Work Program Guidelines
Jabatan Kerja Raya Malaysia
PREFACE
This guideline is based on Project Management Book of Knowledge (PMBoK) and the
Practice Standard for Scheduling by the Project Management Institute (PMI), USA. It is
adapted to the introduction and development of Work Program particularly in Jabatan Kerja
Raya Malaysia.
• Evaluating the work program that has been submitted by the contractors/consultants.
• Microsoft Work program components and items that needs to be included in a work
program;
2
Work Program Guidelines
Jabatan Kerja Raya Malaysia
TABLE OF CONTENT
Page
3
Work Program Guidelines
Jabatan Kerja Raya Malaysia
Project management is one of JKR core business. In this aspect, JKR promised to deliver
the projects on time, within budget and with the specified quality. To achieve this, project
management best practices is being inculcated within JKR working environment.
Project time management is the core function of project management whereby any changes
in time will affect the success of the project. Project time management includes the
processes required to accomplish timely completion of the project. One of the tools being
used to achieve this objective is Work Program.
Work Program describes what the work is to be done, who will undertake the work
(resources) and when it should be done. The benefits of having a work program are:
4
Work Program Guidelines
Jabatan Kerja Raya Malaysia
The purpose of the work program is to provide a useful ‘road map’ that can be used by the
project manager and the project team to:
• Plan, monitor, and control the timely execution of the work, from the day the project
commences through each of its phases to successful completion;
• Track and monitor the progress of the project;
• Manage resources more smoothly;
• Identify and monitor dependencies and constraints between tasks to avert preventable
delays; and
• Communicate more frequently and effectively with stakeholders.
Establishing a realistic and achievable work program is one of the critical initial actions in
setting up a project.
Failure to meet schedule goals is most often due to unrealistic deadlines, passive project
execution, unforeseen problems, or things overlooked in the plan.
A Work program consists of a table of activities with their scheduled dates when activities
and milestones are to take place. In the project management profession, Work programs are
used to guide the execution of the project as well as to communicate to all participants and
contributors to the project when certain activities and events are expected to happen.
5
Work Program Guidelines
Jabatan Kerja Raya Malaysia
1. Define the Project Scope Obtain a clear picture of what the scope,
Charter deliverables and tasks of the project.
4. Define Sequence of Activities Put the tasks into order. Identify and
document the logical relationships
among schedule activities.
6
Work Program Guidelines
Jabatan Kerja Raya Malaysia
In short, a work program tells us how much time a project or any part of it will take.
Define Activities
7
Work Program Guidelines
Jabatan Kerja Raya Malaysia
The schedule component provides a detailed categorized list of the potential components of
a scheduling. Based on Microsoft Project, not all components are required for all projects.
Some guidance is given on those components that are required for JKR projects but the
project manager may add more components if the need arises, please refer to Appendix A.
For all JKR projects, Work program submitted in Microsoft Project (soft and hard copy)
should consist of the followings items:
Network Diagram
8
Work Program Guidelines
Jabatan Kerja Raya Malaysia
Assessment of the work program during the planning stage is where the successful
contractor/consultant will submit the work program for approval.
Appendix B indicates the items that need to be assessed to ensure the work
program is complete and can be used to monitor the project later. Once approved,
the work program will be the baseline program on which the monitoring and control
of the project is based on.
Generation of the financial and physical S-curve for the project must be from the
approved baseline program.
At this stage the contractor will submit the work program showing the progress of the
work.
Once approved, the work program will become the new baseline program on which
the monitoring and control of the project is based on.
Project manager then need to assess the revised work program to justify the
quantum of the EOT.
9
Work Program Guidelines
Jabatan Kerja Raya Malaysia
Finish On Optional
Start On Optional
10
Work Program Guidelines
Jabatan Kerja Raya Malaysia
Duration duration.
11
Work Program Guidelines
Jabatan Kerja Raya Malaysia
Finish Date
12
Work Program Guidelines
Jabatan Kerja Raya Malaysia
2. There will be no
loose ends in the
scheduling logic
(every task and
milestone will have
a predecessor
except the project
start milestone;
every task and
milestone will have
a successor except
the project end
milestone.
13
Work Program Guidelines
Jabatan Kerja Raya Malaysia
Resource Optional
2. Resources, work
Library\Dictionary
and scheduling
Resource Optional
logic shall never be
Rates/Prices
associated with
Resource Type Optional summary elements
in the WBS; they
shall be tied to
tasks and
milestones only.
14
Work Program Guidelines
Jabatan Kerja Raya Malaysia
Activity ID Required
Estimate at Optional
Completion (EAC)
Estimate to Optional
Complete (ETC)
Lag Optional
Lead Optional
Level Optional
Milestone Required
15
Work Program Guidelines
Jabatan Kerja Raya Malaysia
1. Every project
deliverable should
appear by name in
the Work
Breakdown
Structure (WBS).
16
Work Program Guidelines
Jabatan Kerja Raya Malaysia
17
Work Program Guidelines
Jabatan Kerja Raya Malaysia
Appendix B
Project Start Date or Finish Date Start and finish date must be the
same as in the contract date.
Project File Name, Folder Name, Project file name should contain
Revision No. Project Name for ease of
documentation and search.
Revision numbering to be agreed
between JKR and contractor and
should include date revised.
18
Work Program Guidelines
Jabatan Kerja Raya Malaysia
19
Work Program Guidelines
Jabatan Kerja Raya Malaysia
20
Work Program Guidelines
Jabatan Kerja Raya Malaysia
21
Work Program Guidelines
Jabatan Kerja Raya Malaysia
Activity Resource Resource List (Type, Group, Check contractor’s resource plan
Planning Maximum Numbers in project, job for adequacy of resource
functions) allocation, realistic productivity
rates, etc.
EDS→Duration = Quantity /
Production Rate
22
Work Program Guidelines
Jabatan Kerja Raya Malaysia
Duration for Summary Task will be Duration for summary task should
gathered from the sub-tasks not be ‘typed in’. It is
underneath. automatically calculated by the
program if the WBS level is done
correctly.
23
Work Program Guidelines
Jabatan Kerja Raya Malaysia
Information in Gantt Table area Ensure the table has the following
items:
24
Work Program Guidelines
Jabatan Kerja Raya Malaysia
25
Work Program Guidelines
Jabatan Kerja Raya Malaysia
Study and analyze the Financial • 10% planned for the 1st half
S-Curve to ensure the followings at of the project, 90% at 2nd half
high level (Overall Management):
– is it logic/acceptable?
i. Logic
• Equipment installation at the
ii. Workability beginning of project to
increase the planned value
iii. Continuity (work contour)
– can claim more at the
iv. Manageable and track able
beginning of the project. Is it
workable?
26
Work Program Guidelines
Jabatan Kerja Raya Malaysia
Appendix C
27
Work Program Guidelines
Jabatan Kerja Raya Malaysia
• Program to be saved as an
extension to the existing
baseline (eg. Baseline 1_1)
28