Wellington Estate DLF 5

Solar PV Plant Phase 1 commissioned on 10th October 2017


Start of our Solar (Learning) Process…

• January 2014 - First Contact with any Solar


EPC Company
• March 2014 – First techno-commercial
proposal received for a 116 kWp plant,
@Rs.95,000/kWp
• Plan deferred / dropped for following reasons:
• New Concept
• Project cost range found prohibitively high, and
financially unviable at that time.
Our Solar (learning) Process…
Size Price Status
November Not Offer not
Not submitted
2016 submitted submitted
Design
January 2017 350kWp 65,000/kWp
submitted

Design not
February 2017 150 kWp 59,500/kWp
submitted

Design not
February 2017 100 kWp 71,000/kWp
submitted

Design not
March 2017 130 kWp 72,000/kWp
found suitable

Rate not Design not


May 2017 56.70 kWp
submitted found suitable

Design
June 2017 260kWp 55,000/kWp
submitted
Final Selection in June 2017…

 Actively engaged with WECA since Jan  Contacted WECA (in June 2017)
2017. during finalization with Pious.
 Shared full details of design data,  Not ready to submit full details of
including shadow simulation and design data.
production analysis.  Was outsourcing installation and
 Ready to work on component basis. commissioning; Pious being one of
 Offered a choice of component their INC vendors.
vendors.  Not offering a choice of components.
 Offered same SolarEdge technology, as  Not being very open with technical
was being offered by Havells. information being asked.
 Ready to meet WECA target price of  Introduced WECA to SolarEdge
Rs. 50,000/kWp + tax optimizer technology.
Project Implementation Process…

Selection of main Technology Vendors

Solar Panels Invertors & Optimizers


 For subsidy eligibility, Indian panels only  Best in class technology.
could be selected.  Enhanced safety features.
 One of the top solar Solar Panel makers  Longest warranty period.
in India with a 10-year business success  Offering remote online real time
history. monitoring for life.
 Prompt & quick delivery.
Project Implementation Process…
Logistical Challenges
 Unloading and safe storage of
incoming material on ground level.
 Carrying all material from ground level
to roof top (via Lift/Stairs).
 Storage of material on roof top.
 Disturbance to residents from
installation work.
Remote Web Monitoring
Remote Web Monitoring

https://monitoringpublic.solaredge.com/solaredge-web/p/site/public?name=DLF5%20Wellington%20Solar#/dashboard
Wellington Estate DLF 5

Solar PV Plant Phase 2 (150 kWp) planning started


Contribution of Solar Power in
Common Area Electricity

Phase 1 = 200 kWp After Phase 2 = 350 kWp

GRID POWER SOLAR POWER


Annual Financial Savings

Current
Rs. 20 lac

After Expansion
Rs. 35 lac
Annual Environmental Savings

Current~300 tons After Expansion~500 tons


~ 1000 trees ~ 1600 trees
Wellington Solar Plant Aerial View
Wellington Estate DLF 5