Escolar Documentos
Profissional Documentos
Cultura Documentos
Document Class: Z
2, 3, 7, Added General
1 18/JAN/16 K.T R.G M.T
8-13 SWMS
Follow Employer’s
0 27/OCT/14 1,5,6,7 A.S R.G M.T
Comment
A 22/APR/14 All First issue A.S M.T M.T
D R A
IN
18-JA
N - 2 016
Employer Doc. No.
NSRP Complex Project Rev. 1
CONTENTS
1 INTRODUCTION ...................................................................................................................................3
2 REFERENCE DOCUMENTS ................................................................................................................3
3 ABBREVIATION AND DEFINITION .....................................................................................................3
4 SCOPE OF APPLICATION...................................................................................................................3
5 HSE .......................................................................................................................................................4
6 METHOD ...............................................................................................................................................4
6.1 Gravity Flow Flushing Method ...........................................................................................................4
6.2 Power Flushing Method ......................................................................................................................4
7 PRECAUTION .......................................................................................................................................4
8 DETAILS FOR IMPLEMENTATION .....................................................................................................5
8.1 Planning ................................................................................................................................................5
8.2 Preparation/Execution.........................................................................................................................6
9 ACCEPTANCE CRITERIA ....................................................................................................................7
10 POST WORK.........................................................................................................................................7
11 ATTACHMENT......................................................................................................................................7
Attachment-1: General Safe Work Method Statement (SWMS) for Water Flushing………………8-13
D R A
IN
18-JA
N - 2 016
Employer Doc. No.
NSRP Complex Project Rev. 1
1 INTRODUCTION
This document describes the general requirements for carrying out water flushing applied to pipes of the
plant constructed in NSRP Project.
Detailed procedures for implementation of water flushing will be prepared as required on a system basis,
based on the philosophies described in this procedure.
Detailed procedures together with the General Safe Work Method Statement (SWMS) and Job Safety
Analysis (JSA) shall be utilized implementation of water flushing as per Project HSSE requirement.
2 REFERENCE DOCUMENTS
S-000-1710-0001V Pre-commissioning and Commissioning Execution Plan
S-000-1710-0100V Pipe Cleaning Guide
4 SCOPE OF APPLICATION
This method is widely used in pipe cleaning and is usually applied to pipes where liquid flow during
normal operation. Kinetic energy generated by pump or obtained by gravity with pre-filled water with
proper volume is used to flush foreign materials from pipes or collect them in filters/strainers for removal.
Water must be air blown out of system to avoid damage to pipe or contamination of process.
Water flushing utilizes the above principle to expel foreign materials, and improve the cleanness of the
pipe, by having a break in the pipe at the flushing boundary limits, where the water flow is discharged or
to remove foreign materials by installing a temporary strainer/filter in the closed circulation loop.
For water flushing, the high velocity in the pipelines is achieved by being connected to a pump, which is
operated on water.
It is important that the water being used for line flushing is low enough in contaminants in relation to
water quality to ensure that the required flushing specification can be achieved in the water flushing. The
flushing medium shall be in general fresh water. When flushing stainless steel lines, the chloride content
shall be less than 50 ppm.
D R A
IN
18-JA
N - 2 016
Employer Doc. No.
NSRP Complex Project Rev. 1
5 HSE
The following HSE risks are inherent in water flushing:
Potential for injury at water discharge area: The flushing discharge areas shall be cordoned
off with tape, warning notices posted, and patrolled by a commissioning team member to
ensure personnel safety.
Appropriate personal protective equipment (PPE) shall be worn or used. The area will be
barricaded and unnecessary personnel will be asked to leave the affected area.
Suitable back stop (e.g. net or tarpaulin etc.) will be used to capture all foreign materials.
Clear path of water to a sewer.
Build-up of water in low area if not drained.
Erosion of gravel
6 METHOD
Water flushing will be conducted by any one of the following methods:
7 PRECAUTION
The following precautions must be paid when water flushing is conducted.
The execution of flushing works shall also include the necessary measures for safety, for
cleaning of area, and for disposal of waste water. During flushing operations, disposal of
flushing water to comply with the Effluent Discharge Norms as specified in the Environmental
Design Basis (S-000-1240-0111V).
Take suitable measures to prevent flushing debris into equipment.
Suitable back stop (e.g. net or tarpaulin etc.) will be used to capture all foreign materials.
When columns/drums/vessels are used as water reservoir, their vent valves or appropriate
top opening shall be kept open until completion of water flushing to prevent pulling a vacuum
in system.
If pumps will be used for water flushing then these must be safeguard from over current,
cavitation, etc. Vendor instruction and pump curve should be available. Process pumps
should not be used if not designed to pump water.
D R A
IN
18-JA
N - 2 016
Employer Doc. No.
NSRP Complex Project Rev. 1
When any operations data show abnormal pump performance related to vibration, noise,
electric current or temperature exceeds the normal value, stop running the pump at once.
CAUTION: Damage to the pump can occur due to abnormal pump performance.
The line from the suction vessel to the pump shall be water flushed by gravity to the pump
suction. Do not flush through the pump.
All equipment, piping, and component openings shall be provided with plastic pipe caps or
plastic bags to prevent contamination.
Piping which is under construction shall be positively isolated until they are required.
In order to avoid stress corrosion cracks, treated water shall be used for stainless steel pipes
and piping component which come into contact with water. Demineralized water, condensate
and BFW are preferable for stainless steel pipes. In addition, construction water from
temporary RO (Reverse Osmosis purifying) unit will meet the requirement of water quality for
stainless steel pipes.
For all stainless pipes, flushing water shall be immediately drained and pipe shall be blown
dry upon completion of line to avoid chloride corrosion.
D R A
IN
18-JA
N - 2 016
Employer Doc. No.
NSRP Complex Project Rev. 1
8.2 Preparation/Execution
1. Remove or positively disconnect the following devices, and upon completion, reinstall those in the
correct position.
Safety valves
Check valves, if required
Rupture disks
Orifice plates or flow meter elements
In-line mixers/In-line strainer
Spargers
Spray nozzles
Control valves
Self-actuated valves
Soft seated valve which could be damaged by the ingress of water or dirt or restrict the water
flushing flow path
Emergency shut off valves (only when they restrict the flush path)
Thermo wells
All other items which could be damaged by ingress of water or dirt or restrict the flush flow
path
2. Removal of ball/gate valves is normally not necessary since these valves do not restrict the flush flow
path. These valves should be kept in the open position while flushing.
3. Install temporary piping spools and fitting requires for flushing
4. Prior to commencement of flushing, the route shall be checked at site.
5. Each flushing condition should be checked in advance. Any big remaining works that will hinder the
air blowing activity shall be coordinated to concerned discipline.
Pay attention particularly on the following:
Piping and instrumentation works around flushing point
Civil works
Insulation works (if necessary)
D R A
IN
18-JA
N - 2 016
Employer Doc. No.
NSRP Complex Project Rev. 1
6. Before proceeding to flushing, conduct job safety and environmental analysis on this procedure (and
other related topics) to all personnel who will be assigned in these activities. Items to be discussed
are the following:
Safety ― risks, potential hazards, control measures/action, etc.
Communication method (use of radio or hand signal or cell-phone, etc.)
Each personnel responsibility
Work method control (PTW, working at heights, barricades and etc.)
Water Flushing procedure
7. Make line-up of the system in advance and put barricades around the area, if necessary.
8. Removed items should be kept in safe location and should be marked-up for identification. Upon
completion of water flushing, it must be reinstate back exactly to the same location and orientation.
9 ACCEPTANCE CRITERIA
The inspection criteria will be visual inspection of discharged water. When any foreign materials
interfering with actual plant operation are no longer visually checked in flushed water, water flushing shall
be deemed satisfactory completed. When Contractor is considering the system is clean, Employer shall
be invited for final test for witness and approval.
10 POST WORK
1. Ensure pipes are adequately drained and dried. If the system will not be in service immediately after
water flushing activity, dryness of the pipe internal shall be checked to assure free water is
completely drained and dried in order to avoid pipe internal corrosion and water contamination.
2. Pipes and devices removed during flushing shall be reinstalled. A reinstatement check against the
P&IDs will be conducted to ensure the reinstatement is completed and all equipment is correctly
oriented prior to putting a system into service.
3. Acceptance documentation with marked-up P&ID for water flushing activity shall be signed by
Contractor and Employer.
11 ATTACHMENT
Attachment-1: General Safe Work Method Statement (SWMS) for Water Flushing
D R A
IN
18-JA
N - 2 016
NSRP Complex Project General Procedure for Water flushing
Contractor Doc No: S-000-1710-0110V_Rev'1
Attachment-1, General Safe Work Method Statement (SWMS) for Water Flushing
Page 8 of 13
CONTENTS
1 INTRODUCTION ...................................................................................................................................9
2 REFERENCE DOCUMENTS ................................................................................................................9
3 SCOPE ..................................................................................................................................................9
4 RESPONSIBILITIES .............................................................................................................................9
5 PROCEDURE......................................................................................................................................10
5.1 PREPARATION...................................................................................................................................10
5.2 EXECUTION........................................................................................................................................10
5.3 METHOD .............................................................................................................................................11
5.4 POST WORK .......................................................................................................................................11
6 EQUIPMENTS .....................................................................................................................................11
7 MATERIALS........................................................................................................................................11
8 LOCATION ..........................................................................................................................................12
9 SAFETY...............................................................................................................................................12
D R A
IN
18-JA
N - 2 016
NSRP Complex Project General Procedure for Water flushing
Contractor Doc No: S-000-1710-0110V_Rev'1
Attachment-1, General Safe Work Method Statement (SWMS) for Water Flushing
Page 9 of 13
1 INTRODUCTION
Water flushing is widely applied for pipe cleaning especially when pipeline is for liquid service. The objective is
to maintain a water flow through the system at reasonable velocity for certain period of time. To achieve this
objective, the system is connected either with a water source at one end whereas water is discharged from
the other end. Repeated filling and draining is also carried out where continuous flow of adequate amount of
water is not possible. Where possible a closed loop is formed with a pump (permanent or temporary) that
operated on water including the piping system to be cleaned. Circulated dirty water is drained out as long as
the system does not achieve required level of cleanliness.
This document describes the general steps, resources and safety measures for carrying out water flushing
applied to pipes in a safely manner in accordance with the detail procedure prepared.
Before executing an activity this document shall be carefully assessed, amended as necessary based on the
site condition, work location and other special requirements if any stated in the detail procedure. JSA (Job
Safety Analysis) shall be carried out based on the content in this document and detail procedure and
mitigation measure shall be implemented before execution of the work
2 REFERENCE DOCUMENTS
S-000-1654-0100V Job Safety Analysis (JSA) and Safe Work Method Statement (SWMS)
3 SCOPE
This document is applicable for all water flushing activities carried out by JGCS Pre-commissioning,
Commissioning team within the NSRP Project and will be utilized in conjunction with the detail procedure
specific to a system or unit.
4 RESPONSIBILITIES
The organization composed on JGCS and Subcontracted personnel executes all work relating to water
flushing such as preparation, execution and post work. JGCS commissioning engineer, supervisor is
responsible for the necessary documentation and supervision work whereas subcontracted labour carries out
all field execution work under supervision of JGCS members.
Responsibilities of each member involved in water flushing activity is detailed below:
Commissioning Section Leader
Commissioning Section Leader is responsible for approval PTW associated with water flushing. He / She
make sure the organization executes the work is competent, well trained to comply with the site HSSE
requirements.
Commissioning Engineer / Commissioning Senior Supervisor
Commissioning Engineer is responsible for necessary planning and preparation for the work including
checking of PTW associated with water flushing. He / She makes sure site execution team prepares and
executes the work as per plan and procedure. He / She sometime attends TBT / START work to make sure
HSSE risk and mitigation plans are well known among the execution team and implemented well.
Commissioning Supervisor
Commissioning Supervisor is the key role for site execution and is well experienced for the work. He / She
make sure all steps during site execution are carried out according to plan and procedure with observance of
site HSSE requirements. He / She carries out TBT / START before the activity to make whole group well
D R A
IN
18-JA
N - 2 016
NSRP Complex Project General Procedure for Water flushing
Contractor Doc No: S-000-1710-0110V_Rev'1
Attachment-1, General Safe Work Method Statement (SWMS) for Water Flushing
Page 10 of 13
aligned of the work, risk and mitigation measures. During execution stage, he / she closely monitor all aspects
of work.
Subcontracted Personnel
Subcontracted personnel forms the direct execution crew consisting of foreman, rigger, fitter and labour who
actually work under supervision of JGCS commissioning supervisor.
Foreman is the lead of the direct execution crew who is experienced with the similar work and executes the
work under JGCS supervisor or independently. The foreman is supported by the other team members in
preparation, execution and post work.
5 PROCEDURE
Water flushing generally involve preparation, execution and post work. Activities involved in each is detailed in
below subsections.
5.1 PREPARATION
Preparation step of water flushing includes following activities:
Confirm completion of piping construction including availability of pipe supports
Removal or positive disconnection of the piping components which are negatively affected by water
flushing
Install temporary spool, blind plates/flanges, instruments as necessary
Isolate the area of water flushing including the blow points. Install warning / caution signboards as
necessary
Note: warning / caution signboards must be prepared in dual language English and Vietnamese.
Protection of nearby equipment, structures from the impact
Arrange adequate drainage to prevent discharge water from causing water logging
Arrange adequate means to prevent erosion of ground, soil by flushing water discharge and flow
Preparation of an approved PTW
Issue safety flash notice to inform all member about the activity, location and access control
Notification to Employer is issued for witnessing the activity
5.2 EXECUTION
Execution step of water flushing includes following activities:
Perform TBT (Tool Box Talk) /START (Start Task Analysis Risk Talk)
Confirm line up as per detail procedure
Confirm all barricades, warning/caution signboards are in place. No unauthorized personnel are
within or vicinity of the exclusion zone
Set up water supply connection between water source and the subject to be water flushed
Start water supply gradually, and increase to the required level. Check discharge water condition from
the flushing end. Continue the process until flushed water become clean
D R A
IN
18-JA
N - 2 016
NSRP Complex Project General Procedure for Water flushing
Contractor Doc No: S-000-1710-0110V_Rev'1
Attachment-1, General Safe Work Method Statement (SWMS) for Water Flushing
Page 11 of 13
At the Initial stage of flushing the level of foreign material would be high which will come down with
time
When closed loop is formed for flushing with permanent or temporary pump, fill the system first with
water and then start the pump. Gradually increase circulation flow to the maximum possible.
Check circulating water condition and start draining out from selected points. Make up fresh water
into the system to keep the system filled.
Monitor pump condition, clean the suction strainer when needed.
For gravity flushing case, connect the system with water source such as tank and open the tank outlet
valve for flushing out the line. Alternatively fill up the system with water and drain out water quickly
from a manual operated valve suitably big to cause high flow through the system and located at the
lower point.
For this case, the filling-draining process should be repeated until drained water is clean.
Perform flushing from all the points as in detail procedure
Inform Employer to witness the line cleaning status
5.3 METHOD
There are several methods applied for water flushing such as gravity flow and power flushing; power flushing
may be carried out either by connecting with a water source or forming a closed loop with a pump. Detail
procedure shall indicate the method will be adopted for a work and describe in detail the steps for execution.
Common risk and mitigation measures associated with each method is covered in the safety section.
6 EQUIPMENTS
Following equipment are utilized for all components of work associated with water flushing:
Water source (Tank, vessel, tower etc)
Pump (permanent or temporary)
Lifting crane (as necessary)
7 MATERIALS
Following materials are required for all components of work associated with water flushing:
D R A
IN
18-JA
N - 2 016
NSRP Complex Project General Procedure for Water flushing
Contractor Doc No: S-000-1710-0110V_Rev'1
Attachment-1, General Safe Work Method Statement (SWMS) for Water Flushing
Page 12 of 13
Barricading tape
Warning, caution sign
Air horn or whistle
Walky-talky
Hand tools
Scaffolding materials
Temporary pipe spools, blinds, gaskets, instruments
PPEs
Water supply hose with anti-whip fitting
Back stop material (tarpaulin, net or wooden board etc)
8 LOCATION
Detail procedure will indicate the exact location of the work in the form of P&ID mark-up.
Before water flushing safety flash notice will be issued across the project to make people aware of the
work, risk and mitigation measures to be implemented.
9 SAFETY
Below mentioned are potential hazards for all components of work associated with water flushing and
mitigation measures. JSA shall identify the risk and mitigation measures in further details.
Risk Mitigation measures
Improper lifting (tools, equipment, method Project approved tools, equipment, method and
and manpower) manpower shall be utilized
Only experienced, trained and authorized personnel
shall be allowed to work
Fall from height, falling objects All personnel shall have undergone work at height
training and authorized to work at height
100% compliance with PPE and other fall protection
measures are mandatory
Entangled by rotating parts When pump is utilized for water flushing, all rotating
parts shall be well covered
The surrounding area shall be cordoned off with tape,
warning notices posted, and patrolled by a
commissioning team member to ensure personnel
safety.
Only competent persons shall be allowed in the vicinity
and to operate rotating machines
Approved LOTO procedure shall be utilized in case of
activities such as strainer cleaning
Electrical shock Only competent persons shall be allowed to operate
D R A
IN
18-JA
N - 2 016
NSRP Complex Project General Procedure for Water flushing
Contractor Doc No: S-000-1710-0110V_Rev'1
Attachment-1, General Safe Work Method Statement (SWMS) for Water Flushing
Page 13 of 13
D R A
IN
18-JA
N - 2 016