Você está na página 1de 2

4/11/2015 Analysis of net­metering regulation of Rajasthan » OPEN­ACCESS

OPEN­ACCESS
OPEN­ACCES: A Blog by REConnect

OPEN­ACCESS  » Draft Regulation  » Analysis of net­metering regulation of Rajasthan
CATEGORIES
ANALYSIS OF NET­
MAR
16
Select Category

METERING REGULATION OF ARCHIVES
RAJASTHAN April 2015 (4)

Key points of the Regulation: March 2015 (17)

Rajasthan came out with the final net­metering regulation on 26 Feb 2015. The below are key points of the regulation: February 2015 (8)

• Net­metering permission to be provided on a first­cum­first­serve basis by the distribution licensee. Overall capacity to
January 2015 (12)
be limited to 30% of the capacity of the distribution transformer.
• Maximum capacity of the plant will be 80% of the contract demand of the consumer.
December 2014 (10)
• Minimum size of the plant – 1kwp, maximum – 1000 kwp.
• Time bound approval process by the Discom.
November 2014 (14)
Energy accounting related points:
October 2014 (12)
• Consumer will get credit for energy injected into the grid for the billing period
• If electricity injected exceeds the units consumed in the month, credit  will be carried forward to next period to the September 2014 (17)
extent of 50 units (the draft  regulation had allowed a full carry forward to the next month).
• Excess units (>50 units) will be paid for at the rate set by RERC (currently Rs 6.631) by the Discom. August 2014 (16)
• The plant will be exempt from banking, wheeling and cross­subsidy charges. This will encourage the model of third­
party ownership of the plant. July 2014 (24)
• A bi­directional/ net­meter will be required to be installed. Those with ABT meters already installed will not be required
to install a net­meter June 2014 (10)

Issues for consideration: May 2014 (9)

1. Clarity on Solar RPO fulfillment by an obligated entity through net­metered solar PV project:
April 2014 (10)

The policy is not absolutely clear on the ability of an obligated entity to meet its solar RPO through generation of rooftop
March 2014 (8)
solar.  The  policy  says:  “The  quantum  of  electricity  generated  from  the  Rooftop  PV  Solar  Power  Plant  under  net
metering  arrangement  by  an  Eligible  Consumer,  who  is  not  defined  as  obligated  entity,  shall  qualify  towards
February 2014 (12)
compliance of Renewable Purchase Obligation (RPO) for the distribution licensee in whose area of the supply the
Eligible Consumer is located.” (emphasis supplied)
January 2014 (9)
Thus, the Discom can meet its solar RPO through entire generation from a net­metering plant, when the consumer is
not an obligated entity. Since, for an obligated entity the Discom will not be able to use the power generated for RPO December 2013 (8)
offset, it implies that the obligated entity will be able to use it. However, the regulation does not expressly state so.
November 2013 (6)
Can an obligated entity avail RPO benefit by installing a net­metered solar PV project?
October 2013 (7)
In our opinion, the answer is a qualified ‘yes’.
September 2013 (6)
The draft regulation allowed the entire generation from the plant to be adjusted against the consumption by carrying
forward such excess  (without any limit) to the next months.  However, the final regulation allows carry forward to next
August 2013 (8)
month  only  to  the  extent  of  50  units.  The  excess  is  paid  for  by  the  Discom  at  the  preferential  tariff.  This  will  make
claiming RPO offset difficult as when the Discom pays preferential tariff, it will be allowed to use such power to meet its
July 2013 (6)
RPO.

Thus, an obligated entity will only be able to meet its RPO to the extent of offset available against its consumption, not June 2013 (7)
on the excess for which received preferential tariff.
May 2013 (9)
It  is  worth  noting  that  the  ability  of  claiming  RPO  offsets  is  not  expressly  mentioned  in  this  regulation  –  instead  it  is
mentioned in the  RPO regulation (2nd Amendment) as an observation by the commission: April 2013 (6)

Treatment for Roof Top/Land mounted solar plants in consumer premises:  March 2013 (3)

10. The Commission observes that no new provision as suggested by the stakeholders is required in the regulations
February 2013 (4)
since any RE power produced by captive RE source for own consumption or taken through open access is considered
towards fulfillment of their RPO…..
December 2012 (3)
However,  the  energy  accounting  methodology  will  be  complex  (because  of  the  change  where  only  a  limited  carry
forward is allowed). November 2012 (5)
In  our  opinion,  the  best  course  of  action  for  an  obligated  entity  is  likely  to  be  to  build  capacity  well  within  its
consumption requirements on a monthly basis, so that the situation of carry forward does not arise. October 2012 (8)

2. REC eligibility for a net­metered solar plant: September 2012 (4)

http://reconnectenergy.com/blog/2015/03/analysis­of­net­metering­regulation­of­rajasthan/ 1/2
4/11/2015 Analysis of net­metering regulation of Rajasthan » OPEN­ACCESS
The  draft  regulation  contained  a  clause  that  allowed  RECs  as  per  CERC  REC  regulations.  However,  in  the  final
August 2012 (2)
regulation such a clause has been removed. Thus, it appears that net­metered plants will not be eligible for RECs.

The RERC final regulation is available here. July 2012 (4)

June 2012 (6)
Posted on March 16th, 2015 Posted by Team REConnect Comments Off
May 2012 (8)
Filed under: Draft Regulation, Net Metering, Solar Rooftop & Net Metering

Tags: Rajasthan, RERC, RREC April 2012 (2)

March 2012 (3)

COMMENTS February 2012 (8)

Comments are closed. January 2012 (5)

December 2011 (10)

November 2011 (5)

October 2011 (6)

September 2011 (3)

August 2011 (7)

July 2011 (6)

June 2011 (8)

May 2011 (6)

April 2011 (4)

March 2011 (4)

OPEN­ACCESS All Rights Reserved.
Designed by Carla Izumi Bamford
Powered by Wordpress

http://reconnectenergy.com/blog/2015/03/analysis­of­net­metering­regulation­of­rajasthan/ 2/2

Você também pode gostar