Você está na página 1de 5

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/282866406

Productivity enhanced by straight blows during BOF steelmaking

Article  in  Steel Times International · August 2015

CITATIONS

2 authors:

Nand Kishore Jha Somnath Kumar


The Indian Institute Of Metals Steel Authority of India Ltd (SAIL)
2 PUBLICATIONS   0 CITATIONS    16 PUBLICATIONS   4 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Steel Making BOF productivity View project

Development of 55Si7 Spring steel View project

All content following this page was uploaded by Somnath Kumar on 16 October 2015.

The user has requested enhancement of the downloaded file.


OXYGEN STEELMAKING 27

Productivity enhanced by straight


blows during BOF steelmaking
While conventional BOF blowing practice requires waiting for sample results prior to tapping to see if a
re-blow is necessary, a modified single (straight) blowing practice has been implemented in Steelshop
II at SAIL Bokaro in which the quantities of oxygen and flux needed are pre-determined using a static
model which has resulted in a 25% increase in productivity by eliminating four stages of activities in the
steelmaking cycle. By N K Jha* and Somnath Kumar**

THE majority of integrated steel plants


across the globe follow the blast furnace
– oxygen converter (BF-BOF) route of
steelmaking. Blast furnace productivity
is largely dictated by the quality of raw
materials charged coupled with process
control. Steel companies continually Blast furnace Mixer Scrap charging Hot metal Oxygen blowing
endeavour to achieve higher levels of charging

BF throughput. Contrary to this BOF


productivity depends largely on the design
of the steel shop (including logistics) and
steel grades produced rather than input
quality.
Ladle furnace Tapping
Consequently, over a period of time
there has been substantial improvement
in BF productivity, but BOF productivity
has increased only marginally creating
a mismatch in capacities between the
Fig 1: Process route of
BF and BOF. Steelmakers everywhere are Slabs
steelmaking at SMS-II, BSL,
thus confronted with the problem of
Bokaro
finding other means of improving BOF Continuous casting
productivity.
Employing ‘Straight Blowing’ –

*Ex-CEO, IISCO Steel Plant, Burnpur, Steel Authority of India Ltd. **R & D Centre for Iron & Steel, SAIL, Ranchi, India
e-mail nkjha0509@gmail.com (corresponding Author)

www.steeltimesint.com July/August 2015

OXYGEN STEELMAKING BOF.indd 1 7/13/15 11:08 AM


28 OXYGEN STEELMAKING

– main blow – sampling – corrective blow


Event Minutes Comments
(if required) – tapping – de-slagging
Charging scrap and hot metal 5-10 Scrap at ambient temperature, hot metal at ~1300°C followed by the start of a new charge to
Refining–blowing oxygen 14-23 Oxygen reacts with elements, Si, C, Fe, Mn, P in scrap and hot metal and flux repeat the process.
additions to form a slag Table 1 summarises the main events
Sampling–chemical testing 4-15 Steel at 1650°C, chemistry and temperature analysis during BOF steelmaking and the
Tapping 4-8 Steel is poured from furnace into a ladle time taken by each. These times vary
Pouring slag off from BOF 3-9 Most slag is removed from furnace, in some shops slag is used to coat considerably depending on the chemistry
furnace walls
and temperature of the input materials,
the vessel configuration and the chemistry
Table 1: BOF steelmaking event times1
and temperature of the steel to be made.
Major sub- processes of steelmaking are
Sequence No Process involved
depicted in Table 2 for conventional BOF
1 Receipt of hot metal from BF
practice.
2 Hot metal desulphurization at external desulphurization station
The time taken in completing this
3 Transfer of hot metal into hot metal charging ladle sequence is known as the cycle time. The
4 Transportation of hot metal ladle to charging station key to improving productivity is to reduce
5 Scrap and hot metal charging the cycle time. Factors affecting cycle time
6 Setting of blowing and flux addition parameters in terms of quantity, rate and timing based on hot metal are:
analysis and product chemistry e Size of converter vessel;

e Shop logistics;
7 Primary blowing (till major decarburization is achieved)
8 Termination of primary blowing, slagging off, sampling and temperature measurement
e Product chemistry requirement;
9 Analysis of sample
e Hot metal chemistry and temperature;
10 Setting finishing blow parameters based on results of sample analysis
e Steelmaking method followed.
11 Finishing blow
12 Sampling, temperature measurement
13 Tapping of liquid steel into steel ladle, Ferro alloy addition, bottom stirring (as required) Any effort to increase productivity by
14 Slag splashing, dumping residual slag reducing cycle time involves changes in
15 Start of next cycle one or all of these factors. In conventional
turndown practice the furnaces are
Table 2: Sub-processes of BOF steelmaking blown to the ‘endpoint’ to measure the
temperature and dissolved oxygen content
eliminating the intermittent checking of purity oxygen to oxidise carbon, silicon, (in ppm) of the steel bath and to obtain
endpoint parameters – of the BOF is one sulphur, and phosphorus in the charge steel and slag samples prior to tapping.
solution. lowering each to acceptable levels. A BOF In this case the blow finish to tapping
This article explores the method and shop capable of treating a heat size of 270- start time ranges from 10-14 minutes.
pros and cons of straight blowing. 280t in about 45-50 minutes is considered In some cases the tap is delayed until the
optimal. Bath agitation is implemented at turndown steel analysis is received from
Steelmaking at BSL the start of blowing or after the main de- the laboratory to ensure a satisfactory
The Steel Melting Shop-II of Bokaro carburisation cycle, via bottom blowing level of impurities content.
Steel Ltd (BSL) – a member of India’s of argon and/or nitrogen. Slag formation,
SAIL group – produces a variety of steel CO bubbles, and close to equilibrium state Minor corrections
grades through the BOF-Ladle Furnace conditions, are better achieved by this The BOF converter has superior de-
– Continuous Casting route to meet bottom gas injection. phosphorylation ability. If the incoming
the stringent quality requirements of The basic operational steps of the phosphorus in the hot metal is low and
customers. SMS-II produces around 3Mt process are shown schematically in Fig 2. consistent, tapping is permitted as soon as
of low carbon aluminium killed cast slabs This involves receiving hot metal from the turndown tests samples are taken, without
every year. mixer – scrap charging – hot metal pouring waiting for sample analysis2, 4. Any minor
Varieties of steel grades regularly
produced include LPG, EDD, WTCR,
SAILMA, HSFQ and IS2062. SMS-II
consists of two 2500t mixers, two 300t
BOFs with bottom purging facility, two
300t ladle furnaces and two twin strand
slab casters. The charge to the combined
blowing BOF converters normally consists
of around 260-270t of BF hot metal from Main blow
Hot metal from mixer Scrap charging Hot metal pouring
the mixers and 35-40t of scrap depending
on the silicon level of the BF hot metal.
Other fluxes used are lime (~12t), calcined
dolomite (~7-8t), and dolomite chips (5-
6t). The blowing time ranges from 16-
17 minutes and tapping under normal
conditions takes eight to nine minutes.
The average tapping temperature ranges
Sampling
between 1660-1680°C. The process flow Corrective blow
(if required)
Tapping De-slagging

of steel making at SMS-II, BSL is shown


in Fig 1. Fig 2: Steps involved in conventional BOF operation
Basic oxygen steelmaking uses high

July/August 2015 www.steeltimesint.com

OXYGEN STEELMAKING BOF.indd 2 7/13/15 11:08 AM


OXYGEN STEELMAKING 29

Bomb-secure loop 2-wire plug


Bomb head

Blowing Sampling and Tapping Slag off


Rubber-covered electrical cord temperature
Bomb drop loop

Fig 3: Bomb drop-in sensor Fig 4: Steelmaking by straight blows

corrections to chemistry can be made in Pros and cons of straight blows


Event Minutes
the ladle furnace. Besides direct impact on productivity,
let us now consider other pros and cons
Charging scrap and hot metal 10-12
Current global status Refining–blowing oxygen 15-16
of this process which essentially involve
Japan and some European shops achieve Sampling–chemical testing 4-5 change in blowing methodology.
sampling and testing times of one to three Tapping 7-8
minutes by using a quick tap procedure. Slag Splashing 4-6 Pros- the advantages
Most of these shops use sub-lances to Pouring slag off at furnace 3-4 e Since intermittent slogging off is
measure temperature and carbon by the eliminated, metal out flow along with slag
liquidus thermal arrest technique. This is Table 3: BOF steelmaking activities after implementation of is saved leading to marginal improvement
carried out without moving the furnace straight blow practice at SMS-II in yield.
from the upright position. The success e In the conventional process finishing

of quick-tap depends on consistently and composition. Static models are mass blow (post slagging off) is occasionally
meeting the sulphur and phosphorus and energy balances that account for the dry. This doesn’t happen in straight blows.
specification. This procedure can save initial conditions (scrap and hot metal The result is higher lance life.
three to six minutes of laboratory analysis temperatures and compositions) and the e In theory, a lower FeO content in the

time. desired end-point conditions of the bath slag is expected leading to better yield and
These shops simply proceed immediately and slag, and indicate to the operator higher vessel life (FeO mobility towards
to tapping the furnace. the expected total oxygen and fluxes that vessel walls causes refractory erosion).
Some North American shops have are required to reach that end-point. The e In the case of the conventional
adopted a simplified version of the quick- blow is stopped once the pre-determined process, open combustion takes place
tap practice. A few have sub-lances. amount of oxygen has been reached. twice in every cycle as against only once
Others use bomb drop-in thermocouples In addition to the charge model, the when using straight blows. The following
(Fig 3) with or without oxygen sensors. operator relies on other signals, such as advantages result:
Here a heavy cast iron bomb assembly the change in the colour of the flame at a. Higher hood and skirt life;
with a specially wound and protected the mouth of the vessel and a characteristic b. Reduced load on gas recovery system
wire coil is dropped into the furnace. drop in the steam flow in the fume system due to elimination of one phase of open
The wire lasts long enough to take a cooling circuit, to identify when the combustion system;
reading. The readings are more accurate carbon has been depleted3. c. Converter gas (fuel) recovery
if oxygen blowing is stopped, but some In practice, static charge models have a marginally improves;
shops achieve a usable reading even limited ability to predict end-point because d. Duration of refractory-liquid steel
during the blow. Again, tramp elements, they do not account for process dynamics. contact is reduced.
S, P and other residuals are assumed to End-point accuracy is also affected by
be acceptable and tapping proceeds uncertainties in the initial conditions (eg Cons – the down side
immediately. Some shops equipped with mass, temperature and composition of e Due to higher opening temperature,

only two BOF vessels use this technique to the hot-metal, mass and type of scrap the chemistry sometimes goes off
minimise production losses when one of and fluxes added) and by variations in the specification leading to pressure on
the furnaces is being relined or repaired. efficiency of the oxygen lance, not only secondary refining of the steel. Particular
within a heat as the height and flow of the difficulty is faced in dephosphorisation as
Development of Straight Blowing lance is varied, but also from heat to heat the chances of phosphorus reversal are
Practice as the lance wears and the geometry of higher at higher temperatures.
Priority was given at BSL to reduce the the vessel changes with refractory wear3. e Difficulty in maintaining higher
cycle time of BOF steelmaking so as to In the modified process of steelmaking temperature gradient throughout the
increase the productivity of the shop. After at SMS-II, the entire amount of oxygen blowing period.
thorough investigation and deliberation it required is blown in one go at a e Marginally higher consumption of
was concluded that minimising the time predetermined rate thereby combining fluxes.
between the finish of blowing to start the former primary and finishing blows. e Straight blown heats usually carry
tapping is an attractive way to reduce the Activities 8-11 in Table 2 are thus higher oxygen content. Hence, more
BOF cycle time since changing the charge eliminated without altering any other deoxidisers are often required.
size of the converter or changing shop activity. Studies have shown that the e An important negative aspect of
logistics would require a large investment cycle time is reduced by 15% to 20% by straight blows is that steel is at a higher
in capital and time to implement. this process4. The productivity of the steel temperature and the slag stays in contact
To achieve a shorter time between melting shop increases proportionately4. with the vessel refractory for a longer
finishing the blow to start of tapping a This process will henceforth be called period. This reduces vessel refractory life,
new process of steelmaking has been ‘steel making by straight blows’ in this but a counter factor is a lower FeO in the
formulated. A static model was used to article. Fig 4 indicates such steelmaking slag which makes it less aggressive where
calculate the desired endpoint temperature by straight blows. refractory erosion is concerned.
www.steeltimesint.com July/August 2015

OXYGEN STEELMAKING BOF.indd 3 7/13/15 11:08 AM


30 OXYGEN STEELMAKING

No of heats per day 92.93 92.9


93
92.12
30 28.26
92
27.1
90.81
26.3 91
27
25
90
No of heats per day

23.4
24 89 88.6 88.64 88.34

Straight blow %
21.3
88 87.3
21
87

18 86

85

15 84
02-03 03-04 04-05 05-06 06-07 07-08 05-06 06-07 07-08 08-09 09-10 10-11 11-12 12-13

Years Years

Trial Results Fig 5: Improvement in num- Fig 6: Percentage of straight blown heats over a period of time
The straight blow practice was fully ber of heats per day after
implemented at BSL, Bokaro. In the implementation of straight
% Reblow heats % FeO in turndown slag
previous practice, the operator had to blow practice
28 23
decide, before the start of the blow, how
22
the oxygen blow would progress; what 23

% FeO in BOF turndown slag


and when fluxes would be added during 21
the blow to arrive at the desired endpoint 18 20
% Reblow

in terms of temperature and composition. 19


In this practice, at the end of the 13 18
primary blow, the oxygen lance was
withdrawn; and the vessel tilted to take 17
8
samples to check the actual progress of Fig 7: Reduction in reblows 16
the blow with respect to temperature and required and unchanged
3 15
composition. Corrections in temperature FeO level in BOF slag after
02-03 03-04 04-05 05-06 06-07 07-08
and composition were carried out by re- implementation of straight
blowing the bath. blow practice Years

Waiting for sample analysis was more


time consuming since chemical analysis of heats made in SMS-II are now by straight Acknowledgment
the samples by spectroscopy in a separate blowing (Fig 6). The authors are grateful to the
laboratory meant a loss of several minutes Re-blows also decreased to a level of management of the Bokaro Steel Plant
(12-13 minutes). Higher re-blows to less than 5% on average compared to for extending its support to pursue the
adjust temperature/composition thus more than 20% before when straight work. Thanks also to the personnel of
caused loss of production and had other blow practice was not in use. After Steel Melting Shop-II and R&C Lab for
adverse effects such as lower lining life. implementation of the straight blow their extensive support and to BSL during
On implementing the straight practice to the desired endpoint, there execution of the present investigations.
blow practice the entire amount of was no significant over oxidation of the The authors are obliged to Shri Pankaj
predetermined oxygen required was bath and the FeO in the turndown slag did Kumar for support provided and express
blown in one go. not increase appreciably (Fig 7). their gratitude to all who, directly or
Activities of slagging off, sampling indirectly, supported this technical work.
and temperature measurement after the Conclusion t
primary blow were eliminated. Static For SMS-II, BSL productivity improvement
control by using computers improved the of around 25% was achieved after
hit rate of end point temperature and implementation of the straight blow
carbon significantly. BOF steelmaking practice. Additionally, further benefits
activities after implementation of straight were an improvement in end-point target References
blow practice is summarised in Table 3. hit-rate and a reduction in re-blows. 1 ‘Oxygen Steelmaking Processes’, T W Miller
On the down side, a previous increase et al MSTS, The Making Shaping & Treating of
Increased productivity in refractory lining life, gained due to Steel, AISE Steel Foundation, pp 475-522
After implementation of straight blowing improvement in refractory management, 2 ‘Quick direct tap at United States Steel
practice, shop productivity has increased was partially offset by adopting straight Corporation’s Gary Works Q-BOP Shop’ Yun Li
by around 25%. The number of heats per blows. Also, there was an increase in ferro et al Iron & Steel Technology, Nov 2010, page
day increased to an average of 26.5 heats alloy consumption whenever the bath 37-45
(2003-4 to 2012-13) from 21.3 heats in became oxidised. 3 ‘BOF end point prediction’ Joseph Maiolo and
2002-03. In view of the above, it is advisable Doug Zuliani, Metal Producing & Processing,
A maximum of 29.2 heats per day was to make a trade-off considering shop Nov/Dec-2008, page 15-18
achieved in 2012-2013 as shown in Fig 5. logistics, and the extent of productivity 4 ‘Increasing BOF productivity and profitability
The increase in the number of heats was increase required to match the upstream by quick-tapping with drop-in sensor’ Stem, R
made possible by a significant decrease and downstream units of an integrated A , Steelmaking Conference proceedings, Vol
in the time from blow finish to start of steel plant. These aspects vary from plant 78, Publ: Iron and Steel Society/AIME, 1995,
tapping. On an average more than 90% of to plant. page 143-146

July/August 2015 www.steeltimesint.com

OXYGEN STEELMAKING BOF.indd 4 7/13/15 11:08 AM


View publication stats

Você também pode gostar