Plot-196;- Man power requirement-to complete Pending activity

16.5.18

S.No Pending Activity Qty Target Dates No.of Days Remarks Clearnce

Roof

1 Lighting GI conduit ots 180 mtr 31-May 3 Double height


2 Lighting wire pulling 350 mtr 1-Jun 3 Double height
Light fitting Not
lift lobby light fitting
3 16 nos 28-May 2 avilable Cutting awaiting
4 OTS cable tray dropping ( Shops) 40 mtr 29-May 3 Triple Height
5 VRF1,2,3, Isolator installation 18 nos 3 Awiting materils
6 Tray cover installation 850 mtrs 7 material awiting
7 Lighting protection Earth link installation 28 Nos 31-May 2 Cutting awaiting
Desnagging 5-Jun 3 I/P

GYM AREA
8 Lighting pvc pipe installation 300 mtrs 30-May 2
9 Lighting wire pulling 600 mtrs 31-May 2
10 Power pvc pipe installation 160 mtrs 3-Jun 2
11 Power wire pulling 500 mtrs 3-Jun 2
12 DX unit communication cable puling 660 mtrs 3-Jun 3 Double height
13 DX unit Isolator fixing & outerout termination 11 Nos 4-Jun 2 Double height
14 Power final fixing 28 Nos 5-Jun 2
Light fitting Not
15 Lighting final fixing 225 Nos 6-Jun 3 avilable
16 DB Dressing & Termination 4 Nos 4-Jun 2
17 Desnagging 5-Jun 3
FAÇADE LIGHT
18 GI conduit installation 165 mtrs 31-May 3 Triple Height
19 wire pulling 325 mtrs 31-May 3 Triple Height
Light fitting Not
20 Light fitting installation 130 Nos 7 avilable
Desnagging 5-Jun 3
Upper Roof
21 Balance lighting GI conduit 60 mtrs 5-Jun 3
22 Balance Wiring 180 mtrs 5-Jun 2
23 Desnagging 3
First Floor
24 Snaging & Desnaging 31-May 4
25 Lift lobby light fitting 28 Nos 28-May 2
Chandiler light fittings fixing 312 nos 5-Jun 7 Additionalc work
Basement
26 Payment Machine work 4 Nos 26-May 2
Light fitting Not
27 Lift lobby Light 8 Nos 26-May 2 avilable
28 LCS-GI conduiting& wiring 50 mrts 28-May 3
29 Pending lights installation&termination Nos 28-May 6
30 Sinage Board conduiting & wiring-16 nos 12 Nos 4 Additional work
31 DB-Dressing-Additional 2 Nos 1
32 FCU-Coduiting &cabling 11 Nos 28-May 4
33 De-snagging Nos 7

Ground Floor
Light fitting Not
34 Arcade Area Light fitting installation 30 Nos 5-Jun 5 avilable Cutting req.
35 Door Air curtainfinal fix 4 Nos 28-May 2 Channel cuttung req.
Light fitting Not
36 Lift lobby lighting(8)+84 mtrs 8 Nos 29-May 4 avilable Awiting cutting
37 Shop Tray work for Shop FCUs Nos 5-Jun 5 Awiting Tray
Light fitting Not
38 Shop Corridor Lighting and power 48 Nos 29-May 4 avilable
39 Plant room Final fix-Lighting and power Nos 5-Jun 4 No clearance
40 FCU connection Nos complted
41 Floor Lights conduiting-Outside of shops 500 Mtrs 5-Jun 4
42 Floor Lights wiring-Outside of shops 1500 Mtrs 5-Jun 4
43 Sinage Board conduiting & wiring-16 nos 33 Nos 4 Additional work
44 Floor light fixing-Termination 33 Nos 6-Jun 4
45 LCS 50 mtr 2
46 Desnagging 5-Jun 3
Total Man hour Required