Escolar Documentos
Profissional Documentos
Cultura Documentos
CL 409.01
CONSTRUCTION MANAGEMENT
Objective of subject…
• To make aware of the method of construction
management.
• To impart knowledge about different methods of network
planning.
• To acquainted with tendering Procedure and various
constructions contract systems.
• To aware about laws for labors.
1
09-Aug-18
Overview of subject….
1. Construction sector in India
2. Project feasibility report
3. Construction planning, organizing, controlling and
monitoring
4. Project management through networks
5. PERT
6. CPM
7. Contracts and tender
Hours/ 3 2 5
week 4
Marks 100 50 150
Pedagogy
Continuous
Evaluation Syllabus for Test/Exam Marks Equivalent Marks
Assignment/ Online 10 10
course
Total Marks = 30
2
09-Aug-18
Unit: 1
Construction Sector in India (9%)
Introduction
Construction:
It is a process of translating the plans, specification and resources
into physical facility to meet specific requirements of owner
within schedule, cost quality.
Management:
It is process to plan, to organize, to coordinate, to control
resources of project to achieve predetermined goal successfully.
Project:
It is a temporary endeavor(effort) undertaken to provide a unique
product of service.
3
09-Aug-18
Construction Stakeholders…
Project Mang.
Architect
Cons.
Lawyer Const.
Supervision Cons.
Physical
Construction Material Supplier
Sub-contractor
Labour supplier
4
09-Aug-18
Client/ Owner
• The legal entity(person/ organization) that will use facility or
structure after completion of project.
• May be an national and local government, public corporation, public
enterprise, individual, firm/company.
Responsibility:
To define what must be done
To judge the use of funds to execute the project
To make decisions and provide information when required
To appoint engineer and give him power to work on his behalf.
To give possession of site to the contractor.
Architect
• Employed by the employer to provide overall project
guidance, design expertise and to (usually) administer the
contract.
Responsibility:
extracting and understanding the client’s requirements
developing a design response
ensuring the design is constructed (contract administration –
administering the Contract between Employer and Contractor)
Tender preparation and contractor selection.
5
09-Aug-18
Engineer
• Generally the term ‘engineer’ means the consulting engineer who works with
the client to conclude the contract. They provide technical services on behalf
of client.
• consultant is referred to as project management consultant, structural cons.,
const. supervisor cons., geo-technical cons. etc.
Responsibility:
Responsibility varies from consultant to consultant. In general , they are
responsible for
undertaking project feasibility study
preparation, reviewing and coordinating engineering drawing
Geo-technical investigation
Helping client in bidding process, coordinating in execution phase
Project Manager
• They appointed by the Employer, the project manager
may:
Co-ordinate the general flow of the project
Ensure programmes are realistic
Facilitate the flow of information between organizations
Co-ordinate site activities
Ensure the quality of workmanship and materials
Ensure good health and safety practice
6
09-Aug-18
Lawyer
• Some construction companies in India have a legal cell
comprising lawyer specializing in construction dispute.
Responsibility:
Review various documents like contract, inspection report etc.
Resolve the dispute between client and contractor
deals with matters relating to building construction,
engineering and related fields.
Contractor
• The production aspects of construction projects are undertaken by building
contractors who are essentially commercial companies or individual that
contract to construct development projects.
Responsibility:
Carrying out a full site investigation prior to submission of tender to ensure
that the bid includes all the cost of contractual risks and problems.
Submitting priced bills of quantities for examination and/or correction of any
errors when required by the architect.
Planning and programming the works and reprogramming thereafter
whenever unforeseen events frustrate the program.
Controlling directly employed operatives, sub-contractors, suppliers,
materials and plant for the execution of the project to programme and cost.
Coordinating efforts of all operatives and ensuring that the completed works
comply with the contract specification and are also to the satisfaction of the
architect.
7
09-Aug-18
Subcontractor/ supplier/vendor
• In large construction projects, very often no single
contracting company has adequate expertise and resources
to undertake all activities on their own.
• Under such situation, they employ small contractors for
certain specialized item of work, for either execution
purpose or material procurement purpose.
8
09-Aug-18
9
09-Aug-18
6. Financing Issues:
– The owner runs out of money to finance the project, contractor might
not come back to run project if they can’t provide the funds.
7. Unreliable Workers:
– A lack of qualified workers or a team that is unreliable is a invite
disaster when it comes to construction projects
8. Communication Gaps:
– Effective communication is extremely crucial to the success of a
any project. When any of the parties involved aren’t getting the right
information at the right times, it can become a very costly issue. It is
important to establish a chain of command to make sure that all parties
are getting the necessary updates in regards to changes on the project,
design, plans, specs, or timeline.
9. Improper Planning:
– Rigid, inflexible schedules are common in construction projects. If
don’t account for surprises or delays, a project can take longer and
cause cost overruns. It is extremely important to constantly monitor
project tasks closely to ensure sub-ordinates are matching up with the
assigned duration given when planning.
10. Lack of Leadership
– When we see this word, leader, we usually think, the project manager.
However, the people at each management-level have a responsible to
ensure that the project is successful. Management should not
micromanage but provide support to ensure that the PM can follow
through with the expectations placed upon them.
10
09-Aug-18
11
09-Aug-18
Directing &
Coordinating Procuring
Leading
Monitoring
& controlling
12
09-Aug-18
Planning
• Planning gives idea about future course of action.
• It involves deciding in advance…
– What is to be done?
– Where it is to be one?
– How it is to be done?
– In what order it is to be done?
• Planning involves…
– Defining objectives or scope of work
– Collecting and arranging information
– Developing alternative with specified constraint
– Comparing alternatives in terms of feasibility & consequence
– Selecting the optimum course of action
– Establishing policies, procedure, methods, programmes, system standard, budget
to accomplish project.
Scheduling
• Scheduling is related to time resource. It decide starting and ending time of
planned activities. It put plan on calendar date scale.
• In involve breaking project up to activity level so it can easily manage.
Organizing
• It is a process of establishing structural relationships among the function of
people involves in project.
• It involves…
– Deciding job structure.
– Defining performance target & responsibility
– Delegating authority with responsibility
– Establishing structural relationship to secure coordination.
13
09-Aug-18
Co-ordinating
• Bring the different elements of (a complex activity or
organization) into a harmonious or efficient relationship.
Procuring
• Procuring deals with provision of right quality and right
quantity of resources at the right time.
• Procuring involves…
– Preparing resource procurement schedule
– Developing specification for required resources
– Deciding appropriate source of resource
– Budgeting resources
– Arranging approval & purchase
– Preventing wastage during execution of work
14
09-Aug-18
15