Escolar Documentos
Profissional Documentos
Cultura Documentos
- include “those between or among parties to, or who are a. To formulate and adopt an arbitration program for the
otherwise bound by, an arbitration agreement, directly or by construction industry;
reference, whether such parties are project owner, b. To enunciate policies and prescribe rules and procedures for
contractor, subcontractor, fabricator, project manager, construction arbitration;
design professional, consultant, quantity surveyor, c. To supervise the arbitration program, and exercise such
bondsman or issuer of an insurance policy in a construction authority related thereto as regards the appointment,
project.” (CIAC REVISED RULES) replacement or challenging of arbitrators; and
d. To direct its officers and employees to perform such functions
CONSTRUCTION ARBITRATION UNDER THE ADR as may be assigned to them from time to time.
ACT OF 2004
NATURE AND CHARACTER OF THE CIAC
ADR Act of 2004 not only affirmed the original and exclusive
jurisdiction of the CIAC over construction disputes, but also - It is a quasi-judicial agency or body defined as an organ of
strengthened it which include “those between or among parties government other than a court and other than a legislature,
to, or who are otherwise bound by, an arbitration agreement, which affects the rights of private parties through either
directly or by reference, whether such parties are project owner, adjudication or rule-making.
contractor, subcontractor, fabricator, project manager, design
professional, consultant, quantity surveyor, bondsman or issuer - To adjudicate claims and/or determine rights in accordance with
of an insurance policy in a construction project”, and even if the procedures set forth in E.O. No. 1008 is the CIAC’s primary
arbitration is commercial in character. function.
Request for the dismissal of action and the referral to the CIAC • First Rules of Procedure Governing Construction was
for arbitration shall be made through a VERIFIED MOTION which promulgated in August 1988.
shall contain:
a. Statement showing that the dispute is a construction • Latest Revised Rules of Procedure Governing Construction
dispute; Arbitration was approved on November 19, 2005 and took effect
b. Accompanied by proof of the existence of the on December 15, 2005, fifteen (15) days after its publication.
arbitration agreement unless it is already part of the
records of the case; JURISDICTION OF THE CIAC
c. Contain a notice of hearing.
• The jurisdiction of the CIAC is conferred by E.O. No. 1008
Note: An order dismissing the case and referring the dispute to
arbitration by the CIAC is immediately executory. - it has exclusive and original jurisdiction over disputes
arising from, or connected with, contracts, entered into by
THE CONSTRUCTION INDUSTR Y ARBITRATION parties involved in construction in the Philippines, whether
COMMISSION (CIAC) the dispute arises before or after completion of the contract,
or after the abandonment or breach thereof;
CONSTRUCTION INDUSTR Y ARBITRATION LAW
(EXECUTIVE ORDER NO. 1008) - may involve government or private contracts
5. Challenge to arbitrators Note: Generally, in the absence of any showing of grave abuse
The challenge shall be based on the following grounds: of discretion, courts must sustain the factual findings of the CIAC
arbitrator in accordance with established principle that the
a. Relationship by blood or marriage within the sixth determination of certain questions of fact falling within the
degree of either party to the controversy, or the technical expertise of an administrative agency, must be
counsels within the fourth degree, computed accorded great respect, if not finality by the courts.
according to rules of civil law;
b. Financial, fiduciary or other interest in the COSTS OF ARBITRATION
controversy;
c. Partiality or bias; Sec. 5 Art. XV of the Rules of Procedure Governing Construction
d. Incompetence, or professional misconduct; and Arbitration