Summary

Symptom
F&R Analytics data need to be set up in BW.

More Terms
0FRE_ANA_STCKEXC_1, 0FRE_ANA_OP_MCHG_1, 0FRE_ANA_OP_STAT_1,
0FRE_ANA_VAR_1, 0FRE_ANA_WEEKLY_1, 0FRE_REPL_EXC_1, 0FRE_MSGNO_ATTR,
0FRE_MATPLANT_ATTR, 0FRE_OPSTAT_TEXT, 0FRE_SELCLS_TEXT, 0FRE_MSGA1_TEXT,
0FRE_MSGA2_TEXT, 0FRE_STKEXC_TEXT, Delta init

Cause and Prerequisites

o Initial load of data needs to be done in BW for F&R BW

o Master data load from R/3 and F&R needs to be done in BW

o F&R transactional initial delta loads need to be performed in BW

o F&R transactional delta loads needs to be performed in BW


Note: It is recommended that delta loads are performed once a day for
daily cubes and once a week for weekly cubes. This is mainly necessary for
the Order Proposal Changes where the delivered query will require
modification if the data is extracted multiple times per day. Also in this
case, the field 'Original quantity' will loose its meaning and it will show
'Quantity before last BW extraction' instead.

Solution
In order to load data from F&R into BW, the F&R content need to be
installed before hand. Please refer to the Forecasting & Replenishent
Solution Manager documentation to perform the required settings.

1. To load initial data in BW, Forecasting and Replenishment info


packages need to be scheduled in order to retreive data from the
source system:

a) Info package for infosource 0FRE_MSGNO. Info package name: Load F&R
message class /FRE/EMON (0PAK_7BNPMDT9RI4184VO614M11J8P)

b) Info package for infosource 0FRE_MSGA1_TEXT. Info package name:


Load texts for message class /FRE/EMON (Attribute 1)
(0PAK_091ZW7IYYOO1OYPP2APOBL0H7)

c) Info package for infosource 0FRE_MSGA2_TEXT. Info package name:


Load Load texts for message class /FRE//EMON (Attribute 2)
(0PAK_BDQ8Y8T31K94VZ92IE6AWFBMZ)

d) Info package for infosource 0FRE_OPSTAT_TEXT. Info package name:


Load texts for Order Proposal
status(0PAK_7G2K37SJLE8GXLVVS03UANCFD)

e) Info package for infosource 0FRE_SELCLS_TEXT. Info package name:


Load texts for Selling Class(0PAK_A3Z8R619BKKNEC35CN0E77AND)

f) Info package for infosource 0FRE_STKEXC_TEXT. Info package name:

18.06.2008 Page 1 of 3
Note 723899 - Forecasting and Replenishment Analytics BW loading
procedure
Load texts for Stock Exception Type(0PAK_F0VJ1QSJ692BBL7R0AUU41OYX)

2. To load master data from the R/3 leading system, the following
infosources need to be scheduled:

a) Infosource Material(0MATERIAL) with datasource Article


Number(0ARTICLE_ATTR). This infosource allows you to load article
masterdata.

b) Infosource Material (texts)(0MATERIAL_TEXT) with datasource


Material Number(0MATERIAL_TEXT). This inforsource allows you to
load article descriptions in all languages.

c) Infosource Plant (Attributes)(0PLANT_ATTR) with datasource


Plant(0PLANT_ATTR). This infosource allows you to load site master
data.

d) Infosource Plant (Texts)(0PLANT_TEXT) with datasource


Plant(0PLANT_TEXT). This infosource allows you to load site
descriptions in all languages.

e) Infosource Plant Material(0MAT_PLANT) with datasource Material


Number with Plant(0MAT_PLANT_ATTR). This infosource allows you to
load article/site master data.

f) Infosource Plant Material(0MAT_PLANT) with datasource Material


number with plant(0MAT_PLANT_TEXT). This infosource allows youto
load descriptions for your article/site in all languages.

3. To load F&R specific master data into 0MAT_PLANT, the following


infosource need to be scheduled:

a) Infosource 0MAT_PLANT F&R Attributes(0SCM_FRE_MAT_PLANT_ATTR) with


datasource F&R Plant material attributes(0FRE_MATPLANT_ATTR). This
infosource allows you to load F&R specific master data attribute.

4. To initialize delta transfer for F&R transactional data, the following


info packages and then schedule the regular info package once a day:

a) Delta init packages:


F&R Stock Exceptions - Init Delta
F&R Replenishment Exceptions - Init Delta
F&R Order Proposal Manual Change - Init Delta
F&R Minimum Stock Variances - Init Delta
F&R Order Proposal Statistics - Init Delta

b) Regular Delta (once a day after the FRP run is complete):


F&R Stock Exceptions - Delta
F&R Replenishment Exceptions - Delta
F&R Order Proposal Manual Change - Delta
F&R Minimum Stock Variances - Delta
F&R Order Proposal Statistics - Delta

5. To initialize delta transfer for F&R transactional data, the following


info packages need to be scheduled once a week:

a) Delta init package: F&R Weekly Figure - Init Delta

18.06.2008 Page 2 of 3
Note 723899 - Forecasting and Replenishment Analytics BW loading
procedure

b) Regular Delta (once a week after the FRP run is complete): F&R
Weekly Figure - Delta

Header Data
Release Status: Released for Customer
Released on: 22.06.2005 13:22:19
Priority: Recommendations/additional info
Category: Consulting

Main Component BW-BCT-FRE Forecasting and Replenishment Engine Analytics


Additional Components:
SCM-FRE-ANA Analytics

Valid Releases
Software Component Release From To Release and Following
Release
SCM 410 410 410

18.06.2008 Page 3 of 3

Você também pode gostar