Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018
ELECTRICAL
ELECTRICAL
GUEST FLOOR
GUEST FLOOR CORRIDOR
GUEST FLOOR
Page 1 of 11
MEP PROJECT PROGRESS REPORT
Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018
GUEST FLOOR CORRIDOR
Page 2 of 11
MEP PROJECT PROGRESS REPORT
Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018
GUEST FLOOR CORRIDOR
GUEST FLOOR
Page 3 of 11
MEP PROJECT PROGRESS REPORT
Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018
Page 4 of 11
MEP PROJECT PROGRESS REPORT
Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018
GUEST FLOOR
GUEST FLOOR CORRIDOR
Page 5 of 11
MEP PROJECT PROGRESS REPORT
Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018
Page 6 of 11
MEP PROJECT PROGRESS REPORT
Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018
PLUMBING SHAFT
1 Drainage pipe 60% done First Floor
FIRE FIGHTING
1 Main header for sprinkler pipe 95% done First Floor
2 Main header for fire hyderant 95% done First Floor
PLUMBING AND SANITARY
GUEST ROOM
1 Marking & Chiseling for water supply pipe 95% done Second Floor
PLUMBING SHAFT
1 Drainage pipe 60% done Second Floor
Page 7 of 11
MEP PROJECT PROGRESS REPORT
Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018
FIRE FIGHTING
1 Main header for sprinkler pipe 95% done Second Floor
PLUMBING AND SANITARY
GUEST ROOM
1 Marking & Chiseling for water supply pipe 95% done Third Floor
2 Core cutting for drainage pipe 95% done Third Floor
Page 8 of 11
MEP PROJECT PROGRESS REPORT
Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018
Sr No Description of activities
PLUMBING SHAFT
Status as on 22 07 2018 Locations
1 Drainage pipe 60% done Third Floor
FIRE FIGHTING
1 Main header for sprinkler pipe 95% done Third Floor
PLUMBING AND SANITARY
GUEST ROOM
1 Marking & Chiseling for water supply pipe 95% done Fourth Floor
PLUMBING SHAFT
1 Drainage pipe 60% done Fourth Floor
FIRE FIGHTING
1 Main header for sprinkler pipe 95% done Fourth Floor
2 Main header for fire hyderant 95% done Fourth Floor
3 Sprinkler branch line 95% done Fourth Floor
Page 9 of 11
MEP PROJECT PROGRESS REPORT
Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018
PLUMBING SHAFT
1 Drainage pipe 60% done Fifth Floor
FIRE FIGHTING
1 Main header for sprinkler pipe 95% done Fifth Floor
2 Main header for fire hyderant 95% done Fifth Floor
3 Sprinkler branch line 95% done Fifth Floor
Page 10 of 11
MEP PROJECT PROGRESS REPORT
Project: HOTEL PAWAN PALACE, LUMBINI, NEPAL
Date ‐ 22.07.2018
HVAC (Both fronts & materials available & Manpower)
1 Fixing of FCU Indoor units 95% % done First Floor
Page 11 of 11