KALKULASAUN VOLUME
I. SERVISU BA FUNDASAUN NIAN
1. Servisu Dahuluk
a. Limpeza Terrenu
Medida Unidade
Komprimentu 18 m
Largura 16 m
Area KxL
288 m²
Volume 288 m²
b. Monta Estaka
Komprimentu 15 m
Largura 13 m
Perimetru 2x(P+L)
2 x ( 15+13)
56 m
Volume 56 m
Panjang Tiang 1 m
Jarak Ting ke tiang 1;5 m
Banyak Tiang 56/1,5
37.3333333 Bh
38 Bh
Medida Unidade
Komprimentu 6 m
Largura 5 m
Area 30 m²
Volume 30 m²
EIXO HORIZONTAL
No. Eixo Naruk Unidade
1.1 F-A 10 m
1.2 G-B 6 m
1.3 H-A 10 m
1.4 I-A 10 m
1.5 J-B 6 m
K-A 10 m
ƩH 52 m
Medisa Unidade
Komprimentu 94 m
Largura 0.77 m
Espessura 0.1 m
Area 0.077 m²
Volume 7.238 m³
Medisa Unidade
Komprimentu 94 m
Largura 0.77 m
Espessura 0.1 m
Area 0.077 m²
Volume 7.238 m³
c. Hada fundasaun
Medisa Unidade
Komprimentu 94 m
Largura leten 0.45 m
Largurakraik 0.67 m
Altura 1 m
Area 0.56 m²
Volume 52.64 m³
Medida Unidade
Komprimentu 94 m
EIXO VERTIKAL
No. Eixo Naruk Unidade
1.1 A-K 12 m
1.2 B-K 12 m
1.3 C-I 4 m
1.4 D-H 2 m
1.5 E-K 12 m
ƩV 42 m
EIXO HORIZONTAL
No. Eixo Naruk Unidade
1.1 F-A 10 m
1.2 G-B 6 m
1.3 H-A 10 m
1.4 I-A 10 m
1.5 J-B 6 m
K-A 10 m
ƩH 52 m
Medida Unidade
Komprimentu 94 m
Largura 0.2 m
Altura 0.25 m
Area 0.05 m²
volume 4.7 m³
# Seksaun sloof
b. Koluna
Medida Unidade
Komprimentu 2.4 m
Largura 0.25 m
Altura 0.25 m
Area 0.0625 m²
Total koluna 20 bh
Volume 3 m³
# Seksaun koluna
c. Sinta jeral
Medida Unidade
Komprimentu 94 m
Largura 0.2 m
Altura 0.25 m
Area 0.05 m²
Volume 4.7 m³
Medida Unidade
Komprimentu 6.5 m
Largura 0.25 m
Espessura 0.08 m
Area 0.02 m²
Volume 0.13 m³
2. Betaun la Armadu
a. Laje (1:2:3 )
2.Neut Arus
Medida Unidade
Largura 0.12 m
Espesura 0.06 m
Altura 0.05 m
Kuantidade 12 bh
Area 0.0072 m²
Volume 0.00432 m³
Desenho Neut Arus
3. Paredi
a. Deskrisaun Paredi Eixo Horizontal
a. Eixo Vertikal
No. Eixo Area total Area Arus nian Area Netto
1.1 A-K 24.1875 1.8 22.392
1.2 B-K 24.1875 4.57 19.6195
1.3 C-I 8.0625 1.68 6.3815
1.4 E-K 19.35 2.76 16.59
Ʃ 75.7875 11 64.983
Medida Unidade
Area Eixo Horizontal 59.0355 m²
Area Eixo Vertikal 64.983 m²
Espessura Batako nian 0.14 m
Volume 17.36259 m³
Medida Unidade
Komprimentu 10.25 m
Altura 1.31 m
Area 6.71375 m²
Volume 0.939925 m³
4. Arus
a. Arus Odamatan no janela
TIPE ARUS
A1 A2
Volume
A1 A2
0.115488 0.114192
A3 A4 Volume
A3 A4
0.120096 0.229824
Kuda-Kuda
Naran Komprimentu Medida Kuantidade Volume Unidade
Balok Tarik 10.25 6/12 2 0.1476 m³
makelar 4.19 6/12 2 0.060336 m³
Asna 11.86 6/12 2 0.170784 m³
Scora 5.14 6/12 2 0.074016 m³
Balok Dinding 11.86 6/12 2 0.170784 m³
Gording 13.65 5/7 16 0.7644 m³
Ʃ 1.38792 m³
su % Ai Lakon nian 0.138792 m³
c. Servisu Lisplank
b. Monta Perabung
Monta kalen Junta Nian
Medida Volume Unidade
Komprimentu 13.85 2.77 m²
Largura 0.2
Solusaun A
Medida Kuantidade Volume Unidade
Komprimentu (X) 5.8 5/7 4 0.0812 m³
Komprimentu (Y) 1.8 5/7 11 0.0693 m³
Ʃ 0.1505 m³
Solusaun B
Medida Kuantidade Volume Unidade
Komprimentu (X) 3.8 5/7 8 0.0532 m³
Komprimentu (Y) 3.8 5/7 8 0.1064 m³
Ʃ 0.1596 m³
Solusaun C
Medida Kuantidade Volume Unidade
Komprimentu (X) 5.8 5/7 4 0.0812 m³
Komprimentu (Y) 1.8 5/7 11 0.0693 m³
Ʃ 0.1505 m³
Solusaun D
Medida Kuantidade Volume Unidade
Solusaun E
Medida Kuantidade Volume Unidade
Komprimentu (X) 4.2 5/7 6 0.0588 m³
Komprimentu (Y) 1.8 5/7 4 0.0252 m³
Ʃ 0.084 m³
Solusaun F
Medida Kuantidade Volume Unidade
Komprimentu (X) 3.8 5/7 8 0.0532 m³
Komprimentu (Y) 3.8 5/7 8 0.1064 m³
Ʃ 0.1596 m³
Solusaun G
Medida Kuantidade Volume Unidade
Komprimentu (X) 3.8 5/7 8 0.0532 m³
Komprimentu (Y) 3.8 5/7 8 0.1064 m³
Ʃ 0.1596 m³
Solusaun H
Medida Kuantidade Volume Unidade
Komprimentu (X) 3.8 5/7 4 0.0532 m³
Komprimentu (Y) 1.8 5/7 8 0.0504 m³
Ʃ 0.1036 m³
Solusaun I
Medida Kuantidade Volume Unidade
Komprimentu (X) 1.8 5/7 4 0.0252 m³
Komprimentu (Y) 1.8 5/7 4 0.0252 m³
Ʃ 0.0504 m³
Solusaun J
Medida Kuantidade Volume Unidade
Komprimentu (X) 5.8 5/7 5 0.0812 m³
Komprimentu (Y) 1.8 5/7 11 0.0693 m³
Ʃ 0.1505 m³
Somatori Volume 1.3279 m³
Solusaun 1
Medida Kuantidade Volume Unidade
Komprimentu (X) 11.45 5/7 4 0.1603 m³
komprimentu (Y) 0.5 5/7 36 0.063 m³
Ʃ 0.2233 m³
Solusaun 2
Medida Kuantidade Volume Unidade
Komprimentu (X) 0.5 5/7 44 0.077 m³
komprimentu (Y) 13.45 5/7 4 0.1883 m³
Ʃ 0.2653 m³
Somatori Volume 0.4886 m³
c. Balok Gantung
Solusaun
Naran Medida Kuantidade Volume Unidade
Balok gantung Komprimentu 0.35 5/7 36 0.0441 m³
Balok komprimentu 4 5/7 10 0.14 m³
Ʃ 0.1841 m³
2. Monta Plafond
a. Monta Plafond laran
4. Nahe Azuleiju
a. Nahe Azuleiju (20x20) & (30x30)
Area Unidade
104.926 m²
Ventilasi
Tipu Kuaantidade Unidade
A1 1 bh
Volume
Lampu TL (V 75) Fiu Stop Kontak Sakelar Tunggal Sakelar Ganda Panel
9 50 7 4 2 1
Servisu Septicktank
Eskavasaun
Medida Unidade
Komprimentu 2.4 m
Largura 1.2 m
Altura 3.15 m
Volume 9.072 m³
Aterru Rai-henek
Medida Unidade
Komprimentu 2.4 m
Largura 1.2 m
Espessura 0.1 m
Volume 0.288 m³
Cor Laje
Medida Unidade
Komprimentu 1.95 m
Largura 1.2 m
Espessura 0.5 m
Volume 1.17 m³
Hada Batako
Medida Unidade
Komprimentu 7.5 m
Altura 3 m
Area 22.5 m²
Medida Unidade
Komprimentu (d 4') 8.65 m
Komprimentu (d 2') 20.33 m
Volume 28.98 m
Material Haris Fatin & Dapur
Kloset dudut Kitchen Zink Floor Drain Unidade
1 1 1 bh
Medida Unidade
Diametru Knau (d ) 3/4' Ins
Komprimentu 34.49 m
Volume 34.49 m
REKAPITULASAUN VOLUME
Pekerja Oh 0.2495
Tukang Kayu Oh 0.2858
Tenaga Kerja
Kepala tukang Oh 0.0200
Mandor Oh 0.0200
2 1 m' Pengukuran dan pemasangan bowplank
Kayu Usuk 5/7 m3 0.0177
Bahan Paku Biasa 2"-5" Kg 0.0200
Kayu Papan 3/20 m3 0.0070
Pekerja Oh 0.1000
Tukan kayu Oh 0.1000
Tenaga Kerja
Kepala Tukang Oh 0.0100
Mandor Oh 0.0050
3 1 m2 Pembuatan Gudang semen dan alat
Dolken kayu Ø 8-10/4m Btg 1.7000
Kayu m3 0.2074
Paku biasa 2" - 5" Kg 0.3000
Bahan Semen Portland Kg 10.5000
Pasir beton m3 0.0300
Koral beton m 3
0.0500
seng Gelombang BJLS 28 Lbr 1.5306
Pekerja Oh 1.0000
Tukang kayu Oh 2.0000
Tenaga Kerja
Kepala Tukang Oh 0.2000
Mandor Oh 0.0500
4 1 m2 Pembuatan rumah jaga / konstruksi kayu
Dolken kayu Ø 8-10/4m Btg 3.0500
Kayu m 3
0.2807
Bahan
Paku biasa 2" - 5" Kg 0.7117
Seng gelombang BJLS 28 Lbr 1.7090
Pekerja Oh 1.0167
Tukang kayu Oh 1.5250
Tenaga Kerja
Tenaga Kerja
Kepala Tukang Oh 0.1527
Mandor Oh 0.0510
5 1 m2 Membersikan Lapangan dan perataan
Pekerja Oh 0.1000
Tenaga Kerja
Mandor Oh 0.0500
II PEKERJAAN TANAH
1 1 m3 Galian tanah biasa sedalam 1 m
Pekerja Oh 0.6700
Tenaga Kerja
Mandor Oh 0.0320
2 1 m3 Galian tanah biasa sedalam 2 m
Pekerja Oh 0.7500
Tenaga Kerja
Mandor Oh 0.0470
3 1 m3 Galian tanah sedalam 3 m
Pekerja Oh 0.8900
Tenaga Kerja
Mandor Oh 0.0685
4 1 m3 Galian tanah keras sedalam 1 meter
Pekerja Oh 0.9500
Tenaga Kerja
Mandor Oh 0.0530
5 1 m3 Galian tanah cadas sedalam 1 meter
Pekerja Oh 1.5000
Tenaga Kerja
Mandor Oh 0.0600
6 1 m3 Galian Tanah Lumpur sedalam 1 meter
Pekerja Oh 0.9163
Tenaga Kerja
Mandor Oh 0.0700
7 1 m2 Pekerjaan Stripping tebing setinggi 1 meter
Pekerja Oh 0.4230
Tenaga Kerja
Mandor Oh 0.0260
8 1 m3 Membuang tanah sejauh 30 meter
Pekerja Oh 0.3300
Tenaga Kerja
Mandor Oh 0.0125
9 Menimbung kembali 1 m3 galian
Pekerja Oh 0.2142
Tenaga Kerja
Mandor Oh 0.0143
10 1 m3 Pemadatan tanah ( Per 20 cm )
Pekerja Oh 0.5000
Tenaga Kerja
Mandor Oh 0.0500
11 1 m3 Timbunan Pasir
Bahan Pasir Urug m3 1.2000
Pekerja Hr 0.3023
Tenaga Kerja
Mandor Hr 0.0127
12 1 m3 Pemasangan Lapisan Ijuk tebal 10 cm
Bahan Ijuk m3 2.7577
Pekerja Oh 0.1500
Tenaga Kerja
Tenaga Kerja
Mandor Oh 0.0150
13 1 m3 Penimbunan Sirtu Padat untuk peninggian lantai bangunan
Bahan Sirtu m3 1.2000
Pekerja Oh 0.3046
Tenaga Kerja
Mandor Oh 0.0379
Pekerja Oh 1.5000
Tukang batu Oh 0.6000
Tenaga Kerja
Kepala Tukang Oh 0.0905
Mandor Oh 0.0973
2 1 m3 Pasang Pondasi Batu belah 1 Pc : 4 Ps
Batu belah 15/20 cm m3 1.2000
Bahan Semen Portland Kg 163.0000
Pasir Pasangan m3 0.5348
Pekerja Oh 1.8313
Tenaga kerja Tukang batu Oh 0.8404
Kepala Tukang Oh 0.0991
Mandor Oh 0.0750
3 1 m3 Pasang Pondasi batu belah 1 Pc : 5 Ps
Batu belah 15/20 cm m3 1.2000
Bahan Semen Portland Kg 136.0000
Pasir Pasangan m3 0.5440
Pekerja Oh 1.7141
Tukang batu Oh 0.7130
Tenaga Kerja
Kepala Tukang Oh 0.1095
Mandor Oh 0.1919
4 1 m3 Pasangan Pondasi batu kosong
Batu belah 15/20 cm m3 1.2000
Bahan
Pasir Urug m 3
0.3033
Pekerja Oh 0.7800
Tukang batu Oh 0.3900
Tenaga kerja
Kepala Tukang Oh 0.0579
Mandor Oh 0.0579
5 1 m3 Pasangan Pondasi Sumuran Ф 1 meter
Batu belah 15/20 cm m3 0.4500
Bahan
Semen Portland Kg 213.4000
Bahan
Pasir beton m3 0.3837
Kerikil/koral m3 0.5670
IV PEKERJAAN BETON
1 Pembesian 10 Kg dengan besi polos / Ulir
Besi beton ( Polos / Ulir ) Kg 10.5000
Bahan
Kawat beton Kg 0.1500
Pekerja Oh 0.0949
Tukang Besi Oh 0.0757
Tenaga Kerja
Kepala Tukang Oh 0.0109
Mandor Oh 0.0223
2 1 m2 Pasang bekisting untuk Pondasi
Kayu kelas III m3 0.0326
Bahan Paku biasa 5" - 10" Kg 0.1586
Minyak Bekisting Ltr 0.0168
Pekerja Oh 0.5200
Tukang Kayu Oh 0.2600
Tenaga Kerja
Kepala Tukang Oh 0.0260
Mandor Oh 0.0260
3 1 m2 Pasangan Bekisting untuk Sloof
Plywood tebal 9mm Lbr 0.3500
Kayu kelas III m 3
0.0450
Bahan
paku biasa 5" - 10" Kg 0.3000
Minyak Bekisting Ltr 0.0256
Pekerja Oh 0.5200
Tukang Kayu Oh 0.2600
Tenaga Kerja
Kepala Tukang Oh 0.0260
Mandor Oh 0.0260
4 1 m2 Pasangan Bekisting Untuk Kolom
Kayu kelas III m3 0.0400
Paku biasa 5" - 12" Kg 0.4000
Minyak Bekisting Ltr 0.0555
Bahan
Balok kayu kelas II m3 0.0150
Plywood tebal 9 mm Lbr 0.3500
Dolken Kayu 8" - 10"/4m Btg 2.0000
Pekerja Oh 0.6600
Tukang Kayu Oh 0.3300
Tenaga Kerja
Tenaga Kerja
Kepala Tukang Oh 0.0330
Mandor Oh 0.0330
5 1 m2 Pasangan Bekisting untuk balok
Kayu kelas III m3 0.0400
Bahan Paku biasa 5" - 12" Kg 0.4000
Minyak Bekisting Ltr 0.3500
Balok kayu Kelas II m3 0.0360
Plywwod tebal 9 mm Lbr 0.3500
Dolken kayu 8" - 10"/4m Btg 2.0000
Pekerja Oh 0.6600
Tukang kayu Oh 0.3300
Tenaga Kerja
Kepala Tukang Oh 0.0330
Mandor Oh 0.0330
6 1 m2 Pasangan bekisting untuk lantai
Kayu Kelas III m3 0.0400
Paku biasa 5" - 12" Kg 0.4000
Minyak bekisting Ltr 0.0536
Bahan
Balok kayu kelas II m3 0.0360
Plywood tebal 9 mm Lbr 0.3500
Dolken kayu 8" - 10"/4m Btg 2.0000
Pekerja Oh 0.6600
Tukang Kayu Oh 0.3330
Tenaga Kerja
Kepala Tukang Oh 0.0330
Mandor Oh 0.0330
7 1 m2 Pasangan Bekisting untuk Tangga
Kayu Kelas III m3 0.0300
Paku biasa 5" - 12" Kg 0.4000
Minyak bekisting Ltr 0.1500
Bahan
Balok kayu klas II m3 0.0183
Plywood tebal 9 mm Lbr 0.3455
Dolken kayu 8" - 10"/4m Btg 2.0000
Pekerja Oh 0.6600
Tukan Kayu Oh 0.3300
Tenaga Kerja
Kepala Tukang Oh 0.0330
Mandor Oh 0.0161
8 1 m2 Pasangan Jembatan Untuk Pengecoran beton
Kayu klas III ( Papan ) m3 0.0260
Bahan Paku biasa 5" - 12" Kg 0.6000
Dolken Kayu 8" - 10"/4m Btg 0.5000
Pekerja Oh 0.1500
Tukang Kayu Oh 0.0500
Tenaga Kerja
Kepala Tukang Oh 0.0051
Tenaga Kerja
Mandor Oh 0.0080
9 1 m3 Membuat Pondasi beton bertulang K 175, f'c = 14.5 Mpa ( 150 Kg besi + Bekisting )
Kayu klas III m3 0.2000
Paku biasa 5" - 12" Kg 1.5000
Minyak bekisting Ltr 0.0667
Bahan
besi beton polos Kg 150.0000
Kawat Beton Kg 2.2500
Semen Portland Kg 323.0000
Pasir beton m3 0.5200
Koral beton m3 0.7800
Pekerja Oh 4.2108
Tukang Batu Oh 0.3093
Tukang kayu Oh 1.0842
Tenaga Kerja
Tukang Besi Oh 1.0500
Kepala Tukang Oh 0.2450
Mandor Oh 0.1922
10 1 m3 membuat sloof beton bertulang K 175, f'c = 14.5 Mpa ( 200 Kg besi + Bekisting )
Kayu Klass III m3 0.2700
Paku biasa 5" - 12" Kg 2.0000
Minyak bekisting Ltr 0.1000
Besi beton Polos Kg 200.0000
Bahan
Kawat beton Kg 3.0000
Semen Portland Kg 323.0000
Pasir Beton m3 0.5200
Koral beton m3 0.7800
Pekerja Oh 4.9152
Tukang Batu Oh 0.3093
Tukang Kayu Oh 1.5600
Tenaga Kerja
Tukang besi Oh 1.4000
Kepala Tukang Oh 0.3270
Mandor Oh 0.2013
11 1 m3 membuat kolom beton bertulang K 175, f'c = 14.5 Mpa ( 300 Kg besi + bekisting )
Kayu klas III m3 0.4000
paku biasa 5" - 12" Kg 4.0000
Minyak bekisting Ltr 2.0000
Besi beton Polos Kg 300.0000
Bahan Kawat beton Kg 4.5000
Semen Portland Kg 323.0000
Pasir beton m3 0.5200
Koral beton m3 0.7800
Kayu klas II balok m 3
0.1500
Plywood tebal 9 mmm Lbr 3.5000
Dolken kayu 8"/4 m Btg 16.0000
Pekerja Oh 7.1750
Tukang Batu Oh 0.3093
Tukang Kayu Oh 2.7920
Tenaga Kerja
Tukan Besi Oh 2.1000
Kepala Tukang Oh 0.4883
Mandor Oh 0.2747
12 1 m3 membuat balok beton bertulang K 175, f'c = 14.5 Mpa ( 200 kg besi + bekisting )
Kayu klas III m3 0.3200
Bahan
Paku biasa 5" - 12" Kg 3.2000
Minyak bekisting Ltr 2.0000
Besi beton Polos Kg 200.0000
Kawat beton Kg 3.0000
Semen Portland Kg 323.0000
Pasir beton m3 0.5200
Koral beton m 3
0.7800
Kayu Klas II balok m3 0.1500
Plywwod tebal 9 mm Lbr 3.5000
Dolken kayu 8"/4 m Btg 16.0000
Pekerja Oh 7.1750
Tukang batu Oh 0.3093
Tukang Kayu Oh 1.6500
Tenaga Kerja
Tukang Besi Oh 1.4000
Kepala Tukang Oh 0.4883
Mandor Oh 0.2747
13 1 m3 membuat Plat beton bertulang K 175, f'c = 14.5 Mpa (150 kg besi + Bekisting )
Kayu klas III m3 0.1350
Paku Biasa 5" - 12" Kg 1.3497
Minyak bekisting Ltr 0.6750
Besi beton Polos Kg 157.5000
Kawat beton Kg 2.2500
Bahan Semen Portland Kg 323.0000
Pasir beton m3 0.5200
Koral beton m 3
0.7800
Kayu klas II balok m3 0.0505
Plywood tebal 9 mm Lbr 2.1810
Dolken kayu 8"/4 m Btg 16.0000
Pekerja Oh 6.7690
Tukang batu Oh 0.3093
Tenaga Kerja Tukang Kayu Oh 1.3000
Tukang Besi Oh 1.0500
Kepala Tukang Oh 0.2650
Mandor Oh 0.2650
14 1 m' membuat Kolom Praktis beton bertulang ( 11 x 11 ) cm
kayu klas III m3 0.0025
Bahan
Paku 5" - 12" Kg 0.0452
Besi beton Polos Kg 3.0000
Bahan Kawat beton Kg 0.4500
Semen Portland Kg 4.1750
Pasir Beton m3 0.0063
Koral Beton m 3
0.0093
Pekerja Oh 0.1588
Tukang Batu Oh 0.0473
Tenaga Kerja
Tukang Kayu Oh 0.0113
Tukang Kayu Oh 0.0118
Kepala Tukang Oh 0.0108
Mandor Oh 0.0100
15 1 m3 membuat beton mutu f'c = 7.4 Mpa ( K 100 )
Semen Portland Kg 254.0000
Bahan Batu koral beton m 3
0.8197
Pasir Beton m3 0.6200
Pekerja Oh 1.6500
Tukang Batu Oh 0.2890
Tenaga kerja
Kepala Tukang Oh 0.0290
Mandor Oh 0.0200
16 1 m3 membuat beton mutu f'c = 9.8 Mpa ( K 125 )
Semen Portland Kg 284.5500
Bahan Batu Koral beton m 3
0.8273
Pasir beton m3 0.6175
Pekerja Oh 1.6820
Tukang Batu Oh 0.2805
Tenaga Kerja
Kepala Tukang Oh 0.0280
Mandor Oh 0.0200
17 1 m3 membuat beton mutu f'c = 12.2 Mpa ( K 150 )
Semen Portland Kg 315.7000
Bahan Batu koral beton m 3
0.8180
Pasir beton m3 0.5845
Pekerja Oh 1.6915
Tukang Batu Oh 0.2820
Tenaga Kerja
Kepala Tukang Oh 0.0285
Mandor Oh 0.0200
18 1 m3 membuat beton mutu f'c = 14.5 Mpa ( K 175 )
Bahan Semen Portland Kg 323.0000
Batu koral beton m 3
0.7800
Pasir beton m3 0.5200
Pekerja Oh 1.6500
Tenaga Kerja
Tukang Kayu Oh 0.2675
Tenaga Kerja
Kepala Tukang Oh 0.0267
Mandor Oh 0.0200
19 1 m3 membuat beton mutu f'c = 16.9 Mpa ( K 200 )
Semen Portland Kg 325.0000
Bahan Batu koral beton m 3
0.8100
Pasir beton m3 0.5400
Pekerja Oh 1.6500
Tukang Kayu Oh 0.2750
Tenaga Kerja
Kepala Tukang Oh 0.0380
Mandor Oh 0.0300
20 1 m3 membuat beton mutu f'c = 19.3 Mpa ( K 225 )
Semen Portland Kg 377.0200
Bahan Batu koral beton m 3
0.8200
Pasir beton m3 0.5000
Pekerja Oh 1.6694
Tukang Kayu Oh 0.3050
Tenaga Kerja
Kepala Tukang Oh 0.0456
Mandor Oh 0.0400
21 1 m3 membuat beton mutu f'c = 21.7 Mpa ( K 250 )
Semen Portland Kg 384.0000
Bahan Batu koral beton m 3
0.7368
Pasir beton m3 0.4697
Pekerja Oh 1.6500
Tukang Kayu Oh 0.2750
Tenaga Kerja
Kepala Tukang Oh 0.0458
Mandor Oh 0.0400
22 1 m3 membuat beton mutu f'c = 24 Mpa ( K 275 )
Semen Portland Kg 412.0000
Bahan Batu koral beton m3 0.7800
Pasir beton m 3
0.5560
Pekerja Oh 1.6820
Tukang Kayu Oh 0.3125
Tenaga Kerja
Kepala Tukang Oh 0.0500
Mandor Oh 0.0500
23 1 m3 membuat beton mutu f'c = 26.4 Mpa ( K 300 )
Bahan Semen Portland Kg 413.0000
Batu koral beton m3 0.7206
Pasir beton m 3
0.4769
Pekerja Oh 1.6500
Tukang Kayu Oh 0.2750
Tenaga Kerja
Tenaga Kerja
Kepala Tukang Oh 0.0459
Mandor Oh 0.0400
24 1 m3 membuat beton mutu f'c = 31.2 Mpa ( K 350 )
Semen Portland Kg 464.3500
Bahan Batu koral beton m3 0.7800
Pasir beton m 3
0.4867
Pekerja Oh 2.1000
Tukang Kayu Oh 0.3500
Tenaga Kerja
Kepala Tukang Oh 0.0717
Mandor Oh 0.0700
25 1 m3 membuat Sloof beton bertulang K 350, f'c = 31.2 Mpa ( 150 kg besi + Bekisting )
Kayu klas III m3 0.2770
Bahan
Paku biasa 5" - 12" Kg 2.0500
Minyak bekisting Ltr 0.6150
Besi beton Polos Kg 150.0000
Kawat beton Kg 2.2500
Semen Portland Kg 464.3500
Pasir beton m3 0.4867
Koral beton m3 0.7800
Plywood tebal 9 mm Lbr 2.9160
Pekerja Oh 4.3460
Tukang batu Oh 0.2820
Tukang Kayu Oh 1.3325
Tenaga Kerja
Tukang Besi Oh 1.0765
Kepala Tukang Oh 0.2700
Mandor Oh 0.2000
26 1 m3 membuat balok beton bertulang mutu 350, f'c = 31.2 Mpa ( 175 kg besi + bekisting )
Kayu klas III m3 0.3280
Paku biasa 5" - 12" Kg 3.2800
Minyak bekisting Ltr 1.6400
Besi beton Polos Kg 175.0000
Kawat beton Kg 2.6250
Bahan Semen Portland Kg 464.3500
Pasir beton m3 0.4867
Koral beton m3 0.7800
Kayu klas II m 3
0.1500
Plywood tebal 9 mm Lbr 4.0000
Dolken kayu 8"/4 m Btg 16.0000
Pekerja Oh 5.4325
Tukang batu Oh 0.3415
Tukang Kayu Oh 1.6500
Tenaga Kerja
Tukang Besi Oh 1.4000
Kepala Tukang Oh 0.3330
Mandor Oh 0.3000
27 1 m3 membuat balok beton bertulang mutu K 275, f'c = 24 Mpa ( 175 kg besi + bekisting )
Kayu klas III m3 0.3280
Paku biasa 5" - 12" Kg 3.2800
Minyak bekisting Ltr 1.6400
Besi beton Polos Kg 175.0000
Kawat beton Kg 2.6250
Bahan Semen Portland Kg 412.0000
Pasir beton m3 0.5560
Koral beton m 3
0.7800
Kayu klas II m3 0.1400
Plywood tebal 9 mm Lbr 4.0000
Dolken kayu 8"/4 m Btg 16.0000
Pekerja Oh 5.4325
Tenaga Kerja
Tukang batu Oh 0.3415
Tukang Kayu Oh 1.6500
Tukang Besi Oh 1.4000
Kepala Tukang Oh 0.3330
Mandor Oh 0.3000
V PEKERJAAN ATAP
1 1 kg Pekerjaan kuda-kuda baja ( Truss Steel works )
Steel truss box (60x10x1.5 mmx20mm) Kg 1.0250
Bahan
Self Drilling Screws 12 - 14 x 20 mm bh 1.0250
Pekerja Oh 0.0410
Tukang Oh 0.0200
Tenaga Kerja
Kepala Tukan Oh 0.0100
Mandor Oh 0.0100
2 1 kg Purlin Steel works
Steel Purlin 50x20x10x1.5x600 mm Kg 1.0250
Bahan
Self Drilling Screws 12 - 14 x 20 mm bh 1.0250
Pekerja Oh 0.0205
Tukang Oh 0.0105
Tenaga Kerja
Kepala Tukang Oh 0.0011
Mandor Oh 0.0005
3 1 m Pekerjaan rangka atap
RHS 100.50.5 Btg 0.2050
Bahan
Kawat las Kg 0.0105
Pekerja Oh 0.0615
Tukang Oh 0.0615
Tenaga Kerja
Kepala Tukang Oh 0.0060
Mandor Oh 0.0030
4 1 m Pasang Gording Canal C 75.45.15.1.6
Canal C 75.35.15.1.5 Btg 0.2050
Bahan
Kawat Las Kg 0.0105
Pekerja Oh 0.0585
Tukang Las Oh 0.0300
Tenaga Kerja
Kepala Tukang Oh 0.0060
Mandor Oh 0.0030
5 1 m2 Baja Ringan
Light Steel Profile m 4.5600
Bahan Screw Ls 1.0000
Dynabolt Ls 1.0000
Pekerja Oh 0.0770
Tukang Oh 0.1540
Tenaga Kerja
Kepala Tukang Oh 0.0155
Mandor Oh 0.0040
6 1 m2 Pasang atap seng gelombang
Seng Gelombang Lbr 0.7000
Bahan
Paku seng Kg 0.0200
Pekerja Oh 0.1409
Tukang Kayu Oh 0.1256
Tenaga Kerja
Kepala Tukang Oh 0.0510
Mandor Oh 0.0067
7 1 m' Pasang nok atap sirap
Seng Plat 3" x 6" Bjls 28 Lbr 0.4000
Paku 1/2" - 1" Kg 0.0600
Bahan
Paku 2" - 5" Kg 0.0500
Kayu Papan 3 cm m3 0.0060
Pekerja Oh 0.1250
Tukang Kayu Oh 0.2500
Tenaga kerja
Kepala Tukang Oh 0.0420
Mandor Oh 0.0067
8 1 m2 Pasangan atap genteng Plentong besar
Bahan Genteng Plentong bh 23.0770
Pekerja Oh 0.1500
Tukang kayu Oh 0.0656
Tenaga Kerja
Kepala Tukang Oh 0.0070
Mandor Oh 0.0070
9 1 m' Pasang Bubungan Plentong besar
Bahan Bubungan Plentong bh 4.4351
Semen Portland Kg 8.0000
Pasir Pasang m3 0.0320
Pekerja Oh 0.4000
Tukang Kayu Oh 0.2000
Tenaga Kerja
Kepala Tukang Oh 0.0200
Tenaga Kerja
Mandor Oh 0.0020
10 1 m2 Pasang atap Asbes gelombang 1.80 x 0.92 m x 5mm
Asbes Gelombang Lbr 0.7577
Bahan
Paku Pancing Kg 0.1200
Pekerja Oh 0.1400
Tukang kayu Oh 0.0670
Tenaga Kerja
Kepala Tukang Oh 0.0070
Mandor Oh 0.0070
11 1 m2 Pasang Atap Sirap
Genteng Sirap bh 61.0000
Bahan
Paku biasa 1/2" - 1" Kg 0.2033
Pekerja Oh 0.1687
Tukang Kayu Oh 0.2543
Tenaga Kerja
Kepala Tukang Oh 0.0253
Mandor Oh 0.0080
12 1 m2 Pasang Atap Alang - alang
Bahan Alang - Alang Lbr 6.6625
Tali Bengikat Kg 0.5125
Pekerja Oh 0.2050
Tenaga Kerja
Mandor Oh 0.0105
VI PEKERJAAN DINDING
1 1 m2 Pasangan Batako 40 x 20 x 10 cm, Campuran Spesi 1Pc : 4Ps
Batako bh 12.5000
Bahan Semen Portland Kg 12.0000
Pasir Pasang m3 0.0380
Pekerja Oh 0.3518
Tukang Batu Oh 0.1131
Tenaga Kerja
Kepala Tukang Oh 0.0193
Mandor Oh 0.0288
2 1 m2 Pasangan Paving Block 25 x 20 x 6cm
Paving Block bh 20.6000
Bahan Semen Portland Kg 8.3200
Pasir Pasang m3 0.0620
Pekerja Oh 0.3210
Tukang Batu Oh 0.4370
Tenaga Kerja
Kepala Tukang Oh 0.0220
Mandor Oh 0.0175
3 1 m2 Pasang Paving Block 20 x 10 x 6cm
Paving Block bh 51.5000
Bahan Semen Portland Kg 8.3200
Pasir Pasang m3 0.0620
Pekerja Oh 0.3210
Tukang Batu Oh 0.4370
Tenaga Kerja
Kepala Tukang Oh 0.0220
Mandor Oh 0.0175
4 1 m3 Pasangan Bronjong ( 2 x 1 x 1m )
Batu kali m3 1.1000
Bahan
Bronjong Unit 0.5000
Pekerja Oh 0.6667
Tenaga Kerja
Mandor Oh 0.0240
Pekerja Oh 0.2559
Tukang Batu Oh 0.1500
Tenaga Kerja
Kepala Tukang Oh 0.0167
Mandor Oh 0.0167
2 1 m2 Plesteran 1 Pc : 4 Ps, tebal 15 mm
Semen Portland Kg 6.2400
Bahan
Pasir Pasang m3 0.0214
Pekerja Oh 0.2559
Tukang Batu Oh 0.1500
Tenaga Kerja
Kepala Tukang Oh 0.0167
Mandor Oh 0.0167
3 1 m2 Plesteran 1 Pc : 2 Ps, tebal 20 mm
Semen Portland Kg 12.7500
Bahan
Pasir Pasang m3 0.0270
Pekerja Oh 0.3500
Tukang Batu Oh 0.1500
Tenaga Kerja
Kepala Tukang Oh 0.0202
Mandor Oh 0.0273
4 1 m2 Plesteran 1 Pc : 3 Ps, tebal 20 mm
Semen Portland Kg 10.3500
Bahan
Pasir Pasang m 3
0.0310
Pekerja Oh 0.3500
Tukang Batu Oh 0.1500
Tenaga Kerja
Kepala Tukang Oh 0.0202
Mandor Oh 0.0273
5 1 m2 Plesteran 1 Pc : 4 Ps, tebal 20 mm
Semen Portland Kg 8.3200
Bahan
Pasir Pasang m 3
0.0320
Pekerja Oh 0.3500
Tukang Batu Oh 0.1500
Tenaga Kerja
Kepala Tukang Oh 0.0202
Mandor Oh 0.0273
6 1 m2 Plesteran ciprat, 1 Pc : 2 Ps
Semen Portland Kg 5.6080
Bahan
Pasir Pasang m3 0.0110
Pekerja Oh 0.2559
Tukang Batu Oh 0.1270
Tenaga Kerja
Kepala Tukang Oh 0.0130
Mandor Oh 0.0150
7 1 m2 Plesteran 1 Pc : 5 Ps, tebal 15 mm
Semen Portland Kg 4.7751
Bahan
Pasir Pasang m3 0.0220
Pekerja Oh 0.2559
Tukang Batu Oh 0.1500
Tenaga Kerja
Kepala Tukang Oh 0.0167
Mandor Oh 0.0167
8 1 m2 Plesteran 1 Pc : 5 Ps, tebal 20 mm
Bahan Semen Portland Kg 6.4490
Pasir Pasang m 3
0.0230
Pekerja Oh 0.3500
Tukang Batu Oh 0.1500
Tenaga Kerja
Kepala Tukang Oh 0.0202
Mandor Oh 0.0273
Pekerja Oh 0.1500
Tukan Batu Oh 0.0731
Tenaga Kerja
Kepala Tukang Oh 0.0074
Mandor Oh 0.0069
2 Memasang 1 m2 finishing siar Pasangan dinding Conblock ekspose
Bahan Semen Portland Kg 1.6400
Pekerja Oh 0.0720
Tukan Batu Oh 0.0360
Tenaga Kerja
Kepala Tukang Oh 0.0040
Mandor Oh 0.0040
3 Memasang 1 m2 finishing siar Pasangan batu kali adukan 1Pc : 2Ps
Semen Portland Kg 6.3400
Bahan
Pasir Pasang m3 0.0120
Pekerja Oh 0.3000
Tukan Batu Oh 0.1500
Tenaga Kerja
Kepala Tukang Oh 0.0150
Mandor Oh 0.0270
4 1 m2 Acian
Bahan Semen Portland Kg 3.4988
Pekerja Oh 0.1753
Tukan Batu Oh 0.1057
Tenaga Kerja
Kepala Tukang Oh 0.0146
Mandor Oh 0.0146
IX PEKERJAAN KAYU
1 Membuat dan memasang 1 m3 kuse Pintu dan jendela kayu klas I
Balok Kayu m3 1.1080
Bahan Paku 10 cm Kg 1.0031
Lem Kayu Kg 1.0000
Pekerja Oh 6.9380
Tukang kayu Oh 20.8140
Tenaga Kerja
Kepala tukang Oh 2.1521
Mandor Oh 0.4283
2 Membuat dan memasang 1 m3 Kusen Pintu dan jendela Kayu klas II/III
Bahan Balok Kayu m3 1.1080
Paku 10 cm Kg 1.0031
Lem Kayu Kg 1.0000
Pekerja Oh 6.0000
Tukang kayu Oh 18.0000
Tenaga Kerja
Kepala tukang Oh 2.0000
Mandor Oh 0.3890
3 Membuat dan memasang 1 m2 Pintu Klamb Standar, Kayu klas II
Papan Kayu m3 0.0400
Bahan
Paku 5 - 7 cm Kg 0.4750
Pekerja Oh 0.5725
Tukang Kayu Oh 1.5508
Tenaga Kerja
Kepala Tukang Oh 0.1551
Mandor Oh 0.0956
4 Membuat dan memasang 1 m2 Pintu klamb sederhana, kayu klas III
Papan Kayu m3 0.0400
Bahan
Paku 5 - 7 cm Kg 0.4750
Pekerja Oh 0.5725
Tenaga Kerja
Tukang Kayu Oh 1.5508
Kepala Tukang Oh 0.1551
Mandor Oh 0.0956
5 Membuat dan memasang 1 m2 daun Pintu Panel, akyu klas I/II
papan Kayu m3 0.0400
Bahan
Lem Kayu Kg 0.5000
Pekerja Oh 1.0000
Tukang Kayu Oh 2.5543
Tenaga Kerja
Kepala Tukang Oh 0.2556
Mandor Oh 0.0500
6 Membuat dan memasang 1 m2 Pintu dan Jendela kaca, Kayu klas I/II
papan Kayu m3 0.0240
Bahan
Lem Kayu Kg 0.1593
Pekerja Oh 0.8000
Tukang Kayu Oh 2.1006
Tenaga Kerja
Kepala Tukang Oh 0.2043
Mandor Oh 0.0400
7 Membuat dan memasang 1 m2 Pintu dan jendela jalusi, Kayu klas I/II
papan Kayu m3 0.0385
Bahan
Lem Kayu Kg 0.5000
Pekerja Oh 1.0000
Tukang Kayu Oh 3.0000
Tenaga Kerja
Kepala Tukang Oh 0.3000
Mandor Oh 0.0500
8 Memasang 1 m3 Konstruksi kuda-kuda konvensional, Kayu Klas I. II dan III bentang 6 m'
Balok Kayu m3 1.1000
Bahan
Besi strip tebal 5 mm Kg 15.0000
paku 12 cm Kg 3.4460
Pekerja Oh 4.4054
Tukang Kayu Oh 10.1540
Tenaga Kerja
Kepala Tukang Oh 1.0154
Mandor Oh 0.2000
9 Memasang 1 m3 konstruksi kuda-kuda expose, kayu klas I
Balok Kayu m3 1.1150
Bahan Besi strip tebal 5 mm Kg 15.0000
Paku 12 cm Kg 2.4260
Pekerja Oh 4.7508
Tukang Kayu Oh 20.1000
Tenaga Kerja
Kepala Tukang Oh 2.0100
Mandor Oh 0.2375
10 Memasang 1 m3 Konstruksi gording, kayu klas II
Balok Kayu m3 1.1000
Bahan Besi Strip tebal 5 mm Kg 15.0000
Paku 12 cm Kg 3.0000
Pekerja Oh 0.2033
Tukang Kayu Oh 0.3050
Tenaga Kerja
Kepala Tukang Oh 0.0305
Mandor Oh 0.0750
12 Memasang 1 m' Lisplank uk. 3 x 20 cm, Kayu klas I/II
Papan Payu m3 0.0100
Bahan
Paku 5 sampai 7 cm Kg 0.0759
Pekerja Oh 0.1194
Tukang Kayu Oh 0.2390
Tenaga Kerja
Kepala Tukang Oh 0.0239
Mandor Oh 0.0050
13 Memasang 1 m' Lisplank uk. 3 x 30 cm, Kayu klas I/II
Papan Payu m3 0.0110
Bahan
Paku 5 sampai 7 cm Kg 0.0759
Pekerja Oh 0.1194
Tukang Kayu Oh 0.2390
Tenaga Kerja
Kepala Tukang Oh 0.0239
Mandor Oh 0.0050
Pekerja Oh 0.5125
Tukang Batu Oh 0.2050
Tenaga Kerja
Kepala Tukang Oh 0.0205
Mandor Oh 0.0205
2 Memasang 1 m2 lantai keramik ukuran 30 x 30 cm
Keramik bh 11.8700
Semen Portland Kg 8.0000
Bahan
Pasir pasang m3 0.0450
Semen warna Kg 1.5000
Pekerja Oh 0.7000
Tukang batu Oh 0.3500
Tenaga Kerja
Tenaga Kerja
Kepala Tukang Oh 0.0350
Mandor Oh 0.0350
3 Memasang 1 m2 lantai keramik ukuran 40x 40 cm
Bahan Keramik bh 6.6250
Semen Portland Kg 8.0000
Pasir Pasang m3 0.0450
Semen warna Kg 0.9400
Pekerja Oh 0.7000
Tukang Batu Oh 0.3500
Tenaga Kerja
Kepala Tukang Oh 0.0350
Mandor Oh 0.0350
4 Memasang 1 m2 lantai keramik ukuran 60 x 60 cm
Keramik bh 3.0000
Semen Portland Kg 8.0000
Bahan
Pasir Pasang m3 0.0450
Semen warna Kg 0.9321
Pekerja Oh 0.7000
Tulang Batu Oh 0.3500
Tenaga Kerja
Kepala Tukang Oh 0.0350
Mandor Oh 0.0350
Pekerja Oh 0.1000
Tenaga Kerja Tukang Kayu Oh 0.1000
Kepala Tukang Oh 0.0100
Mandor Oh 0.0050
Pekerja Oh 0.0100
Tukang Besi Oh 0.5000
Tenaga Kerja
Kepala Tukang Oh 0.0100
Mandor Oh 0.0050
2 1 bh. Pasang engsel Pintu
Bahan Engsen Pintu bh 1.0000
Pekerja Oh 0.0150
Tukang Besi Oh 0.1500
Tenaga Kerja
Kepala Tukang Oh 0.0150
Mandor Oh 0.0010
3 1 bh. Pasang engsel jendela kupu-kupu
Bahan Engsel jendela bh 1.0000
Pekerja Oh 0.0100
Tenaga Kerja Tukang Besi Oh 0.1000
Kepala Tukang Oh 0.0100
Mandor Oh 0.0010
4 1 bh. Pasang kait angin
Bahan Kait angin bh 1.0000
Pekerja Oh 0.0150
Tukang Besi Oh 0.1500
Tenaga Kerja
Kepala Tukang Oh 0.0150
Mandor Oh 0.0010
5 1 bh. Pasang kunci slot
Bahan Kunci slot bh 1.0000
Pekerja Oh 0.0098
Tukang Besi Oh 0.0683
Tenaga Kerja
Kepala Tukang Oh 0.0068
Mandor Oh 0.0010
6 1 m2 Pasang kaca, tebal 3 - 5 mm
Bahan Kaca bh 1.1000
Pekerja Oh 0.0150
Tukang Besi Oh 0.1500
Tenaga Kerja
Kepala Tukang Oh 0.0150
Mandor Oh 0.0010
Pekerja Oh 1.4501
Tukang Batu Oh 1.2366
Tenaga Kerja
Kepala Tukang Oh 0.1236
Mandor Oh 0.1600
2 Memasang 1 bh kloset jongkok Porselen
Kloset Jongkok Porselen bh 1.0000
Bahan Semen Portland Kg 6.1000
Pasir Pasang m3 0.0103
Pekerja Oh 1.0000
Tenaga Kerja
Tukang Batu Oh 1.5250
Tenaga Kerja
Kepala Tukang Oh 1.5000
Mandor Oh 0.1627
3 Memasang 1 m' Pipa Galvanis Ø 1/2" - 1"
Pipa Galvanis m' 1.2000
Bahan
Asesories ( % dari harga Pipa ) % 35.0000
Pekerja Oh 0.0540
Tukang Batu Oh 0.0900
Tenaga Kerja
Kepala Tukang Oh 0.0090
Mandor Oh 0.0270
4 Memasang 1 m' Pipa Galvanis Ø 1 1/2" - 3"
Bahan Pipa Galvanis m' 1.2000
Asesories ( % dari harga Pipa ) % 35.0000
Pekerja Oh 0.1080
Tukang Batu Oh 0.1800
Tenaga Kerja
Kepala Tukang Oh 0.0180
Mandor Oh 0.0054
5 Memasang 1 m' Pipa PVC tipe AW Ø 1/2" - 1 1/2"
Pipa PVC m' 1.2000
Bahan
Asesories ( % dari harga Pipa ) % 35.0000
Pekerja Oh 0.0360
Tukang Batu Oh 0.0706
Tenaga Kerja
Kepala Tukang Oh 0.0075
Mandor Oh 0.0043
6 Memasang 1 m' Pipa PVC tipe AW Ø 2"
Pipa PVC m' 1.2000
Bahan
Asesories ( % dari harga Pipa ) % 35.0000
Pekerja Oh 0.0450
Tukang Batu Oh 0.0750
Tenaga Kerja
Kepala Tukang Oh 0.0090
Mandor Oh 0.0025
7 Memasang 1 m' Pipa PVC tipe AW Ø 3" - 4"
Bahan Pipa PVC m' 1.2000
Pekerja Oh 0.0810
Tukang Batu Oh 0.1879
Tenaga Kerja
Kepala Tukang Oh 0.0189
Mandor Oh 0.0070
8 Memasang 1 buah kran 1/2" atau 3/4"
Kran air bh 1.0000
Bahan
Seal tape bh 0.0245
Pekerja Oh 0.0100
Tukang Batu Oh 0.1000
Tenaga Kerja
Tenaga Kerja
Kepala Tukang Oh 0.0100
Mandor Oh 0.0050
XV PEKERJAAN PENGECATAN
1 1 m2 Pengecatan bidang kayu baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
Cat meni Kg 0.1850
Dempul / Plamir Kg 0.1380
Bahan Cat dasar Kg 0.1700
Cat Penutup 2x Kg 0.2730
Kuas bh 0.0294
Pekerja Oh 0.0847
Tukang Cat Oh 0.0890
Tenaga Kerja
Kepala Tukang Oh 0.0139
Mandor Oh 0.0051
2 1 m2 Pengecatan bidang kayu dengan Vernis
Vernis Kg 0.2930
Dempul / Plamir Kg 0.0934
Bahan
Amplas Lbr 0.8924
Kuas bh 0.0294
Pekerja Oh 0.0539
Tukang Cat Oh 0.0806
Tenaga Kerja
Kepala Tukang Oh 0.0129
Mandor Oh 0.0046
3 1 m2 Pengecatan tembok baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
Plamir Kg 0.1154
Cat dasar Kg 0.0920
Bahan
Cat penutup 2x Kg 0.2600
Kuas bh 0.0294
Pekerja Oh 0.0362
Tukang Cat Oh 0.0630
Tenaga Kerja
Kepala Tukang Oh 0.0064
Mandor Oh 0.0064
2.8 Unidade de Presu
Unidade do Presu katak folin osan ba material no mão de obra ba servisu 1m³ nian.
tan ne’e iha unidade presu ida ne’e involve folin material no mão de obra ne’ebe vezes ba koefisiente
material no mão de obra nian para hodi bele hetan folin osan ba servisu refere, ba material nia folin halo
peskija folin material sira iha merkadu no loja sira. No folin osan ba trabalhadores sira selu tuir salariu
ne’ebe SEFOPE determina tiha ona.
Tan ne’e unidade presu ba projetu uma simples mak tuir mai ne’e:
Presu Presu
No. Deskrisaun do Servisu Unidade Coeficiente Total ($)
Material ($) Unitario ($)
DESKRISAUN
b. Material
Dobralisa bh 1 15.000
4 Servisu Monta Dobralisa Janela
a.Mao De Obra
Mandor Pd 0.001 0.028
Badaen Ai Pd 0.1 2.800
28.000
Ajudante Pd 0.01 0.280
b. Material
Dobralisa bh 1 28.000
5 Servisu Monta Kait Angin
a.Mao De Obra
Mandor Pd 0.001 0.014
Badaen Ai Pd 0.15 2.100
14.000
Ajudante Pd 0.015 0.210
b. Material
Kait Angin bh 1 14.000
VIII. SERVISU BA PINTURA NIAN
1 Servisu Pinta Paredi
a.Mao De Obra
Mandor Pd 0.0064 2.272
Badaen Ai Pd 0.063 22.364
Ajudante Pd 0.0362 12.851
354.987
b. Material
Cat Dasar Kg 0.092 32.659
Cat 2 x Penutup Kg 0.26 92.297
Kuas Roll bh 0.0294 10.437
2 Servisu Pinta Arus
a.Mao De Obra
Mandor Pd 0.0046 0.162
Tukang Cat Pd 0.0806 2.845
Ajudante Pd 0.0539 1.903
b. Material 35.302
Vernis Kg 0.293 10.343
Dempul / Plamir Kg 0.0934 3.297
Amplas Lbr 0.8924 31.503
Kuas bh 0.0294 1.038
3 Servisu Pinta Plafond
a.Mao De Obra
Mandor Pd 0.000
Badaen Ai Pd 0.000
Ajudante Pd 135.520 0.000
b. Material
Tinta Kg 0.000
Kuas Roll bh 0.000
IX. SERVISU BA KOMPLETARIA LARAN & LIUR
1 Servisu instalasaun Fiu
a. Mao De Obra
Eletrisista Ls 1 50.000
50.000
50.000
b. Material
Kabel NIM 2.5 mm 2 urat m 1 50.000
2 Servisu Monta Lampu
a. Mao De Obra
Eletrisista Ls 1 9.000
9.000
b. Material
Lampu TL bh 1 9.000
3 Servisu Monta Stop Kontak
a. Mao De Obra
Eletrisista Ls 1 7.000
7.000
b. Material
Stop Kontak ( kuak 2) bh 1 7.000
4 Servisu Monta Sakelar Tunggal
a. Mao De Obra
Eletrisista Ls 1 4.000
4.000
b. Material
Sakelar Tunggal bh 1 4.000
5 Servisu Monta Sakelar Ganda
a. Mao De Obra
Eletrisista Ls 1 2.000
2.000
b. Material
Sakelar Ganda bh 1 2.000
6 Servisu Monta Panel
a. Mao De Obra
Eletrisista Ls 1 1.000
1.000
b. Material
Panel bh 1 1.000
7 Servisu Eskavasaun Rai ba Septicktank
a. Mao De Obra
Mandor Pd 0.0685 9.072 0.621
Ajudante Pd 0.89 8.074
8 Servisu Aterru Rai henek ba septicktank
a. Mao De Obra
Mandor Pd 0.0127 0.004
Ajudante Pd 0.3023 0.288 0.087
b. Material
Rai-henek m³ 1.2 0.346
9 Servisu Cor Laje Ba Septicktank
a. Mao De Obra
Mandor Pd 0.02 0.023
Badaen Fatuk Pd 0.2805 0.328
Ajudante Pd 1.682 1.968
1.170
b. Material
Rai-henek m³ 0.6175 0.722
Sementi Portland kg 284.55 332.924
Agregadu m³ 0.8273 0.968
10 Servisu Hada Batako Ba septicktank
a. Mao De Obra
22.500
Mandor Pd 0.0288 0.648
Badaen Fatuk Pd 0.1131 2.545
Ajudante Pd 0.3518 7.916
22.500
b. Material
Rai-henek m³ 0.038 0.855
Sementi Portland kg 12 270.000
Batako bh 12.5 281.250
11 Servisu Instalasaun Bee Foer Ho Pipa PVC 4"
a. Mao De Obra
Mandor Pd 0.007 0.061
Canalizador Pd 0.1879 1.625
Ajudante Pd 0.081 0.701
b. Material 8.650
Pipa PVC 4" m' 1.2 10.380
Asesories ( % dari harga Pipa ) % 35% 3.028
Kolset Ls 1 8.650
Floor Drain Ls 1 8.650
12 Servisu Instalasaun Bee Foer Ho Pipa PVC 2"
a. Mao De Obra
Mandor Pd 0.0025 0.051
Canalizador Pd 0.075 1.525
Ajudante Pd 0.045 0.915
20.330
b. Material
Pipa PVC 2" m' 1.2 24.396
Asesories ( % dari harga Pipa ) % 35% 7.116
Ktchen zink Ls 1 20.330
13 Servisu Instalasaun Be'e Mos Ho Pipa PVC 3/4"
a. Mao De Obra
Mandor Pd 0.0043 0.148
Canalizador Pd 0.0706 2.435
Ajudante Pd 0.036 34.490 1.242
b. Material
Pipa PVC 2" m' 1.2 41.388
Asesories ( % dari harga Pipa ) % 35% 12.072
Loron Ne'ebe Trabalhador
Mak Ne'ebe Mak
Determina Presija
3 4.800
9.600
0.140
2.800
2.800
2
6 0.676
8.843 10
0.046
2 1.094
0.210
1.411
2
2.823
0.790
8.848
19.280
5
1 0.104
1.550
0.473
0.727
3.666
3.290
11.551
0.275
2.792
2.100
0.309
7.175
0.430
2.585
2.193
0.485
11.241
3
3
0.026
0.182
0.040
0.639
0.032
0.297
1.785
2
0.010
0.136
0.814
1
0.092
0.363
1.128
6
0.124
6.032
2.011
2
0.074
6.266
1.481
2
0.010
0.615
2 0.205
0.000
0.021
1 0.010
0.567
10.629
2 11.923
0.037
0.696
1 0.781
1
0.041
0.168
4 0.112
0.169
3.388
4 3.388
1.422
7.815
5 18.234
1.811
13.109
2
21.740
0.410
4 3.295
0.205
3 1.647
3
0.031
3 0.729
0.000
0.000
0.000
1
0.816
8.161
16.322
5
0.500
30.000
2 10.000 4
0.050
5.000
1
0.100
0.030
4.500
1
0.450
1
0.056
5.600
1
0.560
0.028
4.200
1
0.420
0.568
5.591
3.213
4
0.162
2.845
1.903
1
0.000
0.000
4 0.000
25.000
2
2
18.000
1
14.000
1
8.000
1
4.000
1
2.000
1
2 0.311
4.037
0.007
1 0.174
0.047
0.656
3.936
1
1
0.648
2.545
7.916
1
0.121
3.251
1.401
1
0.102
3.050
1.830
1
0.297
4.870
1 2.483
101.0 Dias
14.4 Semana
3.6 mes
449.601
DESCRICAO
NO DO SERVISU ORCAMENTO PERCENTAGEM MES
SEMANAS
1 2 3
I SERVISU HAHU NIAN 684.61 3.27% 3.3%
II SERVISU BA RAI NIAN 1715.64 8.20% 2.0% 2.0%
III SERVISU HADA & REBOKA NIAN 5925.81 28.31%
IV SERVISU BETAUN NIAN 5333.13 25.48%
V SERVISU KAKULUK NIAN 1373.41 6.56%
VI SERVISU PLAFON NIAN 560.21 2.68%
VII SERVISU BA LAJE NIAN 786.95 3.76%
VIII SERVISU ODAMATAN & JANELA 2836.37 13.55%
IX SERVISU PINTURA NIAN 581.82 2.78%
X SERVISU KOMPLETARIA NIAN 1135.95 5.43%
TOTAL 20933.89 100.00%
3% 2% 2%
PRECENTAGEM COMULATIVO DO PLANO 3% 5% 7%
MES MES MES %
SEMANAS SEMANAS SEMANAS
4 5 6 7 8 9 10 11 12 13 14 15 16
100%
2.0% 2.0% 90%
14% 14% 80%
13% 13% 70%
3.3% 3.3% 60%
1.3% 1.3% 50%
1.9% 1.9% 40%
14% 30%
1.4% 1.4% 20%
2.7% 2.7% 10%
0%
16% 16% 14% 13% 16% 5% 3% 2% 1% 1% 3% 3%
23% 39% 53% 66% 82% 87% 90% 92% 93% 95% 97% 100%
2.13 Orariu ba Atividade Projeto Nian.
PENDAHULUAN
ATIVIDADE ESPLIKASAUN
LANGSUNG
A SERVISU HAHU NIAN -
B SERVISU BA RAI NIAN A
C SERVISU BETAUN NIAN B
D SERVISU HADA & REBOKA NIAN C
E SERVISU ODAMATAN & JANELA D
F SERVISU KAKULUK NIAN D&E
G SERVISU PLAFOND NIAN F
H SERVISU BA LAJE NIAN G
I SERVISU PINTURA NIAN F,G&H
J SERVISU KOMPLETARIA I
A E F
HAHU D G I J
B C H
TEMPU
ATIVIDADE ESPLIKASAUN
(SEMANAS)
A SERVISU HAHU NIAN 1
B SERVISU BA RAI NIAN 3
C SERVISU BETAUN NIAN 1
D SERVISU HADA & REBOKA NIAN 3
E SERVISU ODAMATAN & JANELA 1
F SERVISU KAKULUK NIAN 1
G SERVISU PLAFOND NIAN 1
H SERVISU BA LAJE NIAN 1
I SERVISU PINTURA NIAN 1
J SERVISU KOMPLETARIA 2
Diagrama On Node Ba Eearly Star & Early Finish
ATIVIDADE TEMPU ES EF LS LF
A 1 0 1 0 1
B 3 1 4 1 4
C 1 4 5 4 5
D 3 5 8 5 8
E 1 8 9 8 9
F 1 9 10 9 10
G 1 10 11 10 11
H 1 11 12 11 12
I 1 12 13 12 13
J 2 13 15 13 15
Kalkulasaun ba Tempu Folga no Kritiku
SLACK CRITICAL
ATIVIDADE
TEMPU ES EF LS LF LS-ES Path
A 1 0 1 0 1 0 ya
B 3 1 4 1 4 0 ya
C 1 4 5 4 5 0 ya
D 3 5 8 5 8 0 ya
E 1 8 9 8 9 0 ya
F 1 9 10 9 10 0 ya
G 1 10 11 10 11 0 ya
H 1 11 12 11 12 0 ya
I 1 12 13 12 13 0 ya
J 2 13 15 13 15 0 ya
Husi Resultadu Kalkulasaun Iha tabela leten ne'e hatudu Katak Tempu Ne'ebe presija atu realiza atu
hala'o projetu ne'e laiha tempu ne'ebe folga.
`
u realiza atu