Bill of Qunatities for Factory Building; Superstructure Presented by 1305 Engineering and Construction Ltd.

1305 Engineering & Construction Ltd. Quotation


Pl ot No. 14 I. Adu Street, Takaordi Quotation No: C1305-06-01
Tel: +233 244 724 813, +233 274 923 430 +233 242 313 128 Date 28-Jun-18
Email : ventures1305@gmail .com, info@1305engineers.com, Task Manager 233.242.313128

Quotation for Erection of Structural Steel_Factory Building

Item Description Unit Total Quantity UR (GHS) Amount (GHS)

A Erection of Stanchions

Erection of UB 610 x 229 as columns, C1 with 250 x 610 x 24 base plate


A-1 Ton 50.90 2,100.00 106,890.00
with M24 anchor bolts

Erection of UB686 x 254 columns as C2 with 300 x 700 x 24 base plate with
A-2 Ton 18.56 2,100.00 38,976.00
M24 Grade 4.6 anchor bolts.

Erection of UB686 x 254 columns as C3 with 300 x 700 x 24 base plate with
A-3 Ton 25.31 2,100.00 53,151.00
M24 Grade 4.6 anchor bolts.

Erection of UC254 x254 column as C4 with 300 x 300 x24 base with M24
A-4 Ton 5.62 2,100.00 11,802.00
Grade 4.6 anchor bolts.

Erection of UC254 x254 column as C5 with 300 x 300 x24 base with M24
A-5 Ton 5.62 2,100.00 11,802.00
Grade 4.6 anchor bolts.

200 x 450 x 16 base with M24 Grade 4.6 haunch in the middle span and
A-6 Ton 83.92 2,100.00 176,232.00
half haunch at the exterior end.

Erection of UB406 x 178 column as C6 with 200 x 450 x 16 base with M24
A-7 Ton 5.18 2,100.00 10,878.00
Grade 4.6 anchor bolts.

B Crane Beam and Accessories

Erection of UB533 x 210 beam as crane beam supported on crane bracket


B-1 Ton 39.36 2,100.00 82,656.00
UB457 x 191 with 1/2 haunch

B-2 Installation of angle brace L100 x 100 x 8mm No. 120.00 55.00 6,600.00

B-3 Installation of crane rails m 480.00 16.50 7,920.00

C Cladding Works.

Install cladding sheets as specified on the drawing.This includes the


C-1 m2 3,378.00 45.00 152,010.00
installation of channels, 12mm sagrods and cladding panel materials.

D Roofing Works

Install cladding sheets as specified on the drawing.This includes the


D-1 m2 6,454.00 45.00 290,430.00
installation of all purlins, bracings and accessories.

Installation of 1000 x 2400 skylight in all the roof bays as indicated on the
D-2 No. 82.00 200.00 16,400.00
drawing.

E Store Mezzanine floor decking.


Supply and install 2" (50 mm) depth, 18 gauges (1.2 mm) or equivalent
E-1 m2 864.00 300.00 259,200.00
thickness steel deck

F Grouting

F-1 Supply and install 25mm thk. Non Shrink Grout as indicated on drawing. m3 5.67 5,000.00 28,350.00

Ferrofab Factory, Aboadze Factory Erection bill.xlsx Page 1


Bill of Qunatities for Factory Building; Superstructure Presented by 1305 Engineering and Construction Ltd.

SUBTOTAL 1,253,297.00

Preliminaries and General Conditions of Contract (5%) 5.00% 62,664.85

VAT/NHIL (17.5%) 17.50%

TOTAL 1,315,961.85