A Erection of Stanchions
Erection of UB686 x 254 columns as C2 with 300 x 700 x 24 base plate with
A-2 Ton 18.56 2,100.00 38,976.00
M24 Grade 4.6 anchor bolts.
Erection of UB686 x 254 columns as C3 with 300 x 700 x 24 base plate with
A-3 Ton 25.31 2,100.00 53,151.00
M24 Grade 4.6 anchor bolts.
Erection of UC254 x254 column as C4 with 300 x 300 x24 base with M24
A-4 Ton 5.62 2,100.00 11,802.00
Grade 4.6 anchor bolts.
Erection of UC254 x254 column as C5 with 300 x 300 x24 base with M24
A-5 Ton 5.62 2,100.00 11,802.00
Grade 4.6 anchor bolts.
200 x 450 x 16 base with M24 Grade 4.6 haunch in the middle span and
A-6 Ton 83.92 2,100.00 176,232.00
half haunch at the exterior end.
Erection of UB406 x 178 column as C6 with 200 x 450 x 16 base with M24
A-7 Ton 5.18 2,100.00 10,878.00
Grade 4.6 anchor bolts.
B-2 Installation of angle brace L100 x 100 x 8mm No. 120.00 55.00 6,600.00
C Cladding Works.
D Roofing Works
Installation of 1000 x 2400 skylight in all the roof bays as indicated on the
D-2 No. 82.00 200.00 16,400.00
drawing.
F Grouting
F-1 Supply and install 25mm thk. Non Shrink Grout as indicated on drawing. m3 5.67 5,000.00 28,350.00
SUBTOTAL 1,253,297.00
TOTAL 1,315,961.85