MEP PROJECT PROGRESS REPORT

Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018

Sr. No. Description of activities Status as on 22.07.2018 Locations

ELECTRICAL 
  ELECTRICAL
GUEST FLOOR

1 G.I. Box fixing 98% done First Floor


2 Wall Chiseling 98% done First Floor

3 Wall conduiting 98% done First Floor

4 Electrical wiring 98% done First Floor


5 Room DB fixing 95% done First Floor
6 TV Conduiting 100% done First Floor

7 Telephone conduiting 100% done First Floor


8 Data Conduiting 100% done First Floor

9 TV Cabling 95% done First Floor

10 Telephone cabling 95% done First Floor

11 Data Cabling 95% done First Floor

12 Smoke detector cabling 95% done First Floor

13 Smoke detector fixing 95% done First Floor

GUEST FLOOR CORRIDOR

1 G.I. Box Fixing 98% done First Floor

2 Wall Chiseling 98% done First Floor

3 Wall conduiting 98% done First Floor

4 Telephone conduiting 100% done First Floor

5 Data Coduiting 100% done First Floor

6 WIFI Cabling 100% done First Floor

7 Telephone cabling 95% done First Floor

8 Data Cabling 95% done First Floor


9 Smoke detector cabling 95% done First Floor
10 Smoke detector fixing 95% done First Floor

GUEST FLOOR

1 G.I. Box fixing 98% done Second Floor

2 Wall Chiseling 98% done Second Floor

3 Wall conduiting 98% done Second Floor

4 Electrical wiring 98% done Second Floor

5 Room DB fixing 95% done Second Floor

6 TV Conduiting 100% done Second Floor

7 Telephone conduiting 100% done Second Floor

8 Data Coduiting 100% done Second Floor

Page 1 of 11
MEP PROJECT PROGRESS REPORT
Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018

Sr No Description of activities Status as on 22 07 2018 Locations


9 TV Cabling 95% done Second Floor
10 Telephone cabling 95% done Second Floor

11 Data Cabling 95% done Second Floor


12 Smoke detector cabling 95% done Second Floor

13 Smoke detector fixing 95% done Second Floor

GUEST FLOOR CORRIDOR

1 G.I. Box Fixing 98% done Second Floor


2 Wall Chiseling 98% done Second Floor

3 Wall conduiting 98% done Second Floor

4 Telephone conduiting 100% done Second Floor

5 Data Coduiting 100% done Second Floor

6 WIFI Cabling 95% done Second Floor

7 Telephone cabling 95% done Second Floor


8 Data Cabling 95% done Second Floor
9 Smoke detector cabling 95% done Second Floor
10 Smoke detector fixing 95% done Second Floor

Page 2 of 11
MEP PROJECT PROGRESS REPORT
Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018

Sr No Description of activities Status as on 22 07 2018 Locations


Guest Room

1 G.I. Box fixing 98% done Third Floor

2 Wall Chiseling 98% done Third Floor

3 Wall conduiting 98% done Third Floor


4 Electrical wiring 98% done Third Floor

5 Room DB fixing 95% done Third Floor


6 TV Conduiting 100% done Third Floor

7 Telephone conduiting 100% done Third Floor

8 Data Coduiting 100% done Third Floor


9 TV Cabling 95% done Third Floor
10 Telephone cabling 95% done Third Floor

11 Data Cabling 95% done Third Floor


12 Smoke detector cabling 95% done Third Floor

13 Smoke detector fixing 95% done Third Floor

GUEST FLOOR CORRIDOR

1 G.I. Box Fixing 98% done Third Floor

2 Wall Chiseling 98% done Third Floor

3 Wall conduiting 98% done Third Floor

4 Telephone conduiting 100% done Third Floor

5 Data Coduiting 100% done Third Floor

6 WIFI Cabling 95% done Third Floor

7 Telephone cabling 95% done Third Floor

8 Data Cabling 95% done Third Floor

9 Smoke detector cabling 95% done Third Floor

10 Smoke detector fixing 95% done Third Floor

GUEST FLOOR

1 G.I. Box fixing 98% done Fourth Floor


2 Wall Chiseling 98% done Fourth Floor

3 Wall conduiting 98% done Fourth Floor

4 Electrical wiring 98% done Fourth Floor

5 Room DB fixing 95% done Fourth Floor

6 TV Conduiting 100% done Fourth Floor

7 Telephone conduiting 100% done Fourth Floor

8 Data Coduiting 100% done Fourth Floor

9 TV Cabling Not Started Fourth Floor

10 Telephone cabling Not Started Fourth Floor

Page 3 of 11
MEP PROJECT PROGRESS REPORT
Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018

Sr No Description of activities Status as on 22 07 2018 Locations


11 Data Cabling Not Started Fourth Floor
12 Smoke detector cabling 95% done Fourth Floor

13 Smoke detector fixing WIP Fourth Floor

Page 4 of 11
MEP PROJECT PROGRESS REPORT
Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018

Sr No Description of activities Status as on 22 07 2018 Locations


GUEST FLOOR CORRIDOR
1 G.I. Box Fixing 40% done Fourth Floor
2 Wall Chiseling 30% done Fourth Floor

3 Wall conduiting 30% done Fourth Floor

4 Telephone conduiting 30% done Fourth Floor


5 Data Coduiting 30% done Fourth Floor

6 WIFI Cabling 30% done Fourth Floor


7 Telephone cabling Not Started Fourth Floor

8 Data Cabling Not Started Fourth Floor

9 Smoke detector cabling Not Started Fourth Floor


10 Smoke detector fixing Not Started Fourth Floor

GUEST FLOOR

1 G.I. Box fixing 98% done Fifth Floor

2 Wall Chiseling 98% done Fifth Floor

3 Wall conduiting 98% done Fifth Floor

4 Electrical wiring 98% done Fifth Floor

5 Room DB fixing 95% done Fifth Floor

6 TV Conduiting 100% done Fifth Floor

7 Telephone conduiting 100% done Fifth Floor

8 Data Coduiting 100% done Fifth Floor

9 TV Cabling Not Started Fifth Floor

10 Telephone cabling Not Started Fifth Floor

11 Data Cabling Not Started Fifth Floor

12 Smoke detector cabling 30% done Fifth Floor

13 Smoke detector fixing Not Started Fifth Floor

GUEST FLOOR CORRIDOR

1 G.I. Box Fixing 40% done Fifth Floor


2 Wall Chiseling 30% done Fifth Floor
3 Wall conduiting 30% done Fifth Floor

4 Telephone conduiting 30% done Fifth Floor

5 Data Coduiting 30% done Fifth Floor

6 WIFI Cabling 30% done Fifth Floor

7 Telephone cabling 30% done Fifth Floor

8 Data Cabling Not Started Fifth Floor

9 Smoke detector cabling Not Started Fifth Floor

10 Smoke detector fixing Not Started Fifth Floor

Page 5 of 11
MEP PROJECT PROGRESS REPORT
Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018

Sr No Description of activities Status as on 22 07 2018 Locations


PUBLIC AREA

1 Ceiling conduiting 30% done GROUND FLOOR


2 Cable tray fixing 60% done GROUND FLOOR
3 Wall conduiting 10% done GROUND FLOOR
4 TV Conduiting 10% done GROUND FLOOR
5 Telephone conduiting 10% done GROUND FLOOR
6 Data Coduiting 10% done GROUND FLOOR
7 TV Cabling Not Started GROUND FLOOR
8 Telephone cabling Not Started GROUND FLOOR
9 Data Cabling Not Started GROUND FLOOR
10 Smoke detector cabling Not Started GROUND FLOOR
11 Smoke detector fixing Not Started GROUND FLOOR

Page 6 of 11
MEP PROJECT PROGRESS REPORT
Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018

Sr No Description of activities Status as on 22 07 2018 Locations


PLUMBING AND SANITARY 
GUEST ROOM
1 Marking &  Chiseling for water supply pipe 95% done First Floor
2 Core cutting for drainage pipe 95% done First Floor

3 drainage piping in bathroom 95% done First Floor


4 Water supply piping  in bathroom 95% done First Floor

5 flush tank fixing  95% done First Floor

6 fixing of shower mixture 95% done First Floor

PLUMBING SHAFT
1 Drainage pipe  60% done First Floor

2 Soil pipe 60% done First Floor


3 Vent pipe 60% done First Floor

4 Rain water pipe 60% done First Floor

5 cold water supply  60% done First Floor


6 Hot water supply 60% done First Floor

7 Hot water return 60% done First Floor

FIRE FIGHTING 
1 Main header for sprinkler pipe 95% done First Floor
2 Main header for fire hyderant 95% done First Floor

3 Sprinkler branch line 95% done First Floor

PLUMBING AND SANITARY 
GUEST ROOM
1 Marking &  Chiseling for water supply pipe 95% done Second Floor

2 Core cutting for drainage pipe 95% done Second Floor

3 drainage piping in bathroom 95% done Second Floor

4 Water supply piping  in bathroom 95% done Second Floor

5 flush tank fixing  95% done Second Floor


6 fixing of shower mixture 95% done Second Floor

PLUMBING SHAFT
1 Drainage pipe  60% done Second Floor

2 Soil pipe 60% done Second Floor


3 Vent pipe 60% done Second Floor
4 Rain water pipe 60% done Second Floor

5 cold water supply  60% done Second Floor

6 Hot water supply 60% done Second Floor

Page 7 of 11
MEP PROJECT PROGRESS REPORT
Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018

Sr No Description of activities Status as on 22 07 2018 Locations


7 Hot water return 60% done Second Floor

FIRE FIGHTING 
1 Main header for sprinkler pipe 95% done Second Floor

2 Main header for fire hyderant 95% done Second Floor

3 Sprinkler branch line 95% done Second Floor

PLUMBING AND SANITARY 
GUEST ROOM
1 Marking &  Chiseling for water supply pipe 95% done Third Floor
2 Core cutting for drainage pipe 95% done Third Floor

3 drainage piping in bathroom 95% done Third Floor


4 Water supply piping  in bathroom 95% done Third Floor
5 flush tank fixing  95% done Third Floor
6 fixing of shower mixture 95% done Third Floor

Page 8 of 11
MEP PROJECT PROGRESS REPORT
Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018

Sr No Description of activities
PLUMBING SHAFT
Status as on 22 07 2018 Locations
1 Drainage pipe  60% done Third Floor

2 Soil pipe 60% done Third Floor

3 Vent pipe 60% done Third Floor

4 Rain water pipe 60% done Third Floor


5 cold water supply  60% done Third Floor
6 Hot water supply 60% done Third Floor
7 Hot water return 60% done Third Floor

FIRE FIGHTING 
1 Main header for sprinkler pipe 95% done Third Floor

2 Main header for fire hyderant 95% done Third Floor

3 Sprinkler branch line 95% done Third Floor

PLUMBING AND SANITARY 
GUEST ROOM
1 Marking &  Chiseling for water supply pipe 95% done Fourth Floor

2 Core cutting for drainage pipe 95% done Fourth Floor

3 drainage piping in bathroom 95% done Fourth Floor

4 Water supply piping  in bathroom 95% done Fourth Floor

5 flush tank fixing  95% done Fourth Floor

6 fixing of shower mixture 95% done Fourth Floor

PLUMBING SHAFT
1 Drainage pipe  60% done Fourth Floor

2 Soil pipe 60% done Fourth Floor


3 Vent pipe 60% done Fourth Floor
4 Rain water pipe 60% done Fourth Floor
5 cold water supply  60% done Fourth Floor
6 Hot water supply 60% done Fourth Floor
7 Hot water return 60% done Fourth Floor

FIRE FIGHTING 
1 Main header for sprinkler pipe 95% done Fourth Floor
2 Main header for fire hyderant 95% done Fourth Floor
3 Sprinkler branch line 95% done Fourth Floor

Page 9 of 11
MEP PROJECT PROGRESS REPORT
Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018

Sr No Description of activities Status as on 22 07 2018 Locations


PLUMBING AND SANITARY 
GUEST ROOM
1 Marking &  Chiseling for water supply pipe 95% done Fifth Floor

2 Core cutting for drainage pipe 95% done Fifth Floor

3 drainage piping in bathroom 95% done Fifth Floor

4 Water supply piping  in bathroom 95% done Fifth Floor

5 flush tank fixing  95% done Fifth Floor

6 fixing of shower mixture 95% done Fifth Floor

PLUMBING SHAFT
1 Drainage pipe  60% done Fifth Floor

2 Soil pipe 60% done Fifth Floor

3 Vent pipe 60% done Fifth Floor

4 Rain water pipe 60% done Fifth Floor

5 cold water supply  60% done Fifth Floor

6 Hot water supply 60% done Fifth Floor

7 Hot water return 60% done Fifth Floor

FIRE FIGHTING 
1 Main header for sprinkler pipe 95% done Fifth Floor
2 Main header for fire hyderant 95% done Fifth Floor
3 Sprinkler branch line 95% done Fifth Floor

Page 10 of 11
MEP PROJECT PROGRESS REPORT
Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018

Sr No Description of activities Status as on 22 07 2018 Locations

HVAC (Both fronts & materials available & Manpower)
1 Fixing of FCU Indoor units 95% % done First Floor

2 Fixing of TFA duct 95% % done First Floor

3 Fixing of copper piping 95% % done First Floor


4 Fixing of TFA duct in corridor 95% % done First Floor

5 Fixing of Toilet exhaust ducting 95% % done First Floor

6 Fixing of staircase exhaust ducting 95% % done First Floor

1 Fixing of FCU Indoor units 95% % done Second Floor

2 Fixing of TFA duct 95% % done Second Floor

3 Fixing of copper piping 95% % done Second Floor


4 Fixing of TFA duct in corridor 95% % done Second Floor

5 Fixing of Toilet exhaust ducting 95% % done Second Floor


6 Fixing of staircase exhaust ducting 95% % done Second Floor

1 Fixing of FCU Indoor units 85% done Third Floor


2 Fixing of TFA duct 85% done Third Floor

3 Fixing of copper piping 85% done Third Floor

4 Fixing of TFA duct in corridor 85% done Third Floor

5 Fixing of Toilet exhaust ducting 85% done Third Floor

6 Fixing of staircase exhaust ducting 85% done Third Floor

1 Fixing of FCU Indoor units 75% done Fourth Floor

2 Fixing of TFA duct 75% done Fourth Floor


3 Fixing of copper piping Not started Fourth Floor
4 Fixing of TFA duct in corridor 75% done Fourth Floor
5 Fixing of Toilet exhaust ducting 75% done Fourth Floor
6 Fixing of staircase exhaust ducting 75% done Fourth Floor

1 Fixing of FCU Indoor units 75% done Fifth Floor


2 Fixing of TFA duct 75% done Fifth Floor
3 Fixing of copper piping Not started Fifth Floor
4 Fixing of TFA duct in corridor 60% done Fifth Floor
5 Fixing of Toilet exhaust ducting 60% done Fifth Floor

6 Fixing of staircase exhaust ducting 60% done Fifth Floor

1 Positioning of out door units 60% done seventh floor

2 Fixing of FCU Indoor units 75% done Ground floor

Page 11 of 11