7700 TPD-PIONEER CEMENT Doc No.

:
CONST-PK-/QA&QCMS-C-PCL-02
PROJECT Rev: 02
Date of Rev: Sept 29, 2017
METHOD STATEMENT FOR Page: 1 of 8
CONCRETE WORKS

CONTENTS
1. Objective 3
2. Scope 3
3. Definitions/ Abbreviations 3
4. Responsibilities 3
5. Procedure 4
5.1 Batching Plant 4
5.2 Hot Weather Concrete 4
5.3 Concrete Test 4
5.4 Construction Joints 4
5.5 Concrete Embedment 4
5.6 Concrete Operations 5
5.6.1 Transportation 5
5.6.2 Blinding Concrete 5
5.6.3 Placing of Concrete 5
5.6.4 Compaction of Concrete 5
5.6.5 Concrete Finishing 5
5.6.6 Concrete Curing 5
5.6.7 Edges 6
5.7 Hand Finishing 6
5.8 Repair to Damaged or Defective Concrete 6
5.9 Rebars 6
5.10 Formwork 6
6. Tools & Equipment 7
7. HSE Instructions 7
8. Related Documents 8
Signature

Date
Name Asad Naqvi S.A.Haseeb
Position Engineer QC I/C QA&QC CDI PCL
Role Prepared By Reviewed By Approved By

This document is the Intellectual Property of Descon. Any unauthorized use, including the modification and reproduction of the
content is strictly prohibited. © Copyrights Ordinance 2002, All Rights Reserved.
7700 TPD-PIONEER CEMENT Doc No.:
CONST-PK-/QA&QCMS-C-PCL-02
PROJECT Rev: 02
Date of Rev: Sept 29, 2017
METHOD STATEMENT FOR Page: 2 of 8
CONCRETE WORKS

Document Revision/Review History

REVISION REVIEW Reviewed by

No. Date Description No. Date


A

00 July 03, New MS Developed after D


2016 restructuring of Division
E

July 03, Revised due to Organization C


01 2017 transformation
D

B
02 Sept 29, Revised as per Site
2017 requirement C

This document is the Intellectual Property of Descon. Any unauthorized use, including the modification and reproduction of the
content is strictly prohibited. © Copyrights Ordinance 2002, All Rights Reserved.
7700 TPD-PIONEER CEMENT Doc No.:
CONST-PK-/QA&QCMS-C-PCL-02
PROJECT Rev: 02
Date of Rev: Sept 29, 2017
METHOD STATEMENT FOR Page: 3 of 8
CONCRETE WORKS

1. OBJECTIVE

The objective of this Method Statement is to provide guidelines for execution and
Inspection procedure for concrete works.

2. SCOPE

This method statement covers concrete works under the project scope.

3. ABBREVIATIONS

ACI American Concrete Institute


CAR Corrective Action Request
CM Construction Manager
FRM Form
HSE Health, Safety & Environment
IMTE Inspection, Measuring & Test Equipment
MS Method Statement
PM Project Manager
PPE Personal Protective Equipment
PQP Project Quality Plan
QA&QC Quality Assurance and Quality Control
QIP Quality Inspection Plan
SM Site Manager

4. RESPONSIBILITIES
 PM/SM shall be responsible for initialization of the work, as well as to
manage the resources for respective activities in compliance with the
quality, schedule and safety aspects of the project.

 The Area Surveyor shall ensure that location & levels of the concrete
works are as per approved drawings.

 The Area In-Charge shall ensure that the concrete placement activities
are conducted according to this MS, latest project drawings &
specifications.

 QA&QC Inspector shall ensure that all the relevant works are carried
out in conformance with project specifications, PQP and QIP. In case of
any non-conformance, CAR shall control it.

This document is the Intellectual Property of Descon. Any unauthorized use, including the modification and reproduction of the
content is strictly prohibited. © Copyrights Ordinance 2002, All Rights Reserved.
7700 TPD-PIONEER CEMENT Doc No.:
CONST-PK-/QA&QCMS-C-PCL-02
PROJECT Rev: 02
Date of Rev: Sept 29, 2017
METHOD STATEMENT FOR Page: 4 of 8
CONCRETE WORKS

5. PROCEDURE

5.1 Batching Plant

 The batching plant shall produce the concrete in accordance with the
approved design mix, applicable as per project specifications/drawings.

 After loading fresh ingredients, concrete shall be mixed uniformly.

 The Batch Plant Supervisor shall be responsible for checking that all
“wash water” has been removed from the delivery truck prior to loading
the concrete.

 The Quality Control Person shall perform the slump test and keep a
complete record of each truck of concrete.

5.2 Hot Weather Concrete.

 Necessary measures shall be taken for concreting under hot weather.


These measures shall include, but not limited to, spraying water on
aggregates, chilling the mix ingredients with ice and when ice is used in
the mix, maintain the correct amount of water required.

5.3 Concrete Tests

 During concrete production, cubes/ cylinder specimens shall be casted


from each grade of concrete as per specified requirement.

 The characteristic strength of the concrete placed in the formwork shall


be determined for 7 days and 28 days by the Compressive Strength
Testing of test cubes/ cylinders as per project specifications.

 Complete record of cubes/ cylinder testing with location mix design


reference and date of placement etc. shall be maintained.

5.4 Construction Joints

 Approval of the Engineer shall be obtained before introducing joints if not


shown on the drawings.

 Construction joints shall be perpendicular to the plane of the member or


as directed by the Engineer. Continue all specified reinforcement through
joints.

5.5 Concrete Embedment

 All embedment’s in concrete shall accurately be located and secured in


position within approved tolerance to resist loads incidental to placing of
concrete.

This document is the Intellectual Property of Descon. Any unauthorized use, including the modification and reproduction of the
content is strictly prohibited. © Copyrights Ordinance 2002, All Rights Reserved.
7700 TPD-PIONEER CEMENT Doc No.:
CONST-PK-/QA&QCMS-C-PCL-02
PROJECT Rev: 02
Date of Rev: Sept 29, 2017
METHOD STATEMENT FOR Page: 5 of 8
CONCRETE WORKS

 All embedded items locations shall be verified as per construction


drawings. Surveyor shall be responsible for levels and locations of
embedded parts

5.6 Concreting Operations

5.6.1 Transportation

 The concrete shall be transported to site in Transit Mixers immediately


after mixing and shall be placed within allowable time as per project
specifications.

 The concrete delivery note shall be endorsed showing the time of


dispatch of the truck.

 The concrete pour record shall be endorsed with the time of arrival at
placing site and the time of completion of discharging.

 No concreting operations shall be performed without the written approval


of the Engineer.

5.6.2 Blinding Concrete

 Prior to commencement of blinding concrete activity,


excavation/compaction shall be inspected & cleared by the QA&QC
Inspector.

 Surveyors shall layout the foundation on ground before and after Lean.

 Thickness of the blinding concrete shall be as per IFC drawing

5.6.3 Placing of Concrete

 Prior to placing concrete, ambient & concrete temperatures shall be


recorded.

 Placing of rebar and formwork shall be as per drawing and its approval
from the Engineer shall be obtained.

5.6.4 Compaction of Concrete

 Proper compaction shall be done thoroughly around all reinforcement,


embedded fixtures and internal corners with internal vibrators in
accordance with project specifications or standards.

5.6.5 Concrete Finishing

 The concrete face shall be checked for compliance as indicated in the


project specifications or construction drawings.

This document is the Intellectual Property of Descon. Any unauthorized use, including the modification and reproduction of the
content is strictly prohibited. © Copyrights Ordinance 2002, All Rights Reserved.
7700 TPD-PIONEER CEMENT Doc No.:
CONST-PK-/QA&QCMS-C-PCL-02
PROJECT Rev: 02
Date of Rev: Sept 29, 2017
METHOD STATEMENT FOR Page: 6 of 8
CONCRETE WORKS

 The concrete face shall be cleaned and made free from all foreign
matters.

5.6.6 Concrete Curing

 After completion of concrete pouring/finishing, necessary measures to


protect the concrete surface shall be taken. The exposed surfaces shall
be sprayed with an approved curing compound or shall be covered by wet
Hessian. These covers shall be maintained till end of allowable curing
period.

5.6.7 Edges

 The edges of the concrete shall be chamfered elsewhere as required and


as shown in the drawings.

5.7 Hand finishing

 In the event of breakdown of mechanical equipment, hand-finishing


method may be used to finish the concrete already placed and no
additional concrete shall be placed until such equipment is repaired up to
satisfaction of the Engineer.

5.8 Repairs to Damaged or Defective Concrete

 If some damage or defect exists, inspection of location shall be


conducted jointly with the Engineer and method statement for repair of
works shall be submitted to Engineer for approval.

5.9 Rebars

 It shall be ensured that only tested/approved grade of steel bars are


used.

 Cutting and bending of rebar shall be carried out as per approved bar
bending schedule.

 Cut lengths shall be grouped with respect to their mark numbers for
identification and shifting it from steel yard to the site.

 Rebar spacing shall be marked as per the drawings.

 Rebar network shall be properly fixed with binding wire.

 Chairs shall be provided at proper intervals to support the rebar


network.

 Spacer blocks of cement mortar shall be used to provide clear cover to


the reinforcement as mentioned in the construction
drawing/specifications. These blocks shall be placed at the bottom and
to the sides where necessary.
This document is the Intellectual Property of Descon. Any unauthorized use, including the modification and reproduction of the
content is strictly prohibited. © Copyrights Ordinance 2002, All Rights Reserved.
7700 TPD-PIONEER CEMENT Doc No.:
CONST-PK-/QA&QCMS-C-PCL-02
PROJECT Rev: 02
Date of Rev: Sept 29, 2017
METHOD STATEMENT FOR Page: 7 of 8
CONCRETE WORKS

 Lap lengths shall be provided as per drawing / specifications.

5.10 Formwork

 Approved construction drawings shall be thoroughly studied for


concrete work carefully and design of formwork and false work shall be
prepared. The formwork shall be capable of withstanding loads
imposed when the concrete is placed.

 The formwork shall be laid out such that forms are positioned at
specified lines and that these are in plumb & level conforming to shape,
lines, elevations and dimensions of concrete shown on the drawings..

 End shall be braced adequately, to support all formwork so as to


maintain the desired position during and after placing the concrete and
also sufficiently tight to prevent mortar leakage.

 Before any reinforcement is placed, all forms shall be lubricated


properly to ensure ease of removal of forms and to avoid staining of the
concrete.

 Forms shall be positioned accurately to specified tolerance and secure


firmly with the anchors, bolts, inserts, supports, hangers, pipe sleeves,
drains, water stoppers etc. prior to pouring of the concrete.

6. TOOLS AND EQUIPMENTS

 Batching plant,
 Concrete Mixers,
 Super Swingers,
 Transit Mixers,
 Loader (front end),
 Vibrators
 Concrete Pumps,
 Wheel-Barrows etc.
 Bar Bending and Cutting Machine
 Scaffolding
 Crane
 Hand tools

7. HSE INSTRUCTIONS

 Concrete work shall be performed in accordance with relevant project


HSE instructions & HSE policy of DESCON at all temporary and
permanent works.
 All efforts shall be made to keep the environment clean.
 Material or equipment shall be maintained in an orderly manner and
labeled in accordance with statutory requirements shall be used in safe
This document is the Intellectual Property of Descon. Any unauthorized use, including the modification and reproduction of the
content is strictly prohibited. © Copyrights Ordinance 2002, All Rights Reserved.
7700 TPD-PIONEER CEMENT Doc No.:
CONST-PK-/QA&QCMS-C-PCL-02
PROJECT Rev: 02
Date of Rev: Sept 29, 2017
METHOD STATEMENT FOR Page: 8 of 8
CONCRETE WORKS

manner. Beware from falling or flying concrete while pouring is in


progress.
 If buckets are used for pour, riding the bucket is prohibited.
 Electric powered tools, floats & vibrators shall be doubly insulated or
grounded for operator protection.
 Any liquid fuel spills and accidental waste disposal shall be avoided and
properly cleaned up.
 Gumboots shall be used for entering into concrete.
 Eye protection shall be required for labor during placement of concrete.
 HSE Inspector shall ensure proper safety arrangements.
 Area shall be barricaded properly and sign boards shall be installed
prior to commencement of work.
 HSE Inspector shall remain at site during concrete works.

8. RELATED DOCUMENTS

 CONST/PK/QA&QC/FRM-08 Corrective Action Request (CAR) form


 CONST/PK/QA&QC/FRM-206 Request for Inspection and Test (RIT)
 CONST/PK/QA&QC/FRM-166 Survey Report
 CONST/PK/QA&QC/FRM-199 Material Approval Form
 CONST/PK/QA&QC/FRM-180 Summary of Daily Concrete
 CONST/PK/QA&QC/FRM-181 Concrete Pour card
 CONST/PK/QA&QC/FRM-182 Daily program chart for concrete work
 CONST/PK/QA&QC/FRM-202 Concrete Pour Release

This document is the Intellectual Property of Descon. Any unauthorized use, including the modification and reproduction of the
content is strictly prohibited. © Copyrights Ordinance 2002, All Rights Reserved.