n
40 M2
MO 0.2 HH OPERARIO
MO 1 HH PEON
MA 0.01 UND ESCOBA DE PLASTICO CON MANGO
MA 0.2 LT LEGIA
MA 0.01 UND ESCOBILLA DE PLASTICO
MA 0.1 KG DETERGENTE
MA 0.01 UND ESCOBILLA DE ACERO
MA 0.1 KG TRAPO INDUSTRIAL
HE 3 %MO HERRAMIENTAS MANUALES
************************************************************
Trazo nivelaci�n y replanteo durante la obra
600 M
MO 1 HH OFICIAL
MO 4 HH PEON
MO 1 HH TOPOGRAFO
MA 0.001 GL PINTURA ESMALTE SINTETICO
MA 0.005 BL YESO (BOLSA 20 KG)
MA 0.05 KG ACERO DE REFUERZO FY=4200 GRADO 60
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM MIRA TOPOGRAFICA
EQ 0.5 HM NIVEL TOPOGRAFICO
EQ 0.5 HM TEODOLITO
************************************************************
Trazo nivelaci�n y replanteo al finalizar la obra
800 M
MO 1 HH OFICIAL
MO 2 HH PEON
MO 1 HH TOPOGRAFO
MA 0.001 GL PINTURA ESMALTE SINTETICO
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM MIRA TOPOGRAFICA
EQ 0.5 HM NIVEL TOPOGRAFICO
EQ 0.5 HM TEODOLITO
************************************************************
Corte de pavimento flexible - asfalto
40 M
MO 1 HH OPERARIO
MO 0.5 HH PEON
HE 3 %MO HERRAMIENTAS MANUALES
EQ 0.25 HM CORTADORA DE PAVIMENTO
************************************************************
Demolici�n de concreto en pavimento r�gido
40 M2
MO 1 HH OPERARIO
MO 0.5 HH PEON
HE 3 %MO HERRAMIENTAS MANUALES
EQ 1 HM COMPRESORA NEUMATICA 76HP 125-175 PCM
EQ 1 HM MARTILLO NEUMATICO 21-24 KG
************************************************************
Demolici�n de material asf�ltico en pavimento flexible
60 M2
MO 1 HH OPERARIO
MO 0.5 HH PEON
HE 3 %MO HERRAMIENTAS MANUALES
EQ 1 HM COMPRESORA NEUMATICA 76HP 125-175 PCM
EQ 1 HM MARTILLO NEUMATICO 21-24 KG
************************************************************
Excavaci�n de zanja (manual), en terreno compacto hasta H=0.80m. prof.
6.8 M
MO 0.1 HH OPERARIO
MO 1 HH PEON
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Excavaci�n de zanja (manual), en terreno rocoso hasta H=0.80m. prof.
16 M
MO 2.2 HH OPERARIO
MO 2 HH PEON
MA 1 PTO PERFORACION Y VOLADURA DE ROCAS
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM COMPRESORA NEUMATICA 76HP 125-175 PCM
EQ 1 HM MARTILLO NEUMATICO 21-24 KG
************************************************************
Excavaci�n de zanja (manual), en terreno semi rocoso hasta H=0.80m. prof.

4 M
MO 0.1 HH OPERARIO
MO 1 HH PEON
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Refine y nivelaci�n en suelo compacto
70 M
MO 1 HH PEON
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Refine y nivelaci�n en suelo semirocoso
50 M
MO 1 HH PEON
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Refine y nivelaci�n en suelo rocoso
30 M
MO 1 HH PEON
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Excavaci�n de zanja (manual), en suelo normal hasta H=0.80m. prof.
8 M
MO 0.1 HH OPERARIO
MO 1 HH PEON
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Refine y nivelaci�n en suelo normal
100 M
MO 1 HH PEON
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Cama de apoyo con material de pr�stamo seleccionado e = 0.10 m
110 M
MO 4 HH PEON
MA 0.06 M3 MATERIAL DE PRESTAMO SELECCIONADO
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Eliminaci�n de material excedente C/Maquina (Dist. promedio 1Km)
64 M3
MO 0.1 HH OPERARIO
MO 2 HH PEON
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM CAMION VOLQUETE 4x2 210-280HP 8M3
EQ 0.5 HM CARGADOR S/LLANTAS 125 HP 2.5 yd3
************************************************************
Relleno y compactaci�n zanja (manual) T- Normal, hasta H=0.80m de prof.

40 M
MO 4 HH PEON
MA 0.225 M3 MATERIAL PROPIO ZARANDEADO
MA 0.01 M3 AGUA
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM COMPACTADORA VIB. TIPO PLANCHA 4.0HP
************************************************************
Relleno y compactaci�n zanja (manual) T- Rocoso, hasta H=0.80m de prof.

40 M
MO 4 HH PEON
MA 0.225 M3 MATERIAL DE PRESTAMO SELECCIONADO
MA 0.01 M3 AGUA
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM COMPACTADORA VIB. TIPO PLANCHA 4.0HP
************************************************************
Suministro e instalaci�n de tubos PVC C-10 de 2"
600 M
MO 1 HH OFICIAL
MO 1 HH OPERARIO
MO 2 HH PEON
MA 0.002 GLN PEGAMENTO TUB. PVC
MA 1.05 M TUBO PVC C-10 DE 2"
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Suministro e instalaci�n de tubos PVC C-10 de 1.5"
600 M
MO 1 HH OFICIAL
MO 1 HH OPERARIO
MO 2 HH PEON
MA 0.002 GLN PEGAMENTO TUB. PVC
MA 1.05 M TUBO PVC C-10 DE 1.5"
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Suministro e instalaci�n de tubos PVC C-10 de 1"
600 M
MO 1 HH OFICIAL
MO 1 HH OPERARIO
MO 2 HH PEON
MA 0.0015 GLN PEGAMENTO TUB. PVC
MA 1.05 M TUBO PVC C-10 DE 1"
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Suministro e instalaci�n de tubos PVC C-10 de 3/4"
600 M
MO 1 HH OFICIAL
MO 1 HH OPERARIO
MO 2 HH PEON
MA 0.0015 GLN PEGAMENTO TUB. PVC
MA 1.05 M TUBO PVC C-10 DE 3/4"
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Concreto f'c = 210 Kg/cm2
10 M3
MO 1 HH OFICIAL
MO 2 HH OPERARIO
MO 8 HH PEON
MA 1.2 M3 HORMIGON
MA 10.09 BOL CEMENTO PORTLAND TIPO I (42.5KG)
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM MEZCLADORA DE CONCRETO T. TROMPO 8HP 9P3
EQ 0.5 HM VIBRADOR DE CONCRETO
************************************************************
Concreto f'c = 100 Kg/cm2 para solado
120 M2
MO 1 HH OFICIAL
MO 2 HH OPERARIO
MO 6 HH PEON
MA 0.1 M3 HORMIGON
MA 0.25 BOL CEMENTO PORTLAND TIPO I (42.5KG)
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM MEZCLADORA DE CONCRETO T. TROMPO 8HP 9P3
************************************************************
Accesorios para tuber�a PVC C-10 de 2"
1 GLB
MO 1 HH OFICIAL
MO 2 HH OPERARIO
MO 2 HH PEON
MA 0.5 GLN PEGAMENTO TUB. PVC
MA 2 UND TEE PVC SAP DE 4"
MA 2 UND REDUCCION PVC SAP DE 4"x3"
MA 5 UND CODO PVC SAP DE 1.5"x45�
MA 2 UND REDUCCION PVC SAP DE 2"x3/4"
MA 3 UND REDUCCION PVC SAP DE 2"x1"
MA 7 UND REDUCCION PVC SAP DE 2"x1.5"
MA 10 UND TEE PVC SAP DE 2"
MA 4 UND UNION PVC SAP DE 2"
MA 9 UND CODO PVC SAP DE 2"x90�
MA 7 UND CODO PVC SAP DE 2"x45�
MA 5 UND CODO PVC SAP DE 2"x22.5�
MA 2 UND REDUCCION PVC SAP DE 4"x2"
MA 5 UND REDUCCION PVC SAP DE 3"x2"
MA 2 UND TEE PVC SAP DE 3"
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Accesorios para tuber�a PVC C-10 de 1.5"
1 GLB
MO 0.5 HH OFICIAL
MO 2 HH OPERARIO
MO 1 HH PEON
MA 0.25 GLN PEGAMENTO TUB. PVC
MA 6 UND CODO PVC SAP DE 1.5"x45�
MA 7 UND CODO PVC SAP DE 1.5"x90�
MA 12 UND UNION PVC SAP DE 1.5"
MA 2 UND CODO PVC SAP DE 1.5"x22.50�
MA 7 UND REDUCCION PVC SAP DE 2"x1.5"
MA 8 UND TEE PVC SAP DE 1.5"
HE 3 %MO HERRAMIENTAS MANUALES
************************************************************
Accesorios para tuber�a PVC C-10 de 1"
1 GLB
MO 0.2 HH OFICIAL
MO 1 HH OPERARIO
MO 1 HH PEON
MA 0.2 GLN PEGAMENTO TUB. PVC
MA 6 UND TEE PVC SAP DE 1"
MA 2 UND REDUCCION PVC SAP DE 1.5"x1"
MA 3 UND REDUCCION PVC SAP DE 2"x1"
MA 15 UND CODO PVC SAP DE 1"x45�
MA 7 UND CODO PVC SAP DE 1"x22.50�
MA 8 UND CODO PVC SAP DE 1"x90�
MA 2 UND TEE PVC SAP DE 1.5"
MA 2 UND TEE PVC SAP DE 2"
HE 3 %MO HERRAMIENTAS MANUALES
************************************************************
Accesorios para tuber�a PVC C-10 de 3/4"
1 GLB
MO 0.2 HH OFICIAL
MO 1 HH OPERARIO
MO 1 HH PEON
MA 0.25 GLN PEGAMENTO TUB. PVC
MA 10 UND CODO PVC SAP DE 3/4"x22.50�
MA 19 UND CODO PVC SAP DE 3/4"x45�
MA 3 UND CODO PVC SAP DE 3/4"x90�
MA 2 UND TEE PVC SAP DE 3/4"
MA 6 UND REDUCCION PVC SAP DE 1"x3/4"
MA 2 UND REDUCCION PVC SAP DE 1.5"x3/4"
MA 2 UND REDUCCION PVC SAP DE 2"x3/4"
MA 12 UND UNION PVC SAP DE 3/4"
HE 3 %MO HERRAMIENTAS MANUALES
************************************************************
Doble prueba hidra�lica y desinfecci�n de las redes de agua potable
250 M
MO 2 HH OFICIAL
MO 2 HH OPERARIO
MO 4 HH PEON
MA 0.015 M3 AGUA
MA 0.016 KG HIPOCLORITO DE CALCIO AL 70%
HE 3 %MO HERRAMIENTAS MANUALES
EQ 1 HM "EQUIPO DE PRUEBA HIDRAULICA CON TAPONES, ABRASADERA Y OTROS

"
************************************************************
Excavaci�n de zanja (manual), en suelo compacto
3.4 M3
MO 0.1 HH OPERARIO
MO 1 HH PEON
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Relleno y compactaci�n con material propio
8 M3
MO 1 HH PEON
MA 0.2 M3 MATERIAL PROPIO ZARANDEADO
MA 0.01 M3 AGUA
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM COMPACTADORA VIB. TIPO PLANCHA 4.0HP
************************************************************
Filtro con grava de 3/4"
6 M3
MO 1 HH PEON
MA 1.15 M3 GRAVA DE 3/4"
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Concreto ciclopeo f�c=140kg/cm2+70%PM
20 M3
MO 1 HH OFICIAL
MO 2 HH OPERARIO
MO 8 HH PEON
MA 0.45 M3 HORMIGON
MA 3 BOL CEMENTO PORTLAND TIPO I (42.5KG)
MA 0.85 M3 PIEDRA MEDIANA
************************************************************
Curado
24 M3
MO 1 HH PEON
MA 0.25 M3 AGUA
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Tarrajeo exterior con mortero arena cemento
6 M2
MO 1 HH OPERARIO
MO 1 HH PEON
MA 0.025 P2 REGLA DE MADERA
MA 0.025 M3 ARENA FINA
MA 0.2 BOL CEMENTO PORTLAND TIPO I (42.5KG)
MA 0 UND REDUCCION PVC SAP DE 3"x2"
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
V�lvula foltadora + Accesorios
1 Und
MO 0.1 HH OFICIAL
MO 1 HH OPERARIO
MO 0.5 HH PEON
MA 1 UND NIPLE DE F�G� DE 2" x L=35cm
MA 1 UND UNION DE F�G� DE 2" x ROSCA HEMBRA
MA 1 UND VALVULA FLOTADORA CON ROSCA EXTERNA DE 2"
MA 1 UND BOYA DE POLIETILENO
MA 3 UND CINTA TEFLON
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
V�lvula compuerta + Accesorios para CRP-7
1 Und
MO 0.5 HH OFICIAL
MO 1 HH OPERARIO
MO 1 HH PEON
MA 0.1 GLN PEGAMENTO TUB. PVC
MA 1 M TUBO PVC C-10 DE 2"
MA 2 UND NIPLE ROSCADO F�G� DE 2"
MA 2 UND ADAPTADOR UPR PVC DE 2"
MA 1 UND VALVULA COMPUERTA DE BRONCE ROSCADA DE 2"
MA 5 UND CINTA TEFLON
MA 2 UND UNION UNIVERSAL PVC DE 2" CON ROSCA
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Accesorios para rebose
1 Und
MO 1 HH OPERARIO
MO 0.5 HH PEON
MA 0.1 GLN PEGAMENTO TUB. PVC
MA 6.5 M TUBO PVC C-10 DE 3"
MA 1 UND CONO DE REBOSE PVC DE 4"x3"
MA 2 UND UNION SP PVC DE 3"
MA 3 UND TEE SP PVC DE 3"
MA 3 UND TAPON MACHO SP PVC DE 3"
MA 3 UND CODO PVC SAP DE 3"x90�
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Accesorios para ventilaci�n
1 Und
MO 1 HH OPERARIO
MO 0.5 HH PEON
MA 1 UND NIPLE DE F�G� DE 2" x L=35cm
MA 1 UND CODO F�G� DE 2" ROSCA HEMBRA
MA 1 UND NIPLE DE F�G� DE 2" x L=10cm
MA 1 UND CODO F�G� DE 2 CON REJILLA DE PROTECCION EN SALIDA
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Accesorios para salida de CRP-7
5 Und
MO 1 HH OPERARIO
MO 0.5 HH PEON
MA 0.05 GLN PEGAMENTO TUB. PVC
MA 1 M TUBO PVC C-10 DE 3"
MA 2 UND CODO PVC SAP DE 2"x90�
MA 1 UND REDUCCION PVC SAP DE 3"x2"
MA 1 UND CANASTILLA PVC DE 4"x3"
MA 1 UND UNION SP PVC DE 3"
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Accesorios para ingreso al CRP-7
5 Und
MO 1 HH OPERARIO
MO 0.5 HH PEON
MA 0.1 GLN PEGAMENTO TUB. PVC
MA 2 M TUBO PVC C-10 DE 2"
MA 2 UND CODO PVC SAP DE 2"x90�
MA 1 UND REDUCCION PVC SAP DE 3"x2"
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Pintado de muro exterior y losa C/Latex acr�lico
20 M2
MO 1 HH OPERARIO
HE 3 %MO HERRAMIENTAS MANUALES
************************************************************
Corte de pavimento r�gido - emboquillado
32 M
MO 1 HH OPERARIO
MO 0.5 HH PEON
HE 3 %MO HERRAMIENTAS MANUALES
EQ 0.25 HM CORTADORA DE PAVIMENTO
************************************************************
Tuber�a PVC C-10 de 2"
600 M
MO 1 HH OFICIAL
MO 1 HH OPERARIO
MO 2 HH PEON
MA 0.002 GLN PEGAMENTO TUB. PVC
MA 1.05 M TUBO PVC C-10 DE 2"
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Tuber�a PVC C-10 de 3"
500 M
MO 1 HH OFICIAL
MO 1 HH OPERARIO
MO 2 HH PEON
MA 0.003 GLN PEGAMENTO TUB. PVC
MA 1.05 M TUBO PVC C-10 DE 3"
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Accesorios para drenaje
5 Und
MO 1 HH OPERARIO
MO 0.5 HH PEON
MA 0.1 GLN PEGAMENTO TUB. PVC
MA 3 UND CODO PVC SAP DE 2"x45�
MA 1 UND REDUCCION PVC SAP DE 3"x2"
MA 1 UND TEE SP PVC DE 3"
MA 1 UND CODO PVC SAP DE 3"x90�
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Accesorios para ingreso y salida de la VRP
3 Und
MO 1 HH OPERARIO
MO 0.5 HH PEON
MA 0.05 GLN PEGAMENTO TUB. PVC
MA 2 M TUBO PVC C-10 DE 3"
MA 4 M TUBO PVC C-10 DE 2"
MA 0.5 UND REDUCCION PVC SAP DE 2"x1.5"
MA 2 UND CODO PVC SAP DE 2"x90�
MA 1 UND REDUCCION PVC SAP DE 3"x2"
MA 0.5 UND TEE PVC SAP DE 3"
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
V�lvula reductora de presi�n + Componentes y accesorios
1 Und
MO 1 HH OFICIAL
MO 1 HH OPERARIO
MO 1 HH PEON
MA 2 GLN PEGAMENTO TUB. PVC
MA 1.5 UND REDUCCION PVC SAP DE 2"x1.5"
MA 3 UND TEE PVC SAP DE 2"
MA 3 UND CODO PVC SAP DE 2"x90�
MA 7 UND ADAPTADOR UPR PVC DE 2"
MA 10 UND CINTA TEFLON
MA 4 UND UNION UNIVERSAL PVC DE 2" CON ROSCA
MA 3 UND MANOMETRO MEDIDOR DE PRESION 10BARES
MA 3 UND NIPLE DE TUVO PVC C-10 DE 2"
MA 11 UND BRIDAS CON BUGGE PVC SAP C-10 DE 2"-INC. PERNOS Y TUERCAS
MA 3 UND VALVULA COMPUERTA HD BRIDADA DE 2"
MA 1 UND FILTRO DE MALLA HD BRIDADA TIPO "Y" DE 2"
MA 1 UND VALVULA REDUCTORA DE PRESION TIPO Y BRIDADA DE 2"
MA 1 UND VALVULA CHECK HD BRIDADA DE 2"
MA 1 UND VALVULA DE AIRE DOBLE EFECTO 2"x1"
MA 5 UND ABRAZADERA METALICO DE 1"x1/4", PARA DIAMETRO DE 2"
MA 0.5 UND CODO PVC SAP DE 3"x90�
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
V�lvula compuerta + Accesorios
1 Und
MO 0.5 HH OFICIAL
MO 1 HH OPERARIO
MO 1 HH PEON
MA 0.1 GLN PEGAMENTO TUB. PVC
MA 1 M TUBO PVC C-10 DE 2"
MA 0.68 UND BRIDAS CON BUGGE PVC SAP C-10 DE 2"-INC. PERNOS Y TUERCAS
MA 0.67 UND VALVULA COMPUERTA HD BRIDADA DE 2"
MA 0.34 UND VALVULA COMPUERTA DE BRONCE ROSCADA DE 1.5"
MA 0.34 UND LLAVE PARA BASTAGO DE 1.5
MA 0.67 UNS LLAVE PARA BASTAGO 2"
MA 1.35 UND UNION UNIVERSAL PVC DE 1.5" CON ROSCA
MA 1.35 UND ADAPTADOR UPR PVC DE 1.5"
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Accesorios para tuber�a de derivaci�n
1 Und
MO 0.5 HH OFICIAL
MO 1 HH OPERARIO
MO 1 HH PEON
MA 0.15 GLN PEGAMENTO TUB. PVC
MA 2 UND CODO PVC SAP DE 4"x45�
MA 1 UND REDUCCION PVC SAP DE 4"x2"
MA 1 UND TEE PVC SAP DE 4"
MA 1 UND CODO PVC SAP DE 4"x22.50�
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
V�lvula compuerta + Accesorios para VP
5 Und
MO 0.5 HH OFICIAL
MO 1 HH OPERARIO
MO 1 HH PEON
MA 0.1 GLN PEGAMENTO TUB. PVC
MA 0.72 M TUBO PVC C-10 DE 1.5"
MA 0.36 M TUBO PVC C-10 DE 1"
MA 0.92 M TUBO PVC C-10 DE 3/4"
MA 0.59 UND CODO PVC SAP DE 1.5"x45�
MA 0.71 UND CODO PVC SAP DE 1.5"x90�
MA 0.96 UND CODO PVC SAP DE 3/4"x45�
MA 0.96 UND CODO PVC SAP DE 3/4"x90�
MA 0.36 UND CODO PVC SAP DE 1"x45�
MA 0.36 UND CODO PVC SAP DE 1"x90�
MA 0.18 UND REDUCCION PVC SAP DE 2"x1.5"
MA 2 UND CINTA TEFLON
MA 0.36 UND VALVULA COMPUERTA DE BRONCE ROSCADA DE 1.5"
MA 0.72 UND UNION UNIVERSAL PVC DE 1.5" CON ROSCA
MA 2.56 UND ADAPTADOR UPR PVC DE 1.5"
MA 3.4 UND ADAPTADOR UPR PVC DE 3/4"
MA 0.18 UND VALVULA COMPUERTA DE BRONCE ROSCADA DE 1"
MA 0.48 UND VALVULA COMPUERTA DE BRONCE ROSCADA DE 3/4"
MA 0.36 UND TAPON MACHO SP PVC DE 1.5"
MA 0.18 UND TAPON MACHO SP PVC DE 1"
MA 0.48 UND TAPON MACHO SP PVC DE 3/4"
MA 0.36 UND UNION UNIVERSAL PVC DE 1" CON ROSCA
MA 1.3 UND ADAPTADOR UPR PVC DE 1"
MA 0.96 UND UNION UNIVERSAL PVC DE 3/4" CON ROSCA
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Accesorios para ingreso y salida de VP
5 Und
MO 0.5 HH OFICIAL
MO 1 HH OPERARIO
MO 1 HH PEON
MA 0.1 GLN PEGAMENTO TUB. PVC
MA 0.59 UND CODO PVC SAP DE 1.5"x45�
MA 0.96 UND CODO PVC SAP DE 3/4"x45�
MA 0.36 UND CODO PVC SAP DE 1"x45�
MA 0.18 UND REDUCCION PVC SAP DE 2"x1.5"
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Concreto ciclopeo f�c=175 kg/cm2+70%PG
20 M3
MO 1 HH OFICIAL
MO 2 HH OPERARIO
MO 8 HH PEON
MA 0.45 M3 HORMIGON
MA 3.25 BOL CEMENTO PORTLAND TIPO I (42.5KG)
MA 0.85 M3 PIEDRA GRANDE
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM MEZCLADORA DE CONCRETO T. TROMPO 8HP 9P3
EQ 0.25 HM VIBRADOR DE CONCRETO
************************************************************
Trazo nivelaci�n y replanteo de linea de conducci�n
250 M
MO 1 HH OFICIAL
MO 4 HH PEON
MO 1 HH TOPOGRAFO
MA 0.001 GL PINTURA ESMALTE SINTETICO
MA 0.01 BL YESO (BOLSA 20 KG)
MA 0.01 KG ACERO DE REFUERZO FY=4200 GRADO 60
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM MIRA TOPOGRAFICA
EQ 0.5 HM NIVEL TOPOGRAFICO
EQ 0.5 HM TEODOLITO
************************************************************
V�lvula de aire + accesorios
1 Und
MO 0.5 HH OFICIAL
MO 1 HH OPERARIO
MO 1 HH PEON
MA 0.34 UND CODO PVC SAP DE 1.5"x90�
MA 1 UND VALVULA DE AIRE DOBLE EFECTO DE 2"x1.5"
MA 0.34 UND ABRAZADERA HDPE 2 TORNILLOSDE 32mm x 1"
MA 0.66 UND ABRAZADERA HDPE 2 TORNILLOSDE 50mm x 1"
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Instalaci�n de conexi�n domiciliaria de 1/2" y 3/4"
4 UND
MO 0.5 HH OFICIAL
MO 1 HH OPERARIO
MO 0.5 HH PEON
MA 1.5 M TUBO PVC C-10 DE 2"
MA 0.55 M TUBO PVC C-10 DE 3/4"
MA 0.11 UND CODO PVC SAP DE 3/4"x90�
MA 0.27 UND TEE PVC SAP DE 3/4"
MA 0.1 UND TEE PVC SAP DE 1"
MA 0.81 UND ADAPTADOR UPR PVC DE 3/4"
MA 0.33 UND ABRAZADERA HDPE 2 TORNILLOSDE 32mm x 1"
MA 0.32 UND ABRAZADERA HDPE 2 TORNILLOSDE 50mm x 1"
MA 0.08 UND BUSHING ADAPTADOR HDPE DE 1"x3/4"
MA 0.93 UND BUSHING ADAPTADOR HDPE DE 1"x1/2"
MA 5.52 UND ADAPTADOR UPR PVC DE 1/2"
MA 0.92 UND CODO PVC SAP DE 1/2"x90�
MA 4.75 M TUBO PVC C-10 DE 1/2"
MA 1.82 UND CODO PVC SAP DE 1/2"x45�
MA 1.82 UND UNION UNIVERSAL PVC DE 1/2" CON ROSCA
MA 0.22 UND UNION UNIVERSAL PVC DE 3/4" CON ROSCA
MA 1.82 UND NIPLE PVC SAP DE 1/2"
MA 0.22 UND NIPLE PVC SAP DE 3/4"
MA 0.92 UND VALVULA DE BOLA PVC DE 1/2"
MA 0.12 UND VALVULA DE BOLA PVC DE 3/4"
MA 1.01 UND JEBE PRE FABRICADO DE 2"
MA 1.01 UND CAJA DE CONCRETO PRE FABRICADO DE 0.50x0.30x0.25m
MA 1.01 UND TAPA TERMOPLASTICA CON SEGURO
MA 0.07 UND REDUCCION PVC SAP DE 1"x1/2"
MA 0.03 UND REDUCCION PVC SAP DE 1"x3/4"
MA 0.27 UND REDUCCION PVC SAP DE 3/4"x1/2"
************************************************************
Protecci�n con concreto f'c = 175 Kg/cm2
6 M3
MO 1 HH OFICIAL
MO 2 HH OPERARIO
MO 8 HH PEON
MA 1.2 M3 HORMIGON
MA 9 BOL CEMENTO PORTLAND TIPO I (42.5KG)
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM MEZCLADORA DE CONCRETO T. TROMPO 8HP 9P3
EQ 1 HM VIBRADOR DE CONCRETO
************************************************************
Base solado con concreto f'c = 140 Kg/cm2
120 M2
MO 1 HH OFICIAL
MO 2 HH OPERARIO
MO 6 HH PEON
MA 0.1 M3 HORMIGON
MA 0.5 BOL CEMENTO PORTLAND TIPO I (42.5KG)
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM MEZCLADORA DE CONCRETO T. TROMPO 8HP 9P3
************************************************************
Doble prueba hidra�lica y desinfecci�n de las conexiones domiciliarias
250 M
MO 2 HH OFICIAL
MO 2 HH OPERARIO
MO 4 HH PEON
MA 0.015 M3 AGUA
MA 0.016 KG HIPOCLORITO DE CALCIO AL 70%
HE 3 %MO HERRAMIENTAS MANUALES
EQ 1 HM "EQUIPO DE PRUEBA HIDRAULICA CON TAPONES, ABRASADERA Y OTROS

"
************************************************************
Desmontaje de v�lvulas y accesorios deteriorados
1 GLB
MO 1 HH OPERARIO
MO 1 HH PEON
HE 3 %MO HERRAMIENTAS MANUALES
EQ 2 HM LLAVE STYLSON N�24
************************************************************
Demolici�n de piso emboquillado de la v�a
50 M2
MO 1 HH OPERARIO
MO 0.5 HH PEON
HE 3 %MO HERRAMIENTAS MANUALES
EQ 1 HM COMPRESORA NEUMATICA 76HP 125-175 PCM
EQ 1 HM MARTILLO NEUMATICO 21-24 KG
************************************************************
Corte de pavimento r�gido - concreto
30 M
MO 1 HH OPERARIO
MO 0.5 HH PEON
HE 3 %MO HERRAMIENTAS MANUALES
EQ 0.25 HM CORTADORA DE PAVIMENTO
************************************************************
Relleno y compactaci�n zanja (manual) T- Compacto, hasta H=1.00m de prof.

30 M
MO 4 HH PEON
MA 0.225 M3 MATERIAL PROPIO ZARANDEADO
MA 0.01 M3 AGUA
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM COMPACTADORA VIB. TIPO PLANCHA 4.0HP
************************************************************
Refine y nivelaci�n en suelo de relleno
100 M
MO 1 HH PEON
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Perfilado y compactaci�n de subrazante
60 M
MO 4 HH PEON
MA 0.1 M3 MATERIAL PROPIO ZARANDEADO
MA 0.01 M3 AGUA
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM COMPACTADORA VIB. TIPO PLANCHA 4.0HP
************************************************************
Pavimento con carpeta asf�ltica
60 M2
MO 1 HH OFICIAL
MO 1 HH OPERARIO
MO 2 HH PEON
MA 0.12 M3 MATERIAL GRANULAR DE 1/2" A 1" PARA CARP. ASFALTICA
MA 0.36 M3 MATERIAL GRANULAR PARA BASE DE PAVIMENTO
MA 0.75 GLN EMULSION ASFALTICA
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM RODILLO LISO VIBRATORIO MANUAL 10.8HP 0.8-1.1 TON
************************************************************
Refine y nivelaci�n en suelo compacto
42 M2
MO 1 HH PEON
HE 5 %MO HERRAMIENTAS MANUALES
************************************************************
Mitigaci�n de impactos ambientales
1 GLB
MA 1 GLB RIEGO DE LA ZONA PARA MITIGAR LA CONTAMINACION - POLVO
************************************************************
Prueba de compactaci�n del suelo
1 UND
MA 1 UND PRUEBA DE PROCTOR MODIFICADO
************************************************************
Prueba de resistencia de concreto
1 UND
MA 1 UND PRUEBA DE ROTURA DE CONCRETO
************************************************************
Pavimento de Concreto f'c = 175 Kg/cm2
10 M3
MO 1 HH OFICIAL
MO 2 HH OPERARIO
MO 8 HH PEON
MA 1.2 M3 HORMIGON
MA 8.43 BOL CEMENTO PORTLAND TIPO I (42.5KG)
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM MEZCLADORA DE CONCRETO T. TROMPO 8HP 9P3
EQ 0.5 HM VIBRADOR DE CONCRETO
************************************************************
Pavimento de concreto ciclopeo f�c=175 kg/cm2+70%PG
20 M3
MO 1 HH OFICIAL
MO 2 HH OPERARIO
MO 8 HH PEON
MA 0.45 M3 HORMIGON
MA 3.25 BOL CEMENTO PORTLAND TIPO I (42.5KG)
MA 0.85 M3 PIEDRA GRANDE
HE 5 %MO HERRAMIENTAS MANUALES
EQ 1 HM MEZCLADORA DE CONCRETO T. TROMPO 8HP 9P3
EQ 0.25 HM VIBRADOR DE CONCRETO

Você também pode gostar