Document code : UP055A US
Document group : User Documentation
Document title : Project Control System
Edition :A
Date : May 1998
Legend
Mandatory Indicates a mandatory session
session
Indicates a package
CF
Indicates a module
PCS
n Product variants
A product variant can be produced in two ways:
− By using a job-shop type of production. The planning and production is
fully controlled by PCS. The order system of the generic item must be
planned.
− By using a line assembly production. The planning is controlled by the
Configurator package. The order system must be final assembly
schedule (FAS).
Project Data
Project Engineering
Project Calculation
Project Planning
Project History
CPR PCS TS
HRA CF
SFC TP
CP
n Project History
With the Project History business object you can display or print the
historical data of projects and production orders. The data related to
purchase orders, sales orders, and inventory transactions is stored in the
Distribution package and Warehousing package. Figure 1 shows how the
module is positioned in BaanERP.
n Link to Finance
With the Link to Finance business object you can view, delete, and print the
work in process (WIP) transactions that are posted to the Finance package
from PCS.
2
Calculation office
(tcmcs0565m000)
1 Generate Project
Structure for Sales 3
Orders (tdsls4244m000) Calculation office
(tcmcs0565m000)
Copy Projects
(tipcs2210m000)
4
Element Budget Projects
Material Lines (tipcs2501m000)
(tpptc1510m000)
Activity Budget 5
(Material Lines) Maintain Project
(tpptc2510m000) Structure (tipcs2530m000)
6
Project Parts
Project Engineering
(tipcs2511m000)
7
Network Planning
9
Project Status
Module Planning
(tipcs2502m000)
Project Calculation
8
Close Project
(tipcs2250m000)
10
Archive Project
(tipcs2260m000)
The Engineering Allowed field in the session is important. When this check box
is cleared, project engineering is not allowed. As a result, the check box value
changes when the project is maintained. Thus, project calculation and project
planning use the standard costing structures.
The Project Type field in the session is important. The field indicates the
project’s functionality and the method of operation. A project can be of the
following types:
Main project
A main project is a set of related subprojects. The network planning of
subprojects is controlled by the main project. This means that the main project
controls the start or end dates in subprojects. The total costs of the subprojects
are aggregated to the main project.
For a main project you can:
n Maintain project activities
n Define a network planning
n Enter a price calculation code
n Enter operation rates
n Enter subcontracting rates
n Enter surcharges
n Assign a service order
For a main project you cannot:
n Define a module planning for a project
n Engineer the project
n Link items to the main project
Subproject
A subproject is part of a main project, and makes it is possible to manufacture
customized products. The network planning of the main project determines the
planning method and the start and delivery dates of the subproject.
Single project
A single project is never part of a main project. The purpose of this project type
is to produce customized items. The logistical actions for these projects are
determined by the Project Planning business object, although it can use the
Network Planning business object.
Step 5 Maintain Project Structure (tipcs2115m000)
This session is only relevant if the project type is a main project or a subproject.
The project structure defines the relation between a main project and its
subprojects. If only one level of subprojects is allowed, they are all defined on
one level. The start date for a subproject is determined by the start date of the
main project's activity. In other words, the main project’s activity is entered as
the start activity of the subproject.
If an existing project is the same as, or very similar to, the new required project,
the Copy Project session can be used to copy a project to another project. The
target project can be a new project or an existing project. If it is an existing
project, new data will be added without existing data being overwritten. The
data in the Project Engineering and Project Costing business objects will also be
copied. The data that is to be copied to a project can be maintained.
This session is used to remove a selected row of projects and the associated
project data. Only projects with the status Free can be removed.
This session is not mandatory. In this session you can maintain additional
project details, such as the planning method.
This is in contrast to projects, which are related to actual orders. The purpose of
a budget is to estimate project costs and revenues, without requirements being
generated.
Budgets can be copied to a single project or a subproject, or the other way
around. This includes the copying of:
n Bills of material
n Routings
n Costing structures
Quotation Results
6 Project Calculation 12 (tdsls1101s100)
Copy Project
13
(tdsls2210m000)
If the business partner accepts the quotation, you can manually update the sales
quotation with the following information:
n Delivery date
n Confirmed status
n Reason for success
n Competitor code
Step 12 Copy Project (tipcs2210m000)
If a customer agrees with a budget, you can copy the budget to a project using
the Copy Project (tipcs2210m000) session. Budgets that customers do not
approve can be deleted using the Delete Project (tipcs2270m000) session.
When the budget is copied to the project all data assigned to the budget is
copied to the project. All check boxes in the Copy project (tipcs2210m000)
session are selected by default. You must select the Item Data check box.
The creation of a budget procedure ends when the budget is copied to a project.
If you need information about further steps in the procedure, for example how
to maintain project data, see the How to create a project procedure).
You can maintain sales orders that were created from a quotation using the
Sales Orders (tdsls4500m000) session. Afterwards, the other sessions of the
sales-order procedure are carried out.
During the process, a sales-quotation line is generated for each budget part. The
sales price is calculated by adding budget costs and the desired profit margin.
You can generate a product variant structure for an exisiting budget by using a
defined budget calculation code.
A product variant is generated for every generic item on a sales-order line.
A customized item is generated for every to order standard item.
You can also generate a budget with a budget calculation code defined to it.
Projects
4
(tipcs2501m000)
5 Project Parts
(tipcs2511m000)
Routing Operations
7 (tirou1501m000)
Bill of Material
8 (tibom1510m000)
This chapter outlines how the cost price of a project and a budget are calculated.
The procedure outlines how to:
n Define project rates
n Define project surcharges
n Calculate estimated costs
n Calculate actual costs
Project Engineering
(Procedure)
Project Surcharges
1 (tipcs3520m000)
Maintain Activities
3 (tipcs4501m000)
Generate Network
5 Planning (tipcs4210m000)
Generate Network
6 Messages (tipcs4211m000)
Generate Module
8 Planning (tipcs4520m000)
The Link with Finance business object allows you to view, print, and delete the
WIP transactions that are posted to BaanERP Finance from PCS. A WIP
transaction is generated when:
n Materials are issued for a production order
n Hours are booked on a production order
n Finished products are delivered into inventory
n WIP transfers are carried out between work centers
n Surcharges are applied
n And so on
BaanERP Project automatically generates the transactions, and posts them to the
BaanERP General Ledger (GLD) module within BaanERP Finance. The
transactions are posted to specific ledger accounts and dimensions, based on a
mapping scheme for BaanERP Manufacturing, which is defined in the GLD
module in BaanERP Finance. Mapping schemes are based on:
n The transaction’s logistic transaction origin (TROR), for example, Project
(PCS)
n The classification of the financial transaction (FITR), for example, Project
Surcharge
BaanERP uses the combination of transaction origin and financial transaction to
select the ledger accounts to which the financial transactions are posted.
Figure 8 shows the sessions that you can use to display the link with BaanERP
Finance.
WIP Transactions by
Transaction Origin and
Financial Transaction
1 (tcfin1500m000)
WIP Transactions by
WIP Transactions by WIP Transactions by
Financial Period
2 Project (tcfin1500m001) 3 Order (tcfin1500m002) 4
(tcfin1500m003)
WIP Transactions
5 (tcfin1100s000)