SUBTOTAL 100.00
4. COSTOS INDIRECTOS
DESCRIPCION PORCENTAJE V. TOTAL
SUBTOTAL 0
PRECIO UNITARIO TOTAL 1,863.00
DESPERDICIO % -
SUBTOTAL -
2. MANO DE OBRA
TRABAJADOR UN PRESTACION JORN.TOTAL RENDIM. V. TOTAL
CUADRILLA AA HC 13,030 1.00 13,030.00
SUBTOTAL 13,030.00
3. EQUIPO
DESCRIPCION UNIDAD CANTIDAD precio V. TOTAL
HERRAMIENTA MENOR GBL 0.50 1,000 500.00
-
SUBTOTAL 500.00
4. COSTOS INDIRECTOS
DESCRIPCION PORCENTAJE V. TOTAL
SUBTOTAL
PRECIO UNITARIO TOTAL 13,530.00
SUBTOTAL 7,818.00
3. EQUIPO
DESCRIPCION UNIDAD CANTIDAD V.UNIT. VR.UNITARIO
VIBRO-COMPACTADOR DD 0.04 30,000.00 1,200.00
SUBTOTAL 1,200.00
4. COSTOS INDIRECTOS
DESCRIPCION PORCENTAJE VR.UNITARIO
SUBTOTAL 0
PRECIO UNITARIO TOTAL 28,555.50
SUBTOTAL 1,000.00
4. COSTOS INDIRECTOS
DESCRIPCION PORCENTAJE V. TOTAL
SUBTOTAL -
PRECIO UNITARIO TOTAL 379,400.33
DESPERDICIO % -
SUBTOTAL -
2. MANO DE OBRA
TRABAJADOR UN PRESTACION JORN.TOTAL RENDIM. V. TOTAL
CUADRILLA AA HC 13,030 0.40 5,212.00
SUBTOTAL 5,212.00
3. EQUIPO
DESCRIPCION UNIDAD CANTIDAD precio V. TOTAL
HERRAMIENTA MENOR GBL 0.20 1,000 200.00
RETROEXCAVADORA DD 0.02 400,000 8,000.00
VOLQUETA 3 M3 VJ 0.20 30,000 6,000.00
SUBTOTAL 14,200.00
4. COSTOS INDIRECTOS
DESCRIPCION PORCENTAJE V. TOTAL
SUBTOTAL
PRECIO UNITARIO TOTAL 19,412.00
Construccion de un desarenador de .70 x .45 x 1.60 mts, pañetado e impermeabilizado con tapa
en concreto reforzado
UNIDAD: UND
1. MATERIALES
DESCRIPCION UNIDAD CANT. V.UNIT. V. TOTAL
LADRILLO TOLETE UN 220.00 350 77,000.00
MORTERO DE PEGA 1:4 M3 0.12 280,000 33,600.00
BASE EN CONCRETO POBRE E=0.05 M2 0.10 320,000 32,000.00
RECEBO M3 0.15 15,700 2,355.00
ACERO DE REFUERZO 60000 PSI KG 7.00 3,000 21,000.00
SUBTOTAL 165,955.00
2. MANO DE OBRA
TRABAJADOR UN PRESTACION JORN.TOTAL RENDIM. V. TOTAL
CUADRILLA AA HC 13,030 10.00 130,300.00
SUBTOTAL 130,300.00
3. EQUIPO
DESCRIPCION UNIDAD CANTIDAD V.UNIT. V. TOTAL
HERRAMIENTA MENOR GBL 1.20 1,000 1,200.00
SUBTOTAL 1,200.00
PRECIO UNITARIO TOTAL 297,455.00
Construccion cajas de protección de válvulas del sistema de riego, consistente en excavación, piso
en concreto y adecuación de muros en ladrillo con pasantes de tubos de riego, pañete interior.
Todas a altura superior 10 Cm de la válvula. Medidas 1.0 Mt X 0.90 Mt X 1.30 Mt. con tapa en
lamina CR C 18
UNIDAD: UND
1. MATERIALES
DESCRIPCION UNIDAD CANT. V.UNIT. V. TOTAL
LADRILLO TOLETE UN 320.00 350 112,000.00
MORTERO DE PEGA 1:4 M3 0.20 280,000 56,000.00
BASE EN CONCRETO POBRE E=0.05 M2 0.40 320,000 128,000.00
RECEBO M3 0.20 15,700 3,140.00
ACERO DE REFUERZO 60000 PSI KG 20.00 3,000 60,000.00
SUBTOTAL 359,140.00
2. MANO DE OBRA
TRABAJADOR UN PRESTACION JORN.TOTAL RENDIM. V. TOTAL
CUADRILLA AA HC 13,030 6.00 78,180.00
SUBTOTAL 78,180.00
3. EQUIPO
DESCRIPCION UNIDAD CANTIDAD V.UNIT. V. TOTAL
HERRAMIENTA MENOR GBL 1.00 1,000 1,000.00
SUBTOTAL 1,000.00
PRECIO UNITARIO TOTAL 438,320.00
1. MATERIALES
DESCRIPCION UNIDAD CANT. V.UNIT. V. TOTAL
MORTERO 1:3 M3 0.04 267,000 10,680.00
SUBTOTAL 10,680.00
2. MANO DE OBRA
TRABAJADOR UN PRESTACION JORN.TOTAL RENDIM. VR.UNITARO
CUADRILLA AA HC 13,030 0.80 10,424.00
SUBTOTAL 10,424.00
PRECIO UNITARIO TOTAL 21,104.00
1. MATERIALES
DESCRIPCION UNIDAD CANT. V.UNIT. V. TOTAL
YESO BT 0.01 2,000.00 20.00
ESTUCO BT 0.20 1,100.00 220.00
CEMENTO GRIS KG 0.26 460.00 119.60
LIJA UN 0.02 800.00 16.00
VINILTEX GL 0.06 44,000.00 2,640.00
SUBTOTAL 3,015.60
2. MANO DE OBRA
TRABAJADOR UN PRESTACION JORN.TOTAL RENDIM. VR.UNITARO
CUADRILLA CC HC 13,030 1.00 13,030.00
SUBCONTRATO % 0.3 16,045.60 4,813.68
SUBTOTAL 17,843.68
3. EQUIPO
DESCRIPCION UNIDAD CANTIDAD V.UNIT. VR.UNITARIO
HERRAMIENTA DD 0.10 1,000.00 100.00
SUBTOTAL 100.00
PRECIO UNITARIO TOTAL 20,959.28
PINTURA TIPO KORAZA SOBRE PAÑETE
UNIDAD: M2
1. MATERIALES
DESCRIPCION UNIDAD CANT. V.UNIT. V. TOTAL
PINTURA TIPO KORAZA GL 0.2 40,000 8,000.00
DESPERDICIO %
SUBTOTAL 8,000.00
2. MANO DE OBRA
TRABAJADOR UN PRESTACION JORN.TOTAL RENDIM. VR.UNITARO
CUADRILLA CC HC 13,030 1.00 13,030.00
SUBCONTRATO % 45 - -
SUBTOTAL 13,030.00
3. EQUIPO
DESCRIPCION UNIDAD CANTIDAD V.UNIT. VR.UNITARIO
HERRAMIENTA DD 0.1 1,000 100.00
ANDAMIO DD 2 1000 2,000.00
SUBTOTAL 2,100.00
PRECIO UNITARIO TOTAL 23,130.00
SUBTOTAL 13,030.00
PRECIO UNITARIO TOTAL 55,140.00
Suministro e instalacion guardaescoba en ceramica
UNIDAD: M2
1. MATERIALES
DESCRIPCION UNIDAD CANT. V.UNIT. V. TOTAL
GUARDAESCOBA CERAMICA BISELAD M2 1.05 20,000.00 21,000.00
PEGACOR KG 3.00 1,600.00 4,800.00
CEMENTO BLANCO KG 0.70 800.00 560.00
SUBTOTAL 26,360.00
2. MANO DE OBRA
TRABAJADOR UN PRESTACION JORN.TOTAL RENDIM. VR.UNITARO
CUADRILLA AA HC 13,030 1.00 13,030.00
SUBTOTAL 13,030.00
PRECIO UNITARIO TOTAL 39,390.00
Construccion andenes perimetrales en concreto 3000 psi, incluye descapote, sardinel para
confinamiento en el mismo material y base en recebo compacto de .20 mts.
1. MATERIALES
DESCRIPCION UNIDAD CANT. V.UNIT. V. TOTAL
CONCRETO 3000 PSI M3 0.10 350,000 35,000.00
RECEBO COMPACTO E .20 MTS. M3 0.20 40,000 8,000.00
TABLA CHAPA ML 0.51 10,000 5,100.00
SUBTOTAL 48,100.00
2. MANO DE OBRA
TRABAJADOR UN PRESTACION JORN.TOTAL RENDIM. VR.UNITARO
CUADRILLA AA HC 13,030 1.00 13,030.00
SUBTOTAL 13,030.00
PRECIO UNITARIO TOTAL 61,130.00
CONCRETO CICLOPEO
UNIDAD: M3
1. MATERIALES
DESCRIPCION UNIDAD CANT. V.UNIT. V. TOTAL
CONCRETO DE 3000 PSI M3 0.40 350,000 140,000.00
PIEDRA RAJON O MEDIA ZONGA M3 0.60 30,000 18,000.00
DESPERDICIO %
SUBTOTAL 158,000.00
2. MANO DE OBRA
TRABAJADOR UN PRESTACION JORN.TOTAL RENDIM. V. TOTAL
CUADRILLA AA HC 13,030 12.00 156,360.00
SUBTOTAL 156,360.00
3. EQUIPO
DESCRIPCION UNIDAD CANTIDAD V.UNIT. V. TOTAL
HERRAMIENTA MENOR GBL 0.20 1,000 200.00
VIBRADOR A GASOLINA DD 0.04 0 0.00
SUBTOTAL 200.00
4. COSTOS INDIRECTOS
DESCRIPCION PORCENTAJE V. TOTAL
PRECIO UNITARIO TOTAL 314,560.00
Pintura interior en muros, techos y piso, guardaescoba en media caña, tipo epoxica de dos
componentes aseptica.
UNIDAD: M2
1. MATERIALES
DESCRIPCION UNIDAD CANT. V.UNIT. V. TOTAL
PINTURA EPOXICA GL 0.2 160,000 32,000.00
DESPERDICIO %
SUBTOTAL 32,000.00
2. MANO DE OBRA
TRABAJADOR UN PRESTACION JORN.TOTAL RENDIM. VR.UNITARO
CUADRILLA CC HC 13,030 1.50 19,545.00
SUBCONTRATO % 45 - -
SUBTOTAL 19,545.00
3. EQUIPO
DESCRIPCION UNIDAD CANTIDAD V.UNIT. VR.UNITARIO
HERRAMIENTA DD 0.1 1,000 100.00
ANDAMIO DD 2 -
SUBTOTAL 100.00
PRECIO UNITARIO TOTAL 51,645.00
Alistado e impermeabilizado placa maciza en concreto, con manto en full oil de aluminio.
UNIDAD: M2
1. MATERIALES
DESCRIPCION UNIDAD CANT. V.UNIT. V. TOTAL
MORTERO 1:3 M3 0.04 267,000 10,680.00
MANTO FULL OIL DE ALUMINIO M2 1.00 40,000 40,000.00
SUBTOTAL 50,680.00
2. MANO DE OBRA
TRABAJADOR UN PRESTACION JORN.TOTAL RENDIM. VR.UNITARO
CUADRILLA AA HC 13,030 0.80 10,424.00
SUBTOTAL 10,424.00
PRECIO UNITARIO TOTAL 61,104.00
ADMINISTRACION 10%
IMPREVISTOS 5%
UTILIDAD 7%
IVA 16%
TOTAL COSTOS INDIRECTOS