DAILY CONSTRUCTION ACTIVITIES

PROJECT DETAILS
PROJECT NAME Super Space Karachi
PROJECT LOCATION Near to Alddin staff gate
PROJECT #
CONTRACTOR'S SUPERVISOR
CONTRACTOR
REPORT # 1
DAY
DATE 2/26/2018

ACTIVITIES DETAILS
ACTIVITIES PERFORMED TODAY % COMPLETED
Pouring to base of construction building 30%
PROJECT DETAILS
PROJECT NAME Mega Pool Pump House
PROJECT LOCATION Mega Pool
PROJECT #
CONTRACTOR'S SUPERVISOR
CONTRACTOR Hashir Enterprises
REPORT # 1
DAY
DATE 2/26/2018

ACTIVITIES DETAILS
ACTIVITIES PERFORMED TODAY % COMPLETED
Painting carried out today 70%
PROJECT DETAILS
PROJECT NAME Labour Conteen
PROJECT LOCATION Near to electric workshop
PROJECT #

CONTRACTOR'S SUPERVISOR
CONTRACTOR Hashir Enterprises
REPORT # 1
DAY
DATE 2/26/2018

ACTIVITIES DETAILS
ACTIVITIES PERFORMED TODAY % COMPLETED
Pouring to base of construction building 30%
PROJECT DETAILS
PROJECT NAME Mosque Construction
PROJECT LOCATION Near to electric workshop
PROJECT #
CONTRACTOR'S SUPERVISOR
CONTRACTOR Faiz Assciates(Structure), Hashir enterprizes(abulation)
REPORT # 1
DAY
DATE 2/26/2018

ACTIVITIES DETAILS
ACTIVITIES PERFORMED TODAY % COMPLETED
Block masanory for abulation 30%
quering in Masque floor
PROJECT DETAILS
PROJECT NAME AFC Dismentaling
PROJECT LOCATION AFC
PROJECT #
CONTRACTOR'S SUPERVISOR
CONTRACTOR Faiz associates
REPORT # 1
DAY
DATE 2/26/2018

ACTIVITIES DETAILS
ACTIVITIES PERFORMED TODAY % COMPLETED
Dismentaling of walls in progress 50%
PROJECT DETAILS
PROJECT NAME Ride Operator Cabin Construction
PROJECT LOCATION Near new Masjid Point
PROJECT #
CONTRACTOR'S SUPERVISOR
CONTRACTOR
REPORT # 1
DAY
DATE 2/26/2018

ACTIVITIES DETAILS
ACTIVITIES PERFORMED TODAY % COMPLETED
Work halted 70%
PROJECT DETAILS
PROJECT NAME Paver fixing
PROJECT LOCATION PEC Entrance to Marjan gate route
PROJECT #
CONTRACTOR'S SUPERVISOR
CONTRACTOR Hanif Enterprises
REPORT # 1
DAY
DATE 2/26/2018

ACTIVITIES DETAILS
ACTIVITIES PERFORMED TODAY % COMPLETED
Work Halted 35%
PROJECT DETAILS
PROJECT NAME Wave Pool Spiral Slide
PROJECT LOCATION Wave Pool
PROJECT #
CONTRACTOR'S SUPERVISOR
CONTRACTOR Zubair Construction
REPORT # 1
DAY
DATE 2/26/2018

ACTIVITIES DETAILS
ACTIVITIES PERFORMED TODAY % COMPLETED
Work Halted 35%
Prepared By
Muhammad Hashim
Trainee Electrical Engineer