PACKAGE 1: CADANGAN MEMBINA KEMUDAHAN PENGURUSAN ENAPCEMAR

DI LRA PALONG TIMUR, SEGAMAT, JOHOR


List to follow up as at 28/2/2018
Deadline Date Deadline Date
No Description Action By Status
(Proposed) (Actual)
1 Shop drawing for M & E PBE 28.02.2018
2 Shop drawing for Roof Truss & Covering PBE 09.03.2018 in-progress
3 Bending & tensile test for steel bar - Alor Gajah Melaka PBE 27.02.2018 reschedule - 06.03.2018 (tues)
4 Detail of schedule for C & S (WWCT/SBT, Polymer & Geotube PBE 22.02.2018 DONE 23.02.2018
5 Detail of schedule for M & E PBE 26.02.2018
6 Work programme (panel casting) for WWCT/SBT, Polymer & PBE 22.02.2018 DONE 23.02.2018
Geotube
7 Method of repairs for honeycomb PBE 26.02.2018 DONE 26.02.2018
8 Method of repairs for cold joints PBE 02.03.2018 MOS by Mursyid
9 Material to get ready on-site ASAP:
i 300mm dia. Pipe - 2 units PBE 05.03.2018
ii 200mm dia. Pipe - 1 unit PBE 05.03.2018
iii 100mm dia. Pipe - 4 units (Ductiles Pipe) PBE 05.03.2018
iv 100mm dia. Pipe - 4 units (MS Pipe) PBE 05.03.2018 DONE 28.02.2018
v 100mm dia. Pipe - 80 units (MS Pipe) PBE 05.03.2018
vi WS for dry well & wall (foam ties + rubber + inner unit) PBE ASAP DONE 28.02.2018
vii Reinforcement bar for dry well, wall & top slab PBE ASAP DONE 15.02.2018
viii Dawai ikat besi (wire rope) PBE ASAP DONE - continuoues
ix Stagging - 150 sets PBE ASAP 100 sets already delivered
27.02.2018, left for 50 sets
x Formwork - plywood, kokcai, kayu 2" x 3" PBE ASAP DONE - continuoues
xi Scaffold (50 sets) - safety & working platform PBE ASAP 25 sets already delivered on
27.02.2018, left for 25 sets
10 To mobilize long arm excavator from Tangkak PBE 28.02.2018 reschedule - 02.03.2018 (TBC)
11 To fabricate steel reinforcement bar WWCT & SBT PBE ASAP in-progress
12 To update CCC monitoring checklists PBE & PNSB ASAP
13 To prepare CNC letter - to be issued to PBE on 03.06.2018 PNSB ASAP READY 26.02.2018
14 To add up additional Y10 reinforcement at the top of wall to reduce PBE ASAP when installation of rebar for wall
concrete cover by 25mm completed
15 To submit claim for February 2018 ending 18hb PBE 27.02.2018
16 To carry out concrete cube test for WWCT/SBT slab
i 7 days - 9 samples PBE 27.02.2018 DONE 27.02.2018
ii 28 days - 9 samples PBE 20.03.2018
17 To update FAT for horizontal screw pump PBE 02.03.2018
18 To update 1st Rev MIP by adding up schedule & unit complete PBE 02.03.2018
19 To remind PBE site team not to do any works outside hording PBE & PNSB 02.03.2018 to be resolved by 02.03.2018
20 To get detail of drawing for 2 units of pipe at WALL 'D' PNSB 02.03.2018 further discussing with Ishak
21 To collect invert level data for installation of pipe from PBE further discussing with khatim
sedimentation tanks to WWCT & SBT
22 Any discrepency of drawing / BQ - PBE to submit Request For PBE Continuous
Information (RFI)